ID Task Name Duration Start Finish

1 Fit out works -ALEXANDER MCQUEEN SOWWAH SQUARE ABU DHABI 64 days Apr 21 '13 Jul 3 '13
2 Key Dates / Preliminaries works 1 day Apr 21 '13 Apr 21 '13
3 Award of contract 1 day Apr 21 13 Apr 21 13
4 Receipt of construction drawings including project specifications 0 days Apr 21 13 Apr 21 13
5 Site Access 0 days Apr 21 13 Apr 21 13
6 Statutory approval process 61 days Apr 24 '13 Jul 3 '13
7 Preparation of documents for CKR submission 0 days Apr 25 13 Apr 25 13
8 Approval of documents from CKR 2 days May 7 13 May 8 13
9 Preparation of documents for serex submission 2 days May 9 13 May 11 13
10 Approval of documents from serex 2 days May 12 13 May 13 13
11 Civil Defense (CD) - Start Up 15 days May 14 '13 May 30 '13
12 Document preparation for CD approval 7 days May 14 13 May 21 13
13 Document submission for CD 1 day May 22 13 May 22 13
14 Document Review & approval (Duration varies as per CD) 7 days May 23 13 May 30 13
15 Receipt of CD approval 0 days May 30 13 May 30 13
16 ADM Decoration Permit (Duration varies as per ADM) 14 days May 14 '13 May 29 '13
17 Document submission to ADM 1 day May 14 13 May 14 13
18 Document review & approval 12 days May 15 13 May 28 13
19 Receipt of decoration permit 1 day May 29 13 May 29 13
20 Abu Dhabi Distribution company approval - Start up 22 days May 19 '13 Jun 12 '13
21 Electrical drawings & documents submission to ADDC 1 day May 19 13 May 19 13
22 ADDC review & approval (Duration varies as per ADDC) 21 days May 20 13 Jun 12 13
23 Receipt of ADDC approval 0 days Jun 12 13 Jun 12 13
24 Finalization of Sub-Contractors & Supplies 10 days May 22 13 Jun 2 13
25 Shop drawing approval process 28 days Apr 24 '13 May 26 '13
26 Drawing submittal 25 days Apr 24 '13 May 22 '13
27 Coordinated ceiling layout & detail drawings 20 days Apr 28 13 May 20 13
28 Flooring layout & detail drawings 20 days Apr 28 13 May 20 13
29 Joinery drawings 7 days May 15 13 May 22 13
30 Mechanical Drawings 3 days Apr 24 '13 Apr 27 '13
31 HVAC Drawings 3 days Apr 24 13 Apr 27 13
32 Fire Fighting Drawings 3 days Apr 24 13 Apr 27 13
33 Electrical Drawings 3 days Apr 24 '13 Apr 27 '13
34 Lighting layouts 3 days Apr 24 13 Apr 27 13
35 Power layout 3 days Apr 24 13 Apr 27 13
36 Fire alarm layout 3 days Apr 24 13 Apr 27 13
37 Drawings approval 25 days Apr 28 '13 May 26 '13
38 Coordinated ceiling layout & Detail drawings 3 days May 21 13 May 23 13
39 Flooring layout & detail drawings 3 days May 21 13 May 23 13
40 Joinery drawings 3 days May 23 13 May 26 13
41 Mechanical drawings 3 days Apr 28 '13 Apr 30 '13
42 HVAC layout 3 days Apr 28 13 Apr 30 13
43 Fire fighting layout 3 days Apr 28 13 Apr 30 13
44 Electrical drawings 3 days Apr 28 '13 Apr 30 '13
45 Lighting layout 3 days Apr 28 13 Apr 30 13
46 Power layout 3 days Apr 28 13 Apr 30 13
47 Fire alarm layout 3 days Apr 28 13 Apr 30 13
48 Material procurement process 61 days Apr 24 '13 Jul 3 '13
49 Material submittal 6 days Apr 24 '13 Apr 30 '13
50 Gypsum partition & ceiling system 3 days Apr 24 13 Apr 27 13
51 Grid system (BOH) 3 days Apr 24 13 Apr 27 13
52 Joinery items 3 days Apr 28 13 Apr 30 13
53 Paint items 3 days Apr 28 13 Apr 30 13
54 MEP items 3 days Apr 24 '13 Apr 27 '13
55 Basic materials 3 days Apr 24 13 Apr 27 13
56 DBs 3 days Apr 24 13 Apr 27 13
57 AHUs 3 days Apr 24 13 Apr 27 13
13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6
May 2013 June 2013 July 2013
