PURATA KADAR HARGA BAGI ITEM UTAMA

KERJA-KERJA KEJURUTERAAN AWAM


BIL. 2 / 2008
BIL

Nama-nama Bahan/Kerja

Format 'IU'

Unit

Kaw. A
Median
Purata

Kaw. B
Median
Purata

Kaw. C
Median
Purata

Kaw. D
Median
Purata

Kaw. E
Median
Purata

Kaw. F
Median
Purata

ROADWORKS
Site Clearance
A Site clearing including grubbing up roots and
disposal of all material as directed by the S.O

Ha

11,000.00 8,625.00 5,000.00 5,000.00 3,000.00 4,020.00 3,000.00 3,000.00

TM

TM

B Cutting of trees above 1m girth

No

500.00

516.67

TM

TM

TM

TM

500.00

C Stripping top soil to an average depth of 150mm,


including stockpiling for use and disposal of
surplus material

m2

1.20

1.67

1.00

1.00

5.00

6.28

D Excavate unsuitable material, dispose and backfill


with suitable material as directed by the S.O

m3

4.00

12.33

22.00

22.00

10.00

E Excavate in all material other than rock, in cutting,


below embankments or formation level in whatever
ground condition and including transport to areas
of fill

m3

6.00

6.67

7.00

7.00

m3

35.00

35.00

TM

m3

26.00

26.00

m3

2.00

B Fill, spread, grade & compact imported suitable


material in fill areas

m3

C Supply, lay and compact sand fill embankment


D Closed turfing to surface at any inclination average
300mm thick

3,450.00 3,725.00

500.00

TM

TM

500.00

471.00

2.50

2.50

TM

TM

3.20

2.85

11.33

8.00

8.00

TM

TM

15.00

15.48

10.00

9.14

8.00

8.00

TM

TM

15.00

14.22

TM

19.00

19.00

50.00

50.00

TM

TM

50.00

42.50

TM

TM

4.20

6.07

12.00

12.00

TM

TM

25.00

27.74

2.83

25.00

25.00

4.20

6.07

6.80

6.80

TM

TM

4.00

6.32

4.50

4.50

40.00

40.00

TM

TM

15.00

15.00

TM

TM

39.00

42.25

m3

74.00

73.50

TM

TM

47.00

47.00

25.00

25.00

TM

TM

50.00

55.89

m2

4.00

4.00

5.20

5.20

5.30

5.46

3.50

3.50

TM

TM

6.50

6.80

E Preparation of formation level

m2

1.00

1.53

2.50

2.50

1.10

2.02

2.50

2.50

TM

TM

2.75

2.58

F Scarify and breaking up existing pavement

m2

5.00

5.50

TM

TM

3.00

4.26

3.00

3.00

TM

TM

14.70

16.07

G Supply, spread and compact Type D(A) subbase


material

m3

51.00

51.00

TM

TM

100.00

127.33

25.00

25.00

TM

TM

25.00

29.68

H Supply, spread and compact sand for sub-base to


the compacted thickness of 200mm sand as
shown in the drawing

m3

60.00

49.33

40.00

40.00

40.00

31.40

35.00

35.00

TM

TM

60.00

58.43

Supply, spread and compact crushed aggregate


roadbase

m3

26.00

33.33

45.22

45.22

70.33

64.80

48.00

48.00

TM

TM

55.00

48.14

Supply and lay bituminous prime coat

m2

2.50

2.63

2.00

2.00

1.10

1.34

2.00

2.00

TM

TM

3.00

3.50

Supply and lay bituminous tack coat

m2

2.40

2.30

2.00

1.67

1.00

1.20

2.00

2.00

TM

TM

3.00

2.81

Supply and lay bituminous BMR 40

m2

360.00

309.50

TM

TM

TM

TM

500.00

500.00

TM

TM

681.55

681.55

Supply, spread and compact ACB 20

m2

375.00

320.25

TM

TM

TM

TM

500.00

500.00

TM

TM

358.28

358.28

Supply, spread and compact ACB 28

m2

380.00

325.00

333.33

339.44

27.50

93.08

500.00

500.00

TM

TM

358.28

358.28

B Supply, spread and compact ACW 14

m2

390.00

327.75

450.00

1,745.83

260.00

260.00

500.00

500.00

TM

TM

729.20

729.20

C Supply, spread and compact ACW 20

m2

385.00

325.25

TM

TM

18.00

18.00

500.00

500.00

TM

TM

350.08

350.08

D Supply, spread and compact ACW 28

m2

380.00

