Você está na página 1de 119

Shelter Projects 2008 INTRODUCTION

Foreword

Shelter Options 2008

Much has been written over the years about the challenge of providing shelter for households affected by crises, whether
they are human-made or result from natural events. In spite of the many reports commissioned by governments, donors,
independent experts, multilateral and international aid organizations that provide a variety of recommendations on issues
ranging from design to cost analysis methods, shelter remains one of the most controversial and challenging components of
sustainable recovery from disasters.

In recent years, the humanitarian community has looked inward, learning from their past experiences in providing emergency
shelter for the ever-increasing number of populations suffering from crises worldwide. The humanitarian reform process has
helped widen the community of practitioners, reinforced global and country-based coordination systems, and required the
agencies concerned to seek new and better means of ensuring integrated and robust humanitarian programming.

This publication is an example of a series of learning tools being produced to support improved response to crises. It has
been developed by the Emergency Shelter Cluster through a group of agencies within the cluster led by UN-HABITAT.
It contains summaries of a range of experiences applied in crisis situations, and an honest appraisal of their successes and
failures. From these, a number of key principles emerge.

One key principle is that the survivors of these crises must be given every opportunity to engage in their own recovery.
!EO=OPAN=BBA?PA@DKQOADKH@OODKQH@JKHKJCAN>APNA=PA@=OHE=>EHEPEAO1DEOD=OOECJEł?=JPEILHE?=PEKJOKJNA?KIIAJ@A@
approaches to post-disaster shelter and settlement responses, several of which are well illustrated in the case studies in this
publication.

A second principle is that without immediate strategic planning covering land use, tenure, livelihoods and critical services, in
addition to shelter options, there is a danger that temporary solutions become, de facto, permanent ones. As well as failing
to address the risks and vulnerabilities that may have contributed to the scale of the crisis, poor or inadequate programmatic
responses can increase shelter and settlement vulnerabilities. A number of the case studies illustrate these considerations.

A third principle follows from the above – that is, all change demands social mobilization, the involvement of the affected
population and the appropriate local authorities, and legal compliance. Immediate shelter solutions must therefore consider
long-term settlement issues, both for temporarily displaced populations and those who are able to return to the location of
PDAEN@=I=CA@KN@AOPNKUA@ODAHPANO1DA?QHPQN=H OK?E=H=J@A?KJKIE?JKNIOKBPDAOLA?Eł?@EO=OPAN=BBA?PA@OK?EAPEAOIQOP
>ANAŃA?PA@EJODAHPAN=J@OAPPHAIAJPNAOLKJOAOPD=PI=ULKPAJPE=HHU>A?KIA@QN=>HA N=PDANPD=JPN=JOEAJP EJJ=PQNA+KJ
tent based emergency shelter solutions that are rapid and cost effective can also be culturally acceptable to the populations
they are designed for, in both the short term and over a longer period of recovery. This publication highlights a number of
such examples.

łJ=HLNEJ?ELHABKHHKSOBNKIPDAPDNAAKQPHEJA@=>KRA-QPPEJCLAKLHAĠOQNRERKNO=J@RE?PEIO
łNOP LH=JJEJC=J@LNKCN=IIEJC
EJ=@R=J?A ?KJOE@ANEJCPDALKPAJPE=HKBHKJCANPANIOKHQPEKJO =J@łJ=HHU ?NA=PEJCOL=?APK=@@NAOOH=J@=J@LNKLANPU>=OA@
losses following a crisis, all contribute to reducing demand on humanitarian capital while maximizing potential opportunities
for recovery.

1DANA=NAI=JUIKNAHAOOKJOEJPDEO>KKGPD=PSEHH>AKB>AJAłPPKPDANA=@AN,J>AD=HBKBKQN=CAJ?EAO =J@EJ?KHH=>KN=PEKJ
with our interagency partners from the Emergency Shelter Cluster, we encourage the study and widespread use of these
lessons.

i
INTRODUCTION Acknowledgments

Acknowledgments

Project coordinated by UN-HABITAT on behalf of the Emergency Shelter Cluster: Esteban Leon, Joseph Ashmore
Edited by: Joseph Ashmore
Lead authors: Joseph Ashmore (Asia, LAC), Jon Fowler (Africa), James Kennedy (Sri Lanka, Cuny Center).
Authors (specific sections): Eddie Argenal (Peru - self-build transitional shelters), Milton Funes (Honduras), Dave Hodgkin
(Jogyakarta), Kurt Rhyner (Peru - community mobilisation).
Editiorial support: Seki Hirano

Special thanks: The authors would like to give special thanks to the following people for providing case study information,
editing drafts, and for providing the photographs:

Hassan Abdalla, Subhan Ahmadov, Eddie Argenal, Dyfed Aubrey, Lizzie Babister, Eric Baranick, Rick Bauer, Isaac Boyd, Joana
Cameira, Michelle Carter, Chris Cattaway, John Flomo, Tom Corsellis, Milton Funes, Valle Galan, Catherine-Lune Grayson,
Jens Grimm, Anamul Haque, John Howard, Cynthia Jones, Yasmin Keith-Krelik, Peter Krouwel, Unni Lange, Mark Lawler,
Dan Lewis, Manoucher Lolachi, Julia Macro, LeGrand Lee Malany, Bill Marsden, Tom McKnight, Jelena Milosevic, Douglas
Osmond, Paul Neale, Nicole Poirier, Anna Pont, Albert Reichert, Adelmo Risi, David Sanderson, Qurat Sadozai, Graham
Saunders, Hassan Noor Saadi, Anna Maria Sellari, Charles Setchell, Thierry Schweitzer, Alister Shields, Jo Da Silva, Joana
Sousa, Mikael Adri Budi Sulistyo, Wondwossen Teffera, Ombretta Tempra, Kim Williamson, Matthias Wohlfeil, Jake Zarins.

Additional thanks to the Cuny Center in Washington DC, USA for allowing access to the documents that have provided the
case studies in Section D.

A final thanks to all of the field staff who have worked so hard to make all of these projects possible.

Copyright notice:
The copyright for this booklet is retained by UN-HABITAT. Reproduction for non-profitable objectives is encouraged.
The copyright for the photographs remains with the photographers whose names are indicated on each photograph.
While every effort has been made to ensure the accuracy and completeness of the content of this book, no liability can be
accepted for any errors or omissions contained within it.

ii
Shelter Projects 2008 INTRODUCTION

Contents

Introduction
Foreword on behalf of the cluster i
Acknowledgments ii
Contents iii
Introduction iv
Overview of Case Studies v
Section A - Africa......................................................................................................................... 1
A.1 D.R. Congo - Goma - 2002 - Volcano - Distribution and technical support 2
 "NEPNA= KJŃE?P =ILQLCN=@AO 
A.3 Kenya - 2007- Flooding - Shelter and disaster mitigation 8
A.4 Kenya - 2008- Election violence - Transitional shelter kits 11
 )E>ANE=&!- /ABQCAAO0AHB>QEH@ODAHPANO 
A.6 Mozambique- 2007- Cyclone - Shelter material packages and training 17
A.7 Rwanda - 2008 - Returns - Materials distribution and technical guidance 20
 0KI=HE= EREH?KJŃE?P/AOAPPHAIAJP 
 !=NBQNĠKJCKEJC
 KJŃE?P*=PANE=HO@EOPNE>QPEKJ 
Section B - Asia............................................................................................................................ 29
B.1 Afghanistan - 2002 - Returns - Shelter construction 30
 VAN>=EF=J KJŃE?P-AKLHA@EOLH=?A@2LCN=@AKB?KHHA?PERA?AJPNAO 
B.3 India - Gujarat - 2001 - Earthquake - Non-food items and shelters 36
B.4 Indonesia - Aceh - 2004 - Tsunami and earthquake - Shelter or housing? 39
 &J@KJAOE= 'KCU=G=NP="=NPDMQ=GA,RANREASKBPDANAOLKJOA 
 &J@KJAOE= 'KCU=G=NP="=NPDMQ=GA =OD=J@1N=JOEPEKJ=HODAHPAN 
 &J@KJAOE= 'KCU=G=NP="=NPDMQ=GA"IANCAJ?U=J@PN=JOEPEKJ=HODAHPAN 
 &JCQODAPE= KJŃE?P-AKLHA@EOLH=?A@ =ODBKNODAHPANDKOPB=IEHEAO 
 -=GEOP=J"=NPDMQ=GA,RANREASKBPDAA=NPDMQ=GANAOLKJOA 
-=GEOP=J"=NPDMQ=GA1N=JOEPEKJ=HODAHPAN?KJOPNQ?PEKJ 
 -=GEOP=J"=NPDMQ=GA0DAHPANI=PANE=HO@EOPNE>QPEKJ 
 0NE)=JG= KJŃE?PNAPQNJO KNAODAHPAN 
B.13 Sri Lanka - 2004 - Tsunami - Overview of the tsunami response 64
B.14 Sri Lanka - 2004 - Tsunami - Transitional shelter construction 66
Section C - Latin America and Caribbean............................................................................ 69
C.1 Honduras - 1998 - Hurricane Mitch - Transitional shelter 70
C.2 Peru - 2007- Earthquake - Overview of the response 73
C.3 Peru - 2007 - Earthquake - Community mobilisation 74
C.4 Peru - 2007 - Earthquake - Self-build transitional shelters 77
 -ANQ"=NPDMQ=GA-NAB=>NE?=PA@PN=JOEPEKJ=HODAHPANO 
Section D - Historical Case Studies........................................................................................ 83
D.1 Historical case studies - Overview - Case studies from the Cuny Centre 84
! &J@E= KJŃE?P/ABQCAAO#ENOP?=ILLH=JJEJCCQE@AHEJAO 
D.3 Nicaragua- 1973 - Earthquake - Small Camp 89
! =JCH=@AOD KJŃE?P-AKLHA@EOLH=?A@0DAHPANQLCN=@AO 
! $Q=PAI=H="=NPDMQ=GA*=PANE=HO@EOPNE>QPEKJ=J@PN=EJEJC 
D.6 India - Andhra Pradesh - 1977 - Cyclone - Materials distribution and training 97
! 1D=EH=J@-KHEPE?=H?KJŃE?P/ABQCAA?=IL 
D.8 Tonga - 1982 - Cyclone Isaac - Disaster mitigation 102
! 0Q@=J KJŃE?P-H=JJA@?=ILO 

Annex - Further reading................................................................................................. 109

iii
INTRODUCTION Introduction

Introduction
The case studies in this book are While the number of people made Selection of case studies
of real shelter projects that have been newly homeless in 2007 was in excess Given the scale of emergency
EILHAIAJPA@ "=?D LNKFA?P EO OLA?Eł? KB  IEHHEKJ  = OECJEł?=JP LNKLKNPEKJ shelter need every year, the case
to an individual context and is the of people are not able to return to studies in this book focus on imple-
outcome of local assessments and their place of origin for many years. mented projects rather than small-
monitoring. As a result, the total number of people scale trials or concepts that were
None of the case studies in displaced in the world has remained not implemented on any scale. There
roughly constant at approximately is also a regional bias towards Africa
this book should be directly 15 million refugees2 and a further and Asia, where the post-disaster and
copied. 25 million internally displaced people LKOP?KJŃE?PODAHPANJAA@O=NAH=NCAOP
Ġ&!-O
3.
Because these projects were imple- The case studies were selected
mented in diverse and often challenging according to the following criteria:
&!-AOPEI=PAO>UNACEKJĠ

conditions, they illustrate both good


and bad practices. From every case /ACEKJ Number of IDPs Š The shelter project had to have
study there are lessons that should countries ĠIEHHEKJO
been implemented in full.
be learned, and aspects that should be Africa 20 12.7 Š A minimum of 500 families were
repeated or avoided elsewhere. sheltered by the project's activities.
Americas 4 4.2 Š The project was implemented
Global shelter need Asia and 18 6.6 H=NCAHU SEPDEJ PDA łNOP UA=N BKHHKSEJC
It is estimated that over 5 million Middle =J=PQN=H@EO=OPAN#KN?KJŃE?P=BBA?PA@
LAKLHASANAI=@ADKIAHAOO>U?KJŃE?P East populations, chronic emergencies and
and natural disasters in 20071. This cor- returns processes, longer timescales
Europe 10 2.5
responds to approximately 1 million were considered.
families. While the largest proportion Total 52 26
Š Accurate project information was
KB LAKLHA I=@A DKIAHAOO >U ?KJŃE?P available from the staff involved in the
are in Africa and the Middle East, the Estimated number of people project implementation.
majority of those made homeless by made homeless by natural
natural disasters are in Asia. Although @EO=OPANOĠKPDANPD=J@NKQCDP

the numbers of people displaced by 2000-20084 The case studies that have been
?KJŃE?P=J@J=PQN=H@EO=OPANOKRANPDA selected are intended to illustrate a
/ACEKJ Number of
past ten years run into the several diversity of approaches to helping
homeless
IEHHEKJO PDAU=NAOECJEł?=JPHUHKSANEJ meet shelter need. Most of them go
ĠEJIEHHEKJO

Latin America and the Caribbean than beyond ‘throwing shelter relief items
in Africa, the Middle East and Asia. Africa 2 off the back of a lorry’ or delivering
Asia 20 shelters as a design or a product.
There are approximately 40 Latin America 1.5
million refugees and internally and Carribean
displaced people in the world - Ġ)

people who have been forced Europe 0.1


to leave their homes... North America 0.1

1DEOłCQNAS=ONA=?DA@>U?KI>EJEJC PDAłCQNABNKIPDA"IANCAJ?U"RAJPO!=P=>=OAĠDPPLġSSSAI@=P>A
BKNPDA
JQI>ANKBLAKLHAI=@ADKIAHAOOSEPDPDAłCQNAKBIEHHEKJJAS&!-OMQKPA@EJInternal displacement: Global overview of
trends and developments in 2007Ġ&JPANJ=H!EOLH=?AIAJP*KJEPKNEJC AJPNA
1DEOłCQNAAT?HQ@AOJASNABQCAAO
2. A refugee is a person who has crossed an international border and is unable to return through well-founded fear of
LANOA?QPEKJĠOAA2+% /Handbook for Emergencies N@A@EPEKJ  BKN=BQHHAN@AłJEPEKJ

&!-O=NA>NK=@HU@AłJA@=OLAKLHASDKD=RA>AAJBKN?A@PKŃAAPDAENDKIAOOQ@@AJHUKNQJATLA?PA@HUEJH=NCAJQI>ANO
=O=NAOQHPKB=NIA@?KJŃE?P EJPANJ=HOPNEBA OUOPAI=PE?REKH=PEKJKBDQI=JNECDPOKNJ=PQN=HKNI=JI=@A@EO=OPANO=J@SDK
are within the territory of their country.
1DEO@=P=EOOKQN?A@BNKIPDA"IANCAJ?U"RAJPO!=P=>=OAĠDPPLġSSSAI@=P>A
KJ'QHU

iv
Shelter Projects 2008 INTRODUCTION

Overview of case studies

The case studies in this book cover Support the people affected  Sphere standards and in-
a diversity of projects, from support 1DA łNOP =J@ I=EJ ABBKNP EJ =HH @E?=PKNO ĠJJAT
 LNKRE@A ?KIIKJ
for families in collective buildings over responses is made by the people who standards on participation, initial as-
=JAECDPUA=NLANEK@ĠVAN>=EF=J 
 are themselves affected. Of the case sessment, monitoring and evaluation.
to emergency distributions of plastic studies listed in this book, the more
effective projects all had the close in- Supporting the people affected
sheeting within hours of an earthquake EO PDA łNOP LNEJ?ELHA KQPHEJA@ EJ PDA
Ġ'KCU=G=NP= 
!AOLEPAPDALNKFA?PO† volvement of the people affected, often
through existing community groups or guidelines of Transitional Settlement and
differences, there are many recurring Reconstruction after Natural Disasters
themes. Some of these themes are specially established committees.
ĠJJAT

discussed in the following pages.

Non-food item Shelter


Labour
distribution construction

Community
Transitional

Contracted
Household

Permanent

Technical
expertise
Shelter

Direct
Cash
!/ KJCK

A.2 Eritrea - 2002

(AJU=

Graphics: Transitional Settlement and Reconstruction after Natural Disasters


(AJU=

A.5 Liberia - 2007

A.6 Mozambique - 2007

/S=J@=

A.8 Somalia - 2007

A.9 Sudan - 2004

B.1 Afghanistan - 2002

B.2 Azerbaijan - 1997

&J@E=Ġ$QF=N=P


B.4 Indonesia - 2004

B.6 Indonesia - 2006

B.7 Indonesia - 2006

B.8 Ingushetia - 1999

B.10 Pakistan - 2006

B.11 Pakistan - 2006

B.12 Sri lanka - 2007

B.13 Sri lanka - 2005

C.1 Honduras -1998

C.3 Peru - 2007

C.4 Peru - 2007

C.5 Peru - 2007


Overview of assistance methods used in projects

v
INTRODUCTION Introduction
Settlement Options Phases of response Which is better: a high
The case studies illustrate support /AOLKJOAOPK@EO=OPANOKN?KJŃE?P=NA level of support for fewer
for disaster-affected people in a variety commonly split into the phases of: people or a lower level of
of settlements. These include host Š preparedness before the disaster; support for more people?
B=IEHEAO Ġ&JCQODAPE=  
 ?KHHA?PERA Š emergency response;
?AJPNAO ĠVAN>=EF=J  
 >KPD NQN=H Š the recovery phase; and Self-build and contractor models
Ġ-=GEOP=J 
=J@QN>=JĠ0KI=HE= 
 Š durable solutions. of construction
contexts, and planned and unplanned Many of the case studies include Different projects used different
?=ILOĠ=JCH=@AOD !
 shelter responses aimed at bridging ways of organising the labour required
the gap between emergency shelter to build shelters. The case studies in
&PS=ONAH=PERAHU@EBł?QHP and durable housing solutions. Housing Peru illustrate a mixture from self-build
PKłJ@?=OAOPQ@EAOKB programmes can take many years Ġ 
 PK OQLLKNPA@ OAHB>QEH@ Ġ 
 =L-
supporting host families. to complete, especially when imple- proaches, to contractors prefabricat-
mented on a large scale. The project ing shelter components that were then
Finding shelter with friends and EJ /S=J@= Ġ
 EHHQOPN=PAO = DKQOEJC ANA?PA@>UDKIAKSJANOĠ 
*=JUKB
relationsor by renting are common project that took two years to build the projects in this book provided car-
coping mechanisms for families who 220 houses. The speed of durable penters or masons to support self-build
have lost their house in a disaster. shelter construction can leave a gap, projects. In many projects, families were
%KSARAN  EP S=O @EBł?QHP PK łJ@ ?=OA with families in emergency shelter for provided with some money to either
studies of organisations providing many years. Transitional responses aim support them while building or to allow
support for hosting or rental arrange- to bridge this gap. them to employ others to build.
ments. Logistics and supply
A comparison of the strategies
Transitional settlement: displaced =@KLPA@ EJ ?AD Ġ
 =J@ 0NE )=JG= In many projects, logistics and
populations ĠJJAT
Ġ
 BKHHKSEJC PDA  POQJ=IE EH- OQLLHU EOOQAO D=@ OECJEł?=JP EIL=?PO
lustrates how long housing can take to on both the design of shelters and
In most case studies, the timescale for implementation. The
land ownership was a complete in comparison to transitional
scale of some procurements was huge
@AłJEJCB=?PKNEJSD=P projects. However, as the case studies
ĠAC $QF=N=P Ġ

 *=JU LNKFA?PO 
types of shelter support note, in implementing the transitional
response there should be a vision of OQ?D =O PDA KJA EJ %KJ@QN=O Ġ 

were offered. AILHKUA@OLA?Eł?ODAHPANHKCEOPE?OOP=BB
what is being transitioned to. Often,
Land ownership there is not follow-on funding or land to ensure that shelter projects were
Those without land are often E@AJPEłA@BKNLANI=JAJPDKQOAO implemented. Shelter staff had to work
among the most vulnerable people in closely with these staff members.
society. Approaches to land ownership Scale of programme
The responses illustrate the Assistance methods
varied between the case studies. For The case studies selected include:
AT=ILHA  EJ -ANQ Ġ  
 KNC=JEO=- challenge of whether to implement
high quality programmes for fewer giving money to host families,
tions built primarily only on the land of upgrading squatted communal blocks,
people who could offer proof of land people or poorer quality responses
to support more people. The case establishing an inter-agency pipeline of
title. Building lighter shelters allowed shelter items and constructing shelters
people to later move them. OPQ@EAOEJ-=GEOP=JĠ
EHHQOPN=PA
this challenge. One project delivered through both unpaid volunteers and
A more active approach to estab- materials to over 2% of the affected contractors.
lishing land for families is illustrated by population without support, while the &PS=O@EBł?QHPPKłJ@OQBł?EAJP@AP=EH
PDA?=OAOPQ@UEJ?AD &J@KJAOE=Ġ
other project built transitional shelters on projects where families were given
after the tsunami, where the organisa- for 0.2% of the affected population. vouchers that they could redeem with
tion helped to negotiate land with title certain suppliers, although according to
deeds for entire villages. anecdotal evidence this type of project
has been successfully conducted. No
case studies were found of loans being
provided to support families through
By using transportable shelter the emergency or transitional phases
materials, transitional shelter of the response.
solutions can sometimes be found Other sectors
until land rights issues are resolved Many of the more effective projects
Photo IFRC

were integrated with other sectors of


the response, especially water supply
and sanitation.
 1DA 0LDANA -NKFA?P ĠJJAT

provides useful guidance on integration
with other sectors.

vi
Shelter Projects 2008 INTRODUCTION

Photo: Joseph Ashmore


Effective shelter programmes are developed and implemented by involving the affected communities

(AU 
Duration of natural disaster
 !QN=PEKJKB?KJŃE?PKN@EOLH=?AIAJP
Duration of project
Africa
Asia
Latin America and Caribbean
C.3 Peru 2007 24 days Historical case studies
(AJU= 2 months
D.3 Nicaragua 1973 2 months
B.7 Indonesia, Jogyakarta 2006 2 months
C.4 Peru 2007 3 months
B.10 Pakistan 2006 3 months
A.9 Sudan 2004 3 months
B.12 Sri Lanka 2007 3 months
A.8 Somalia 2007 3 months
D.2 West Bengal 1971 4 months
C.1 Honduras 1998 4 months
B.11 Pakistan 2006 4.5 months
A.6 Mozambique 2007 5 months
A.5 Liberia 2007 6 months
C.5 Peru 2007 9 months
B.13 Sri lanka 2005 9 months
B.3 India, Gujarat 2007 10 months
D.6 India 1977 10 months
!/ KJCK 10 months
B.6 Indonesia, Jogyakarta 2006 10 months
D.9 Sudan 1985 1 year
(AJU= !=@==> 1 year
D.5 Guatemala 1976 13 months
/S=J@= 14 months
/QOOE= &JCQODAPE= 2 years
B.1 Afghanistan 2002 2 years
D.8 Tonga 1982 2½ years
D.4 Bangladesh 1975 3 years
B.4 Indonesia, Aceh 2004 3½ years
A.2 Eritrea 2004 10 years
B.2 Azerbaijan 1997 13 years
D.7 Thailand 1979 14 years
5

10
Pr
3
6 nth rt
9 nth
1 nth

ye
m t st
m s
m s
ye s

ye
oj

ye
o a
o
o

a
ec

ar

ar

rs

a
s

rs

Duration of project
Illustration of the duration of the case studies

vii
INTRODUCTION Introduction

Shelter design
For most projects, the design of
the shelters themselves was less chal-
lenging than the design and planning of
the shelter project.
Many projects that built shelters left
the design and construction of shelters

Photos: Joseph Ashmore


to the people affected, focusing instead
on ensuring that people had the means
to build them or the support to build
them safely.
All of the projects that successfully
?KJOPNQ?PA@=OLA?Eł?IK@AHKBODAHPAN
developed the basic shelter model in
direct consultation with affected com- Left: Design for a timber-free domed shelter proposed as a response to an earthquake
munities, taking into account their in 2005. Affectees were not involved in the design and it was not used on any scale.
skills, capacities and resources.
Right: Shelter using reclaimed materials built by affectees weeks after the earthquake.
Shelters such as this were common and supported by programmes of toolkits and
corrugated iron distribution (see case studies B.10-B.12) .
‘If 3.5m2 per person cannot
be achieved, or is in excess
of the typical space used by
the affected or neighbouring covered living space

2
Shelter size

48m
population, consideration
The illustration below shows the
should be given to the
diversity of shelter-covered areas in
impact on dignity, health these case studies. These vary from
and well-being of the people 9m2Ġ 
PKI2 Ġ
1DEOEO=NAOQHP
accommodated...’ of varying needs, permanency, budgets,
2

logistics constraints, host standards


36m

- A guidance note to the =J@KBł?E=HLKHE?EAO


Sphere (Annex) shelter and
settlement standard for
2
2

25m
24m
21m 2

7 people x 3.5m2
2
5m
2
6m 2
20m
20.
2

6 people x 3.5m2
18.
18m
2
16m

5 people x 3.5m2
5m 2
13.
2
12m

4 people x 3.5m2
2
11m
2
10m
Size of shelter
9m 2

3 people x 3.5m2

2 people x 3.5m2

1 person x 3.5m2

I I I I I I I I I I I I I I I I I I I I I I
C
B. Peru
C ndia
A. Hon
A. oz ras
A. om biq
C rit a
C Peru
B. Peru
B. Pak
 Pak an
B. AJ an
A. Sri !=
B. ud ka =>
B. Sri
B. fgh ka
B. ogy ista
 ndo arta
A. / sia
 ibe KJC
B. AJ
 ndo
.3

.1

.5 re
.4
3

11
10 is

12 U=

13 an
1
7
6 ak n

4 U=
6 d
8 am
2 al ue

 is

9 la @=

 ne
5 
 ria K

 ne
I

A lan
J an
I

I
M u
S
E i

( t

S n

!
L
(

/S si
=J a
a

@=
t

Case study

Chart showing sizes of the shelters in the case studies in comparison with the suggested allocation of 3.5m2 per person.
Note that smaller shelters are often constructed after assessment of local and host population standards, as well as what
is practically possible. Shelter size is not necessarily a good indicator of the quality of a shelter programme.

viii
Africa Shelter Projects 2008 A.1

Strengths and weaknesses (continued)


- The affected population contributed 5,000 individual
land plots, 6,000 days of voluntary labour and payment for
14,000 days of contract labour (equivalent to US$ 40,000). After six years, a donor assessment found that:
- US$ 140,000 was invested by the affected population Š The project was used as a model for the provision of
itself into the upgrading of their housing units by the end 8,000 more shelters funded by other donors.
of October 2002. Š Transitional shelters had been converted into
8 For families of eight or more people, space was permanent housing.
EJOQBł?EAJP Š The Disaster Risk Reduction (DRR) projects to monitor
8 0KIA >AJAł?E=NEAO BAHP PD=P PDA LH=OPE? S=HHO the volcano continue, with a weekly report broadcast on
compromised their privacy and security. It was easy to see local radio.
what people were doing at night due to the shadows cast
on the plastic by lamps and people were worried that the
plastic sheeting could be easily cut by thieves.