Fit out works for Alexandwer McQueen @ Sowwah Square
Apr 29 13 Page 1 Rev00
ID Task Name Duration Start Finish
58 AC grills & diffusers 3 days Apr 24 13 Apr 27 13
59 VCDs 3 days Apr 24 13 Apr 27 13
60 Fire alarm devices 3 days Apr 24 13 Apr 27 13
61 Wiring accessories 3 days Apr 24 13 Apr 27 13
62 Material approval 6 days Apr 28 '13 May 4 '13
63 Gypsum partition & ceiling system 3 days Apr 28 13 Apr 30 13
64 Grid system (BOH) 3 days May 1 13 May 4 13
65 Joinery items 3 days May 1 13 May 4 13
66 Paint items 3 days May 1 13 May 4 13
67 MEP items 6 days Apr 28 '13 May 4 '13
68 Basic materials 3 days May 1 13 May 4 13
69 DBs 3 days Apr 28 13 Apr 30 13
70 AHUs 3 days Apr 28 13 Apr 30 13
71 AC grills & diffusers 3 days Apr 28 13 Apr 30 13
72 VCDs 3 days Apr 28 13 Apr 30 13
73 Fire alarm devices 3 days May 1 13 May 4 13
74 Wiring accessories 3 days Apr 28 13 Apr 30 13
75 Material Procurement 43 days May 1 '13 Jun 19 '13
76 Gypsum partition & ceiling system 3 days May 1 13 May 4 13
77 Grid system (BOH) 3 days May 5 13 May 7 13
78 Joinery items 3 days May 5 13 May 7 13
79 Paint items 3 days May 5 13 May 7 13
80 MEP items 43 days May 1 '13 Jun 19 '13
81 Basic materials 3 days May 5 13 May 7 13
82 DBs 3 days Jun 13 13 Jun 16 13
83 AHUs 28 days May 1 13 Jun 2 13
84 AC grills & diffusers 3 days Jun 17 13 Jun 19 13
85 VCDs 3 days May 1 13 May 4 13
86 Fire alarm devices 3 days May 5 13 May 7 13
87 Wiring accessories 3 days Jun 17 13 Jun 19 13
88 Client supplied items required dates 0 days J un 15 '13 J un 15 '13
89 Carpet flooring - C1 0 days Jun 15 13 Jun 15 13
90 Fit-Out works 47 days May 11 '13 Jul 3 '13
91 General 4 days May 11 '13 May 14 '13
92 Mobilization 2 days May 11 13 May 12 13
93 Hoarding works 2 days May 13 13 May 14 13
94 MEP 1st fix above ceiling 10 days May 15 '13 May 26 '13
95 Cable tray, trunking & Conduting 10 days May 15 13 May 26 13
96 Fire fighting lines 10 days May 15 13 May 26 13
97 A/C ducts installation 8 days May 18 13 May 26 13
98 MEP 2nd fix 9 days May 21 '13 May 30 '13
102 CAT walk installation 9 days May 27 13 Jun 5 13
103 MEP works below floor screed 3 days May 15 13 May 18 13
104 Floor screed 4 days May 16 13 May 20 13
105 Wall partition & supports 7 days May 27 '13 Jun 3 '13
106 Gypsum partitions / Linear walls framing works 4 days May 27 13 May 30 13
107 FR Gypsum lining works 3 days May 27 13 May 29 13
108 Frameworks for FR MDF 3 days May 28 13 May 30 13
109 Gypsum partition / lining wall - MEP works 3 days May 29 13 Jun 1 13
110 FR Gypsum partition works 3 days May 29 13 Jun 1 13
111 FR MDF works towards shop front 3 days May 30 13 Jun 2 13
112 FR Gypsum partition / linear wall taping & jointing 3 days May 30 13 Jun 2 13
113 Shop front support works (if required) 3 days Jun 1 13 Jun 3 13
114 Back of House / Stocks 19 days Jun 4 '13 Jun 25 '13
115 Wall & bulkhead painting up to 1st coat 7 days Jun 4 13 Jun 11 13
116 AHUs installation &chilled water pipe connection 5 days Jun 5 13 Jun 10 13
117 Grid ceiling works 5 days Jun 10 13 Jun 15 13
118 Grid ceiling - MEP plenum box & sprinkler drops 5 days Jun 13 13 Jun 18 13
119 Inspection before ceiling closure 1 day Jun 20 13 Jun 20 13
120 Fixing of Ceiling Tiles 1 day Jun 22 13 Jun 22 13
13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6
May 2013 June 2013 July 2013
Fit out works for Alexandwer McQueen @ Sowwah Square
Apr 29 13 Page 2 Rev00
ID Task Name Duration Start Finish
