Holcim Works Schedule:

Clarifications PO Manufacture Drawings Order Confirmation LC Manufacturing


Delevery/ Freight/
Clearence
At Site/ Erection
1 MV Panel
Supply and Installation of 8BK80 36kV
25kA/3s 400A Switchgear including 01
incomer panel,02 T/F outgoing panels
with Bus Coupler
As per Annexure C- Technical Details of
MV Panel
done done done done pending
2 MV Cable
Supply, laying and termination of 33kV, 3-
Core,185sqmm XLPE insulated power
cables.
As per Annexure E-Technical Details of
MV Cable
pending(cable avalable at Valiveriya yard)
3 LBS
Supply and installation of Loadbreak
switch at the CEB metering point
Pending
4 Earthing
5 Other
Activities Done/Pending
Special remarks Description Item
ITEM DESCRIPTION Qty Pending/done
Supply and Installation of 8BK80 36kV 25kA/3s 400A switchgear including 01 incomer panel,02
t/f outgoing panels with Bus Coupler
Supply (Transport to site)
8BK80 Switchgear 1.00 Ok
Duty and Clearing
Clearig Cost & Duty 1.00 Ok
Material & services
Handling (5 Ton Folk) 2.00
Panel structure 1.00
Gland 3.00
Aux. Power Supply cable 15.00
Steel Conduit 15.00
Earthing modification 20.00
Ancors 8.00
Cable relocation 45.00
Cable Trasing Equipment 1.00
Mics 1.00
Labour
Electricians
Helpers
Supply, installation and termination of 33kV, 3-Core,185sqmm XLPE insulated power cables.
75.00
Supply (Transport to site)
33kV Cable 75.00 Pending
Duty and Clearing
Clearig Cost & Duty 75.00
Cable termination of HT Cables 1.00
Material
Termination (Including Kits with lugs) 2.00
Consumables 2.00
Material & services
Sand 13.50
Backfill 2.00
Cable tiles 115.38
Warning tape 75.00
Ladders & accessories 2.00
Concreet 0.80
Equipments 4.00
Labour
Electricians
Helpers
Supply and installation of Earthing system with necessary earth bars and earth electrodes with
cables. 1.00
Material & services
External Earthing rods and clamps 4.00
Copper Plate 1.00
185sqmm bare copper conductor 40.00
Cable Isothermic Connections 10.00
Copper Tape 10.00
Earthpits 5.00
Accessories (Clips, etc) 4.00
Electricians 6.00
Helpers 12.00
LBS 1.00
Supply (Transport to site)
LBS 1.00
Duty and Clearing
Clearig Cost & Duty 1.00
Material
Cables ( 25sqmm - flexi) 10.00
Conduit ( 1") and accessories 5.00
Labour
Electricians 4.00
Helpers 6.00
Testing and Commissioning 2.00
Megger 2.00
CPC100 2.00
CMC356 2.00
Engineer Charges 2.00
Charted engineer 2.00
Sub Total for Local Items
SN Drawing Description
recevied form
Manu/Client
Designed Checked Approved
1 SLD - Ok
2 Panel drawing ok - ok ok
3 LBS pending