The document provides details of the construction project for roads and infrastructure in West Bay Block 2500 in Doha, Qatar. The project will develop roads, drainage, utilities and infrastructure to support approximately 80 residential plots, a mosque, parks, and governmental buildings on a 70.5 hectare site. Qatar Building Company will undertake the QR 53,457,853 project over a 310 day construction period and 400 day maintenance period. The project involves excavation, road works, utility works, drainage, lighting, signage and landscaping according to a schedule of productivity rates.
Descrição original:
Título original
Programme Narrative of Roads and Infrastructure in West Bay Block a 2500 (1)
The document provides details of the construction project for roads and infrastructure in West Bay Block 2500 in Doha, Qatar. The project will develop roads, drainage, utilities and infrastructure to support approximately 80 residential plots, a mosque, parks, and governmental buildings on a 70.5 hectare site. Qatar Building Company will undertake the QR 53,457,853 project over a 310 day construction period and 400 day maintenance period. The project involves excavation, road works, utility works, drainage, lighting, signage and landscaping according to a schedule of productivity rates.
The document provides details of the construction project for roads and infrastructure in West Bay Block 2500 in Doha, Qatar. The project will develop roads, drainage, utilities and infrastructure to support approximately 80 residential plots, a mosque, parks, and governmental buildings on a 70.5 hectare site. Qatar Building Company will undertake the QR 53,457,853 project over a 310 day construction period and 400 day maintenance period. The project involves excavation, road works, utility works, drainage, lighting, signage and landscaping according to a schedule of productivity rates.
PROJECT NAME: Roads and Infrastructure in west Bay Block 2500 PROJECT LOCATION AND SCOPE: The site is located approximately 10km north of the centre of Doha, Qatar. The project area is irregular in shape and covers an area of approximately 70.5 Hectares (Ha).The eastern boundary of the site is defined by West Bay Lagoon gated community with associated residential properties and infrastructure. The northern boundary is defined by a dual lane highway with Doha Golf Club beyond. Al Jamiaa Street defines the western boundary of the site, with a Wadi present immediately to the west of this road and Qatar University beyond. The southern boundary is defined by West Bay Lagoon Street. The site is currently in the early stages of development with some temporary roads constructed, comprising tarmac roads with no kerbs or footpaths. Although the majority of the West Bay Block 2500 site is still to be developed, there are areas where large villas that have been completed or are under construction with some already occupied. In addition, a large development for the Supreme Education Council is under construction at the southern end of the site with associated access roads and infrastructure. A number of completed substations were identified within West Bay Block 2500. Some utilities have been laid, consisting of water, electricity, telecommunication and sewerage with no road drainage on site. The project will provide infrastructure, roads, drainage and utilities, for approximately 80residential plots, a mosque, recreation parks, few governmental public institution and Supreme Education Council (currently under construction) occupying a substantial portion at the southern end of this development with an internal and perimeter highway network of roads within a 16m wide corridor. The proposed road network will contain simple priority junctions, including right-in/right-out junctions and tie-ins to existing Al Jamiaa Street and Golf Course Street.
Submitted Programme is draft programme and detail programme will be submitted after commencement PROJECT INFORMATION EMPLOYER PUBLIC WORKS AUTHORITY INFRASTRUCTURE AFFAIRS PROJECT MANAGEMENT (ROADS) PROJECT MANAGEMENT CONSULTANT To be identified DESIGN & SUPERVISION CONSULTANT To be identified MAIN CONTRACTOR QATAR BUILDING COMPANY CONTRACT VALUE QR.53,457,853 CONSTRUCTION PERIOD 310 Days MAINTENANCE PERIOD 400 Days
Based on the below productivity details, durations are calculated and its sequenced by traditional method for each and every activity and ensures that satisfying the contractual and codal requirements.
Activity Unit Productivity Site Clearance Ha 1000 SQ.M/Day Removal of road furnitures Same as site Clearance Excavation & Disposal Cu.m 200 Cu.m/Day Filling Cu.m Same as excavation Granular Sub-base SQ.M 550 SQ.M/Day Bituminous base 1 st layer SQ.M 650 SQ.M/Day Bituminous base 2 nd layer SQ.M 650 SQ.M/Day Bituminous wearing course SQ.M 650 SQ.M/Day Fixing of Kerb LM 80 LM/Day Semi-rigid barrier LM 100 LM / Day Street lighting poles Nos 10 Nos / Day Street lighting cables LM 50 LM/Day Fixing of Paving block for footway SQ.M 75 SQ.M/Day Water works (incl. protection works, pipeline works, abandon water pipes & alteration of chamber) Water works will start parallelly with excavation works and it will be completed before surface preparation works Electricity works (incl. duct works, and existing cable protection HV,MV & EHV cables) Electricity works will start parallelly with excavation works and it will be completed before surface preparation works Q-tel works (incl. Duct work, existing duct protection & manhole alteration) Q-tel works will start parallelly with excavation works and it will be completed before surface preparation works QAF works (Duct works) QAF works will start parallelly with excavation works and it will be completed before surface preparation works TSE line (Protection of existing line, Relocation of existing distribution chamber and proposed valve chamber) TSE works will start parallelly with excavation works and it will be completed before surface preparation works Road Drainage works (Gullies, Soakway, Catch pit, Connection pipeline, storm water manhole) Road Drainage works will start parallelly with excavation works and it will be completed with granular sub-base layer
Street lighting works (incl. Duct & cable laying works & street lighting works) Street lighting works will be start parallelly with excavation works and it will be completed with finishing works Traffic signaling works (incl. Duct & cable laying works, Inspection chamber, fixing of gantry & signaling works) Signaling works will be start parallelly with excavation works and it will be completed with finishing works Road furniture works (Traffic signs, road markings and signaling equipment) All road furniture works, cleaning and demobilization works will be completed within 12 days from completion of bituminous works