326.25

TM

TM

25.00

24.00

500.00

500.00

TM

TM

760.45

760.45

E Supply, spread and compact BML10

m3

340.00

251.67

TM

TM

TM

TM

500.00

500.00

TM

TM

60.00

60.00

m
m
m
m
m

200.00
266.50
393.50
585.50
228.00

168.00
258.25
379.25
577.75
212.67

TM
TM
TM
TM
TM

TM
TM
TM
TM
TM

280.00
300.00
500.00
700.00
400.00

280.00
300.00
500.00
700.00
400.00

TM
TM
TM
TM
TM

TM
TM
TM
TM
TM

313.20
565.80
580.00
876.67
942.50 1,164.47
1,418.10 1,768.66
TM
TM

m
m
m
m
m
m

560.00
820.00
900.00
1,050.00
2,100.00
2,330.00

623.33
816.33
1,342.00
1,420.00
2,506.67
2,536.67

TM
TM
TM
TM
TM
TM

TM
TM
TM
TM
TM
TM

TM
TM
TM
TM
TM
TM

TM
TM
TM
TM
TM
TM

TM
1,514.20
2,228.00
2,349.00
3,948.00
4,335.00

TM
1,513.03
2,442.23
2,650.40
3,816.57
4,256.00

m2

50.00

50.00

TM

TM

152.50

152.50

80.00

80.00

TM

TM

130.85

130.85

350.00

316.67

TM

TM

155.00

155.00

200.00

200.00

TM

TM

296.90

308.97

No
No
No

936.50
480.00
262.50

936.50
480.00
262.50

TM
TM
TM

TM
TM
TM

155.00
TM
TM

155.00
TM
TM

500.00
500.00
230.00

500.00
500.00
230.00

TM
TM
TM

TM
TM
TM

912.20
884.38
884.38

912.20
884.38
884.38

C Supply all materials & install in position road


marking using approved hot applied superimposed
reflecturised thermoplastic road marking as shown
on the drawing

3.75

3.88

3.55

3.55

2.50

2.50

18.50

18.50

TM

TM

3.80

8.30

D Ditto Yellow thermoplastic material

5.00

6.25

2.25

2.25

3.00

3.00

19.00

19.00

TM

TM

5.00

13.83

E Supply and lay


a) Concrete kerb
b) Semimountable kerb

m
m

45.00
45.00

41.25
51.25

35.00
TM

35.00
TM

45.00
TM

45.00
TM

38.00
45.00

38.00
45.00

TM
TM

TM
TM

22.50
27.00

21.34
26.28

F Supply and install signboard


a) 1 m to 2 m
b) 3 m to 4 m
c) 6 m to 8 m
d) 10 m to 12 m
e) Regulatory sign
f) Warning sign
g) Directory sign

No
No
No
No
No
No
No

2,000.00
3,195.00
5,750.00
9,150.00
600.00
650.00
650.00

TM
TM
TM
TM
TM
TM
TM

TM
TM
TM
TM
TM
TM
TM

1,400.00
2,800.00
5,156.00
8,600.00
630.00
630.00
TM

1,293.33
2,940.00
4,868.67
9,106.67
630.00
630.00
TM

G Standard warning and regulartory traffic sign


(mounted on 1 post) of High Intensity Retro reflective plastic sheeting including all posts
brackets painting and everything complete as
shown in the drawing and as directed by the s.o

No

650.00

TM

TM

469.50

469.50

TM

TM

Earthworks
Excavation

Excavate in rock and dispose


Filling

G Borrow fill material other than rock from


Contractor's own source, transport lay and
compact in embankment and other fill areas as
directed by the S.O

Filling (cont'd)
A Placement and compaction of excavated suitable
material in fill areas

Pavement

Pavement (cont'd)
A

Drainage
F Supply and lay RC pipe culvert including excavation,
blinding, concrete bed, wire mesh and jointing:
a) 600mm Dia CIass Z pipe
b) 900mm Dia. Class Z pipe
c) 1200mm Dia. Class Z pipe
d) 1500mm Dia. Class Z pipe
e) 900mm Dia. Class X pipe

TM
TM
TM
TM
TM
TM
3,000.00 3,000.00
TM
TM

G Supply and lay RC box culvert including


excavation, blinding, concrete bed, wire
mesh and jointing:
a)1500mm x 1200mm
b)1800mm x 1800mm
c) 2000mm x 1800mm
d) 2000mm x 2000mm
e) 3000mm x 3000mm
f) 3300mm x 2100mm
H Supply and lay 300mm thick stone
pitching

825.00
825.00
800.00
800.00
2,500.00 2,500.00 1,000.00 1,000.00
2,000.00 2,000.00 1,800.00 1,800.00
2,250.00 2,250.00 2,000.00 2,000.00
TM
TM
3,000.00 3,000.00
TM
TM
3,200.00 3,200.00