Photo: Graham Saunders


Sample of a temporary house
Situation before emergency Approximately 80% of the affected Two examples of the shelter were
According to an NGO survey, population reported that their >QEHP=J@QOA@=OLNKFA?PKBł?AOOKPD=P
Goma, an important border trading economic conditions had worsened as >AJAł?E=NEAO GJAS SD=P PDA ODAHPANO
town in the north-east of the Dem- a result of the disaster. A quarter had would look like and to make it easier
ocratic Republic of Congo, had a previously used their homes as the to discuss construction issues. These
depressed economy before the base for their income-generating ac- KBł?AO =HKJCSEPDO?=HAIK@AHO SANA
eruption, with 46% unemployment tivities. used to train all households in how to
and only 40% of people able to sustain build the transitional shelters.
themselves and their family on their Implementation
income. Local authorities suggested a new Tools and a marked length of string,
area of land, largely bush land, for de- used to measure out bracing sections,
Before the emergency, shelter con- velopment into a new site. This site were supplied with each kit. Few con-
ditions were varied, with the average was rejected, as it would have required struction problems were reported due
house size containing around 31.5m2 of the construction of a whole new infra- to the simplicity and familiarity of the
covered living space. The volcano had structure network (roads, sanitation, design.
last erupted in 1977. etc.) as well as requiring considerable
Although all households received
After the emergency levelling. It would also have meant
PN=EJEJC  =NKQJ@  KB >AJAł?E=NEAO
1DAH=R=ŃKSA=OEHUOAP=HECDPPN=@E- taking resettled people away from the
paid others to construct their housing
tional timber-framed houses, covering economic opportunities in the town.
unit.
13% of the town in a layer of molten Instead, an emergency shelter
rock one to three metres deep in a By the end of October 2002, the
response was jointly developed by a
single day. Much of the central admin- joint intervention had assisted 11,307
group of INGO, UN and local NGO
istrative and commercial district was families and plans were made to help a
representatives to provide a transition-
damaged, affecting the capacity of the further 1,318. Those assisted included
al shelter to families (who met certain
local authorities to respond. all of the families who had occupied the
criteria) once they had negotiated a
collective sites within the town itself,
Some of the 87,000 people new plot to build on within the town
and families who had been ‘hosted’ by
displaced sought temporary refuge itself. This plot was either bought,
others.
in communal buildings, while others rented or donated by relatives. This
moved in with relatives whose houses kept the economic activity within the 0AHA?PEKJKB>AJAł?E=NEAO
had not been affected. In this way, town, used the existing infrastructure Families in collective sites (such as
all found some form of immediate, =J@ AJOQNA@ PD=P >AJAł?E=NEAO SANA schools) were prioritised as local au-
temporary shelter themselves without resettling somewhere where they thorities wished to reopen the schools
direct international agency assistance. wanted to be. as soon as possible. The remaining

3
A.1 D.R. Congo - Goma - 2002 - Volcano - Distribution and technical support Africa

The transitional shelters measured AJAł?E=NEAO OKIAPEIAO OPNAJCPD-


5m x 4.8m, provided 24m2 of covered ened the frame with bush sticks.

Photo: Graham Saunders


HEREJCOL=?ABKNłRAPKOETLAKLHA =J@ Although the potential environmen-
followed Sphere minimum standards. tal damage of this activity was not
1DA@EIAJOEKJOSANA@AłJA@>UHK?=HHU measured, alternative materials could
available timber sizes, in order to have been considered at the start of
maximise section spans and minimize the project.
wastage from cutting. The tradition-
Each assisted family was also
al use of volcanic rock for walls was
provided with a latrine, improving
Structural skeleton of a house, showing NAFA?PA@=OPKKOHKS=J@@EBł?QHPPK?QP
Goma’s pre-eruption sanitation.
cross-bracing and size correctly, and too expensive
funds were allocated on a neighbour- to transport.

Photo: Graham Saunders


hood-by-neighbourhood basis, based The unit was designed for robust-
on the proportion of families affected ness, without the need for cast foun-
by the eruption. dations, so it could be dismantled and
A household in a neighbourhood IKRA@EBJA?AOO=NUAJAł?E=NEAOSANA
could make an application for assist- instead encouraged to build up foun-
ance once they could prove they had dations with rocks and earth in order
negotiated a new plot of land for re- to reduce surface water inside the
>QEH@EJC 1DEO S=O RANEłA@ KJ OEPA houses.
through discussion with neighbours The roofs were covered with cor-
and local authorities. rugated zinc sheets, which, despite Logistics and materials
Final selection was overseen by their high cost and solar gain, were Materials were sourced locally
a Local Advisory Group made up of locally known for their ease of use. where possible. A joint agreement
community representatives and an As the budget did not stretch to between agencies to share supplier
agency staff member, following jointly- timber-clad walls, the design had to lists and agree on the materials to be
agreed upon criteria. Decisions and be braced well enough to stand un- provided reduced inter-agency compe-
details of complaint processes were IK@EłA@ 1DA S=HHO SANA ?KRANA@ PEPEKJ=J@HK?=HLNE?AEJŃ=PEKJ
published on a notice board. with plastic sheeting held in place with The possibility of setting up a local
Prior ownership of a property was timber laths and protected from the timber mill was considered but not
not made a requirement for assist- weather by the overhang of the roof. implemented. Lack of capacity at the
ance, in order to ensure that people Households normally divided their local mills meant that some timber was
who were renting before the eruption houses into separate rooms, so the procured from outside of Goma.
were also able to obtain a transitional transitional shelter was designed to *K@Eł?=PEKJ
shelter. allow families to partition the space By October, many had made im-
Technical solutions using their own materials or plastic provements to their homes, often using
Although other emergency shelter sheeting provided by agencies. salvaged corrugated metal sheeting or
solutions, such as tents, could have timber cladding to replace the plastic
been deployed, these were rejected
‘Goma’s recovery was sheet walls. However, around 30% of
as they could not have been updated
dependent largely on the families felt they could not afford
for permanent use. The transitional
economic regeneration. to make these upgrades and would
shelters cost just US$ 55 more than a
By concentrating the be living in the transitional shelter as
standard relief tent and took longer to
activities within the town provided for some time.
deploy, but provided a stepping stone
itself, this project consid-
ered the sustainability of 0KIA AJPANLNEOEJC >AJAł?E=N-
to permanent reconstruction. EAO I=@A @AOECJ IK@Eł?=PEKJO #KN
regeneration’. - Donor
example, one family paid a contractor
Environment to build a kiosk into one end of the
1DA ?ANPEł?=PEKJ KB PEI>AN EJ PDA house in order to run a small business
Photo: Graham Saunders

HK?=H =NA= S=O @EBł?QHP PK RANEBU  OK to raise money for new furniture.
timber from fast-growing eucalyp- Disaster Risk Reduction (DRR)
PQO S=O OLA?EłA@ =J@ >KQCDP BNKI This shelter programme was im-
a number of different sources to plemented alongside a DRR project to
minimise potential local deforestation. support the Goma Volcano Observa-
tory’s hazard monitoring and a com-
munity-based early warning system.

Families were trained to construct their shel-


ters, but around 70% hired others to build.

4
A.2 "NEPNA=KJS=N@O KJŃE?P =ILQLCN=@AO Africa

Photo: Joseph Ashmore

Photo: Joseph Ashmore


Traditional hudno house with earthen roof Over 60,000 people were living in tent camps six years
=BPANPDAKQP>NA=GKB?KJŃE?P
Situation before emergency Technical solutions In 2002, the organisation began the
Eritrea is one of the poorest 1DA KBł?E=H LKHE?U S=O PD=P ?=ILO @EOPNE>QPEKJKBBQAHABł?EAJPOPKRAO=J@
countries in the world, with more than were temporary and that the displaced GANKOAJAOPKRAO OECJEł?=JPHU@A?NA=O-
KBEPOLKLQH=PEKJHEREJC>AHKSPDA population would be returning home EJCPDA@AI=J@BKNBQAHSKK@>U&!-O
J=PEKJ=HLKRANPUHEJAKB@=U&JPDA OKKJ =BPAN PDA LA=?A PNA=PU 1DEO
?KJŃE?P=BBA?PA@ =NA=O  LAKLHA HERA@ meant that organisations were dis-
mainly in soil-block homes, in stone- ?KQN=CA@BNKILNKRE@EJCIKNA@QN=>HA
?KJOPNQ?PA@DKIAOSEPDDA=RUA=NPDAJ ODAHPAN OKHQPEKJO %KSARAN  PDA OHKS
roofs or in lighter-weight thatched diplomatic resolution of the border
NKQJ@DQPO demarcation and the need to properly

Photo: Joseph Ash-


demine return areas meant that ten
After Eritrea’s independence from
years after their initial displacement
Ethiopia in 1993 the border between
some IDPs remained in camps and
PDAPSK?KQJPNEAOS=O@EOLQPA@&J*=U
NA?AERA@KJHUAIANCAJ?UODAHPANEPAIO
1998 the dispute escalated into war,
displacing thousands from their homes Tents and plastic sheeting formed
EJPDA@EOLQPA@=NA=O PDA?KNAKBPDAODAHPANNAOLKJOA!QA
to the short lifespan of such materials, #ENASKK@?KHHA?PEKJHA@PKOANEKQO?KJŃE?P
After the emergency SEPDPDADKOP?KIIQJEPUA?=QOAPN=@E-
many tents that had rotted, blown
O=NAOQHPKBPDAłCDPEJC PDKQO=J@O PEKJ=HOPKRAOSANAJKPRANUABł?EAJP =J
=S=UKN?=QCDPłNAD=@PK>ANALH=?A@
of people left the disputed border EILNKRA@OPKRAOLNKFA?PS=OOAPQL
@QNEJCPDALANEK@KB@EOLH=?AIAJP
=NA= KPD ?KQJPNEAO =HOK @ALKNPA@
Implementation
=NKQJ@   ?EPEVAJO 0APPHAIAJPO  There were trials with other
Distributions of shelter items were
including about 20 designated camps, I=PANE=HO &J  PDA KNC=JEO=PEKJ
I=@A EJ ?KKN@EJ=PEKJ SEPD PDA CKR-
were formed in the states of Gash- @EOPNE>QPA@ L=HI HA=RAO BKN PDA NAL=EN
ernmental Eritrean Relief and Refugee
=NG=  !A>Q> =J@ /A@ 0A= 1DAOA KB KRAN   PN=@EPEKJ=H DKIAO EJ
KIIEOOEKJ
were intended to be temporary and and around Barentu, in the Gash-Bar-
to house no more than 20,000 people G= NACEKJ 1DAOA SANA RANU >QHGU PK BPAN=I=OO@EOPNE>QPEKJKB 
KJA=?DOEPA,PDANLAKLHAOP=UA@SEPD PN=JOLKNP &J   SKRAJ I=PO SANA tents in 2000 when the total popula-
family members or rented accom- LNK@Q?A@ BKN KJA ?=IL PK LNKRE@A = tion in camps reached around 150,000
IK@=PEKJ *=JU &!-O =PPAILPA@ PK more traditional shelter material, but people, all camp residents were
?KJPEJQA=CNE?QHPQN=H=?PEREPEAOKJPDAEN PDEOS=OJKPATPAJ@A@PKKPDAN?=ILO =OOAOOA@ =O D=REJC PDAEN >=OE? ODAHPAN
H=J@SDEHANAI=EJEJC@EOLH=?A@ JAA@OIAP
4EPD &!-O HEREJC EJ ?=ILO BKN
%KSARAN  JA=NHU   NALH=?A-
By June 2000 as many as 1 million much longer than expected, addi-
ment tents were required between
people were displaced within Eritrea, tional pressure was placed on natural
 =J@  1DEO NA@EOPNE>QPEKJ
PDKQCD PDEO łCQNA BAHH OD=NLHU H=PAN NAOKQN?AO EJ PDA =NA= &!-O =J@ PDA
of basic emergency shelter items
that year to around 200,000 people in host community were soon competing
was enough to rehouse nearly half of
?=ILO=J@ KQPOE@AKB?=ILO BKNO?=N?AłNASKK@=J@H=NCA=NA=OKB
the total camp population of around
H=J@JA=NPDA?=ILOSANA@ABKNAOPA@
Six years after the outbreak of the   LAKLHA KJOE@AN=>HA MQ=JPE-
?KJŃE?P =NKQJ@ &!-ONAI=EJA@ ties of plastic tarpaulins were also
@EOLH=?A@ 1DAOA LAKLHA SANA AEPDAN distributed, although as some of these
from disputed border areas, from the were distributed to returnees an exact
Photo: Joseph Ashmore

Ethiopian side of the border or had łCQNABKN?=ILNAOE@AJPOEO@EBł?QHPPK


>AAJLNARAJPA@BNKINAPQNJEJCPKPDAEN K>P=EJ
H=J@=O=NAOQHPKBH=J@IEJAO
The table shows the distribution
Ten years after the outbreak KB PAJPO =J@ P=NL=QHEJO 2+ =CAJ?EAO
KB ?KJŃE?P   LAKLHA NAI=EJ and other NGOs were also supporting
@EOLH=?A@ IDPs with emergency shelter items in
the early period of displacement, but
-=HIHA=RAOSANA@EOPNE>QPA@PK B=IEHEAO by 2002 the agency was responsible for
ODAHPANLNKREOEKJEJPDA?=ILO
6
Africa Shelter Projects 2008 A.2

Year Number Tents Plastic


uses and to decrease the footprint Though the high consumption of
of IDPs distributed tarpaulins
KB PDA PAJP 0DKNPAJEJC PDA CQU NKLAO wood and the impossibility of trans-
distributed
meant that the wall height shrunk to porting stone ruled out hudno con-
1999 30,000 4,207 2,000
around 30cm, reducing the internal struction in the camps, many people
2000 150,000 15,254
RKHQIAKBPDAPAJP?KJOE@AN=>HU adapted their temporary shelters to
2001 65,000 look and act more like the homes from

Photo: Joseph Ashmore


2002 63,000 SDE?DPDAUD=@>AAJ@EOLH=?A@ =IL
2003 63,000 3,406 11,471 residents in Gash-Barka made the
2004 63,000 6 20,547 BKHHKSEJCIK@Eł?=PEKJOġ
2005 46,500 +KłCQNAO Structure: IDPs extended the height
Ġ=LLNKT
5,000 to =J@ ŃKKN OL=?A KB PDAEN ODAHPANO >U
NAPQNJAAO
building large wooden frames and
2006 D=JCEJCPAJPO=J@KPDANI=PANE=HKRAN
2007 10,000 +KłCQNAO People upgraded their tents using local PDAPKL
Ġ=LLNKT I=PANE=HOPKLNKRE@AIKNADA=@NKKI
30,000 to The wooden frame was construct-
NAPQNJAAO
b) Quality of materials A@BNKIHKCOQLPKPDNAAIAPNAOHKJC
Total *EJEIQI *EJEIQIKB Weather conditions in this part of The logs were cut down locally or
of 22,873 34,018 Eritrea included extreme heat during LQN?D=OA@>UPDA&!-OPDAIOAHRAO1DA
4DANAPDANAEOJK@=P= ?AHHO=NAHABP>H=JG the day, cold at night, considerable dust BN=IAO SANA JKP L=NPE?QH=NHU ABł?EAJP
=J@ OPNKJC SEJ@O +KP =HH PDA ODAHPAN in the use of timber, consuming around
materials distributed were of the right 200kg of wood for a family shelter with
OLA?Eł?=PEKJPK@A=HSEPDPDAOA?KJ@E- ?KJOE@AN=>HAOPNQ?PQN=HNA@QJ@=J?U
Photo: Joseph Ashmore

PEKJO1AJP?=JR=OHEBAOL=JR=NEA@BNKI
BKQN UA=NO PK FQOP OET IKJPDO 1DEO /KKłJCġ )=UANO KB PAJP ?=JR=O 
R=NE=PEKJ?=J>AATLH=EJA@>U@EBBANAJP plastic sheeting, grain sacks and straw
ODELIAJPO  SEPD OKIA PAJPO LNKRE@A@ I=PO SANA QOA@ =O NKKłJC I=PANE=HO
from emergency stocks, some ordered For those IDPs who did not possess
JAS =J@ OKIA @KJ=PA@ 0KIA ?=JR=O a tent, plastic sheeting was used as
samples could be torn by hand after =J KQPAN H=UAN SEPD KPDAN =R=EH=>HA
HAOOPD=J=UA=N-H=OPE?ODAAPEJCKBPAJ I=PANE=HO LH=?A@ KRAN PDA PKL PK
ripped in the wind, partly due to poor LNARAJPLH=OPE?ODAAPEJCBNKI@ACN=@EJC
People adapted their tents in many
S=UO łTEJCPA?DJEMQAO=J@=H=?GKBOQEP=>HA EJOPNKJCOQJHECDP
NKLA Walls: External walls were made of
Adaptations by IDPs
Many of the camp residents in the PDAO=IAI=PANE=H=OPDANKKłJC&JOE@A
An assessment made in 2002
$=OD=NG=NACEKJD=@LNAREKQOHUHERA@ the shelters, a ‘wall’ around 20cm high
NARA=HA@ PD=P I=JU >AJAł?E=NEAO D=@
EJDKQOAO?=HHA@DQ@JKO1DAOADKQOAO was built up around the edge using
I=@A OECJEł?=JP IK@Eł?=PEKJO PK
D=@DA=RUNKKBO=J@PDE?GS=HHO SDE?D @KJGAU@QJCKNIQ@1DAS=HHOSANA
their shelters for two main reasons:
kept interiors cool during the hot day used as benches or beds and also
AIANCAJ?UODAHPANEPAIOLNKRE@A@PKK
=J@S=NI@QNEJCPDAJECDP LNKRE@A@OKIALNKPA?PEKJ=C=EJOPN=EJ
HEPPHA?KRANA@OL=?A=J@D=@PKKODKNP
=HEBAOL=J The roof of a hudno uses a lot of Partitions: Partitioned interior space
SKK@  PDA NKKB BN=IA EO ?KRANA@ >U S=O ?NA=PA@ >U D=JCEJC I=PANE=H KRAN
a) Space
IKNASKK@SEPD=H=UANKBIQ@KJPKL PEI>AN BN=IAO 0KIA B=IEHEAO =HOK
1DA OP=J@=N@ NAHEAB PAJP LNKRE@AO
The walls are generally made of stone, created separate areas for storing
only 16m2 KB ?KRANA@ OL=?A ĠAJKQCD
KBPAJQOEJCIQ@=OIKNP=N OPN=SBKN=JEI=HBAA@
BKN=B=IEHUKBBKQNLAKLHASEPDI2
LANLANOKJ
=J@I=JUH=NCAB=IEHEAOBAHP
PD=P PDAU SANA HEREJC EJ KRAN?NKS@A@
?KJ@EPEKJOUIK@EBUEJCPDAENODAHPANO
some IDPs managed to increase their
Photo: Joseph Ashmore

?KRANA@ ŃKKN OL=?A PK =NKQJ@ I2


and to also ensure that they could
stand up in them, something only
LKOOE>HAEJPDAIE@@HAKBPDAPAJPO
While a standard ridge tent may
D=RA S=HHO KB ?I EJ DAECDP SDAJ
erected with long guy ropes, tents in
the camp were pitched with shorter
NKLAOEJKN@ANPKO=RANKLABKNKPDAN ŃUODAAPOAL=N=PA@BNKI=JEJJANPAJP=J@?KRANA@SEPDLH=OPE?EOQOA@PKBKNI=J
ATPAJOEKJ0PE?GOSANAQOA@PKN=EOAPDAOE@AOPKEJ?NA=OAPDAEJPANJ=HRKHQIA

7
Africa Shelter Projects 2008 A.3

=IKJC=CAJ?EAOSKNGEJCEJ@EBBANAJPOA?PKNO

Photo: Joana Cameira


Village constructed through community-based project

Photo: Joana Cameira


Brick production
Situation before emergency After the emergency It was decided that the agency would
Three refugee camps (Ifo, Hagadera 1DAOARANAŃKK@EJCEJPDA&BK?=IL follow the idea of previous shelter pro-
and Dagahaley) sheltering mainly destroyed over 2,000 shelters and left grammes in building mud-brick houses,
Somali refugees were established close IKNA PD=J   LAKLHA DKIAHAOO but would improve the durability of the
to the town of Dadaab, in Northern This meant that many refugees had to design, increase the involvement of the
(AJU= EJ=J@UPDAU move to a new camp neighbourhood, communities and reduce the need to
had a population of around 173,000 ĺ0A?PEKJ+† L=U>AJAł?E=NEAOBKN?KJOPNQ?PEKJ
LAKLHA
Section N was not a popular choice The aims of the programme and
Dadaab is an area with little veg- BKN I=JU NABQCAAO  HPDKQCD PDA the implementation of the strategy
etation and refugees’ access to natural ground was higher and less affected by were explained to camp leaders who
resources (including building materials) ŃKK@O PDAOEPAS=OBQNPDAN=S=UBNKI @EOOAIEJ=PA@PDAEJBKNI=PEKJOSAHH 
EO HEIEPA@ 1DA CKRANJIAJP KB (AJU= the market and its lack of trees meant community mobilisers (agency staff
does not encourage activities that are HEPPHAJ=PQN=HOD=@A who were based in the blocks for eight
‘permanent’, so refugees rely on aid hours per day) ensured that the right
agency support rather than self-suf- 0AHA?PEKJKB>AJAł?E=NEAO EJBKNI=PEKJS=ONA=?DEJCARANU>K@U
ł?EAJ?U PDNKQCD =CNE?QHPQNA KN KPDAN AJAł?E=NEAOD=@>AAJLNAOAHA?PA@
by a UN agency, following standard A public demonstration of ‘brick
HERAHEDKK@O
RQHJAN=>EHEPU ?NEPANE= PD=P S=O RANEłA@ throwing’ to test the strength of bricks
The camps are highly congested, PDNKQCD@KKNPK@KKN?DA?GO made from different soils ignited the
?NA=PEJC O=JEP=PEKJ LNK>HAIO =J@ łNA EJPANAOP KB LKPAJPE=H >AJAł?E=NEAO =J@
O=BAPUEOOQAO1DAI=FKNEPUKBODAHPANO Implementation addressed the fears of mud-brick
in the camp are of two types, both The agency faced two main chal- DKQOAO >AEJC SA=G 1DA =CAJ?U ?KJ-
AILHKUEJC DECDHU Ń=II=>HA NKKłJC lenges: convincing refugees that structed some prototype shelters that
I=PANE=HOġ PN=@EPEKJ=H PQGQHO „ I Section N could become a nice place were then used as classrooms for the
diameter dome structures made of to live and that improved mud-brick ?KJOPNQ?PEKJPN=EJAAO
wooden sticks, covered in fabric; and constructions would be stronger than
the previous buildings that the refugees The agency then provided a ‘training
adobe huts – 6m x 3m shelters using a
D=@OAAJS=ODA@=S=U of trainers’ to a small group of refugees
large number of sticks for walls with a
on construction techniques and brick-
NKKBI=@AKBHK?=HRACAP=PEKJ
I=GEJC "BBKNPO SANA I=@A PK AJOQNA

