ANC 7D Meeting June 10, 2014 2 Project Team EJ Simie, P.E. DDOT Project Manager Josh Gormer CH2M HILL Project Manager Bryon Johnston AWI Public Information Manager Stephanie Lewis AWI Workforce Development Manager 3 Agenda AWI Program Update Anacostia Riverwalk Trail Overview Kenilworth Segment Design Construction Progress and Schedule DBE and Workforce Management More Information 4 30-Year, $10 Billion Program Created by March 2000 Memorandum of Understanding Between the District and 19 Other Federal and Regional Agencies 5 Key Themes: o Restore: A clean and active river. o Connect: Eliminating barriers and gaining access. o Play: A great riverfront park system. o Celebrate: Cultural destinations of distinct character. o Live: Building strong waterfront neighborhoods. Creating a World-Class Waterfront 5 AWI Transportation Projects 6 Anacostia RiverwalkTrail Backbone of Anacostia Waterfront 15 of 28 Planned Miles of Trail Open Will Connect Tidal Basin with Northeast Maryland Border Seamless Pedestrian and Bicycle Travel Between Popular Destinations and 16 Neighborhoods $33 Million of Anticipated $50 Million Invested to Date 7 Kenilworth Trail Segment Connects Benning Road in the District with Bladensburg Park in Maryland Missing link in 70-mile Regional Trail Network 3.9 miles of asphalt-paved trail and ancillary structures o 3.4 miles in the District o 0.5 miles in Maryland 8 Key Project Features 5 Prefabricated bicycle/pedestrian bridges 1,250 feet of heavy-duty boardwalk 2.11 acres of soil restoration and reforestation in Maryland Minimal excavation Work in Amtrak right-of-way Environmental Restrictions Included in Contract 9 Existing Hayes/Jay Street NE 10 Future Hayes/Jay Street NE 11 Project Milestones and Schedule Notice to Proceed January 2014 Construction Start March 2014 Project Completion Spring 2016 12 Construction Progress Erosion Control Near Jay Street NE Construction Progress Near Jay Street NE Tree Protection Fencing and Erosion Control Near Deane Ave. NE Construction Entrance Near Deane Ave. Construction Entrance Near Deane Ave. 13 Disadvantaged Business Enterprise (DBE) Goals DBE goal is 15% for both Maryland and the District. Separate DBE plans will be required for each jurisdiction. DBE goal must be met in each jurisdiction independently, and no double-dipping is allowed. Adherence to DBE goals will be monitored and audited 14 Workforce Development 5 employee training positions are required as part the DC portion of the project: o 2 landscape workers, o 1 laborer, o 1 electrical worker, and o 1 traffic control worker 15 Good-neighbor Construction o Limit Impacts to Neighbors and Environment o Daytime Construction Safety At All Times o Dust Control o Construction Worker Parking in Staging Areas Minimizing Construction Impacts 16 More Information For more information, visit www.anacostiawaterfront. org/KenilworthSegment To receive project updates, ask questions or comment: o Sign up for the project email list o Email: ddot.awi@dc.gov o Call: 202-741-8528 QUESTIONS?