CONSTRUCTION OF WEST

BAY BLOCK -2500






QATAR BUILDING COMPANY

NARRATIVE STATEMENT FOR
PROGRAMME




PROJECT SUMMARY:

PROJECT NAME:
Roads and Infrastructure in west Bay Block 2500
PROJECT LOCATION AND SCOPE:
The site is located approximately 10km north of the centre of Doha, Qatar. The project area is irregular
in shape and covers an area of approximately 70.5 Hectares (Ha).The eastern boundary of the site is
defined by West Bay Lagoon gated community with associated residential properties and infrastructure.
The northern boundary is defined by a dual lane highway with Doha Golf Club beyond. Al Jamiaa Street
defines the western boundary of the site, with a Wadi present immediately to the west of this road and
Qatar University beyond. The southern boundary is defined by West Bay Lagoon Street.
The site is currently in the early stages of development with some temporary roads constructed,
comprising tarmac roads with no kerbs or footpaths. Although the majority of the West Bay Block 2500
site is still to be developed, there are areas where large villas that have been completed or are under
construction with some already occupied. In addition, a large development for the Supreme Education
Council is under construction at the southern end of the site with associated access roads and
infrastructure. A number of completed substations were identified within West Bay Block 2500. Some
utilities have been laid, consisting of water, electricity, telecommunication and sewerage with no road
drainage on site.
The project will provide infrastructure, roads, drainage and utilities, for approximately 80residential
plots, a mosque, recreation parks, few governmental public institution and Supreme Education Council
(currently under construction) occupying a substantial portion at the southern end of this development
with an internal and perimeter highway network of roads within a 16m wide corridor. The proposed
road network will contain simple priority junctions, including right-in/right-out junctions and tie-ins to
existing Al Jamiaa Street and Golf Course Street.

Submitted Programme is draft programme and detail programme will be submitted after
commencement
PROJECT INFORMATION
EMPLOYER
PUBLIC WORKS AUTHORITY
INFRASTRUCTURE AFFAIRS
PROJECT MANAGEMENT (ROADS)
PROJECT MANAGEMENT
CONSULTANT
To be identified
DESIGN & SUPERVISION
CONSULTANT
To be identified
MAIN CONTRACTOR QATAR BUILDING COMPANY
CONTRACT VALUE QR.53,457,853
CONSTRUCTION PERIOD 310 Days
MAINTENANCE PERIOD 400 Days

Based on the below productivity details, durations are calculated and its
sequenced by traditional method for each and every activity and ensures
that satisfying the contractual and codal requirements.

Activity Unit Productivity
Site Clearance Ha 1000 SQ.M/Day
Removal of road furnitures Same as site Clearance
Excavation & Disposal Cu.m 200 Cu.m/Day
Filling Cu.m Same as excavation
Granular Sub-base SQ.M 550 SQ.M/Day
Bituminous base 1
st
layer SQ.M 650 SQ.M/Day
Bituminous base 2
nd
layer SQ.M 650 SQ.M/Day
Bituminous wearing course SQ.M 650 SQ.M/Day
Fixing of Kerb LM 80 LM/Day
Semi-rigid barrier LM 100 LM / Day
Street lighting poles Nos 10 Nos / Day
Street lighting cables LM 50 LM/Day
Fixing of Paving block for footway SQ.M 75 SQ.M/Day
Water works
(incl. protection works, pipeline works,
abandon water pipes & alteration of
chamber)
Water works will start parallelly with excavation works and it will
be completed before surface preparation works
Electricity works
(incl. duct works, and existing cable
protection HV,MV & EHV cables)
Electricity works will start parallelly with excavation works and it
will be completed before surface preparation works
Q-tel works
(incl. Duct work, existing duct protection
& manhole alteration)
Q-tel works will start parallelly with excavation works and it will
be completed before surface preparation works
QAF works
(Duct works)
QAF works will start parallelly with excavation works and it will be
completed before surface preparation works
TSE line
(Protection of existing line, Relocation of
existing distribution chamber and
proposed valve chamber)
TSE works will start parallelly with excavation works and it will be
completed before surface preparation works
Road Drainage works
(Gullies, Soakway, Catch pit, Connection
pipeline, storm water manhole)
Road Drainage works will start parallelly with excavation works
and it will be completed with granular sub-base layer

Street lighting works
(incl. Duct & cable laying works & street
lighting works)
Street lighting works will be start parallelly with excavation works
and it will be completed with finishing works
Traffic signaling works
(incl. Duct & cable laying works,
Inspection chamber, fixing of gantry &
signaling works)
Signaling works will be start parallelly with excavation works and
it will be completed with finishing works
Road furniture works (Traffic signs, road
markings and signaling equipment)
All road furniture works, cleaning and demobilization works will
be completed within 12 days from completion of bituminous
works