9
A.3 Kenya - 2007- Flooding - Shelter and disaster mitigation Africa

that training teams included women


=J@ PDA AH@ANHU  "=?D PN=EJAN OQLAN-
vised around four families per month,

Photo: Joana Cameira


assisting them with layout, foundations,
S=HHEJC=J@LH=OPANEJC =NLAJPANOSANA
deployed to give technical support on ‘I used to live in a bush
NKKB=J@H=PNEJA?KJOPNQ?PEKJ house. It was not really a
ĺ&PS=OIUłNOPFK>&P=H- house. It is better here’. –
lowed me to support my Elderly refugee
family’. – Female refugee
construction trainer Completed house
mortar or cow dung and the roof was next stages of the implementation
Soil-sourcing sites, both within and
?KRANA@ SEPD ENKJ ODAAPEJC &ILNKRA- strategy, to increase the supply at lower
KQPOE@AKBPDA?=IL SANAE@AJPEłA@>U
ments were made to ventilation to ?KOPO=J@EJ=ODKNPANPEIABN=IA
the agency, which also supplied brick
decrease the high internal temperature
moulds, pangas (knives), wheelbarrows
KBLNAREKQO@AOECJO
Logistics and materials
and plastic sheeting to cover completed Families originally used soil from
>NE?GO @QNEJC PDA N=EJ 1KKHO SANA A change in the position of the planned and unplanned areas within
shared among the community groups house on the plot improved sanita- PDA?=ILLNKFA?PPK@ECJASC=N>=CA
and returned to the agency when not PEKJ)=PNEJAOSANAIKRA@PKPDABNKJP pits outside the camp presented an op-
EJ QOA 4=PAN OPKN=CA S=O LNKRE@A@ of the plot next to the street and the LKNPQJEPUBKN=JASOKEHOKQN?A
JA=NPDAOKEHOKQN?EJCOEPAO house was positioned at the back of the
To reduce the water consumption
LHKP1DEOHABPOL=?ABKNIKNA?KJOPNQ?-
Agency staff maintained quality- necessary for brick production, ‘spilled
tion inside the plot and prevented the
control checks on all the constructions S=PAN†BNKIP=LOP=J@OS=O?KHHA?PA@
problems of a dirty backyard blocked
to ensure the safety of the houses, par- The rest of the water was supplied by
>US=OPAS=PANNQJKBB
ticularly as previous mud brick failures truck and stored in oil drums distribut-
had been mostly due to poor con- AJAł?E=NUIK@Eł?=PEKJO ed around Section N or in water tanks
OPNQ?PEKJN=PDANPD=J@AOECJ AJAł?E=NEAO I=@A = JQI>AN KB if the bricks were being produced
Upon completion of the mud-brick IK@Eł?=PEKJO PK PDA JAS OPNQ?PQNAO KQPOE@APDA?=IL
structures, the agency supplied the These included:
/KKłJC =J@ @KKN I=PANE=HO SANA
?KJOPNQ?PEKJI=PANE=HOPD=PPDA>AJAł- Š AOPDAPE?ġ-=EJPEJC=J@@A?KN=PEJC procured in the capital with support
ciaries could not produce or purchase Š 4EJ@KSOġ1DAOEVAS=O=@FQOPA@ from a UN agency, while other
PDAIOAHRAO OQ?D=ONKKłJCODAAPO=J@ Sometimes they were partially closed materials were procured in the nearest
@KKNO with other bricks or sticks to increase H=NCAPKSJ
The combination of a team of security and reduce sunlight but
The total cost of materials, including
trainers able to transfer skills to the I=EJP=EJRAJPEH=PEKJ
transport, was around US$ 440 if the
?KIIQJEPU =J@ >AJAł?E=NEAO SEHHEJC Š Furniture: Some families
soil was sourced within the camp,
to participate in the construction of constructed beds and tables out of the
rising to US$ 480 if soil was sourced
their own shelter at no cost led to mud bricks, which helped to demarcate
KQPOE@A PDA ?=IL )=>KQN ?KOPO BKN
full engagement of the community and PDAEJPANJ=HHEREJCOL=?A
A=?DODAHPANSANA=NKQJ@20
guaranteed that people would maintain Š -HKP>KQJ@=NUġ0I=HHS=HHOPK@AłJA
PDAENLNKLANPEAOPDAIOAHRAO the extent of a plot were often built Quantity Unit
SEPDOL=NAKN>NKGAJ>NE?GO Iron sheets (2.5m length) 20 pieces
Technical solutions Š Plastering: Some families plastered
Timber - cypress (2mx2m) 120 m
The 6m x 3m houses required their house with cement mix, making
1,700 bricks, considerably more than PDAS=HHOEILANIA=>HA Plain sheet (2.4m x 1.2m) 1 piece
previous designs implemented in Š Gutters were made out of waste Nails 4" 4 kg
PDA ?=IL 4DEHA @EO=OPAN IEPEC=PEKJ PEJODAAP=J@PEJ?=JO Nails 3" 1 kg
was primarily achieved by relocat- Š Livelihoods: Market stalls were
Nails 1" 0.5 kg
ing refugees to the higher ground of built as extensions onto or between
Section N, extra bricks were necessary houses, increasing the income of the /KKłJCJ=EHO 5 kg
to build a thick foundation and lower families and providing more options Butt hinges 4" 3 pieces
wall to improve the structure’s per- BKNKPDANNAOE@AJPOPKODKLHK?=HHU Padbolt 6" 1 piece
BKNI=J?AEJDA=RUN=EJO >KQP  KB PDA >AJAł?E=NEAO Tower bolt 1 piece
"ECDP LEHH=NO LNKRE@A@ OQLLKNP BKN employed other refugees at some stage
GI Ridges (1.8m length) 4 pieces
the walls and roof trusses, increas- KB PDA ?KJOPNQ?PEKJ 1DEO EJ?NA=OA@
Binding wire 5 kg
EJC PDA OP=>EHEPU KB PDA NKKB EPOAHB the income generated in the housing
EJ@QOPNU EJ PDA ?=IL 0Q?D EJEPE=PERAO Wood preservative 8l
Mud-brick walls were plastered with
inspired the agency to look into the

10
A.4 Kenya - 2007-2008 - Election violence - Transitional shelter kits Africa
Strengths and weaknesses (continued)
promoted sustainable return. roofs and doors had been looted.
8 Occupancy was not as high as hoped for, with some 8 The kit included spare sheets and plastic sheeting for
IDPs not ready to move back. the construction of latrines. These materials were often
8 +KP=HHKBPDAI=PANE=HO=NA=R=EH=>HAHK?=HHUEJOQBł?EAJP used to extend the roof instead.
quantities. Sourcing of materials needs to be reconsidered 8 0KIA >AJAł?E=NEAO OP=PA@ PD=P PDAU SKQH@ D=RA
before the project can be upscaled. preferred to have been given the cash value of the plastic
8 Only those whose houses had been completely so that they could buy local materials themselves to build
destroyed received the kit. Further attention needs to be the walls (cash grants are being considered for the post-
given to those whose houses are partly damaged, as many pilot phase).

Photo: Mark Lawler


Transitional shelter built on the family’s own land

Situation before emergency 0AHA?PEKJKB>AJAł?E=NEAO


A number of the tensions related to The Shelter Cluster agreed that J =@ DK? >AJAł?E=NU OAHA?PEKJ
PDAAPDJE?J=PQNAKBLKHEPE?=H=BłHE=PEKJ 481 transitional shelter kits would be committee was established by the
in Kenya, unresolved land issues, in- distributed as a pilot project to test the local administration, with appropriate
equality of wealth distribution, high un- design of the shelter and the response representation of women and IDPs,
AILHKUIAJP =J@ ?KJŃE?P KRAN J=PQN=H KB>AJAł?E=NEAO PK OAHA?P PDA łJ=H >AJAł?E=NEAO 1DEO
resources led to violence following the committee was monitored by the im-
It was important that the site
December 2007 election. plementing agency.
chosen should be one where security
The majority of those displaced was good, IDPs were willing to return The degree of vulnerability of the
from the Rift Valley province had lived to and the community they were households was also assessed and was
in small timber pole-framed houses returning to was ready to accept them. EJPAJ@A@ PK >A QOA@ =O =JKPDAN łHPAN
with timber or adobe wall cladding, *P=N=CKJ EJPDA(ELGAHEKJ!EOPNE?P łP EJ >AJAł?E=NU OAHA?PEKJ QP =O PDA
thatch or iron-sheet roofs and the requirements. number of shelters to be provided
?KIL=?PA@ OKEH ŃKKNO  OPNAJCPDAJA@ almost matched the number of houses
The local administration had a
with dung or cement. completely destroyed, vulnerability
record of all IDPs. Their assessment of
criteria was used to determine the level
After the emergency the impact of the violence, correlated
of construction assistance a household
The election crisis was compound- with the agency’s own assessment,
required, rather than to select the ben-
ed in April by food security problems, showed that around 500 houses had
Ał?E=NEAOPDAIOAHRAO
ŃKK@EJCEJOKIA=NA=O=J@@NKQCDPEJ been completely destroyed.
the north. The pattern of displacement To qualify for construction assist-
The following criteria were used
was complex. People were displaced ance, the household had to be headed
to decide which of the 500 house-
from many different parts of the by a single parent or a child or have
holds who had no shelter to return to
country as one ethnic group escaped members who were elderly, disabled
would be chosen to receive a kit. The
the threat of violence from another. or had special health requirements.
OAHA?PA@>AJAł?E=NEAOġ
Around half of IDPs found shelter The criteria for the upscaled
Š were registered as an IDP by the
in camps. The rest sought refuge with LNKFA?PS=OIK@EłA@BNKIPDA0DAHPAN
local administration;
friends or relatives and some moved Cluster’s Transitional Shelter Strategy
Š were willing and ready to return;
back to their ‘ancestral’ land where developed in March 2008, following
Š had proof of land ownership.
support services were limited. feedback from the pilot project.
A response plan was developed Proof of land ownership was only Implementation
through the Cluster System, which required for this pilot project. It A prototype of the shelter was
would provide non-food items and was anticipated that an appropriate tested for structural quality and
tents to meet the need for emergency response would later be developed by reviewed by IDPs for its suitability. At
shelter while a transitional shelter the Shelter Cluster to deal with those PDAO=IAPEIA=OPDAłJ=HOAHA?PEKJKB
design was developed to bridge the without formal titles to their property >AJAł?E=NEAOS=O>AEJCI=@A =OA?KJ@
emergency and permanent shelter or whose houses were only partially prototype was built in a prominent
phases. damaged.

12
Africa Shelter Projects 2008 A.4

location in Mtaragon to sensitize bene- ground at a depth of around 60cm. The Materials Quantity
ł?E=NEAO=OPKSD=PS=O>AEJCLNKRE@A@ poles supported a timber ring beam,
Walls
and to get feedback on the design. which in turn supported the timber
rafters onto which an iron sheet was Cedar posts 14 units
Local craftsmen and unskilled 9', 4" diameter
nailed.
labourers were recruited into ten Walling-polythene sheeting- 45 m2
teams and trained. Although not Walls were clad in plastic sheeting 1000g
planned, the teams were a 50-50 mix =J@ŃKKNOSANA?KILNAOOA@A=NPD1DA Cypres timber 2x3", 20 m
BNKIPDAAPDJE?CNKQLPD=PD=@ŃA@=J@ @KKNOSANAŃ=LOEJPDALH=OPE?ODAAPEJC 6 x 2m, 3 x 2m
the ethnic group that they felt threat- and weighted with timber battens. Ordinary nails 4" 2 kg
ened by. This side effect of the project The design was based on the ver- Roof
had a positive impact on peacebuild- nacular housing typically lived in by Cypess timber 2x3", 40 m
ing. The donor organisation directly IDPs prior to their displacement. 2 x 10m, 3 x 3m, 1 x 8m
procured the materials within Kenya This enabled IDPs to upgrade their Cypes timber 2x2" 41 m
and delivered them to the implement- shelters incrementally using materials 6.5 x 6m
ing agency’s warehouse in Nakuru. and methods that they were already CGI ridge covers-30g -1.5 m 4 units
The implementing agency then familiar with. The walls could be clad CGI sheets-30g 20 units
distributed the materials at three with timber, adobe or even brick and 2 x 0.9m
HK?=PEKJOAJAł?E=NEAO?KHHA?PA@PDAI cement. Cement could be used to Ordinary nails, 2kg 4", 2kg 4.5 kg
and took them to their plots up to EJ?NA=OAPDA@QN=>EHEPUKBPDAŃKKN 3", ½kg 2"
three kilometres away, using their own The use of plastic sheeting allowed /KKłJCJ=EHO 4 kg
transportation (either by hand, by shelters to be built and occupied Iron hoop 1 kg
donkey, or by tractor and trailer). RANU MQE?GHU  PDKQCD OKIA >AJAł?E=N- Tools
The kits also included the basic ies replaced the plastic sheeting walls
Stanely claw hammer 1 unit
tools necessary to build the shelter. immediately with adobe or reclaimed
building parts, such as doors or timber. Stanley woodcutting saw 1 unit
ĺ&†IKRAN=J@QJ=>HA The plastic sheeting could then be sold Panga knife 1 unit
PKCAPPDAI=PANE=HOPK or used for temporary house exten- Hoe and handle 1 unit
>QEH@KJIUKSJ!AOLEPA sions, and provided waterproof storage Manaila thread 30m (roll) 1 unit
SD=PD=LLAJA@ &D=RA for seeds and fertilisers.
Measuring tape 1 unit
PK?KJPEJQAOP=UEJCDANA The use of regular frame and
AEJCIUH=J@&?=JJKP roof sections made the construction
NQJ=S=U&BARANU>K@U modular – it could be easily extended
can be assisted in the or adapted. The choice of materials ‘The prototypes built by
way I was, that would meant that there was no part of the local craftsmen in each
>ACNA=P-H=OPE?ODAAPEJC >QEH@EJC PD=P ?KQH@ JKP >A łTA@ KN project location enabled
EO,( >QP&SKQH@D=RA replaced locally. structures to be tested and
LNABANNA@PEI>AN =OEP†O important feedback from
OPNKJCAN=J@?=J†P>A *KOP >AJAł?E=NEAO ANA?PA@ PDAEN
>QEH@ANO=J@>AJAł?E=NEAO
>HKSJ=S=U†- AJAł?E=NU shelters on exactly the same site as
to be incorporated into
their previous homes had been, so
Guidance was given by the local little site clearance or ground levelling PDAłJ=H@AOECJ†–
craftsmen on how to put the shelter was required. Engineering coordinator
PKCAPDAN 1DA >AJAł?E=NEAO LNKRE@A@
Logistics and materials
the labour themselves and the houses
Materials were sourced in Kenya,
were normally completed within one
and chosen for their familiarity, durabil-
or two days.
ity and low cost. Timber was supplied
,RANKBPDA>AJAł?E=NEAOIAP by private forestries who were only
PDA RQHJAN=>EHEPU ?NEPANE= =J@ MQ=HEłA@ considered if they had government-
to have their houses built by the con- approved replanting projects in place.
struction teams. Plastic sheeting was made from recycled
Photo: Dyfed Aubrey

plastic. The total cost of materials and


Technical solutions
labour for one transitional shelter was
The structure had a covered space
20   JKP EJ?HQ@EJC PN=JOLKNP =J@
of 18m2 (6m x 3m), was split into two
agency administrative costs.
rooms, and had good clearance above
head height.
The frame was made up of 10cm
diameter cedar poles, dug into the Transportation

13
Africa Shelter Projects 2008 A.5
Strengths and weaknesses (continued)
- The project ran alongside water and sanitation and could be more clearly seen.
education programs, which was necessary to ensure that 8 Maintenance issues could have been considered further,
people had access to the services they needed in order to SEPDI=JU>AJAł?E=NEAO=OGEJCBKN?AIAJPBKNŃKKNEJC=J@
resettle. walls.
- 1DA?KJOPNQ?PEKJKBODAHPANOBKNRQHJAN=>HA>AJAł?E=NEAO 8 Technical supervision could have been more intensive
appeared to inspire other returnees to begin rebuilding from the beginning, as some construction work had to be
spontaneously, as it created a positive atmosphere of NA?PEłA@
recovery. 8 Donor-driven partnerships with community-based
- The project was better suited to a rural context than an organisations from previous projects had to be dropped
urban one, as community mobilisation was much easier in due to corruption and a lack of community involvement.
OI=HHANREHH=CAOSDANAPDA>AJAłPOPKPDASDKHA?KIIQJEPU

-DKPKġ'=GA7=NEJO

-DKPKġ'=GA7=NEJO
KILHAPA@DKQOAOBKNNAPQNJAAO

Situation before emergency


After years of civil war, many of assistance did not extend beyond the CERAJ =J@ PDA ?NEPANE= BKN >AJAł?E=NU
Liberia’s 3 million inhabitants had standard repatriation package (sleeping selection, were prepared and signed by
been displaced within or outside mat, blanket, cooking kit, food and >AJAł?E=NEAO  ?KIIQJEPU HA=@ANO  =J@
of the country. Between 2004 and transportation) issued in the return- agency representatives.
2007, 327,000 IDPs were assisted in a transit camp.
returns process, leaving an estimated
Technical solutions
  EJ ?=ILO ,RAN  
0AHA?PEKJKB>AJAł?E=NEAO The traditional house design is a
Using the opportunity of a routine bush pole-framed, mud-walled con-
refugees returned at the same time.
check of returnee names, the agency struction with a thatched roof of grass
NKQJ@   )E>ANE=J NABQCAAO
made notes of those living in over- or palm leaves. The project improved
remain outside of Liberia, making the
crowded shelters and poor conditions the design to include a corrugated
PKP=HłCQNAKBPDKOA@EOLH=?A@KRAND=HB
before communities were aware of a iron roof, which reduced the need to
a million.
proposed shelter programme. This maintain a thatch roof, and a stronger
It is estimated that the number of eliminated the temptation for people central pole to improve structural
people living on less than one dollar to temporarily overcrowd their stability.
LAN@=UNKOABNKIEJPK shelters on assessment day. By corre- Many local houses do not have
in 2007. As well, the sanitation and lating this information with a joint UN/ closable doors and windows, and
JQPNEPEKJ?KJ@EPEKJOKBPDAA=NHUO NGO monitoring project to establish S=HHO =J@ ŃKKNO D=RA PK >A BNAMQAJP-
had seriously deteriorated by 2004. vulnerability categories (including ly repaired after damage from the
female-headed households, unaccom-
After the emergency AHAIAJPO O RQHJAN=>HA >AJAł?E=NEAO
panied minors, the chronically ill and were unlikely to be able to undertake
The vast majority of returnees did
physically disabled) the agency was much maintenance themselves, doors
not have appropriate shelter when
able to draw up a shortlist of potential and windows were included in the
they returned, due to their houses
>AJAł?E=NEAO build.
being destroyed or simply deteriorat-
ing during the two civil wars. 1DA łJ=H OAHA?PEKJ KB  >AJAł-
In rural forested areas, building
ciaries was carried out by the agency, ‘I now have a good place
traditional shelters required families
in collaboration with local authori- to stay, and my family
to collect materials and provide the
ties and community representatives, will come to stay with me
labour to rebuild. While some support
after several visits and open meetings. in my new home’.
was provided for rebuilding (such as
Three-way Memorandums of Under- – AJAł?E=NU
standing, describing the assistance
this project), most returnees’ shelter

15
A.5 Liberia- 2007- IDPs, refugees - Self-build shelters Africa

areas and small communities, where


there was no pressure on land. In
more densely populated communities
‘The project was a suc- (though not urban) land had a price. In
cess because we were these areas the NGO had to check the
accountable, delivered site selection as there was a tempta-
what we said we would tion to allocate land to vulnerable ben-
deliver and had constant Ał?E=NEAO PD=P S=O EJ=LLNKLNE=PA BKN
discussion with the com- building. This was solved through joint
munities themselves. The meetings with the local authorities and
communities understood community representatives.
that supporting vulnera- Logistics and materials
>HALAKLHAS=OKB>AJAłP Materials were collected locally,
to everyone’. apart from doors and windows. It
-NKFA?P?KKN@EJ=PKN

Photo: John Flomo


was not thought that environmental
damage would be caused by local col-
lection. The total cost of materials for
each shelter was US$ 320 (US$ 240
for imported materials, US$ 40 for
local materials bought from communi-
1N=@EPEKJ=HODAHPANOQJ@AN?KJOPNQ?PEKJ ties, and US$ 40 for labour provided by
The doors and windows originally and US$ 40 for the labour. This was the community).
produced by each local construction not a salary, but an incentive. The
gang were found to be of inconsist- ?KIIQJEPU@A?E@A@SDKSKQH@>AJAłP
ent size and quality, so it was decided from the money; normally it was used
to prefabricate these components in to pay for the food of those who
the NGO’s compound using skilled provided labour.

-DKPKġ'=GA7=NEJO
workers. The sum was large enough to be
Implementation an incentive to get people involved, but
,J?A >AJAł?E=NEAO D=@ >AAJ OI=HHAJKQCDPKLNARAJP?KJŃE?PKRAN
selected and cooperation of the SDK >AJAłPA@ 1DA 20  BKN PDA
community was agreed upon through a materials was only paid once construc-
series of open meetings, a skilled local tion up to the roof was completed. Completed house
carpenter was chosen to lead the con- -=UIAJP KB PDA łJ=H 20  S=O Materials Quantity
struction of between one and three made upon occupancy rather than
houses. The carpenter would also act
3" nails 65 (0.3kg)
when the structure was completed.
as a community mobiliser to organise 4" nails 28 (0.3kg)
This was a lesson learned from
people to collect materials and provide previous projects, where payment had Hammer 
labour for construction. been made upon structural comple- 7EJ?NKKłJCODAAPO 2 bundles
Progress was monitored by one of tion. The NGO was then unable to (0.66m x 2.4m)
łRA ODAHPAN OQLANREOKNO  =HH KB SDKI prevent occupancy of the structures Zinc nails L=?GAPO
had construction knowledge and skills. >UJKJ>AJAł?E=NEAO=BPANS=N@O
Door and frame 2
The supervisors were managed by Shelter supervisors marked out the
a shelter coordinator and a project Window and frame 2
agreed 25m2. A standard design was
director. proposed for a two-room construc- Hinges 4 pairs
Supervisors were expected to visit tion with a veranda. However, ben- Nails ĠGC

A=?D>AJAł?E=NU=PHA=OPKJ?A=SAAG Ał?E=NEAOSANABNAAPK=HPANPDEO@AOECJ Hasp/staples 4 pairs


The coordinator usually visited sites according to their needs. The NGO Window and door 4 pieces
four days a week. Such close and direct felt it necessary to make further stipu- bolts
monitoring was a key reason for the lations about central support poles, to
ensure that the building was safe once /KKłJCBAHP LEA?A
project’s success, as problems were
E@AJPEłA@=J@NAOKHRA@MQE?GHU=J@PDA the project was underway. Materials collected locally:
quality of building could be examined Central pole 
The project was completed on
throughout the project. This enabled PEIASEPD=K??QL=J?UN=PA Poles for frame NKQJ@
ongoing improvements to be made. Rafters (poles) 50
Land issues
The NGO paid US$ 40 for the The community allocated the land Bamboo/rope for As required
materials collected to build the house themselves. This was easy in rural ceiling mats

16
A.6 Mozambique- 2007- Cyclone - Shelter material packages and training Africa
Strengths and weaknesses (continued)
BQJ@EJCIA=JPPD=POKIA>AJAł?E=NEAO@E@JKPD=RAOQLLKNP required repetition of the messages.
for basic shelter needs for at least three weeks. 8 Local suppliers were sometimes unable to meet
8 Technical advice was not always implemented by the deadlines. This resulted in the project requiring an
>AJAł?E=NEAOHPDKQCD>AJAł?E=NEAO=PPAJ@A@PDAPN=EJEJC  extension. Delays were partly due to legal requirements
the construction may have been carried out by someone for supplier registration and payment of taxes by suppliers.
else or they had not been convinced by the advice. This

Photos: Lizzie Babister


A damaged house and self-built reconstructed house using distributed items
Situation before emergency
Many of Mozambique’s inhabitants Unable to respond with immediate Five different shelter packages were
HERA EJ ŃKK@LH=EJO =J@ PDA ?KQJPNU EO emergency items, the organisa- designed to be distributed depending
regularly hit by cyclones. As a result, it tion decided to run a rehabilitation on the type of home the household
has repeatedly required disaster-recov- programme, distributing materials had previously had – traditional round
ery assistance. for the repair or rebuilding of houses houses or rectangular ‘mixed’ houses
belonging to vulnerable households. built from a mix of traditional and
After the emergency
The agency participated in the national modern materials – and the level of
Over 300,000 people were directly
Shelter Cluster meetings and received damage suffered.
affected by the combined effects of the
a donation of plastic sheeting. This was
ŃKK@=J@PDA?U?HKJA>KQP  Technical solutions
included as part of the general distri-
of the displaced sought shelter in Training in simple construction
bution.
communal accommodation, which had techniques to improve the durability
been pre-positioned after the 2001 0AHA?PEKJKB>AJAł?E=NEAO of structures in the event of further
ŃKK@OBQNPDAN LAKLHA>AC=J The agency supported vulner- ?U?HKJAOS=OLNKRE@A@PK>AJAł?E=NEAO
moving to ‘resettlement areas’ – part =>HA >AJAł?E=NEAO EJ PDA @EOPNE?PO KB on the day of distribution.
of the government’s programme to Inhassoro and Govuro. These included
Agency staff demonstrated the use
encourage people to resettle on higher women-headed households, children,
of improved building techniques on a
ground. Others stayed on their own the elderly, the disabled or the chroni-
lived-in house in the village of distri-
land, rebuilding where possible. cally ill, and those without resources
bution. Techniques included advice on
to rebuild a home that had been com-
The government conducted an J=EHEJC NKKłJC ODAAPO IKNA OA?QNAHU
pletely destroyed.
initial needs assessment and three and using wire doubly crossed over in
international agencies were made re- An initial target was set of 1,300 an x-shape to strengthen joints.
sponsible for delivering the three main households (around 6,600 people) who
The demonstration lasted a couple
needs of water, food and shelter. had remained on their own land but
of hours and was made before the
had inadequate shelter. This rose to
The international organisation in materials were distributed. A later as-
2,219 vulnerable households (11,095
this case study had limited local experi- sessment showed that while many had
people) following additional funding.
ence of emergency shelter response, as implemented the techniques, others
it was mostly involved in development Assessments of the shelter needs had not, despite being present at the
projects and non-shelter emergency of each of the vulnerable households training. It is not clear if these tech-
responses. With no stockpiles and no were made in partnership with the niques were not implemented due to
immediate funding, the agency was not HK?=H CKRANJIAJP AJAł?E=NU HEOPO D=>EP KN @QA PK @EBł?QHPEAO EJ EILHA-
able to respond with an emergency were checked and double-checked by menting the training.
ODAHPAN@EOPNE>QPEKJQJPEH=BPANPDAłNOP the agency and local authorities.
Hammers and pliers were distrib-
two weeks.
A simple assessment form was QPA@PKCNKQLOKB>AJAł?E=NEAOSDKOA
The majority of those affected developed, illustrated with simple entire homes had been destroyed.
in the area of the agency’s operation graphics, to enable teams to quickly
found shelter with relatives. Many had classify what kind of shelter kit a
rebuilt their own shelters within the household would require (see table at
łNOPPSKIKJPDO the end of this case study).