Road Furniture
A Supply and install corrugated single
beam guardrail with steel post
B Supply and install end treatment guardrail inclusive
of post, washers, bolts and nuts:
a) 90 degree twist
b) Buffer end
c) Fish tail unit
Road marking

2,197.50 1,750.00 1,750.00 500.00


699.67 1,200.00 1,200.00
3,447.50 2,600.00 2,600.00 3,500.00 3,500.00 2,400.00 2,400.00
7,325.00 3,500.00 3,500.00 8,500.00 8,500.00 4,800.00 4,800.00
13,875.00
TM
TM
TM
TM
7,200.00 7,200.00
600.00
450.00
450.00
TM
TM
750.00
750.00
637.50
450.00
450.00
TM
TM
750.00
750.00
650.00
TM
TM
TM
TM
650.00
650.00

666.67

TM

TM

TM

TM

590.00

590.00

750.00

750.00

PILING WORKS
Reinforced Concrete Pile
A Allow for mobilisation and demolisation of all
labour,plants piling equipment on site
B Supply and deliver to site 150mm x 150mm
Reinforced Concrete piles Class C 9m length

item

5,000.00 7,833.33

8,000.00 8,000.00 10,000.00 10,000.00

22,187.50 22,187.50

30.00

27.50

TM

TM

28.00

28.00

36.00

36.00

TM

TM

TM

TM

C Supply and deliver to site 300mm x 300mm


Reinforced Concrete piles Class C 9m length

61.00

76.33

TM

TM

78.00

78.00

90.00

90.00

TM

TM

144.90

144.90

D Ditto 9m length extension piles

61.00

80.00

TM

TM

82.00

82.00

90.00

90.00

TM

TM

TM

TM

E Fillet weld vertical extension piles joints

30.00

30.33

18.00

18.00

28.00

28.00

60.00

60.00

TM

TM

145.90

145.90

F Handle, sling, pitch and drive initial /


extension piles head from site

No

6.70

6.70

75.00

75.00

10.00

10.00

19.00

19.00

TM

TM

77.40

77.40

G Cut piles to required level, dispose off


surplus piles head from site

No

60.00

58.33

30.00

30.00

25.00

25.00

25.00

25.00

TM

TM

54.53

54.53

H Provide all labour, temporary staging


kentledge testing equipment etc and
test load 300mm x 300mm rc test pile
up to 60 tons

No

TM

TM

TM

TM

5,000.00 5,400.00

7,500.00 7,500.00 5,500.00 5,500.00

9,600.00 9,600.00

BRIDGE WORKS
Earthwork
m3

13.00

12.33

TM

TM

10.00

8.14

10.50

10.50

TM

TM

18.00

25.47

A 50mm thick blinding concrete Grade 10/20

m2

12.50

12.17

TM

TM

15.00

15.00

7.50

7.50

TM

TM

70.30

110.10

B 50mm thick blinding concrete Grade 15/20

m2

13.70

12.85

180.00

180.00

13.40

13.47

7.50

7.50

TM

TM

52.60

113.53

C Concrete Grade 25/20 in approach slab

m3

242.50

242.50

TM

TM

TM

TM

220.00

220.00

TM

TM

330.00

351.17

D Concrete Grade 30/20 in approach slab

m3

275.00

276.67

TM

TM

TM

TM

350.00

350.00

TM

TM

329.95

329.95

E Concrete Grade 40/20 in approach slab

m3

285.00

278.33

280.00

280.00

300.00

290.44

390.00

390.00

TM

TM

350.00

348.08

F Concrete grade 35/20 as specified in pier foundation m3


abutment, diaphgram, caping beam or deck slab

295.00

278.00

260.00

260.00

250.00

250.00

350.00

350.00

TM

TM

321.90

321.90

G Concrete grade 40/20 as specified ditto

302.50

288.75

TM

TM

311.10

300.55

390.00

390.00

TM

TM

350.00

346.42

TM
TM

TM
TM

4,800.00 4,473.33 2,700.00 2,700.00


4,200.00 4,200.00 2,700.00 2,700.00

TM
TM

TM
TM

4,215.00 4,215.00
4,299.00 4,299.00

tonne 4,250.00 3,925.00 5,000.00 5,000.00 3,600.00 3,733.33 2,700.00 2,700.00


tonne 4,150.00 3,850.00 5,000.00 5,000.00 4,200.00 4,200.00 2,700.00 2,700.00

TM
TM

TM
TM

5,000.00 4,518.58
5,000.00 4,546.83

TM

TM

42.50

42.23

TM
TM
TM
TM
TM

TM
TM
TM
TM
TM

18,333.00
26,666.00
46,375.00
59,833.00
77,500.00

18,333.00
26,666.00
46,375.00
59,833.00
77,500.00

Excavate in all material except rock to


any depth for structural foundation,
backfill with suitable material and
remove from site
Concretor