121 Graniti tiles flooring 3 days Jun 23 13 Jun 25 13
122 Front of House / Shop front 14 days Jun 2 '13 Jun 17 '13
123 DB installation & termination 2 days Jun 2 13 Jun 3 13
124 Gypsum ceiling/Bulkhead/Cove framing & support works 3 days Jun 3 13 Jun 5 13
125 Gypsum ceiling/bulkhead/cove-MEP sprinkler drops &
plenum box
3 days Jun 6 13 Jun 9 13
126 Inspection before ceiling closure 1 day Jun 10 13 Jun 10 13
127 FR Gypsum ceiling bulkhead / cove boarding 3 days Jun 11 13 Jun 13 13
128 FRGypsum ceiling/bulkhead/cove- taping & jointing 2 days Jun 12 13 Jun 13 13
129 FR Gypsum ceiling/bulkhead/cove- painting works 2 days Jun 12 13 Jun 13 13
130 FR Gypsum ceiling/bulkhead/cove- MEP marking &
cutting
1 day Jun 12 13 Jun 12 13
131 Marble stone flooring ST1 3 days Jun 11 13 Jun 13 13
132 Carpet flooring required for millworkers joinery installation 2 days Jun 15 13 Jun 16 13
133 Protection works 1 day Jun 17 13 Jun 17 13
134 Shop front & signage works 11 days Jun 15 '13 Jun 26 '13
135 Shop front fascia above glazing 2 days Jun 15 13 Jun 16 13
136 Shop front glazing for window display 4 days Jun 17 13 Jun 20 13
137 Installation of glass shutter door 3 days Jun 22 13 Jun 24 13
138 Installation of shop front signage 2 days Jun 25 13 Jun 26 13
139 MEP final fix 3 days Jun 13 '13 Jun 16 '13
140 Grills & diffusers / black powder coated metal 3 days Jun 13 13 Jun 16 13
141 Strip installation for AC slots 3 days Jun 13 13 Jun 16 13
142 Fire alarm devices fixing 3 days Jun 13 13 Jun 16 13
143 Switches & sockets fixing 3 days Jun 13 13 Jun 16 13
144 Light installation 3 days Jun 13 13 Jun 16 13
145 Joinery Installation works 6 days Jun 17 '13 Jun 23 '13
146 White Shell Construction Complete Date ( Excluding
MEP final Fix)
0 days Jun 17 13 Jun 17 13
147 Mill worker joinery installation 6 days Jun 17 13 Jun 23 13
148 Final Painting Works 3 days Jun 17 13 Jun 19 13
149 BOH Joinery works 5 days Jun 26 '13 Jul 1 '13
150 Pantry counter & OH cabinet above pantry counter 3 days Jun 26 13 Jun 29 13
151 Skirting works 1 day Jun 26 13 Jun 26 13
152 Mirrors installation 2 days Jun 27 13 Jun 29 13
153 Acrylic sheet on wall @ exit door entrance 2 days Jun 27 13 Jun 29 13
154 Installation of discreet internal access shutter for pool faade 2 days Jun 27 13 Jun 29 13
155 Platform for the safe 2 days Jun 27 13 Jun 29 13
156 Cleaning & snagging 2 days Jun 30 13 Jul 1 13
157 Authority inspection, approval & testing & commissioning
& final inspection
9 days Jun 24 '13 Jul 3 '13
158 Fire alarm testing & commissioning & panel programming 1 day Jun 24 13 Jun 24 13
159 Civil Defense application submission 1 day Jun 25 13 Jun 25 13
160 Civil Defense inspection & approval 2 days Jun 26 13 Jun 27 13
161 ADM documents submission 1 day Jun 26 13 Jun 26 13
162 ADM approval 2 days Jun 27 13 Jun 29 13
163 ADDC inspection application 1 day Jun 25 13 Jun 25 13
164 ADDC inspection & approval 1 day Jun 26 13 Jun 26 13
165 Getting electrical meter & power supply 1 day Jun 29 13 Jun 29 13
166 Electrical testing & commissioning 2 days Jun 30 13 Jul 1 13
167 A/C air balancing & commissioning 2 days Jun 30 13 Jul 1 13
168 Mall final inspection & approval 1 day Jul 2 13 Jul 2 13
169 Final inspection by client 1 day Jul 3 13 Jul 3 13
170 Client possession 1 day Jul 3 13 Jul 3 13
13 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6
May 2013 June 2013 July 2013
Fit out works for Alexandwer McQueen @ Sowwah Square
Apr 29 13 Page 3 Rev00