18
Africa Shelter Projects 2008 A.6

Implementation 1DA@=U>ABKNA@EOPNE>QPEKJ >AJAł- Although the distribution of items


The project began in mid-March ciaries’ identities were cross-checked was successful, the organisation over-
after a delay in securing funding. The by the agency and authorities. They estimated the level of social cohesion.
time during the delay was used to were given the voucher, information This was a surprise, as their usual work
make thorough assessments. By the on what time to attend the distribu- with local associations suggested the
PEIA PDA >AJAł?E=NEAO SANA OAHA?PA@ tion, and informed that only one other existence of a reasonably community-
many people who had the resources family member should be with them. minded attitude among the population
had already rebuilt. The distribution that would help those most vulnerable.
The voucher system, coupled with
S=O ?KILHAPA@ SEPDEJ łRA IKJPDO 
including a one-month extension that
effective cooperation between the ‘We did not consider all
S=ONAMQENA@@QAPKPDA@EBł?QHPEAOKB
organisation and the local authori- the aspects of construc-
procuring locally.
ties, meant that distributions were tion in terms of labour for
conducted smoothly. However, the the extremely vulnerable
The shelter items were distributed preparation of the vouchers them- and we learned a lot from
using a voucher system that detailed selves, to avoid counterfeiting, added this project. In Cyclone
what kind of shelter package would to the preparation time. Jokwe in 2008, we applied
be received. The voucher system was
To further reduce crowd manage- the lessons and we are
introduced in order to reduce the
ment issues at distribution, community now a lot better prepared
BN=Q@ =J@ I=JELQH=PEKJ KB >AJAł?E=NU for the next disaster’.
mobilisers employed by the organi-
lists, which the organisation had ex-
sation led crowds in song to reduce – Project manager
perienced early on in the project. The
tensions and prevent potential overre-
voucher system also reduced the time
action by authorities, who were quick An assessment three months after
JAA@A@ PK RANEBU >AJAł?E=NEAO KJ PDA
to beat back crowds with sticks. the distribution had been competed
day of distribution.
showed that 15% of those who had
received shelter materials had been
unable to use them to rebuild their
7EJ?NKKłJCODAAPO

homes. The vulnerable households


Purlins and rafters
/KKłJCJ=EHOĠ

between families)
Metal wire (2kg)
Roof trusses (3)

Plastic sheeting
Wall poles (10)

either did not have the money to pay


Tools (shared
(3 bundles)

(1 sheet)

someone to rebuild their homes or


(10)

did not have any relatives willing to do


the rebuilding. With everyone strug-
gling after the disaster it appears that
people were too occupied with solving
their own problems to assist others
Mixed house (3m x 6m) without additional support.
Totally destroyed Y Y Y Y Y Y
Although it was recommended that
>AJAł?E=NEAO P=GA KBB PDA KH@ NKKłJC
thatch, attach plastic sheeting under-
neath and then re-thatch the roof, many
Roof missing Y Y Y Y people had simply spread the plastic
sheeting over the roof as they did not
D=RAOQBł?EAJPH=>KQNPK?=NNUKQPPDEO
very physical task. Consequently, plastic
ODAAPEJCS=OJKPSAHHłTA@KJPDANKKB
Traditional house and tore easily.
Totally destroyed Y Y Y Y Y
Logistics and materials
All materials were purchased
locally, though the ability to guarantee
the sustainable management of the
forests from which the poles were
No roof covering Y Y cut was limited. The use of alterna-
tive materials was not pursued due to
transporting issues and the potential
for further delays.
Due to a shortage in dry grass,
No roof structure Y Y Y
plastic sheeting was distributed as a
NKKłJCI=PANE=H1DAODKNP=CAKBKPDAN
locally available materials delayed the
implementation of the project.

19
A.7 Rwanda - 2008 - Returns - Materials distribution and technical guidance Africa

A.7 Rwanda - 2008 - Returns


Materials distribution and technical guidance
Project type:
Community mobilisation
Establishment of beneficiary associations
Technical guidance
Materials distribution
Emergency:
Forced repatriation of people of ‘Rwandan origin’ from
Tanzania to Rwanda
No. of people displaced:
Approximately 60,000 people considered to be illegal
immigrants in Tanzania were required to return
to Rwanda. 8,000 people had been forced to return

Tanzania
by June 2007.
Rwanda
Project target population:
469 households
Occupancy rate on handover:
All 220 shelters completed by August 2008 were occupied.
Shelter size
48 m2 (6m x 8m)

Summary
This project provided support to people of Rwandan origin expelled from Tanzania by providing
materials for house building, masons and providing shared services at the site of return. Communities
were mobilised by forming beneficiary associations in consultation with the local government. The
role of the associations was to collectivise the tasks required for house building.

Project timeline
6 6 6 06 h hs hs hs hs
20
0
20
0 00 20 ont t t nt ont
94 96 2 v m on on o
m m
19 19 ar ay y
Jul No 1 m m
M M 6 8 12 14
I I I I I I I I I I
re n to
or
47 ees om
re nda

Fir
Rw

18 pha dan nme


Fir Rw gov
Rw 000 a

Jo ania ed
50 anza

Ta for
to

te
Re

Se ph
De nts ex

Th
Se
int n
sid b

am
fug fr

igi
5,0 re Ta

co as
,00 se an nt

co
0, ni

nz m

st
st an er
tu

ird
T

cla of pel
a
an Rw

rn

nd e b
nd
ph
00 tur nza

0 be d al
da an

ra R led

sb

re gi

as
tio wa
n

ph eg
ph
Rw ne nia

tu ns

ee
ge dan

eg
e

as ins
as
n: nd

rn
an d to
no s fl

in

ee
eb
nd
all an

ee
da
cid ee

nd
eg
ille

s
n
e.

ins

s
ga
l

Strengths and weaknesses


9 By collectivising activities in mixed beneficiary
associations, shelter was built for all members of the 8 Some houses were quickly attacked by termites as
community without requiring a different construction timbers had not been treated or protected.
process for vulnerable households. 8 People had to resolve their current shelter problems as
9 Participation of vulnerable beneficiaries in the best they could until their house was completed. For some
construction process was possible and necessary. families this meant living in makeshift shelters for nearly
9 Integration of returnee families and local families in two years.
one resettlement site meant that the association approach
increased opportunities for integration.

20
Africa Shelter Projects 2008 A.7

Photo: Matthias Wohlfeil


Completed shelters
Situation before emergency
Despite a long history of welcoming through a transit centre in Kiyanzi, in solidarity among the returnees and
Rwandan refugees, the Government the Kirehe District of Rwanda, where the local families that had moved to
of Tanzania decided in March 2006 to they would wait before being allocated the new villages, and to support the
expel people of ‘Rwandan origin’ who land in the east of the country by the returnees in providing for themselves.
had arrived in Tanzania at any time government. Both returnees and local families
from the 1920s onwards and who did living in the resettlement sites were
The Rwandan government identi-
not have legal permission to stay. ?KJOE@ANA@ =O >AJAł?E=NEAO KB PDA
łA@ = JQI>AN KB NAOAPPHAIAJP OEPAO 
Four categories of illegal immi- including Rugeyo and Ndego. Joining project, with all households requiring
CN=JPOSANA@AłJA@ġIECN=JPOBNKIPDA 208 returnee families in Ndego were shelter. Vulnerability criteria were used
1920s, 1959 refugees, 1994 refugees 156 poor households from the sur- to decide which houses would be built
and those that had arrived from rounding area, which the Rwandan gov- łNOP
2005 onwards. Most of these people ernment hoped would help with inte- Implementation
lived in the Kagera region of north gration in establishing the new ‘villages’. AJAł?E=NU =OOK?E=PEKJO SANA AO-
Tanzania (which borders Rwanda) and In Rugeyo, 105 returnee households tablished by the agency in collabora-
many did not speak Kinyarwanda, the were settled on their own. tion with local authorities. The associ-
primary language of Rwanda. Only a =PEKJOSANAOI=HHCNKQLOKB>AJAł?E=NU
Although each household was
BASDQJ@NA@KBPDKOAOLA?EłA@>UPDA families formed to collectivise the
allocated its own plot of land, the re-
criteria lived in the refugee camp in tasks required for house building. Peer
settlement sites lacked both water and
the region. The vast majority were in- pressure within the group helped to
sanitation. In cooperation with the
tegrated into the local Tanzanian com- ensure that tasks got done.
local district authorities, the project
munities.
agency provided accommodation and The formation of associations was
Forced returns began in May 2006 latrines to 469 families in the Rugeyo accompanied by an intense community
and many of those forced to return and Ndego resettlement sites. mobilisation campaign. Representatives
experienced violence in some form of local authorities and community
4DEHA PDA >AJAł?E=NEAO ?KILHAPA@
and had their property seized. Many leaders conducted meetings with all
their houses, they lived in temporary,
returnees, the majority of whom were >AJAł?E=NEAOPKATLH=EJPDA=EIOKBPDA
makeshift mud huts with roofs made of
women and children, arrived in Rwanda project and how the project would be
plastic sheeting, which was distributed
empty-handed and without relatives to implemented.
as part of a return package.
stay with.
0AHA?PEKJKB>AJAł?E=NEAO AJAł?E=NEAO SANA BNAA PK ?DKOA
After the emergency With returnees having to rebuild which group they wanted to join as
A return process was agreed to by their livelihoods from scratch, the long as each group had a mixed mem-
the Rwandan and Tanzanian govern- project used the construction pro- bership. Each group had to include
ments in July 2006. Returnees passed grammes to create a sense of women and men, young and old people,

21
A.7 Rwanda - 2008 - Returns - Materials distribution and technical guidance Africa

those of different physical abilities, as The associations were supported Logistics and materials
well as able people. >U=CAJ?UłAH@SKNGANOSDK@A=HPSEPD Some materials were transported
questions and resolved problems. directly to the site and distributed
Each association produced the
to each plot. Other materials of high
necessary materials to build houses Technical solution
value or requiring special storage were
for all the families in its group. They After approval of the house design
stocked in a nearby warehouse and
produced the clay bricks needed by the Ministry of Infrastructure, the
distributed on demand.
(1,800 for a house; 200 for a latrine), building of houses was monitored by
dug latrines, de-barked timbers to be the agency, with inspections made by AJAł?E=NEAO SANA EJRKHRA@ EJ PDA
used for construction and cleared and local authority representatives. quality control of materials and were
levelled sites. Associations were regis- responsible for ensuring the security of
The design is based on local building
tered with the local authority and all the warehouse.
traditions but with some upgrading,
work was unremunerated.
such as cement plastering. Materials Quantity
‘Nobody is vulnerable! Each house provides 48m of 2 I) Foundation
You can always give covered living space (6m x 8m) and has Twine for setting out 2 balls
something to your com- four rooms and one corridor with two Cement 2.5 sacks
munity!’ -Slogan of the mobi- doors. A foundation of hardcore, sand
Plastic sheeting for roof 0.2 roll
lisation teams in the returnee and cement is laid for each house and
communities the exterior of the mud-brick walls is Hardcore 10 m3
coated in ‘rough-cast’ – a mixture of Sand 5m3
Through the collectivisation of cement and other materials to provide II) Walls
tasks it was possible to build houses protection against the weather. Brick mould 1 piece
for all members of the community.
This would not have been possible if The roof is made of galvanised Plastic sheeting for water 1 piece
families had worked alone. Materials NKKłJCODAAPEJC=J@=@@EPEKJ=HNKKłJC Timber planks 5.5 pieces
that could not be produced were sheets were used for the guttering. Breeze blocks 8 pieces
provided: cement, foundation stones, Each house is equipped with a Poles for scaffolding 4 pieces
sand, construction wood, doors and rainwater catchment system, storing Mud bricks (20 x20x35 cm) 1800
windows, roof sheeting, as well as tools up to 1.2 cubic metres of water. The
and other non-food items. Materials III) Roof
system follows the local design and
were provided at the appropriate stage Poles for truss 26 pieces
uses cement layers cast together over
of construction. a reed mould. Local technicians were Nails 15cm 3 kg
Before house building began, the hired to produce the mould and others Nails 12cm 3 kg
agency contracted skilled masons to make the cement layers. Nails 10cm 3 kg
to build latrines, each shared by two To reduce the fuelwood used for Nails 6cm 2 kg
households. Once the latrines were cooking, the agency has developed a /KKłJCJ=EHO 3 kg
completed and the necessary con- stove design in collaboration with the /KKłJCODAAPO 29 pieces
struction materials were produced, Kigali Institute for Science and Technol-
house building could begin. Strip iron - for binding 18 pieces /
ogy. The stove can be built out of local joints 1.5m each
Although no other shelter materials and has greatly improved fuel IV) Exterior
materials were provided for the tran- ABł?EAJ?U LNKPA?PEJCPDA?KIIQJEPU†O Cement 3 sacs
sitional period between arrival in the natural resources from deforestation.
Doors 2 pieces
new villages and construction of new Planned shared services
houses, the agency supported initial Windows 4 pieces
In its third phase, the project is
livelihood recovery with a distribution V) Other
now concentrating on the following
of seeds and food rations. shared services: /KKłJCODAAPOBKNCQPPAN 2 pieces
The construction of each house Š  IQHPELQNLKOA ?KIIQJEPU
was overseen by a skilled mason hired centre to be shared with surround-
by the agency and paid a total of US$ ing villages. It is intended be a
EJłRAEJOP=HIAJPOBKNA=?DDKQOA semi-open hangar accommodating up
Each household appointed one person to 300 people with storage rooms
from the household to be an assistant for materials and products of local
to the mason, who monitored the workshops.
attendance and contribution of the
assistant. In return for providing their ŠA day centre for children whose
labour, the ‘assistants’ learned basic L=NAJPOSKNGA@EJPDAłAH@O
construction skills as well as improving Š KNADKHAO =NA =HOK LH=JJA@ PK
their physical living conditions. improve access to clean water.

22
A.8 0KI=HE= EREH?KJŃE?P/AOAPPHAIAJP Africa

Strengths and weaknesses (continued)


@A?EOEKJO =J@ =CNAAIAJPO I=@A S=O KB HEPPHA DAHL @QA PK 8 At times not all the humanitarian agencies involved
HEPAN=?UEOOQAO ?KIIQJE?=PA@ PDA O=IA IAOO=CAO 1DEO IA=JP PD=P
8 0AHA?PEKJ KB >AJAł?E=NEAO PKKG IQ?D HKJCAN PD=J =CNAAIAJPOOKIAPEIAOD=@PK>ANAJACKPE=PA@
ATLA?PA@  OK OKIA ?KJOPNQ?PEKJ SKNG >AC=J >ABKNA
GJKSEJCSDKPDAłJ=H>AJAł?E=NEAOSKQH@>A1DEOHEIEPA@
L=NPE?EL=PEKJ

Photos: Ombretta Tempra


Sites and services: the project focused on negotiating land and providing access,
secure compound walls, water and sanitation.
Background
KOO=OK EO = ?K=OP=H PKSJ EJ PDA 1DALNKFA?PEJ@ENA?PHUP=?GHA@CKR- agency to improve livelihood oppor-
-QJPH=J@ NACEKJ KB JKNPDANJ 0KI=HE= ernance-related issues relating to land, PQJEPEAOBKN>AJAł?E=NEAO=J@LNKIKPA
-QJPH=J@  SEPD  IEHHEKJ IKOPHU and broader urban development and LA=?A>APSAAJPDA&!-O=J@PDADKOP
nomadic/pastoralist inhabitants, has ?EPULH=JJEJCEOOQAOLLNK=?DEJCPDAOA LKLQH=PEKJ
>AAJ OAIE=QPKJKIKQO OEJ?A  EOOQAO@ENA?PHU SEPDKQP=?HA=NHUREOE>HA
 ?KIIEPPAA S=O AOP=>HEODA@ PK
Due to its relative stability, it has LNKFA?P SKQH@D=RA>AAJ@EBł?QHP
E@AJPEBUH=J@SEPDEJPDA?QNNAJPQN>=J
become an attractive area for IDPs
Implementation CNKSPD =NA=O !QNEJC /=I=@=J  ?=HHO
ŃAAEJC ?KJŃE?P EJ 0KQPD AJPN=H
+ACKPE=PEKJO SEPD =QPDKNEPEAO BKN SANAI=@ABKNH=J@@KJ=PEKJO#ERAKB
0KI=HE=
accepting the permanent resettlement PDAKBBANA@OEPAOSANAOAHA?PA@=J@KB-
KOO=OK D=O = OECJEł?=JP LKLQH=- KB&!-OSEPDEJKOO=OK =J@PDANAH=PERA ł?E=HHUD=J@A@KRANPKPDAIQJE?EL=HEPU
PEKJKB&!-O I=JUKBSDKID=@>AAJ provision of suitable land, began in 1DAH=J@PN=JOBANS=OAJ@KNOA@>UPDA
LNAOAJPBKNKRANPAJUA=NO1DAHERAHE-  1DAOA JACKPE=PEKJO SANA HEJGA@ OD=NE=?KQNPEJ!A?AI>AN
hood opportunities created by the fast- to a joint UN strategy for IDPs in 4EPD JK ?HA=N HAC=H BN=IASKNG
developing port of Bossaso is a strong 0KI=HE=LQ>HEODA@EJ in Puntland, customised ‘letters of
LQHHB=?PKN =HKJCSEPDOKIA&!-O†?H=J
Once a strategy for Bossaso had =HHKPIAJP†D=@PK>A@ARAHKLA@PKOQ>-
?KJJA?PEKJOEJPDA=NA=
>AAJ=CNAA@QLKJ>APSAAJDQI=JEP=N- OPEPQPABKN=JĺKSJANODELPEPHA†AJAł?E-
There is no land administration and ian agencies and Bossaso authorities, aries received the right of occupation,
PDANA=NABAS@K?QIAJP=NUNA?KN@O OK PDALNKFA?P>AC=JEJ&PS=OEILHA- QOA =J@ EJDANEP=J?A BKN PDA łNOP 
?QOPKI=NUH=S OA?QH=NH=S=J@OD=NE= mented by a consortium of agencies, UA=NOBPANPDEO A=?DB=IEHUSKQH@=HOK
H=S=HHKRANH=L =HH KB SDKI SANA NALNAOAJPA@ EJ PDA =?MQENAPDANECDPKB@EOLKO=HĠOAHHEJCPDA
JASHU AOP=>HEODA@ 0KI=HE= 0DAHPAN LNKLANPUBKNLNKłP
#KNPDA@K?QIAJP
Aim of the project to provide the strongest protection for
HQOPAN
The idea of the permanent reset-
&!-PAJQNA EPS=OOECJA@>UPDA>AJAł-
PHAIAJP LNKFA?P S=O PK OQ>OP=JPE=HHU KJOPNQ?PEKJS=O?KILHAPA@>UPDA
ciary, the mayor, the minister of local
improve IDP protection, security of AJ@KB1DA@QN=PEKJKBPDALNKFA?P
government and the magistrate of the
tenure, access to basic services and in- S=OHKJCANPD=JEJEPE=HHUAJREO=CA@ @QA
OD=NE=?KQNP
BN=OPNQ?PQNAĠAOLA?E=HHUS=PAN=J@O=JE- PK @EBł?QHPEAO EJ K>P=EJEJC H=J@  = HKJC
P=PEKJ
=J@PKLNKRE@A=OKHE@>=OABKN >AJAł?E=NU OAHA?PEKJ LNK?AOO =J@ PDA 0AHA?PEKJKB>AJAł?E=NEAO
EJ?KIACAJAN=PEJC =?PEREPEAO ĠNAJPEJC challenges of maintaining consensus  AJAł?E=NU OAHA?PEKJ PKKG HKJCAN
out rooms, space for shops or pro- SEPD=NAH=PERAHUQJOP=>HA=J@EJATLANE- PD=J LH=JJA@ 0KIA  KB LHKPO
@Q?PERA =?PEREPEAO
 EJ =@@EPEKJ PK PDA AJ?A@HK?=HCKRANJIAJPOUOPAI SANA PK >A =HHK?=PA@ PK &!-O =J@
LNKREOEKJKB=>APPANODAHPAN  PK LKKN B=IEHEAO BNKI PDA DKOP
Land issues ?KIIQJEPU 1DEO =LLNK=?D HEIEPA@
Freeing IDPs from paying rent for The original site proposed by the
PDA EJPANAOP KB LKSANBQH IAI>ANO KB
EJ=@AMQ=PA ODAHPAN IA=JP PD=P PDAU HK?=H =QPDKNEPEAO S=O NAFA?PA@ KJ PDA
the host community from exerting
could use resources for basic services, CNKQJ@O PD=P EP S=O PKK B=N BNKI PDA
PKK IQ?D EJŃQAJ?A EJ PDA OAHA?PEKJ
OQ?D =O A@Q?=PEKJ =J@ DA=HPD KJ- PKSJ=J@HEIEPA@A?KJKIE?EJPACN=PEKJ
KB &!- >AJAł?E=NEAO -KOPK??QL=J?U
OPNQ?PEKJ PN=EJEJC SKQH@ LNKRE@A >AJ- KBPDA&!-OSEPDPDADKOP?KIIQJEPU
=OOAOOIAJPO BKQJ@ PD=P BAS KB PDA
Ał?E=NEAOSEPDJASOGEHHO 1DEO S=O = GAU NAMQENAIAJP >U PDA
QN>=JLKKN>AJAł?E=NEAOEJPDALNKFA?P

24
Africa Shelter Projects 2008 A.8

Photo: J. Ashmore
*=JUKBPDAOEPAOEJEPE=HHUKBBANA@SANANAFA?PA@>A?=QOAPDAUSANAB=NBNKIKOO=OK=J@LKOOE>HAHERAHEDKK@O1DAłRAOAHA?PA@OEPAOSANA
donated following requests for land made during Ramadan.

