HINDUSTAN AERONAUTICS LIMITED


BANGALORE COMPLEX
FACILITIES MANAGEMENT DIVISION

FM/NE-P/EC-2535/716/2014

Dear Sir[s],
Clarification No.-1

Sub: Design, supply, installation, testing and commissioning of 100 KWp roof top
Solar photo voltaic power plant including 5 years Comprehensive
Maintenance at Administrative Building, HAL(BC)."
Cont.No.HAL/FMD/EC-2535/14-15.


The following queries were raised by some of the intending tenderers towards the subject
work. The point wise clarification for the same is as follows and to be noted by all intending tenderers.

Sl.
No.
Clarification Sought References
indicated
Clarification
1. Power performance ratio shall be lower
than 70% in the morning and evening
slots. It will also be low in peak time due
to high temperature in peak time. Hence
please relax the clause for guarantee of
only Energy performance ratio.
Technical
specification
para. 3.1.11 b
of page 70 of
110
Not agreed. To be complied as per
technical specifications.
2. Does the class I licence for electrical
contractor required shall be of Karnataka
or licence of other states work as well?
Tender notice
sl.no. 1.1 ii)
Any state class I Electrical licence is
acceptable
3. Does contractor has the freedom to
choose makes of material with prior
approval from HAL?
Approved
make list
Page No.95 of
110
Tenderer should supply items as per
Approved make if available.
Otherwise, tenderer can supply any
standard make meeting technical
specification with prior approval of
HAL.
4 MNRE Subsidy arrangement is fine to
be done by the EPC, but whether HAL
would bring the subsidy from MNRE
directly(being government organization,
they have this option). This is not clear
from the RFP.
Technical
Specification
Para 1 Page
68 of 110
Tenderer to make necessary
arrangements for claiming the
subsidy from MNRE.
5 Whether HAL would allow SECI
bidders to bid for their project? If yes,
then it is not a level playing field for all
the bidders since bidders who won SECI
project would have a clear advantage.
The tenders are called in open mode.
Clarification is not required.
6 A lot of trees around Building rooftop
which may cast shadows at different
points on the roof throughout the year.
The RfP asks for a contracted
performance against which we need to
provide a guarantee. We believe that we
will not able to provide such guarantees
unless we do a thorough shadow analysis
or we get a guarantee from you that such
obstructions will be cleared for the
project and will remain clear during the
period of the contract.
Technical
specification
para. 3.1.11 b
of page 70 of
110
Para 3.10 of
Page 75 of
110
The power plant layout should be
optimized based on the results of
shadow analysis to derive the
maximum output. HAL will arrange
for trimming of tree branches if
required.
PDF created with pdfFactory trial version www.pdffactory.com
01/07/2014
Page 2 of 2

7 Extend the Date of opening of tender Not agreed
8 The channel partner cannot execute the
project without getting approval from
MNRE. Hence HAL clause of finishing
the project within a time frame of
5months, can be a trouble. As we know
that MNREs window for subsidy opens
once in a year and we depend on their
discretion for subsidy, its our sincere
request the time taken by MNRE for
subsidy approval additional to time
provided for installation and
commissioning of the project.
General
Conditions of
Contract
Clause No.20
Page 32 of
110
Special
conditions of
Contract
Clause No 23
Page 48 of
110
The time period of 5 months includes
the time required for MNRE sanction
and commissioning of the plant. Any
delays will be dealt with as per the
terms of the contract.


This clarification No.1 will also be a part of Tender Document.

Thanking you,
Yours faithfully,
For HINDUSTAN AERONAUTICS LIMITED,

Sd/-
( A. JUDITH PERCY )
MANAGER (WORKS),
FACILITY MANAGEMENT DIVISION.