H Mild steel reinforcement supplied, cut


to length, bent and binding wires:
a) 12mm diameter and below
b) 16mm diameter and above
J

High tensile reinforcement supplied, cut to


length, bent and binding wires:
a) 12mm diameter and below
b) 16mm diameter and above

K Formwork

m3

tonne 4,100.00 3,646.67


tonne 4,040.00 3,580.00

m2

35.50

36.00

40.00

40.00

35.00

a) 'I' Beams
i. 10m length
ii. 20m length
iii. 30m length
iv. 32m length
v. 40m length

No
No
No
No
No

12,950.00
23,400.00
45,800.00
48,750.00
77,500.00

b) 'M' Beams
i. 10m length
ii. 24m length
iii. 30m length

No
No
No

10,000.00 10,000.00
30,000.00 30,000.00
45,000.00 45,000.00

TM
TM
TM

TM
TM
TM

c) 'T' Beams
i. 10m length
ii. 18m length
iii. 24m length
iv. 30m length

No
No
No
No

14,200.00
27,150.00
45,800.00
51,250.00

14,200.00
27,150.00
47,266.67
51,250.00

TM
TM
TM
TM

TM
TM
TM
TM

TM
TM
TM
TM

d) 'Y' Beams
i. 10m length
ii. 20m length
iii. 30m length

No
No
No

10,000.00 10,000.00
30,000.00 30,000.00
45,000.00 45,000.00

TM
TM
TM

TM
TM
TM

34.85

36.00

36.00

Beams
A Precast prestressed reinforced conrete members
including launching and fixing in position.

12,950.00
TM
TM
26,500.00 31,331.73
TM
TM
23,400.00 36,000.00 36,000.00
TM
TM
28,560.00 28,560.00
47,766.67
TM
TM
TM
TM
TM
TM
48,750.00
TM
TM
TM
TM
TM
TM
77,500.00
TM
TM
TM
TM
TM
TM

15,800.00 15,800.00
TM
TM
TM
TM

TM
TM
TM

TM
TM
TM

TM
TM
TM

TM
TM
TM

23,333.00 23,333.00
26,442.00 26,442.00
51,875.00 51,875.00

TM
TM
TM
TM

TM
TM
TM
TM

TM
TM
TM
TM

TM
TM
TM
TM

TM
TM
TM
TM

24,167.00 24,167.00
TM
TM
51,313.00 51,313.00
58,444.00 58,444.00

TM
TM
TM

TM
TM
TM

TM
TM
TM

TM
TM
TM

TM
TM
TM

TM
TM
TM

26,000.00 26,000.00
49,333.00 49,333.00
71,667.00 71,667.00

Bridge Bearings
B Supply and install 350mm x 200mm x 57mm thick
laminated bearing pad

No

380.00

380.00

TM

TM

383.75

529.38

185.00

185.00

TM

TM

710.50

710.50

C Supply and install 400mm x 350mm x 70mm thick


laminated bearing pad

No

600.00

600.00

TM

TM

TM

TM

TM

TM

TM

TM

m
m
m

300.00
800.00
100.00

300.00
800.00
100.00

TM
TM
TM

TM
TM
TM

TM
25.00
TM

TM
24.73
TM

TM
TM
TM

TM
TM
TM

TM
TM
TM

TM
TM
TM

389.00
820.00
125.00

389.00
820.00
125.00

No

80.00

80.00

TM

TM

TM

TM

TM

TM

TM

TM

72.90

72.90

No

100.00

100.00

TM

TM

31.50

27.83

TM

TM

TM

TM

64.40

64.40

B Supply and install 100mm diameter


porous concrete pipe behind abutment

24.00

24.00

TM

TM

45.00

91.33

23.00

23.00

TM

TM

40.00

40.00

C Ditto 150mm diameter UPVC drainage outlet pipe

74.00

74.00

TM

TM

TM

TM

TM

TM

TM

TM

51.60

51.60

1,147.00 1,147.00

Bridge Bearings (cont'd)


A Movement Joints
a) Transflex 250 or equivalent expansion joint
b) Thorma joint or equivalent
c) 6mm Thick compressible joint filler
d) 32mm Dia. high yield dowel bar 600mm long
with rubber cap and compressible joint filler
e) 32mm Dia.high yield dowel bar 750mm long
with rubber cap and compressible joint filler

TM - tiada maklumat
Kaw A - Pulau Pinang, Kedah & Perlis
Kaw B - Perak
Kaw C - Kuala Lumpur, Selangor, Nergeri Sembilan & Melaka
Kaw D - Johor
Kaw E - Pahang
Kaw F - Kelantan Terengganu

IU CIVIL/1of1