occupied their site, preferring instead KJPN=?PKNO SANA QOA@ PK PN=?A The cost for the second phase
PK NAJP KQP PDA JAS =??KIIK@=PEKJ NK=@O BKN PDA JAS OAPPHAIAJP =J@ S=O 20  LAN DKQOEJC QJEP 1DEO
KN HA=RA PDA DKQOA AILPU  SDEHA PDA ?KJJA?P EP PK PDA IQJE?EL=H S=PAN excluded agency staff costs and food-
occupancy rate on project completion OQLLHU1DEO=HOK>AJAłPA@PDKOAHEREJC BKNSKNG ?KJPNE>QPEKJO >QP EJ?HQ@A@
BNKI&!-B=IEHEAOS=O =HKJC PDA NKQPA KB PDA JAS S=PAN all other logistics, administrative and
LELAO J KJCKEJC OKH=NLKSANA@ I=PANE=H?KOPO
The selection process, managed
OPNAAPHECDPEJCLNKFA?PS=O=HOKOP=NPA@
by the multi-representative Bossaso Logistics and materials
PKS=N@OPDAAJ@KBPDALNKFA?P
selection committee, began in *=PANE=HO SANA LNK?QNA@ HK?=HHU 
0ALPAI>AN  &!- >AJAł?E=N- LHKPS=OLNKRE@A@SEPDEJPDAOAP- SEPD?KJPN=?PKNONAOLKJOE>HABKNPDAEN
EAO SANA OAHA?PA@ >U LNEH   >QP tlement for each family to construct KSJLNK?QNAIAJP
=CNAAIAJPKJQN>=JLKKN>AJAł?E=NEAO PDAEN KSJ DKQOA  SEPD OQLLKNP BNKI
Bill of quantities
S=OJKPNA=?DA@QJPEH+KRAI>AN PDA?KJOKNPEQI
1DA BKHHKSEJC P=>HA ODKSO PDA >EHH
Before selecting individual families, 1SK@EBBANAJP=CAJ?EAOEILHAIAJP- KBMQ=JPEPEAOBKN-D=OAKBPDALNKFA?P 
PDA &!- OAPPHAIAJPO SEPD PDA SKNOP A@PDA?KJOPNQ?PEKJKBPDADKQOEJC =RAN=CA@BKN=OEJCHAQJEPĠOKIAQJEPO
ODAHPAN ?KJ@EPEKJO SANA E@AJPEłA@ QJEPOEJPSKLD=OAOQOEJC?KJPN=?PKNO SANA ?KNJAN QJEPO N=PDAN PD=J BNAA-
0AHA?PEKJ?KIIEPPAAOSANABKNIA@EJ 1DA łNOP LD=OA PKKG łRA IKJPDO =J@ OP=J@EJC

A=?D KB PDAOA OAPPHAIAJPO =J@ SANA involved the construction of foun-
P=OGA@SEPDLQPPEJCBKNS=N@EJ@ERE@Q=H @=PEKJO  >KQJ@=NU S=HHO  O=JEP=PEKJ Materials Quantity
DKQOADKH@O SDK D=@ HERA@ EJ KOO=OK ĠODKSAN PKEHAPO=J@OALPE?LEPO
=J@= Hollow concrete blocks 281 pieces
BKNIKNAPD=JOETUA=NO SEPDJKłTA@ ITIŃKKNOH=>-D=OA?KOP20 (150 mm x 390 mm x 180
mm)
=OOAPO=J@=PHA=OPPDNAA?DEH@NAJ*KNA  LANDKQOEJCQJEP
@AP=EHA@ ĺRQHJAN=>EHEPU† ?NEPANE= SANA Cement for mortar and 5 bags
The second phase began after concrete ring beam
rejected due to the complexity of
>AJAł?E=NU OAHA?PEKJ S=O ?KILHAPA Sand for mortar and concrete 1 tonne
0KI=HEB=IEHUOPNQ?PQNA=J@PDAH=?GKB ring beam
=J@ PKKG PDNAA IKJPDO  łJEODEJC EJ
E@AJPEł?=PEKJ@K?QIAJPO
!A?AI>AN  1DA >AJAł?E=NU Aggregate / ballast for ring 0 tonnes
0AHA?PEKJ HEOPO SANA I=@A LQ>HE? families moved onto their plot, living in beam concrete
PK =HHKS PEIA BKN ?KILH=EJPO PK >A =PAILKN=NUPAJPHEGAODAHPANLNKRE@A@ Y8 bars (12m long) for ring 4 pieces
EJRAOPEC=PA@ ĠKJA KB PDA OAPPHAIAJPO >U=JKPDAN=CAJ?UQJPEHPDASKNGS=O beam
produced a list that excluded an ethnic ?KILHAPA@ 1DA PAILKN=NU ODAHPANO R6 rings (6m long) for ring 2 pieces
IEJKNEPU
 1DA łJ=H OAHA?PEKJ KB PDA SANAH=PANQOA@=O=@@EPEKJ=HNKKIOKN beam
 &!- B=IEHEAO S=O I=@A PDNKQCD BKNOPKN=CA 6x1 white wood for form 12 metres
work
a lottery broadcast on local TV and
#KK@ BKN SKNG BKN = I=TEIQI KB 28-gauge galvanised 14 pieces
N=@EK SDE?DS=O@AAIA@=B=ENIAPDK@
 @=UO S=O LNKRE@A@ PK >AJAł?E=N- corrugated iron sheets
>U>AJAł?E=NEAO
ies for the construction period, along Structural grade 150 x 50 18 m
SEPD20PKDENA=I=OKJĠB=IEHEAO (6' x 2') timber roof rafters
‘Compared to the shelter OKIAPEIAO @E@ I=OKJNU SKNG PDAI- Structural Grade 75 x 50 27 m
I had before, I can now OAHRAO SEPDPA?DJE?=HOQLLKNP =J@GALP (3' x 2') timber roof purlins
say that my life has im- PDAIKJAU
1DAI=EJ=CAJ?ULNKRE@A@ /KKłJCJ=EHO 1 kg
proved 100 percent. The technical support in the form of cash
resettlement programme Ordinary wire nails 1 kg
BKNOGEHHA@H=>KQN=J@AILHKUIAJPKB=
was completely transpar- BKNAI=JBKNOQLANREOEKJ
Steel single doors
(0.8m x 2m)
1 set
ent and well done’.
Giving the families the oppor- Double leaf-steel window 1 set
PQJEPU PK OAHA?P PDAEN KSJ I=OKJ (1m x 1m )
Technical solutions ĠN=PDAN PD=J BKHHKSEJC PDA SEODAO KB White wash 4 bags
This project provided the infra- PDA HK?=H =QPDKNEPEAO SDK S=JPA@ PDA Brushes for whitewashing 2
structure for a serviced community SDKHA ?KJOPNQ?PEKJ LNK?AOO ?KJPN=?P- Bamboo/rope for ceiling mats As
OAPPHAIAJP  SAHH EJPACN=PA@ SEPD PDA A@ KQP
 IA=JP PD=P PDAU D=@ CNA=PAN required
host population, and support to IDPs MQ=HEPU ?KJPNKH KRAN PDA SKNG @KJA
BKNPDA>QEH@EJCKBEJ@ERE@Q=H@SAHHEJCO =J@ =HHKSA@ PDA =CAJ?U PK =RKE@ PDA
SEPDEJPDAOAPPHAIAJP LNK>HAIOKB=PAJ@ANEJCLNK?AOO

25
Africa 0DAHPAN-NKFA?PO A.9

Strengths and weaknesses (continued)


=HHKSA@PDALNKFA?PPKIKRAMQE?GHU!KJKN?KKN@EJ=PEKJ 8 4EPDKQP PDA @EOPNE>QPEKJ KB = BN=IA  PDA @EOPNE>QPEKJ
IA=JP BQJ@EJC SAJP PDNKQCD = ?AJPN=H ?D=JJAH  =RKE@EJC KB LH=OPE? ODAAPEJC @E@ JKP ?KJOPEPQPA = ?KILHAPA ĺODAHPAN
@QLHE?=PEKJKBLNKFA?PO OKHQPEKJ†&BJKPLNKRE@A@>U=J+$,SKNGEJCEJPDAłAH@ 
9 &J@ERE@Q=H=CAJ?EAOEJPDAłAH@=QCIAJPA@PDALNKREOEKJ &!-OD=@PKLNKRE@APDAOAEPAIOPDAIOAHRAO SDE?D?=NNEA@
KBODAHPANEPAIOSEPDPDAENKSJHK?=HHULNK?QNA@I=PANE=HO NEOGOEJPANIOKB?KHHA?PEJCI=PANE=HBNKIQJO=BA=NA=OKN
ĠOQ?D=OLKHAO
PKLNKRE@AODAHPANOKHQPEKJO D=REJCPK>QUHK?=HI=PANE=HO=PDECDLNE?AO
8 /KHAO ?KQH@ D=RA >AAJ @A?E@A@ IKNA MQE?GHU =P PDA 8 0DAHPAN EOOQAO SANA OAAJ =O >AEJC @A=HP SEPD >U PDA
>ACEJJEJC  =O OHKSIKREJC @EO?QOOEKJO @AH=UA@ EJEPE=H LNKREOEKJ KB >=OE? I=PANE=HO =J@ PDA LNKFA?P D=@ HEIEPA@
EILHAIAJP=PEKJ PA?DJE?=H OQLLKNP PK DAHL ?KJOE@AN SD=P KPDAN ODAHPAN
8 0KIA GAU EPAIO ĠLKHAO =J@ ?KKGEJC BQAH
 SANA EOOQAOIECDPJAA@PK>A=@@NAOOA@
LNK>HAI=PE? PK LNK?QNA EJ >QHG =J@ PDA LKHAO SANA JKP 8 ??AOOS=OOARANAHUNAOPNE?PA@@QAPKPDA?KJŃE?PEPOAHB
OQLLHEA@ =J@HEIEP=PEKJOOAP>UPDACKRANJIAJP

Photo: Joseph Ashmore


Queue for distribution of materials

Situation before emergency Situation at the initial FANNU?=JO=J@OK=L&J0ALPAI>ANPDA


ABKNA   !=NBQN S=O KJA KB response stage JQI>AN KB >AJAł?E=NEAO EJ JAA@ S=O
PDA LKKNAN =NA=O KB +KNPD 0Q@=J N=EOA@PKIEHHEKJ=J@>U!A?AI>AN
P PDA AJ@ KB   DQI=JEP=NE=J
HPDKQCD PDANA =NA JK AT=?P łCQNAO  =NKQJ@KBPDEOP=NCAPLKLQ-
=CAJ?EAOSANA=>HAPK=??AOOHAOOPD=J
EPOIKOPHUNQN=HLKLQH=PEKJD=@HEIEPA@ H=PEKJ D=@ NA?AERA@ =OOEOP=J?A 1DEO
 KB &!-O @QA PK PN=RAH NAOPNE?PEKJO
=??AOOPKO=BA@NEJGEJCS=PAN=J@D=@ AMQ=PA@PK=HIKOPD=HB=IEHHEKJ>H=JGAPO
EILKOA@>UPDA$KRANJIAJPKB0Q@=J
LKKN ?DEH@ JQPNEPEKJ 1DA NACEKJ†O EJ- =J@ KPDAN I=PANE=H >U PDA KJOAP KB
1DEOI=@A=??QN=PAJAA@O=OOAOOIAJP
?NA=OEJCHU O?=N?A J=PQN=H NAOKQN?AO KB SEJPAN  J =@@EPEKJ=H AOPEI=PA@ 
@EBł?QHP1DA*=UNAREOEKJKBPDA
CN=VEJCH=J@=J@S=PANSANAKJAKBPDA S=O ?KRANA@ >U KPDAN =CAJ?EAO JKP
KJOKHE@=PA@ LLA=HO -NK?AOO BKN
B=?PKNO>ADEJ@PDA?KJŃE?P QOEJCPDA?KIIKJLELAHEJA
0Q@=J AOPEI=PA@ = 20  IEHHEKJ
1DA OEPQ=PEKJ EJ !=NBQN >A?=IA JAA@ BKN ODAHPAN =J@ JKJBKK@ EPAIO Technical solutions
EJ?NA=OEJCHU RKH=PEHA PDNKQCDKQP   BKNPDANAI=EJ@ANKBPDAUA=N 4EPDPDAODAHPANI=PANE=HOOQLLHEA@ 
SEPD NABQCAA IKRAIAJPO >ACEJJEJC 1DAOARANAH=?GKBODAHPAN=R=EH=>HA >AJAł?E=NEAOSANA=OOQIA@PK>A=>HA
=O A=NHU =O LNEH 1DA ?NEOEO >AC=J PK &!-O S=O = I=FKN DA=HPD PDNA=P  PK?KJOPNQ?P>=OE?ODAHPANOQOEJCLKHAO
PK AO?=H=PA =P PDA AJ@ KB PDA UA=N SEPDATLKOQNAPKDA=P=J@@QOP@QNEJC =OBN=IAO LH=OPE?ODAAPEJC=O=NKKB=J@
/AOLKJOA PK PDA ?NEOEO EJ !=NBQN S=O PDA@=U=J@RANU?KH@PAILAN=PQNAO=P NKLABKNłTEJCO
D=ILANA@ >U PDA 0Q@=JAOA CKRANJ- JECDPU*=U ATLKOQNAPKN=EJOHA@PK %KSARAN  LNK?QNEJC LKHAO EJ >QHG
IAJP†O NAOPNE?PEKJ KB =??AOO PK PDA =JEJ?NA=OAEJ?KIIQJE?=>HA@EOA=OAO =P=J=PEKJ=HHARAHLNKRA@PKK@EBł?QHP
=BBA?PA@=NA=O =J@PDAOASANAHABPKQPKBPDAL=?G=CA
0AHA?PEKJKB>AJAł?E=NEAO
1DEO IA=JP PD=P JK ?KILHAPA ODAHPAN
1DALNKFA?P=EIA@PKNA=?D=HHKB
OKHQPEKJS=OLNKRE@A@
PDKOA @EOLH=?A@ >U łCDPEJC EJ !=NBQN 
SDE?D>ULNEHS=OAOPEI=PA@PK *=JU=CAJ?EAOEJPDAłAH@LH=JJA@
>A=PKP=HKBIEHHEKJLAKLHAAJAł- = ODAHPAN NAOLKJOA SDANA PDAU
?E=NEAOSANAPDAJ@ERE@A@EJPK?=PACK- =QCIAJPA@ PDA I=PANE=HO NA?AERA@
NEAOKBBQHHKNL=NPE=H=OOEOP=J?AOKPD=P PDNKQCD PDA LELAHEJA SEPD EPAIO
PDA IKOP RQHJAN=>HA SKQH@ NA?AERA = PDAU LNK?QNA@ HK?=HHU  OQ?D =O LKHAO
BQHH L=?G=CA KB EPAIO 1DKOA NA?AEREJC %KSARAN PDAH=?GKB=?HA=NE@A=KBDKS
Joseph Ashmore

=L=NPE=HL=?G=CASANA=OOQIA@PK>A >AJAł?E=NEAOSKQH@QOAEPAIOPK?NA=PA
=>HAPKOQLLHUIEOOEJCI=PANE=HOPDAI- ODAHPANOIA=JPPD=POKIA>AJAł?E=NEAO
OAHRAO  SDE?D I=U JKP D=RA =HS=UO SKQH@D=RAD=@PKOKQN?A?KJOPNQ?PEKJ
>AAJPDA?=OA I=PANE=HOPDAIOAHRAO1DAOAI=UD=RA
>AAJ ATLAJOERA  KN  EJ PDA ?KHHA?PEKJ
U QCQOP   KB PDA >AJAł?E=N-
KBLKHAO D=RAAJP=EHA@PDAO=IANEOGO
Unloading a lorry of relief items
EAOSANANA=?DA@SEPDĺłNOPPEAN†+#&O 
PKLANOKJ=HOA?QNEPUPD=PI=JUSKIAJ
?KILNEOEJC LH=OPE? ODAAPEJC  >H=JGAPO 
B=?A@SDAJ?KHHA?PEJCSKK@BKNBQAH

27
A.9 !=NBQNĠKJCKEJC
 KJŃE?P*=PANE=HO@EOPNE>QPEKJ Africa

1DA HEIEPA@ ?KJOE@AN=PEKJ KB OP=NPA@ H=PAN EJ PDA UA=N


 J +$, 1DA ?AJPN=HEOEJC KB LNK?QNAIAJP
PA?DJE?=HODAHPANEOOQAOS=OQJOQNLNEO- S=ONAOLKJOE>HABKNPDAKJCKEJCPN=JO- =J@PDAI=J=CAIAJPKB=JABł?EAJP=J@
EJC ?KJOE@ANEJC PD=P PDA LNKCN=IIA†O LKNP=PEKJ =J@ OPKN=CA KB PDAOA EPAIO ?KOPABBA?PERAOQLLHU?D=EJNA@Q?A@PDA
I=EJ BK?QO S=O KJ PDA HKCEOPE?=H ?D=H- PK OQ>HARAH S=NADKQOAO =J@ PDA 2+ HKCEOPE?OKRANDA=@OBKN=CAJ?EAOKJPDA
HAJCAOKBI=OO@EOPNE>QPEKJ =CAJ?UPD=PI=@APDAKNECEJ=HLELAHEJA CNKQJ@ BNAAEJCPDAIQLPK?KJ?AJPN=PA
LNKLKO=HS=OI=@ANAOLKJOE>HABKN?K- KJ@ENA?P=OOEOP=J?APK>AJAł?E=NEAO
Implementation KN@EJ=PEJCPDAOQLLHU?D=EJ
*AAPEJCO PK @EO?QOO PDA E@A= KB = 1DA ?KKN@EJ=PEJC =CAJ?EAO SANA
LELAHEJASANADAH@EJ*=N?D SEPD &J =@@EPEKJ  = PDEN@ 2+ =CAJ?U =>HA PK GAAL =J QLPK@=PA >NK=@
= ?KJ?ALP L=LAN BKN BQJ@EJC EJ?HQ@A@ =CNAA@KJLNEHPK=?P=O=ĺ?KJOECJAA† KRANREAS KB PDA NAMQENAIAJPO EJ
EJ PDA QL@=PA@ KJOKHE@=PA@ LLA=HO PK KBł?E=HHU NA?AERA EILKNPA@ CKK@O  !=NBQN  SDE?D DAHLA@ PK @ENA?P =OOEOP-
-NK?AOO NAHA=OA@ =P PDA >ACEJJEJC KB =JATPAJOEKJKBPDAENNKHAEJNA?AEREJC =J?APKPDKOA=NA=OIKOPEJJAA@=J@
*=U BKK@EPAIO1DEOS=O?NQ?E=H =OEJ@ERE@Q- LNARAJPA@=@QLHE?=PEKJKBNAOLKJOA
=H+$,OSANAQJ=>HAPK?HA=N?QOPKIO
4EPDOQ?D=H=NCA=BBA?PA@LKLQH=- JU =CAJ?U SEODEJC PK NA?AERA
=O MQE?GHU =O PDA SAHHAOP=>HEODA@ 2+
PEKJ =J@ PDA CKRANJIAJP NAOPNE?PEJC EPAIO BNKI PDA LELAHEJA D=@ PK łHH EJ
=CAJ?U
>KPD =??AOO =J@ EILKNPO  PDA I=EJ = NAMQAOP BKNI =J@ = >=OE? JAA@O =O-
=EIKBPDALELAHEJAS=OPKCAPAJKQCD ,JPDALNKCN=II=PE?OE@A ?KKN@E- OAOOIAJP BKNI 1DA LNK?QNAIAJP
JKJBKK@EPAIO=J@ODAHPANEPAIOEJPK J=PEKJKBJAA@O=J=HUOEO C=LE@AJPEł?=- =CAJ?U @AHERANA@ EPAIO PK "H ,>AE@
PDAD=J@OKB>AJAł?E=NEAO=OMQE?GHU=O PEKJ=J@EJPAN=?PEKJSEPDDQI=JEP=NE=J =J@KN +U=H= #NKI PDANA PDA +$,
LKOOE>HAPK?KRAN>=OE?JAA@O L=NPJANO EJ PDA łAH@ S=O ?=NNEA@ KQP NAOLKJOE>HA BKN @EOPNE>QPEKJ =NN=JCA@
>U PDA 2+ ?KKN@EJ=PEKJ =CAJ?U =J@ BKN @AHERANEAO PK PDAEN S=NADKQOAO EJ
!QNEJCLNEH=OPNQ?PQNAS=O
PDA =CAJ?U PD=P EJEPE=PA@ PDA SDKHA PDA@EBBANAJPOP=PA?=LEP=HO1DAEJ@ERE@-
=CNAA@QLKJBKNPDAI=J=CAIAJP=J@
LNKFA?P Q=H+$,ONAOLKJOE>HABKNI=GEJCPDA
EJEPE=H NAMQAOP SKQH@ PDAJ I=GA PDA
łJ=H@EOPNE>QPEKJPK>AJAł?E=NEAO
&JBKNI=PEKJOD=NEJCKJJAA@OC=LO 
?QNNAJPOPK?GO=J@OQLLHU?D=EJQL@=PAO
S=O=?DEARA@PDNKQCDNACQH=NIAAPEJCO
=J@=??AOOPK=JKLAJSA>OEPA
Logistics and materials
 >=OGAP KB JKJBKK@ EPAIO S=O
=CNAA@ KJ >U L=NPE?EL=PEJC =CAJ?EAO
1DEO >=OGAP EJ?HQ@A@ LH=JO BKN OKIA
O=JEP=NU EPAIO  ?HKPDEJC =J@ GEP?DAJ
OAPO&JEPE=HLH=JOBKN=@@EPEKJ=HODAHPAN
EPAIO„LKHAO=J@NKLA„SANA@NKLLA@
=BPANEPLNKRA@PKK@EBł?QHPPKLNKRE@A
PDAI -H=OPE? ODAAPEJC S=O IKOPHU
@KJ=PA@ BNKI =>NK=@ KN EILKNPA@
Joseph Ashmore

,PDANJKJBKK@EPAIOSANALQN?D=OA@
EJ(D=NPKQIKN+U=H=
Shelter items in the NFI
basket
+KPAġ,PDANEPAIO OQ?D=OO=JEP=-
PEKJ EPAIO  SANA =HOK OQLLHEA@ EJ PDA
Emergency shelters JKJBKK@ EPAI >=OGAP  >QP =NA JKP
EILHAIAJP=PEKJ KB PDA LELAHEJA 1DA
LNK?AOO S=O OQLLKNPA@ >U OARAN=H HEOPA@DANA
@KJKNO =J@ PDA łJ=H =HHK?=PEKJ KB NA-
‘Coordination with all of Materials Quantity
OLKJOE>EHEPUS=OQJ@ANP=GAJ>UPDA2+
the agencies was key. We H=JGAPO 2
KQJPNU1A=I1DAKNC=JEO=PEKJKBPDA
held weekly meetings in
(D=NPKQI=J@PDAłAH@ -H=OPE?ODAAP 
LELAHEJAS=OOLHEPEJPKPSKI=EJL=NPOġ ĠITI

=OQLLHUL=NP=J@=LNKCN=IIAL=NP
and set up information-
sharing systems such as a /KLA I
#KN PDA OQLLHU L=NP KB PDA website. No one had an -KHAO LH=JJA@ >QP
LNKCN=IIA  KJA 2+ =CAJ?U S=O excuse for not knowing JKP@EOPNE>QPA@
JKIEJ=PA@ BKN LNK?QNAIAJP  SDE?D what was going on!’ 0HAALEJCI=P 2
SKQH@>A@EOPNE>QPA@=OB=N=O=?AJPN=H- - Coordinator
EOA@ S=NADKQOA ĠPDKQCD PDEO LNK?AOO

28
Asia Shelter Projects 2008 B

Section B
Asia

B.8
&JCQODAPE=
KJŃE?P
B.1
Afghanistan
B.2 KJŃE?PNAPQNJO
Azerbaijan
KJŃE?P 
-=GEOP=J
"=NPDMQ=GA
B.3
India
"=NPDMQ=GA
B.10
0NEH=JG=
 KJŃE?PNAPQNJO
0NEH=JG= B.4
1OQJ=IE Indonesia, Aceh
"=NPDMQ=GA=J@POQJ=IE

&J@KJAOE= 'KCU=G=NP=
"=NPDMQ=GA

29
Asia Shelter Projects 2008 B.1

Photo: Joseph Ashmore


Urban housing in Kabul

Project background Land issues Technical solutions


Since 2002, there have been over The project could only provide Shelter programmes in Afghani-
5 million returnees to Afghanistan, shelter materials to those who had stan started as a distribution of tents
@EOLH=?A@KRANUA=NOKB?KJŃE?P1DA land to build on. Returnees with no and household items. The main focus
largest returns are from Pakistan and land had apply to the Government of gradually turned to shelters.
Iran. Three million refugees remain in Afghanistan’s managed land allocation
This programme began building
host countries and it is estimated that 1 scheme. However, this scheme has
mud-block shelters with wooden roofs,
million more will return by 2013. proven slow to operate in the past. As
windows and doors. Due to supply and
of mid-2008, approximately 500,000
1DKOA NAPQNJEJC PDNKQCD KBł?E=H sustainability issues, steel was used to
returnees have registered for land and
schemes receive a ‘one-off’ grant of replace the timber.
very few of them are now living on reg-
US$ 100. ‘There are strong indications
istered land.
0AHA?PEKJKB>AJAł?E=NEAO that more women are now
It was originally anticipated that 55 participating in programme
Traditionally, there is serious under- land allocation sites would be provided
representation of women in public
decision-making’.
through the support of the Ministry of
decision-making in Afghanistan and sig- Refugees and Returnees. This number As the programme worked across
JEł?=JP?KJPNKHEOEJPDAD=J@OKB=BAS was reduced to thirteen, partly due to the entire country of Afghanistan, there
non-elected individuals. To remedy this, the unsuitability of selected sites. SANA OECJEł?=JP R=NE=PEKJO EJ ?HEI=PA 
>AJAł?E=NU ?KIIEPPAAO SANA BKNIA@ cultural values, construction materials,
in each project area. Each committee One of the challenges with building capacity of implementing partners and
consisted of the lead and implementing on new sites has been to coordinate community support mechanisms. This
organisation, a local government repre- with other organisations to provide led to the development of standard
sentative and members of the popula- services on previously uninhab- BKNI=PO BKN PA?DJE?=H OLA?Eł?=PEKJO 
tion for whom the project was targeted. ited sites. In some cases this has not data collection, reporting, feedback and
happened and has led to shelters being analysis.
unusable.

31
B.1 Afghanistan - 2002 - Returns - Shelter construction Asia

The following key regional varia-


tions of shelter design were adopted:
Š Dome-type ceiling without beams
in west and north Afghanistan;
Š Flat roof with beams in central,
east, south-east and south Afghanistan;
Š Smaller windows in the Central
Highlands area than in other areas.
Relatively wider windows can also be
found in the central region.

Photo:Øyvind Nordlie
Implementation
The shelter programme is
based on a four-stage process:
Stage I: Planning - Allocation
of shelter per region/province/
@EOPNE?P  >Q@CAPEJC  E@AJPEł?=PEKJ KB
implementing partners, establishment
of materials supply contracts. Completed shelters

Stage II: Contracting – Establishing


contracts with implementing partners.
Stage III: Assessment – Local needs
=OOAOOIAJP =J@ >AJAł?E=NU OAHA?PEKJ
Stage IV: Implementation.
Š Work started on site and
foundation completed (eight weeks).
Š Walls erected, lintels installed

Photo: Wondwossen Tef-


(four weeks).
Š Shelter completed (four weeks).
Š Handover (liquidation period, four
weeks).
Logistics and materials
&JPDAłNOPUA=NOKBPDEOLNKCN=IIA 
the timber was sourced from South
Africa and Pakistan. Supply challenges
and major sustainability issues with the Steel trusses
sourcing of timber have led to revised
During 2007 and 2008, rising costs of steel led to cost escalations from US$
designs for 2007 onwards that will use
900 per shelter to in excess of US$ 1500 per shelter. This caused serious budget
steel in place of timber.
shortages and the materials used consequently needed to be reassessed.
Photo: Wondwossen Tef-

Photo:Øyvind Nordlie

Completed shelter Internal view

32
B.2 VAN>=EF=J KJŃE?P-AKLHA@EOLH=?A@2LCN=@AKB?KHHA?PERA?AJPNAO Asia

Photo: NRC Azerbaijan

Photo: NRC Azerbaijan


Photo Predes
Selection of buildings Technical solutions
A programme to upgrade the public Inhabitants saw broken sewerage as
Photo: NRC Azerbaijan

buildings and schools was adopted. the greatest problem in the buildings.
Other common problems included
Criteria for the selection of
shortage of water, leaking roofs and
public buildings for inclusion in the
@=ILJAOOO=NAOQHP LH=OPANEJC ŃKKNO
programme were adjusted throughout
and ceilings in toilets and bathrooms
the project period. However, the main
were damaged in most buildings.
criteria remained unchanged: at least
70% of building inhabitants had to be A typical repair of a public building
Bathrooms before and after upgrade IDPs; other organisations could not involved:
have previously worked in the building;
Context Š rehabilitation of the shared areas
and the building had to be in exception-
1DA ?KJŃE?P EJ +=CKNJK(=N=>=GD - toilets, bathrooms, washing rooms,
ally bad condition.
between Azerbaijan and Armenia in the kitchens and corridors;
early 1990s led to over 500,000 people &J EPO łNOP UA=NO Ġ
 PDA Š infrastructure repairs - electricity,
becoming internally displaced and a project prioritised hostels located sewerage, water and sewerage pipes;
further 200,000 becoming refugees. next to each other and that shared a Š repair of roofs;
Around half of the internally displaced common yard. Such locations made Š installation of new water heaters,
people moved to urban areas, most of repair works easier and reduced costs. sinks, stoves, faucets, showers, light
them to the capital, Baku. Letters from local or central authori- bulbs, circuit breakers, switchboards,
ties, as well as applications from the windows and doors;
In Baku, many people moved into residents, were also considered in the Š installation of electricity
dilapidated, overpopulated public selection process. transformers (this was not costly but
buildings, most of which were origi- served a large number of IDPs).
nally student residence halls and dor- The willingness of the building
mitories. The buildings were designed residents to work with the NGO
with rooms intended for one person, S=O PDA @A?EOERA B=?PKN EJ PDA łJ=H The most durable output of the
JKP BKN B=IEHEAO KB łRA KN IKNA 1DA selection. Inhabitants had to be willing project was the provision of electric-
kitchens and bathrooms were shared. In to volunteer to help with repairs, and ity systems (including transformers and
some cases the buildings were without to clean corridors and shared areas. In switchboards) and new roofs.
water supply or sanitation. This was in some cases, works had to be suspended
The project was not always success-
PDA ?KJPATP KB = OECJEł?=JP CNKSPD EJ QJPEHPDA?KIIQJEPU=CNAA@PKBQHłHPDA
ful in solving problems with the water
wealth in Baku, in part due to the oil NGO’s conditions.
supply. A durable solution would have
industry. +KP ARANUKJA >AJAłPA@ AMQ=HHU required dealing with the malfunctions
The temporary shelter solutions from the project. Although similar outside the building, which was beyond
BKQJ@ BKHHKSEJC PDA ?KJŃE?P H=OPA@ works were performed in most of the the scope of the project. Cooking
longer than was expected. Many of buildings, several of them were only stoves and taps in the rehabilitated
PDKOA @EOLH=?A@ BKHHKSEJC PDA ?KJŃE?P partially rehabilitated (only roof or buildings had short lifespans because
electricity) for a variety of reasons. many people used them.
Photo: Predes

had been living in one of twelve camps.


Photo: NRC Azerbaijan
Photo: NRC Azerbaijan

The last of these did not close until


  =BPAN łBPAAJ UA=NO 2LKJ EPO
closure, many of the camp residents
were resettled rather than being able
to return to their original homes.
The climate in Baku is cool and wet
in the winter and hot and dry in the
summer, leading to challenges of leaking
roofs and poor sanitation. Kitchens before and after upgrade
34
Asia Shelter Projects 2008 B.2
Implementation
An average building took two

Photo: NRC Azerbaijan


months to rehabilitate, with the imple-
IAJP=PEKJ O?DAIA >AEJC OECJEł?=JPHU
improved over the years.
In the beginning, contractors
were hired to implement the work.
In practice, this meant that the NGO
purchased construction materials
and hired contractors to implement
all works. The payment of labourers
lacked transparency and important ir-

Photo: NRC Azerbaijan


regularities in the system were found.
This led to the dismissal of project staff
and the adoption of a new implementa-
tion scheme.

Photo: NRC Azerbaijan


After two years of project imple-
mentation the NGO hired construc-
tion workers directly.
BPAN łRA UA=NO KB LNKFA?P EILHA-
One of the occupied public buildings in Baku
mentation the NGO subcontracted a
local company to supply construction
materials. The supplier was selected on Occupancy
Along with the large-scale con-
the basis of submitted quotes. A survey conducted upon the com-
struction of new settlements, urban
pletion of the project found that all of
Over time, a good team of core public building rehabilitation became
the buildings were still occupied by
construction workers, most of them part of the 2004 State Programme on
IDPs. However, the occupancy of indi-
IDPs, has been formed. Many of these IDPs and Refugees. In many cases the
vidual rooms changed constantly. Many
have subsequently found work on repairs implemented by the State Social
IDP families moved out of the buildings
other projects run by the NGO. Fund for the Development of IDPs have
to an outskirt of Baku. In some cases,
copied this project.
The involvement of community the emptied rooms were given to local
members in the work was seen as a key families or those moving to Baku from
to the successful implementation of other regions, but usually to other
the project. The goal of the community IDPs. According to the building su-
LNKCN=IIAS=OPKAJOQNA>AJAł?E=NU perintendents, IDPs sell their rooms
to relatives or friends. Yet some also

Azerbaijan
buy-in and participation in the project.
This was believed to be instrumental in lock their rooms and keep them as a
creating a feeling of ownership and in storage space.

Rhyner
the further maintenance and upkeep of Obviously, the families who could
Kurt NRC
the rehabilitated buildings. afford to leave the public buildings
were those who managed to establish Photo:
some livelihoods and were relatively
Photo

well off. The remaining occupants of


the public buildings are still the most
vulnerable of those living in the cities.
Photo: NRC Azerbaijan
Photo: NRC Azerbaijan

‘The project was based


on learning...We drew
conclusions from the
previous experience and
made improvements
every year. The work be-
?=IAIKNAABł?EAJPKRAN
time’.
Wiring before upgrade
- Project staff member
Corridors before and after upgrade

35
Asia Shelter Projects 2008 B.3

Photo: David Sanderson


!=I=CABKHHKSEJCPDAA=NPDMQ=GA=P$QF=N=PPD=P?KILHAPAHU@AOPNKUA@KRAN DKQOAO&JPDAłNOPSAAGO=BPANPDAA=NPD-
quake the organisation distributed non-food items through partners. This was followed by a transitional shelter programme.

After the earthquake to have introduced some inclusion (as ‘What the international
The earthquake struck the State of well as exclusion) errors.
NGO saw as normal
Gujarat on 26 January 2001, and par-
Technical solutions professional procedures, the
ticularly affected the district of Kutch
A low-cost shelter design was local organisation saw as
and its neighbouring areas.
developed using low 1m walls and a
meaningless bureaucracy. The
News of the earthquake spread bamboo-framed and grass-thatched
rapidly through the international media. roof. With time it was recognised international NGO had bent
Local communities, the Central and that there was a need to preserve the its own rules in favour of the
State governments, the defense forces, CN=OOBKN=JEI=HBK@@AN OKPDANKKłJC local NGO to such an extent
donors, and international and national material was replaced with locally PD=P KQN łJ=J?E=H ?KJOQHP=JP
NGOs all responded to the emergency. produced Mangalore clay tiles.
became highly concerned…
Within one week, a network The dimensions of the shelters But ultimately there is no
of 22 local organisations, including de- built were approximately 4m x 2½m. doubt that the international
velopmentally minded architects, had Although this provided a covered area
formed a partnership agreement with of only 10m2 for a family, these dimen- NGO's real achievement in
an international organisation. Members sions were carefully selected to focus the Gujarat response was its
of this local network had been working on earthquake safety. A larger span link with local NGOs and the
on low-cost construction technolo- SKQH@D=RANAMQENA@OECJEł?=JPHUIKNA temporary housing project’.
gies prior to the earthquake and were materials to ensure the same level of – Evaluation by the Disasters
able to act as an effective coordination safety.
mechanism. During the earthquake
Emergency Committee (the donor)
The distribution of construction
their focus was on:
materials was phased to ensure that
Š interim, transitional shelter buildings were built safely:
(it would not be possible to build
Š First, a shallow foundation was Working with partners
permanent shelter to meet the needs
built. When this was complete the The way in which the international
of all affected families within a year and
cement for the walls was distributed. NGO was able to work in partner-
PAJPO SANA JKP @QN=>HA AJKQCD PK łHH
Š Walls then had to be built. When ship with a strong local network of
the gap);
PDAOASANA?KILHAPA S=HHO=J@NKKłJC NGOs was one of the strengths of this
Š examples of low-cost and safe
materials were distributed. project. However, the relationship at
public buildings.
After the initial shelters were built, times became strained, in part due to
&J PDA łNOP SAAGO KB PDA NAOLKJOA
EOOQAOSANABKQJ@SEPDPDANKKłJC=J@ the different working methods and the
the focus was on the distribution of
an upgrade programme was required. speed at which the working relation-
non-food items.
This involved distributing four pieces ship was set up.
0AHA?PEKJKB>AJAł?E=NEAO of bamboo (1½m long ) to brace the
The initial assessment was rapid and roof. The international NGO had
@AłJA@OKIA?NQ?E=HJAA@O%KSARAN  internal rules and donor requirements
The distributions of materials were for paperwork and processes for ac-
it relied on individual competence and accompanied by the training of local
was not standardised. countability. The local organisations
masons and carpenters, to mobilise the saw much of this as overly bureaucratic.
The criteria and procedures for communities and raise their awareness These organisational differences were
PDA OAHA?PEKJ KB >AJAł?E=NEAO BKN NAHEAB of seismic-resistant construction. A sig- compounded by high staff turnover.
distribution in the communities were JEł?=JP=IKQJPKBSKNGS=ONAMQENA@
JKP =HS=UO ?HA=NHU @AłJA@ 1DAU SANA to ensure that people correctly braced Many of the procedures, logistical
commonly left to the subjective inter- their shelters and to explain that once =J@ łJ=J?E=H ?KJPNKHO SANA HKKOAJA@
pretation of the village-level workers braced, the buildings would be stronger However, the shelter programme
and the communities. Although this and safer. was very effective according to both
=HHKSA@=@ACNAAKBŃATE>EHEPU EPEOHEGAHU internal and external evaluations.

37
B.3 India - Gujarat - 2001 - Earthquake - Non-food items and shelters Asia

Photo: David Sanderson

Photo: Chris Cattaway


By working through a network of local These school buildings were adapted from the transitional shelters. The low walls reduce
NGOs, it was possible to mobilise large the risk of masonry falling on occupants during future earthquakes.
numbers of people.

‘Generally, the concept of Construction materials were procured


working through a local through the local NGOs’ procurement Materials list
NGO partner is better than team. Two entire trains were chartered Relief items distributed in 259
to bring in 265,000 bamboo poles from villages until 31 March:
working directly, particularly Assam. As the Bhuj train station did
in relief distribution. INGOs not have freight handling capacity, the Relief items Quantity
have less detailed knowledge station had to be closed for 24 hours Tent 847
about the affected people’s while the trains were unloaded. It took Plastic sheet 8,835
needs. On the other hand, 120 trucks to transport the materials Blankets 127,515
onwards to temporary stores in the
local NGOs may lack village from where they could be
Bucket 3,728
the skills to meet donors’ distributed. Jerry can 1,328
requirements. Collaboration Children's clothes 7,237
The remaining bamboo was
between INGOs and local procured from Nagpur and brought to
NGOs, thus, is mutually Bhuj through trucking companies. Total distribution of construction
>AJAłPEJC’. Roof tiles are traditionally produced
materials from 1 May to 15 October
- Project evaluation report 2001:
by small-scale suppliers. In order to
Implementation and logistics purchase the 12 million required, it Relief items Quantity
4EPDEJ PDA łNOP SAAG   = >=OA S=OJA?AOO=NUPKOAJ@=łJ=J?AKBł?AN Cement 72,684
camp and warehouse were set up in to pay multiple roadside suppliers.
Bamboo 422,217
DQF =J@ = HE=EOKJ KBł?A S=O AOP=>- Wooden purlins, rafters and patties Woven mats 149,878
lished in Ahmedabad. Tents, plastic were procured from the timber
sheeting, some blankets, jerry cans, Wooden spacers 9,689,295
merchants and transported by truck, in
children’s clothes and WHO medical Wooden rafter 178,401
some cases directly from the sawmills.
kits were procured from outside India. Wooden purlin 39,250
They were brought to Bhuj by four Record keeping for procurement,
Roof tile 12,114,483
?D=NPANA@ ŃECDPO H=JGAPO =J@ OKIA supplies and distribution was not very
good. This was the result of the complex Roof ridge 325,600
tents were procured from Bangalore
and Kanpur and were brought to the and very rapid procurement of multiple Iron wire 52,22
Bhuj warehouse through transport items. In addition, the multiple partner Mild steel rod 97,532
agencies. organisations had different working
practices. The resulting programme
Relief materials were delivered to ?NA=PA@@EBł?QHPEAOBKNPDA=Q@EPKNO >QP
the network of NGOs. Its members was effective in providing shelter for a
collected the relief materials at large number of people.
the warehouse and transported
them to the villages for distribution.

38
B.4 Indonesia - Aceh - 2004 - Tsunami and earthquake - Shelter or housing Asia

Photo: Joseph Ashmore


Photo Predes
&JPDAłNOPSAAGO=BPANPDAPOQJ=IE LAKLHABKQJ@ODAHPANEJH=NCA?KHHA?PERAPAJPOĠHABP
OMQ=PPA@>QEH@EJCOĠNECDP
PAJPO NAJPA@DKQOEJCKNSEPD
BNEAJ@O=J@B=IEHU1DACKRANJIAJP>QEHPPN=JOEPEKJ=HHEREJC?AJPNAOĠ?AJPNA


Before the tsunami Throughout the response and developed in each district.
The Indonesian state of Aceh is a reconstruction, government housing
As part of the agreements
densely forested state in the north of policy had a strong impact on the
reached with the communities, the
the island of Sumatra. The majority of response. Policy required that the
łNOP OAIEPEI>ANA@ ODAHPANO  SDE?D
the population live along the coast and shelters that were built create a
had provided transitional shelter
the main access is by sea or along the minimum covered area of 36m2. The
for as long as two years, were
coastal roads. KJHU KBł?E=H PN=JOEPEKJ=H NAOLKJOA
upgraded at the NGO’s expense
was the building of transitional living
Aceh has had intermittent periods centres, also known as ‘barracks’.
KB ?KJŃE?P OEJ?A  &J *=U  

Photo: Predes
These were long, timber-framed
the government of Indonesia declared and panelled buildings on stilts with
martial law in the province. As a plywood separation between families.
NAOQHPKBPDA?KJŃE?PPDANAS=OHEIEPA@
involvement of non-governmental Technical solutions
organisations in the province. Traditional coastal Achinese
Road
once all shown twohad
shelters yearsbeen
aftercompleted.
the tsunami.
shelters are entirely made of local ??AOOS=OEJEPE=HHU@EBł?QHP=HKJCIQ?D
After the tsunami timber and have thatched roofs. They of the west coast of Aceh.
The earthquake that struck on 26 are often on stilts to keep them off
December 2004 was one of the largest the ground. More recent construction
ever recorded and damaged many of has a concrete plinth and low brick
the larger concrete-framed buildings Who builds?
walls, with a timbered superstructure Planning of the programme started
in Aceh. The ensuing tsunami caused built on top. The roof is covered in
extensive damage in many of the approximately six weeks after the
corrugated iron. tsunami, as a community-led con-
countries in the Indian Ocean. The
province of Aceh was the worst hit, This project began building semi- struction programme to build shelters
due to its proximity to the earthquake permanent shelters based on local similar to those that many families had
and because the majority of the popu- designs. These had concrete and brick before the disaster. The programme
lation live in low-lying coastal areas. foundations and low brick walls, and sensibly aimed to build skills and ca-
were topped with timber frames, pacities within the villages, create live-
Following the tsunami, the majority a corrugated iron roof and timber lihood opportunities and cultivate a
of emergency shelter needs were met panels. higher level of ownership by encourag-
EJ PDA łNOP SAAGO >U PDA &J@KJAOE=J ing self-build approaches.
military, Indonesian organisations and About ten months after the
>AJAł?E=NEAO PDAIOAHRAO 1DEO S=O tsunami, the house model changed to a The scale of the construction in
due to logistical challenges and the reinforced concrete-framed structure ?ADS=OOECJEł?=JPHUCNA=PANPD=JD=@
fact that foreign access was limited with brick walls and a wood-framed ever before been experienced in the
by infrastructure damage and travel roof. It included over 50 separate com- region, requiring over 109,000 houses
restrictions resulting from the ongoing ponents, as well as toolkits. This was from a building industry that had only
?KJŃE?P 0DAHPAN S=O LNKRE@A@ EJ seen as ‘building back better’, although built a fraction of that number. As
collective tents, existing buildings, there were some safety concerns time passed and villagers started to
individual family tents, by use of plastic where builders had taken shortcuts. regain their livelihoods, NGOs found
sheeting and by families moving inland EPD=N@ANPKłJ@=SKNGBKN?ABNKIPDA
1DEO LNKFA?P S=O >=OA@ EJ łRA villages.
to where the damage was not as bad. distinct districts, with different
designs and implementation methods

*=JULAKLHA>QEHPPDAENKSJODAHPANOQOEJCNA?H=EIA@I=PANE=HO

40
Asia Shelter Projects 2008 B.5

There is a strong tradition of bamboo- A transitional shelter strategy was adopt-


based construction in Jogyakarta. ed by the Shelter Cluster members.

Bamboo jointing details

Bamboo being bound with string Electric power drills used to drill holes in
the bamboo so that it can be pegged
Photos: IFRC

Prefabrication of a wall panel Connecting a vertical post to Foundation pads cast with bamboo to
the foundation connect them to the frame

43
B.6 Indonesia, Jogyakarta - 2006 - Earthquake - Overview of the response Asia

Public information messages distributed as part of the response

44
B.6
B6 Jogyakarta - 2006 - Earthquake - Cash and transitional shelter Asia
Community-built shelter
AJAł?E=NEAO SANA OPNKJCHU AJ-
couraged to follow the design, but not
compelled to. In some cases people
ECJKNA@ KN IK@EłA@ PDA @AOECJ  OQ?D

Photo: IFRC
as in Delingo, a remote community

Photo: IFRC
with widespread construction skills
and local construction resources.
The volunteers/supervisors were
A completed transitional shelter built A transitional shelter built on the site of essential to guide and support good
through cash grants a destroyed house construction. The more the volunteers
SANA ?KJł@AJP =J@ AJC=CA@ EJ PDA
Design process process, the more the construction
AJAł?E=NUOAHA?PEKJ
This project aimed to empower followed the design and was of
Small cash grants were given out via
community members to rebuild their OQBł?EAJP MQ=HEPU 3=NE=PEKJO SANA JKP
traditional mutual support mechanisms
lives, starting with the construction of problematic as long as the general
to neighbourhood groups to buy tools
a transitional shelter. The transitional principles were followed and the
and basic materials to build temporary
shelter design was developed through essential points (such as building size,
shelters.
an understanding of locally available O=BA?KJJA?PEKJO AP?
SANAO=PEOłA@
Meetings were held with each materials, community needs and the Delay in project startup
group to discuss the project and to capacity and objectives of the organi- The organisation was initially
sign a contract with the community. In sation. hesitant to give cash directly to ben-
order to participate, each neighbour-
It took one month for the design Ał?E=NEAO &B PDANA D=@ >AAJ MQE?GAN
hood (20-50 houses) had to form a
process, one month for community institutional support for the project, it
shelter committee that had to include
preparation and demonstration could have been scaled up faster and
a head of the group, a treasurer (who
shelters, and one week to build 740 reached more people.
had to be a woman) and a secretary.
The positions could not be held by ‘model’ houses through a public com- Community knowledge
HK?=HKBł?E=HOKNPDAENB=IEHUIAI>ANO petition. Community levels of knowledge
The competition involved three about the use of bamboo varied. The
The committee was responsible
categories and offered prize money more urbanised the environment,
BKN PDA OAHA?PEKJ KB >AJAł?E=NEAO 
that went to the neighbourhood for: the lower the level of traditional
who could be anyone currently living
knowledge in the community, which
in a tent or under a tarpaulin, with Š the most number of houses; led to a lower quality of bamboo con-
a house unsuitable for habitation. Š the most beautiful houses; and struction.
Priority was given to vulnerable people Š the involvement of women.
such as widows, orphans, disabled The rural mountainous commu-
people, pregnant women, the sick The programme was rolled out nities recovered relatively quickly,
and the elderly. Funds were delivered over seven months, with 12,250 despite higher levels of damage from
through group bank accounts in three shelters built in 761 communities. the earthquake and higher levels of
to four instalments. The community Shelters cost under US$ 200 per unit. general poverty. One of the reasons
contributed labour and materials for this was that many locals had
recovered from the rubble. worked in the construction industry
prior to the earthquake.
Photo IFRC

The interior of a transitional shelter

46
Asia Shelter Projects 2008 B.7
Community training lasted up to As per the requirements of the
one week. During this time the vol- cluster-wide transitional shelter
unteers and the community built the design, untreated bamboo was used
łNOP ODAHPAN PKCAPDAN  SEPD OQLLKNP- (which deteriorates after two years).
ing media (a step-by-step guide, an in- If treated bamboo had been integrated

Photos: IFRC
formative video about using bamboo in into the programme, the shelter
construction, safe construction adver- structures could have been safely used
PEOAIAJPO =J@ = >KKGHAP
 3KHQJPAANO in communities for up to 25 years.
lived in the communities in a tent or
Transporting bamboo mats to a Resource management
transitional shelter and worked with
construction site The shelter programme built
the communities every day.
Implementation partners 12,250 transitional shelters that used
Throughout this project, the or- Working with volunteers allowed more than 100 culms of bamboo per
ganisation worked with national vol- a large-scale programme to be set up. shelter, using a total of more than 1.2
unteers, two local universities, un- The volunteers were often enthusias- million culms of bamboo.
dergraduate architecture students, tic and very willing to help, but some
To avoid deforestation of the
a training team, NGO facilitators/ D=@=HKSHARAHKB?KJł@AJ?AKNATLA-
bamboo stock, this project could have
trainers, an implementation team, and rience. This led to some challenges in
set up purchasing control mechanisms
a bamboo expert with experience in ensuring adequate quality control.
to manage the bulk procurement of
3AJAVQAH= =J@ #HKNAO  =J@ ?KIIQJE- 3KHQJPAANO SANA L=E@ = OI=HH bamboo that controlled quality, en-
ties in Jogyakarta and Central Java. stipend and supported with cooking vironmental impact, procurement
The local universities were involved AMQELIAJP  OHAALEJC CA=N =J@ łAH@ methods and treatment of the bamboo.
and helped to: OQLLKNP  SAAGHU NAŃA?PERA HA=NJEJC It would have also been possible to
training session was held. allocate money to reforestation pro-
Š develop technical inputs for shelter grammes.
design and messages; The Shelter Cluster design
Š develop posters, pamphlets, guidelines included seismic Materials Quantity
t-shirts, etc.; resistance, lasting up to two Bamboo mats 10 mats
Š train students to deliver 'build years, using materials that 6 walls, 3 ceiling, 1 door
back better' messages under staff Round poles (for columns) 12 poles
supervision; and
could be recycled and that 3' diameter, 3m long
Š set up mobile construction clinics. cost under US$ 200. Round poles (for beams 11 poles
and roof joists)
Ongoing use of shelters 7.5cm diameter, 3m long
The local media also got involved,
reinforcing best practice shelter and In the densely populated area of 1EI>ANBKNłTEJCPDAI=PO 7 beams
construction messages on the radio, Klaten, the transitional shelters were /AEJBKN?A@LH=OPE?ODAAP ITI
television and in print. eventually demolished to make room Nails 2.2 kg
for permanent housing. 5cm, 7.5cm and 10cm
‘Achieving good recovery and In the rural areas, the majority Wire 1 kg
risk reduction outcomes in of the transitional shelters were still Hinges 3 units
shelter is not about building being used after permanent shelters Lock 1 units
structures. It is about building were built, but for purposes such as
trust with communities’. storage sheds, shelter for cattle and
- Recovery coordinator for the livestock, or for small restaurants.
programme

Working with volunteers


The shelter programme mobilised
volunteers as community trainers, with
two volunteers per neighbourhood.
1DA RKHQJPAANO łNOP SAJP PDNKQCD
three days and nights of hands-on
training making straw models and a
IK?GQL BN=IA  =O SAHH =O łJ=J?A
Photos: IFRC

training and team-building exercises.


They then worked with communi-
ties on selecting and buying materials,
the technical aspects of working with
bamboo and building the shelters.
Public information was a critical component of the project.

47
Asia Shelter Projects 2008 B.7

Photos: Dave Hodgkin


‘You know you chose the appropriate
technology for transitional shelter when
that technology gets appropriated by
the rest of the local community’.
-H=OPE?ODAAPO@EOPNE>QPA@=OL=NPPDAłNOPLD=OAKBPDANAOLKJOASANAKBPAJQOA@PKI=GAOD=NA@PAILKN=NUODAHPANO

Distribution - plastic sheeting At the request of local communi- and equipment for cleanup and
The organisation implementing this ties and in support of the local self-help reconstruction; and
project was one of the few agencies tradition of ‘gotong royong’, all distri- Š a shortage of clean sleeping mats.
with full-functioning capacity at the butions occurred at the community
time of the earthquake. It started its level instead of the individual level. All
needs assessments and distributions The rush by affected families to re-
łNOP @EOPNE>QPEKJO PAJ DKQNO =BPAN PDA
were conducted by local implementing construct permanent houses raised a
earthquake.
partners. Communities were responsi- number of advocacy concerns. These
As rain was falling each night there included issues about the quality
>HABKN>AJAł?E=NUOAHA?PEKJ
was an urgent need for shelter, but of construction, health and safety,
supplies were too limited to supply Because local NGOs conducted treatment of the asbestos within the
one tarpaulin per family. all distributions and evaluations, the rubble and the construction of shelters
amount of human resources that the in precarious positions.
A broader distribution through
international NGO itself had to deploy
local partners was conducted. Each The emergency programme was
was extremely limited. At its peak
REHH=CA S=O LNKRE@A@ SEPD OQBł?EAJP followed by an Enhanced Emergency
EP AILHKUA@ KJHU OET ODAHPANOLA?Eł?
tarpaulins to ensure that the sick, the Shelter programme, which provided:
staff, and focused its resources more
weak, the young and the elderly were
on logistics and partnership support. Š woven bamboo wall sheeting
=@AMQ=PAHU QJ@AN ?KRAN &J PDA łNOP
Expansion of the emergency (gedek) to affected communities to
days, villages joined tarpaulins together
shelter programme AJOQNA PD=P A=?D B=IEHU D=@ OQBł?EAJP
to form large communal shelters that
Early analysis of the progress of material to build walls for their
housed the whole village at night (up
community recovery showed: emergency shelter;
to ten times the expected number of
Š combined community toolkits for
>AJAł?E=NEAO
 Š the use of tarpaulin for both clean-up and reconstruction; and
As funds and capacity from other NKKłJC=J@S=HHEJC NAOQHPEJCEJHEIEPA@ Š sleeping mats.
organisations arrived, the project undercover space;
S=O NA@Q?A@ PK =J EJłHH LNKCN=IIA  Š OQBł?EAJP NA?H=EI=>HA PEI>AN It also launched an advocacy
returning to previously assisted villages for temporary shelter framing, but and public outreach programmes to
and supplying 48m2 of plastic sheeting EJOQBł?EAJPI=PANE=HBKNS=HH?H=@@EJCĢ address safety and health issues.
per family (two 6m x 4m sheets). Š a pressing need for tools
Photos: Dave Hodgkin

?KHHA?PERAODAHPAN>QEHP>U>AJAł?E=NEAOQOEJC@EOPNE>QPA@LH=OPE?P=NL=QHEJO

49
B.7
B7 Jogyakarta - 2006 - Earthquake - Emergency and transitional shelter Asia

Photos: Dave Hodgkin


The extension of the emergency programme provided additional plastic sheets so that each needy family received one sheet.

Transitional shelter grants the emergency shelter distributions. Cluster members as a part of shelter
O=łJ=HL=NPKBPDAKNC=JEO=PEKJ†O These were based on a tender process material distributions. In total, four
emergency shelter programme, a that resulted in a cost of US$ 100-300 batches of 20,000 posters each were
programme was started to support per shelter. distributed to the disaster-affected
the transition into temporary housing. population.
As well as housing 2,000 families
The transitional shelter programme and improving the capacity of a The public outreach working group
was conducted in accordance with the number of local partners, this went on to develop a range of public
Emergency Shelter Cluster guidelines programme produced a range of outreach and advertising materials to
that had been developed locally well-documented transitional shelter promote safe reconstruction.
following the earthquake. solutions as potential examples for
further expansion or adoption by
‘The best we can do as other agencies.
Materials Quantity
shelter managers, is to be "IANCAJ?UODAHPANLNKCN=IIA
responsive and adaptive to Public outreach and advocacy Plastic tarpaulin 20-30 per
1DA łJ=H =OLA?P KB PDEO LKOP ITI sub-village
the changing needs of the earthquake shelter response was (200-300 families)
affected community;providing a public outreach and advocacy EJłHHLNKCN=IIA
minimalist but strategic and programme, where the organisation Plastic tarpaulin 1 per family
incremental inputs into the provided technical advice to the Shelter ITI

communities' natural path Cluster. This led to the formation of "JD=J?A@AIANCAJ?UODAHPANLNKCN=IIA


technical working groups. One group Woven bamboo ODAAPOLANB=IEHU
from inadequate to adequate working on public outreach produced ODAAPEJC
permanent shelter’. posters on a range of issues including: ITI
Tikka matts 2 per family
Cultural, environmental and cost Š safe clean-up;
Toolkits
concerns led to the creation of a Š safe siting of temporary shelters;
Š safe reconstruction; 1) Clean-up Distributed per
set of common guidelines based on village
traditional bamboo frame construction Š safe handling of asbestos and dust; 2) Reconstruction
with clay roof tiles and woven bamboo Š building next to hazardous 3) Village level
wall cladding. Flexibility in design to buildings; and &JJKR=PERA1ODAHPANCN=JPO
allow for innovations was encouraged. Š an introduction to simple bamboo
=OD CN=JP >=OA@ US$ 100-300 per
and concrete construction techniques. on tender process ODAHPAN
This programme provided eight The organisation led a cluster
cash grants to local community organi- -Q>HE?KQPNA=?DLNKCN=IIA
working group to design and print
sations/businesses and groups, to work -Q>HE?KQPNA=?D >=P?DAOKB 
posters. These were then distributed posters posters
with communities already serviced by by the local government and by Shelter
Photos: Dave Hodgkin

Grants were provided to build transitional shelters. Many different and innovative designs were built.

50
B.8 /QOOE= &JCQODAPE= KJŃE?P-AKLHA@EOLH=?A@ =ODBKNODAHPANDKOPB=IEHEAO Asia

Strengths and weaknesses

9 +K ARE?PEKJ KB &!-O @QNEJC PDA SEJPAN IKJPDO KB 8 1DADECDJQI>ANKB>AJAł?E=NEAOEJ@EBBANAJP@=P=>=OAO
=J@SANANALKNPA@ NAMQENA@=JEJPAJOERARANEł?=PEKJLNK?AOO
9 +K =>QOA @QNEJC ?=OD @EOPNE>QPEKJ KN =JU OA?QNEPU 8 Implementation of the 2nd phase during the following
EJ?E@AJPOK??QNNA@@AOLEPA=N=PDANPAJOAOA?QNEPUOEPQ=PEKJ SEJPAN S=O ATLKOA@ PK OARANA BN=Q@ =PPAILPO  =O OKIA
9 1DA LNKCN=IIA O HARAH KB PN=JOL=NAJ?U =?DEARA@ DECD EJ@ERE@Q=HO D=@ I=JELQH=PA@ KBł?E=H @K?QIAJPO EJ KN@AN
=??ALP=J?A=IKJC>AJAł?E=NEAO=J@HK?=H=QPDKNEPEAO IAAPPDAAHECE>EHEPU?NEPANE=%KSARAN PDABN=Q@QH=JP?=OAO
9 Professional cooperation with the Russian postal SANA OKNPA@ KQP =J@ ATLAHHA@ BNKI PDA >AJAł?E=NU HEOPO
OANRE?AĠ&JCQOD>N=J?D
=HHKSA@BKN=PEIAHU=J@=??QN=PA >ABKNAL=UIAJPS=ONAHA=OA@
cash disbursement. 8 In view of the scope of the project (the entire Republic of
9 1DAOECJEł?=JPEJŃQTKBHEMQE@?=ODOQLLKNPA@PDAHK?=H &JCQODAPE=
=JAR=HQ=PEKJKBPDALNKFA?PS=ONA?KIIAJ@A@
A?KJKIU to reveal detailed information about its effects and impact.

Photo: Mathias Rickli


The project worked with host families.
Context Eligibility criteria
1DA?KJŃE?PEJ DA?DJU=OP=NPA@EJ 1DEOLNKFA?PNA?KCJEOA@PD=POP=UEJC  DKOP B=IEHU S=O AHECE>HA BKN PDA
 BKN?EJC LAKLHAPKIKRA SEPD DKOP B=IEHEAO S=O LOU?DKHKCE?=HHU ?=ODCN=JPSDAJPDAUġ
to the Republic of Ingushetia. At one >APPANBKN&!-OPD=JHEREJCEJ?=ILO&P
Š LNAOAJPA@ KBł?E=H NACEOPN=PEKJ
OP=CA EJ A=NHU   PDANA S=O KJA also sought to encourage the solidar-
@K?QIAJPOLNKREJCPD=PPDAU=J&JCQOD
@EOLH=?A@ LANOKJ BNKI DA?DJU= BKN EPUABBKNPKBPDA&JCQODLKLQH=PEKJO
resident; and
ARANU&JCQOD?EPEVAJ =NAOQHP PDALNKFA?P=EIA@PKOQLLKNP
Š LNAOAJPA@ = DA?DAJ &!-†O
host families with economic incentives
HIKOPPSKPDEN@OKBPDA&!-OSANA PAILKN=NUNACEOPN=PEKJ@K?QIAJPSEPD
to encourage them to continue hosting
=??KIIK@=PA@>U&JCQODDKOPB=IEHEAO the same address and a registration
PDA&!-O
This was possible because of close date within a given time period.
B=IEHU =J@ NAHECEKQO PEAO >APSAAJ PDA Assessments were conducted in Implementation
two countries. PDAOLNEJCKB1DAOA?KJłNIA@ġ Registration - The registration
&J PDA OLNEJC KB   PDANA S=O Š the appropriateness of the cash for KB >AJAł?E=NEAO S=O >=OA@ KJ 2JEPA@
OKIA ARE@AJ?A PD=P &!-O D=@ >AAJ shelter approach; Nations and the Federal Migration
evicted from private accommoda- Š acceptance among potential Service lists. The two lists were
PEKJ1DEOS=O?KIIKJHU=O=NAOQHPKB >AJAł?E=NEAO=J@=QPDKNEPEAOĢ=J@ ?KI>EJA@ =J@ łHPANA@ 1DA NAOQHPEJC
łJ=J?E=HLNAOOQNAOKJB=IEHEAO I=JUKB Š the readiness of partner >AJAł?E=NUHEOPOSANA?HA=NA@
SDKI D=@ >AAJ DKOPEJC PDA &!-O BKN KNC=JEO=PEKJO PK LNKRE@A OA?QNEPU =J@ 3ANEł?=PEKJ To ensure that the
IKNAPD=JKJAUA=N logistics. NACEOPANA@ >AJAł?E=NEAO SANA DKOPEJC

52
Asia Shelter Projects 2008 B.8

Photo: Mathias Rickli


By supporting host families with one off cash grants, the project aimed to avoid evictions.
&!-O  IKJEPKNEJC PA=IO SANA OAJP PK
PDANACEOPANA@>AJAł?E=NEAO†=@@NAOO
Public information - The
intention to implement a cash project
S=OEJEPE=HHU=JJKQJ?A@PKPDA/QOOE=J
federal government as well as to the

Photo: Mathias Rickli


Ingush government and the humani-
P=NE=J=E@?KIIQJEPU/ACQH=NNALKNPO
on local television kept the popula-
tion updated on the programme and
EPO LNKCNAOO !AP=EHA@ EJBKNI=PEKJ
KJ AHECE>EHEPU =J@ HEOPO KB >AJAł?E=NEAO
SANALKOPA@=PLKOPKBł?AO=J@KJPDA
premises of local administrations.
Cash for shelter collection point
Complaints - A complaints
process involving the project man- Assistance provided - Each Security -*KRAIAJPS=ODA=REHU
=CAIAJP S=O KNECEJ=HHU JKP BKNAOAAJ B=IEHU NA?AERA@ PDA AMQER=HAJP KB 20 NAOPNE?PA@ =O = NAOQHP KB OA?QNEPU NA-
Complainants were asked to refer to  „ PDA AMQER=HAJP KB =J =RAN=CA strictions on international staff. Small
PDA &JCQOD CKRANJIAJP  SDE?D @APAN- IKJPDHUO=H=NU LNKFA?POSANAREOEPA@>UHK?=HOP=BB
IEJA@ PD=P  ?=OAO ĠKQP KB  

were eligible for compensation. 1DEO LNKFA?P S=O =??KIL=JEA@ >U Impacts - Although there were
 OI=HH LNKFA?PO  OQ?D =O AMQELIAJP some signs of eviction reported among
!QNEJC PDA OA?KJ@ LD=OA EJ for computer classes and support to the international humanitarian aid
PDA SEJPAN KB     B=GA@ soup kitchens. The objective of this ?KIIQJEPU JKARE?PEKJKB&!-O@QNEJC
@K?QIAJPO SANA E@AJPEłA@ ĠKQP KB was to acknowledge the goodwill of PDA SEJPAN IKJPDO KB   =J@
 OQ>IEPPA@
1DEOS=ONAOKHRA@=O PDAHK?=H?KIIQJEPU S=OKBł?E=HHUNALKNPA@
a result of close cooperation with the
*EJEOPNUKB&JPANEKN 0P=BłJC - The team consisted of ??KN@EJCPKQJKBł?E=HOQNRAUO PDA
PSK ATL=PNE=PA OP=BB Ġ= LNKCN=IIA ?=OD CN=JP S=O I=EJHU QOA@ BKN @=EHU
Payments - -=UIAJPOSANAI=@A I=J=CAN =J@ = @ALQPU LNKCN=IIA JAA@O =O SAHH =O BKN PDA L=UIAJP KB
>U PDA &JCQOD >N=J?D KB PDA /QOOE=J I=J=CAN
 BKQN HK?=H AILHKUAAO  AHA?PNE?EPU>EHHO
postal service. The postal service two drivers and up to 24 part-time
NA?AERA@ =  ?KIIEOOEKJ BKN =HH !QA PK PDA OECJEł?=JP OEVA KB PDA
monitors and drivers. The staff were
transactions and personal invitations PSK LNKFA?P LD=OAO  = PKP=H =IKQJP
>=OA@KQPKBPSKKBł?AO KJAEJ&JCQOD-
BKN >AJAł?E=NEAO 1DA ?KKLAN=PEKJ KRAN 20  IEHHEKJ S=O EJ@ENA?PHU
etia and one in North Osetia.
S=OAT?AHHAJPEJPANIOKBNAHE=>EHEPUKB EJRAOPA@EJPDAHK?=HA?KJKIU
L=UIAJPLNK?A@QNAO

53
Asia 0DAHPAN-NKFA?PO B.9

Destroyed rural houses (left, centre) and urban houses (right) in Kashmir

Self-built shelters in Kashmir built using reclaimed materials only ten days after the earthquake

Photos: Joseph Ashmore


Left to right: Self-built shelters in Kashmir using donated iron and toolkits, an emergency shelter days after the earthquake, tents.

Above, assorted model shelters built in the North-West Frontier Province and Kashmir. Note that not all of these models (e.g. the domed
ODAHPAN@AOECJEJPDA?AJPNA
SANA?QHPQN=HHU=??ALP=>HA OQBł?EAJPHU@QN=>HAKNOL=?EKQOAJKQCDBKNLAKLHAPKHERAEJ

55
B.10
B.10 Pakistan - 2005 - Earthquake - Transitional shelter construction Asia
Villagers collected their shelter There was a warehouse for each
GEPO=PPDAL=NGKBł?A1DA=IKQJPKB LNKFA?P =NA= *=PANE=HO SANA PDAJ
materials included in each kit depended transported to the villages; from there
upon the family size. There was a it was the responsibility of villagers to
PKKHGEPBKNARANUłRAB=IEHEAO carry them to construction sites.
After some initial issues with The shelters after two years
shelters not being completed, the After two years, nearly half of the
NKKłJC I=PANE=HO  EJ?HQ@EJC PDA IKOP shelters were still standing in their
valuable part of the kit, the corrugated original position. Of those that had
iron, were distributed only upon com- been removed, one was reassembled
pletion of the frame. in the summer pastures. Shelters were
commonly removed to make space
Most of the shelters were con-
for the ‘permanent’ house or to reuse
structed by a team of two to four
the materials. The corrugated iron and
workers in less than one week. The
the timber were the most commonly
LNKFA?P LNKRE@A@ =J =HHK?=PEKJ KB łRA
reused materials.
‘person days’ of payment for the con-
struction of each shelter. In practice, Materials Quantity
the technical assistance teams ended Polypropylene sand 350
up constructing many of the shelters. bags
Progress was periodically halted by
Wire 14g/PP strips ¼ roll
deteriorating weather conditions, par- 20 x 6mm
ticularly in early January.
Polypropylene 6 rolls
1DAI=FKN?KJOPN=EJPOEJPDAEILHA- string
IAJP=PEKJKBPDALNKFA?PSANANAH=PA@ Corrugated iron 16
to the procurement and transporta- sheets
tion of materials and the weather con- 2.74m x 0.99m
ditions. The corrugated iron sheeting, Iron ridge sheets 6.7m
SDE?D S=O QOA@ =O PDA NKKłJC BKN Nails 5kg
ODAHPANO  S=O @EBł?QHP PK LNK?QNA EJ
the required quantity. A tender for
Salvaged timber was also used for the
sheeting was placed in November
NKKłJCBN=IA
but suppliers were not able to deliver.
Eventually it was imported from India,
1KKHGEPO SANA OD=NA@ >APSAAJ łRA
which required high-level negotiations
families and contained: an adze
to relax the import restrictions into
(woodworking axe) with handle, a cold
Pakistan for Indian materials.
chisel, a 1.3 m crowbar, a hacksaw
with 20 blades, a 2kg hammer, a claw
Photo Kurt Rhyner
Logistics and materials hammer, 10m of transparent hose,
For much of the duration of the three needles, a pick with handle,
LNKFA?P LANEK@  NK=@ =??AOO PK PDA pliers, a 400mm handsaw, a shovel, a
LNKFA?POEPAOS=O>HK?GA@>UH=J@OHE@AO I P=LA IA=OQNA =J@ =J =@FQOP=>HA
As a result, materials had to be driven wrench.
to Muzaffarabad and then airlifted to
PDAOEPA1DAłJ=HOP=CAKBPN=JOLKNP=-
tion was by donkey and by foot.
Photos: Albert Reichart
Photo Albert Reichart

Inside one of the transitional shelters Building one of the transitional shelters

58
B.11
B.11 Pakistan - 2005 - Earthquake - Shelter materials distribution Asia
0AHA?PEKJKB>AJAł?E=NEAO earthquake damage to roads meant
Within one week of the earthquake, that many people incurred costs in
I=FKNłAH@KBł?AOSANAOAPQLEJ=CD getting to the distribution points and
and Muzaffarabad, the two operational transporting materials home. This was
hubs for relief operations in Pakistani- by far the largest cause of dissatisfac-
controlled Kashmir. The programmes tion with the distribution process.
were in rural areas, selected on the
Corrugated iron became a much
basis of the level of damage and
sought-after commodity in distribu-
coverage by other organisations.
tions. A combination of the cost of the
The initial lists of people who iron and the very low incomes of many
should qualify for support were affected families meant that a distribu-
provided by community leaders. A tion of corrugated iron was equivalent

Photo Hassan Noor Saadi


IAI>ANKBPDAłAH@PA=IPDAJREOEPA@ to months’ or even years’ worth of dis-
each house, often climbing a long posable income to families. The value
way to reach it. People were checked was such that many people did not use
against a number of criteria, including it to meet immediate shelter needs as
the level of damage to their house. intended. Instead they stored it for use
Each qualifying homeowner then in reconstruction or sold it for cash.
received a distribution card, which
The non-availability of land was
could be exchanged for items at an
due to areas being prone to landslides
agreed distribution point at an agreed
The shelter programme distributed and the remaining land being owned
time. directly to affected families or used for farming. Due to the scale
The only location where there materials in standardised kits was to of the programme and challenges in
S=O OECJEł?=JP @EOO=PEOB=?PEKJ SEPD NA@Q?A @EBł?QHPEAO =J@ PAJOEKJO =P identifying staff, it was not possible to
the assessment process was where the distribution points, but it led to provide support in negotiating access
the distribution took place through a distributions being less targeted to to land or to support construction.
local partner NGO, where prominent individual needs.
It was noted that affected people
local individuals may have biased the At a later stage, cooksets, stoves tended to act more as individuals
selection. and coal were procured and distrib- and families than as ‘communities’
Technical solutions uted, but not in the same quantities as following the earthquake. Individual
$ERAJ PDA HKCEOPE?O =J@ OP=BłJC PDAPKKHGEPO=J@PDANKKłJCI=PANE=HO families limited their responsibilities
constraints and the scale of the need, An evaluation indicated that many to building their own shelters, rather
a programme was developed that LAKLHA @E@ JKP łJ@ PDA PKKHGEPO RANU than creating and supporting initiatives.
was based exclusively on distribution useful. In Muzaffarabad, where the The challenges of the earthquake, the
directly to affected families. Tents and PKKHGEPOSANAEJEPE=HHUOLA?EłA@PDNKQCD environment and the weather made
>H=JGAPO SANA @EOPNE>QPA@ EJ PDA łNOP a rapid consultation process, satisfac- people prioritise to ensure that their
weeks. However, a revised plan to tion was higher than in Bagh, where own needs were met.
@EOPNE>QPA >H=JGAPO  NKKłJC I=PANE=HO consultation had been very limited. It
and toolkits was rapidly agreed upon. Material No.
is not known whether the distribution
People were expected to salvage their KBH=NCAMQ=JPEPEAOKBłTEJCO=J@IAP=H Corrugated iron sheets 10
own timber to construct a frame and strapping served to make buildings 8’x3’
a roof. more seismically resistant. Quilts 4
Corrugated iron and plastic Reasons for dissatisfaction with Blankets 2
sheeting were distributed for use as the toolkits Toolkit: spade, hammer, 1
NKKłJC I=PANE=HO 1DA =@R=JP=CA KB wood saw, iron saw, 20m
corrugated iron and plastic is that they These included:
rope, pliers, hoe, 8kg nails
are relatively lightweight. Even a poorly Š limited consultation in the design
ĠEJ?HQ@EJCNKKłJCJ=EHO

built shelter is unlikely to kill people in of the toolkits due to time pressures;
Š the varying skills and capacities of Plastic sheet 6m x 4m 1
the event of further aftershocks and
building collapse. affected populations to use the tools; Stove with exhaust pipes 1
Š the variable security surrounding Jerry can 20l 1
Toolkits containing basic carpentry Bagh;
and earthmoving tools, as well as nails Jackets – 1 large, 1 medium, 1
Š lack of support to help people use
=J@IAP=HOPN=LLEJCBKNQOA=OłTEJCO  1 small
their tools to rebuild; and
were developed through a limited but Š the inconsistent quality of tools. Plastic shoes – I large, 1
rapid community consultation. The Implementation 1 medium, 1 small
time pressure was such that orders Although distribution points were Cookset: 3 pots, 6 large 1
for large numbers of kits could be selected with the consent of community plates, 6 small plates, 6
rapidly placed, leading to cost and representatives and communities were spoons, 1 knife, 2 mugs
logistics savings. The idea of delivering JKPEłA@SAHHEJ=@R=J?A PDAPANN=EJ=J@

60
B.12 0NE)=JG= KJŃE?PNAPQNJO KNAODAHPAN Asia

Photo: Jake Zarins


Photo: Jake Zarins
Core shelter under construction Completed core shelter
Before the project 0AHA?PEKJKB>AJAł?E=NEAO
1DA @EOPNE?P KB (=NQG=IQJ=E  EJ "BBA?PERA ?KKN@EJ=PEKJ =IKJC PDA PK ATL=J@ EP EJ @EBBANAJP @ENA?PEKJO
JKNPDA=OP0NE)=JG= D=@>AAJKJPDA shelter actors resulted in the allocation ĠBNKJP  OE@A
 0LA?Eł? BA=PQNAO SANA
BNKJP HEJA KB PDA łCDPEJC >APSAAJ PDA of the nine different Grama Niladarai EJ?KNLKN=PA@PKCERAPDAS=HHOCNA=PAN
0NE )=JG=J CKRANJIAJP =J@ PDA )E>- administrative areas to different @QN=>EHEPU ĠOP=>EHEO=PEKJ =J@ ?QNEJC
AN=PEKJ1ECANOKB1=IEH"H=INA>AHOBKN OLA?Eł? =CAJ?EAO 4EPDEJ PDA KJA =@- KB PDA >QEH@EJC >HK?GO
 =J@ CNA=PAN
many years. Families from the area had IEJEOPN=PERA=NA==OOECJA@PKPDA+$,  resistance to cyclones and heavy rains
>AAJ@EOLH=?A@PK?=ILOJA=NPDAH=NCA the local authorities supplied a list of (steel bar reinforcement of wall pillars,
LKNP PKSJ KB =PPE?=HK= @QNEJC PDA J=IAO KB  AHECE>HA DKQOADKH@O ,B NKKBPNQOOAO >EJ@EJCKBPNQOOAOPKS=HHO 
DAECDPAJEJCKBDKOPEHEPEAOEJ PDAOA SANA=>HAPKCERAPDA+$, QOAKB'DKKGOBKNPDANKKłJCODAAPO 
OP=BBPDAJA?AOO=NU?KJłNI=PEKJKBHKOO KRAND=JCKBNKKBPKLNKPA?PS=HHOBNKI
In July 2007 many displaced families
KBDKQOEJC=J@PAJQNAKBPDAH=J@ rain, adequate foundations, raised
NAPQNJA@ PK PDAEN REHH=CAO PK łJ@
ŃKKNEJC
 4DANA LKOOE>HA  PDA N=EOA@
many of their homes destroyed or in Land rights / ownership
ŃKKNO SANA >QEHP QOEJC NA?KRANA@
disrepair. The majority of the previous "=?D>AJAł?E=NUDKQOADKH@D=@PK
materials from the destroyed houses.
DKQOEJC OPK?G D=@ >AAJ ?KJOPNQ?PA@ show the location and remains of their
BNKIIQ@>NE?G=J@L=HIPD=P?DNKKBO  destroyed house as proof of tenure. 1DA >AJAł?E=NEAO QOA@ = R=NEAPU
and had often fallen apart due to the 1DEO S=O PDAJ ?KJłNIA@ >U PDA HK?=H KB I=PANE=HO SDAJ >QEH@EJC ATPAJ-
SA=PDAN  H=?G KB I=EJPAJ=J?A KN AJ- =QPDKNEPEAO  =HPDKQCD PEIA ?KJOPN=EJPO OEKJO  N=JCEJC BNKI >QEH@EJC >HK?GO PK
croachment by elephants. @E@ JKP LANIEP PDA +$, PK I=GA LH=OPE?ODAAPEJC=J@L=HIPD=P?D&PS=O
BQNPDAN EJRAOPEC=PEKJ KJłNI=PEKJ estimated that the construction of
-NAREKQOPKPDEOLNKFA?P PDACKRANJ-
S=O DEJ@ANA@ >U PDA H=NCA JQI>AN A=?D ODAHPAN SKQH@ P=GA =>KQP PDNAA
ment had insisted upon a 500 ft2 foun-
of families who had lost documents SAAGO EJ?HQ@EJCPDAKJASAAGJAA@A@
@=PEKJ&JI=JU?=OAOPDA>AJAł?E=NEAO
@QNEJCPDA@EOLH=?AIAJP BKN?QNEJCPDA>QEH@EJC>HK?GO
did not have the personal resources to
?KILHAPA PDA H=NCAN ODAHPAN EIIA@E- Technical solutions ‘It’s nearly the same size as
=PAHU KND=@ATLA?PA@KPDAN+$,OKN Analysis showed that there would our previous house, but with
PDACKRANJIAJPPKLNKRE@APDAISEPD be little difference in costs between
PDAODAHPANATPAJOEKJ a semi-permanent shelter of the
a good door and window’.
The district was very isolated, OPUHA QOA@ @QNEJC A=NHEAN POQJ=IE
responses, and a core shelter made Implementation
SDE?D I=@A @ENA?P IKJEPKNEJC KB PDA HK?=HO?DKKHS=O@AOECJ=PA@=O=
LNKFA?P @EBł?QHP &P =HOK BKN?A@ PDA with permanent materials. After
research and discussions in the ?AJPN=HOPKN=CA=NA=BKN=HHPDAI=PANE=HO
NGO to adopt a relatively hands-off >AEJC >NKQCDP EJ >U PDA +$,  =J@
=LLNK=?D   =J@ CNA=PAN NAOLKJOE>EHEPU communities, the NGO also came to
the conclusion that a smaller (18.6m2) = OPKNAGAALAN S=O AILHKUA@ BNKI
for construction quality and comple- the local community. Each family
PEKJ S=O =HHK?=PA@ PK PDA >AJAł?E=N- core shelter would be acceptable to
PDA?KIIQJEPEAO =OHKJC=OPDANASANA S=O NAMQENA@ PK OECJ = ?KJPN=?P SEPD
ies themselves. At the same time, the the NGO, which clearly stated the
NGO was under pressure to show K>REKQO@AIKJOPN=PEKJOKBPDA@AOECJ†O
=@=LP=>EHEPU=J@ATL=J@=>EHEPU&JCNKQL responsibilities of the NGO and those
results in a short period of time. This KBPDA>AJAł?E=NEAO
S=OL=NPHUATLNAOOA@=OPDASEODKBPDA IAAPEJCO SEPD PDA ?KIIQJEPEAO PDA
HK?=HCKRANJIAJP >QP=HOKEJNA?KCJE- core shelter version was chosen. The NGOs delivered the materials
PEKJKBPDAODKNPPEIA>ABKNAPDAJATP The core shelter has a fully (apart from the locally sourced river
rainy season. enclosed space, as well as a veranda O=J@
=J@C=RAOI=HHCN=JPO LNKRE@A@=P
area that can also be enclosed. @EBBANAJPOP=CAOKB?KILHAPEKJ PK?KRAN
1DA?KIIQJEPUD=@=H=NCA?=L=?EPU H=>KQN ?KOPO 1DA >AJAł?E=NEAO SANA
BKNOAHB>QEH@SKNG=J@=GJKSHA@CAKB 1A?DJE?=H @N=SEJCO SANA LNKRE@A@ PK
demonstrate basic possible variations NAOLKJOE>HA BKN P=GEJC PDA I=PANE=HO
carpentry and masonry, and was also from the central distribution site, for
A=CANPKłJEODPDASKNGMQE?GHU

62
Asia Shelter Projects 2008 B.12
provided all materials, apart from
locally sourced sand. All other materials
were procured in Trincomalee, the
JA=NAOPH=NCALKNP1DAI=FKNEPUKBPDA
PEI>ANS=O?K?KJQPPEI>ANP=GAJBNKI
OQOP=EJ=>HUI=J=CA@OKQN?AO1DA>AJ-
Ał?E=NEAO SANA CERAJ OI=HH CN=JPO PK
pay for the transportation of materials
from the central distribution site.
After the project

Photo: Jake Zarins


More than 80% of the families used
personal resources or sweat equity
PK OP=NP PDA LNK?AOO KB EILNKREJC
their shelters. Some members of the
?KIIQJEPU SANA =HOK =>HA PK C=EJ
HERAHEDKK@ KLLKNPQJEPEAO >U @KEJC
I=OKJNU KN ?KJOPNQ?PEKJ SKNG BKN
More than 80% of the families used personal resources or their own time and effort to other members of the community.
upgrade their core shelters. The isolation of the location and the
KNC=JEOEJC PDA ?KJOPNQ?PEKJ =J@ BKN to those members of the communities @=I=CA PK PDA A?KJKIU ?=QOA@ >U
quality assurance, both of the shelters SDKBAHHEJPK?=PACKNEAOKBRQHJAN=>EHEPU  PDA?KJŃE?PIA=JPPD=PPDANAS=OHEPPHA
and of any subsequent additions. The >QPPD=PPDEOATPN=DAHLIECDP>AHEIEPA@ other competition for employment
NGO also distributed instructions on PK LNKRE@EJC I=PANE=HO BKN PDA ŃKKN =IKJCIAI>ANOKBPDA?KIIQJEPU
LNKLAN IAPDK@O KB >HK?GI=GEJC =J@ łHHEJC=J@ATPN=BQJ@EJCBKNPDASKNGKB
Material Quantity
PA?DJE?=H @N=SEJCO KB IK@AH @AOECJO ŃKKN ?KIL=?PEKJ Ġ=HH KPDAN ?KJOPNQ?-
Cement 50 kg bag 26
for the shelters. PEKJJAA@OSANA=HNA=@UP=GAJ?=NAKB
River sand (tractor load) 4
PDNKQCDPDALNKREOEKJKBPDAI=PANE=HO
1DA +$, HK=JA@ SKNG PKKHO BKN 20mm aggregate (metal) 0.3m3
=J@PDACN=JPOBKNH=>KQN
&JPDAAJ@ 
each community to share, with the Gravel (existing debris could 1.3m3
few members of the community came be used)
EJPAJPEKJ PD=P A=?D B=IEHU SKQH@ P=GA
forward with such requests. 10mm diameter steel 2
their turn with them and then pass
reinforcement
PDAIKJ KNSKQH@OECJPDAIKQP=J@ O = ?KILHAIAJP=NU LNKCN=IIA 
6mm diameter mild steel 3.7m
CERAPDAIPKDENA@I=OKJO&JLN=?PE?A the NGO provided repairs of pre- reinforcement
PDAIAPDK@KBOD=NEJCPDAPKKHO@AREOA@ ATEOPEJC PKEHAPO =J@ =HOK E@AJPEłA@ = Binding wire 0.2kg
by the community members was more partner for the provision of new toilets Wall plate 50mm x 100mm 15m
informal, but did not produce com- where needed. Ridge plate 50mm x 100mm 7.5m
plaints. Tie beam 75mm x 125mm 3.7m
Logistics and materials
!QNEJC EJEPE=H ?KIIQJEPU @EO?QO- Because of the isolation of the Prop 75mm x 125mm 1m
OEKJO  PDA +$, ATLH=EJA@ PD=P PDAU HK?=PEKJ  PDA KJCKEJC ?KJŃE?P  =J@ Rafter 50mm x 100mm 44m
SKQH@ ?KJOE@AN CEREJC ATPN= OQLLKNP PDA H=?G KB HK?=H OQLLHEANO  PDA +$, Reaper 25mm x 50mm 60m
Soligram 10 litres
28-gauge corrugated iron 20
sheet, 2.4m long sheets
Tar sheet 0.9m wide 3.4m
Ridge tiles 20
L-hook with nut & washer, 6kg.
75mm
Nails 100mm 2kg
Nails 50mm 2kg
10 mm diameter bolt and nut, 2
150mm
10 mm diameter bolt and nut, 6
100mm long
Door 0.9m x 1.8m with frame, 1
including ironmongery and
łTEJC
Photo: Jake Zarins

Window 0.9m x 1m with 1


frame, including ironmongery
=J@łTEJC

A durable upgrade of a core shelter

63
Asia Shelter Projects 2008 B.13

Photo: Joseph Ashmore

Photo: Joseph Ashmore


There was no construction allowed within 200m of the high- In some cases, small groups of transitional shelters were built on
tide mark in some areas and within 100m in other areas. small plots of land that were negotiated on a temporary basis.

Photo: Joseph Ashmore


+ASOAPPHAIAJPOKN?=ILOD=@PK>A>QEHPBKNI=JUKBPDA@EOLH=?A@*=JUKBPDA=HHK?=PA@OEPAOSANALNKJAPKŃKK@EJC=J@=S=UBNKI
livelihoods.

Photos: Jo Da Silva and others.

The shelter strategy allowed for many different shelter designs. Over 70,000 transitional shelters were built.

65
Asia Shelter Projects 2008 B.14
Before the tsunami The metal frames also meant that
Many families had built houses the shelters could be relocated and
on customary plots in ribbon settle- reused if necessary, unlike shelters

Photos: Jim Kennedy


ments along the coast road. This was made from wood. The roofs were
a response to the economic develop- made from galvanised metal (a material
ment of the region over the previous OLA?Eł?=HHUEJOEOPA@QLKJ>UPDA>AJAł-
decade and was spurred on by gov- ?E=NEAOPKNAŃA?PPDAENLAN?AERA@OK?E=H
ernment-backed housing programmes. status), with open eaves under the
However, consideration was not given roofs to provide for ventilation.
to the consequences of cyclone and
1DA >AJAł?E=NEAO SANA =OGA@ PK
ŃKK@EJC NEOGO PK EJ@ERE@Q=H DKQOAO KN
Shelters were arranged in small groups provide the rubble for the raised foun-
to the consequences of drying out on plots of land, often negotiated with dation and the sand for the cement mix.
?K=OP=HI=NODAO=J@J=PQN=HHUŃKK@EJC the help of the NGO. A half-wall of concrete blocks was built
areas. The haphazard layout of the
Land rights / ownership along the edge of the foundation. Each
housing also limited the possibility of
Many of the families living beyond household was given a small grant to do
community-wide or municipal sanita-
the 100m coastal buffer zone had lived PDAI=OKJNUKNPKłJ@HK?=H?N=BPOIAJ
tion and drainage solutions in many
on traditional plots, although many did The sides of the shelters were then
cases.
not have clear ownership titles. Almost initially covered with plastic sheeting,
In-country experiences all of these families chose to remain on which was reinforced by plywood. The
This project was implemented by their traditional plots of land. work was done by ‘shelter crews’ of
an NGO that had previously worked local tsunami-affected youth from the
For those who had lived within the
on transitional shelter programmes for communities involved.
buffer zone, the NGO worked with the
PDKOA @EOLH=?A@ >U PDA ?KJŃE?P EJ PDA
?KIIQJEPEAO PK łJ@ DKOP B=IEHEAO KJ A detached veranda was later
north of Sri Lanka. Much of the shelter
whose plots shelters could be built. In added as an upgrade. This could be po-
design and the methods for interact-
three cases, small planned settlements sitioned on any side of the basic shelter
ing with the communities and the local
of 15-30 families were constructed, and could be used either as additional
government were adapted from this
as close to sea-based livelihoods as living space or as a kitchen area. Later,
previous programme.
possible. guttering and rainwater harvesters,
Minor changes were made in the =OSAHH=ONKKłJCEJOQH=PEKJ=J@>=OE?
)K?=H CKRANJIAJP KBł?E=HO SANA
design of the shelter from the previous electrical wiring, were added.
usually willing to allow families to
project, giving the shelters greater
construct shelters on their previous As part of a parallel programme,
height.
spots. This deferred ownership issues families without latrines were provided
In the previous programme in the until the time when permanent with materials and technical advice for
JKNPD I=JUKBPDA>AJAł?E=NEAOSANA reconstruction would start. latrine construction.
living in IDP camps and had limited
Technical solutions Implementation
access to livelihoods. This meant
Shelters needed to be easy Shelter materials were delivered
that they could spend more time on
PK ?KJOPNQ?P OK PD=P >AJAł?E=NU upon completion of each stage of the
shelter construction, and were more
participation could be maximised. >QEH@EJC 1DA BN=IA =J@ NKKłJC SANA
inclined to work on each other’s
They also needed to be movable, @AHERANA@ łNOP  PDAJ PDA ?KJ?NAPA
shelters. In contrast, the tsunami-
to help people as they moved out blocks for the half-wall, followed by the
affected populations in the south had a
from living with host families or siding materials. However, the timing of
culture of working independently, with
were disassembled to make way for the delivery of second- and third-stage
more diverse livelihoods. This led to
permanent reconstruction. materials was complicated by families
the project running more slowly than
building at different speeds.
anticipated. The basic shelters were made from
box-bar metal frames, which could 1DABN=IAO=J@NKKłJCODAAPOSANA
0AHA?PEKJKB>AJAł?E=NEAO
be rapidly assembled into the basic prepared in the NGO’s warehouse,
The NGO approached local village
skeleton of the shelter so that even while the plastic sheeting was cut to
KBł?ANO=J@?KKN@EJ=PA@SEPDPDAIPK
those with little physical strength or measure in a small workshop set up
receive a full list of those in need of
prior construction knowledge could by tsunami-affected families in one
shelter. This was then cross-checked
assemble them. community.
by door-to-door visits conducted by
NGO staff. The cross-checking process
was also used to identify vulnerable
households eligible for support
from NGO technical teams in the
Photos: Jim
Kennedy

construction of their shelter. All the


>AJAł?E=NEAO BNKI = ?KIIQJEPU SANA
asked to nominate a small committee
to store the shelter materials and help
Site with poor drainage. Not all available shelter sites were ideal.
with their distribution.

67
B.14 Sri Lanka - 2004 - Tsunami - Case study: Transitional shelter construction Asia
Materials list
Material Quantity

Photo: Colin Heinz-Loya


Steel column - 8
40mm x 40mm x 1.85m
Steel bracing - 20 mm x 4
20 mm x 2.13m box bar
Steel purlin - 20mm x 4
20mm x 5.7m box bar
Steel trusses - 25mm x 4
Shelters built with tanks for rainwater 25mm box bar
harvesting
Steel rear side bar - 3
&J A=?D ?KIIQJEPU  PDA łNOP KJA 20 mm x 20mm x 3.48m
or two shelters were constructed by box bar
NGO staff for the most vulnerable
Steel side bar - 20mm x 2
people, as a way of demonstrating the
20mm x 5.18m box bar
assembly method to the rest of the
community. Steel front side bar - 1
20mm x 20mm x 230mm
The longer times taken by many
Pop rivet - 3mm x 16mm
families to complete their shelters
meant that the amount of time needed G.I. bolt & nut - 75mm x 32
for support and supervision by the 6mm and 64mm x 6mm
NGO staff also increased. This in Door (fully completed) 1
turn meant that the NGO was not Door stopper - 1
able to extend its support into more 25mm x 25mm x 45mm
communities and caused the initial
Hinges -100mm x 75mm 2
forecasts for completed units to be
reduced twice across the programme. Cement (50Kg) 1
/KKłJC0DAAPII 8
Logistics and materials /E@CAODAAPIIT 1
45mm
There was an effort to ensure
that the procurement process would Hook bolt nut 32
support the national economy, while Concrete block - 380mm 210
trying to avoid creating scarcity or x 180mm x 100mm
LQPPEJC EJŃ=PEKJ=NU LNAOOQNAO KJ Concrete feet for 8
the materials needed for permanent columns
reconstruction. Most materials were 0=J@ĠLNKRE@A@>U>AJAł?E=NEAO

supplied from the south and west of


Sri Lanka, with the exception of the After June 2005, an upgrade
NKKłJCODAAPO=J@PDALH=OPE?ODAAPEJC  veranda extension was made using the
which both came from abroad. following materials:
There were concerns that the Material Quantity
?KJ?NAPA >HK?GO SKQH@ ?KJŃE?P Pillar plate - 100mm x 4
with demand due to permanent 50mm x 250mm
reconstruction. Many of the concrete
/=BPANO 6
blocks supplied for the transitional
50mm x 50mm x 200mm
ODAHPANO SANA JKP KB OQBł?EAJP MQ=HEPU
for hazard-proof permanent housing. Tie bars - 8
50mm x 50mm x 125mm
The supply of sand (for mortar and
Wire nails 1.5kg
for constructing the foundations) also
50mm & 75mm
LKOA@ @EBł?QHPEAO &JEPE=HHU PDA +$,
had encouraged the communities to /KKBODAAP 4
Photos: Jim Kennedy

take sand from the beaches, but this Umbrella nails 0.2kg
was counter to government bans and G.I. ridge sheet - 0.9m x 1
also had a potentially negative impact 2.4m
on the environment. In some cases,
communities were given small grants In July and August 2005, basic elec-
to buy sand from local suppliers. trical wiring (one plug socket and one
The construction of the shelters was not
HECDP OK?GAP
 =J@ NKKłJC EJOQH=PEKJ =@EBł?QHPLNK?AOO
were added.
68
LAC Shelter Projects 2008 C

Section C
Latin America and
Caribbean

C.1
Honduras
Hurricane 1998

C.2 - C.5
Peru
Earthquake 2007

69
LAC Shelter Projects 2008 C.1

Land and ownership


For those families who chose to
stay near their destroyed home and
D=@=J=NA=PD=PS=OO=BA Ń=P=J@@NU 

Image: Milton Funes


PDAKNC=JEO=PEKJDAHLA@PDAIPKANA?P

Image: Milton Funes


a transitional shelter on their own land.
#=IEHEAOSANANAMQENA@PK?HA=N=OLKP
in the ruins of their former home.
In some other cases where safe
H=J@S=OJKP=R=EH=>HAJA=NPDAKNECEJ=H
site, the organisation coordinated with
Computer model of the timber frame of Computer model of the shelter with a HK?=H =QPDKNEPEAO PK @AłJA PAILKN=NU
the shelter corrugated iron roof and plastic sheeting relocation sites.
walls
The disaster Technical solutions
#NKI,?PK>ANPK+KRAI>AN >AJAł?E=NEAO SEPDKQP NAOKQN?AO SANA 1DA ODAHPAN IK@AH =@KLPA@ S=O =
  %QNNE?=JA *EP?D @NKLLA@ =OOEOPA@łNOP BKHHKSA@>UPDKOASEPDKQP timber-framed structure.
historic amounts of rainfall on PDA łJ=J?E=H NAOKQN?AO PK LNKRE@A
%KJ@QN=O SEPDQJKBł?E=HNALKNPOKBQL =@AMQ=PA ODAHPAN BKN PDAIOAHRAO ĠPDA Implementation
to 1900mm of rain. Deaths due to cat- LKKN
 Materials for one shelter were
=OPNKLDE?ŃKK@EJCI=@AEPPDAOA?KJ@ @AHERANA@ PK A=?D >AJAł?E=NU B=IEHU
4DEHAĺPDALKKN†=NAKBPAJ@EBł?QHP *=JU B=IEHEAO  AOLA?E=HHU PDA IKOP
deadliest Atlantic hurricane in history:
PK @AłJA  PDA BKHHKSEJC PULAO KB RQHJAN=>HA  H=?GA@ PDA OGEHHO PK >QEH@
JA=NHU   LAKLHA SANA GEHHA@ =J@
B=IEHEAOSANALNEKNEPEOA@ġB=IEHEAOPD=P sound frames for the shelter without
KRAN SANAIEOOEJC>UPDAAJ@KB
remained without adequate shelter direction, although they could often
1998.
PSK SAAGO =BPAN PDA @EO=OPAN  =J@KN LNKRE@A?KJOPNQ?PEKJH=>KQN
1DA ŃKK@EJC ?=QOA@ ATPNAIA B=IEHEAOE@AJPEłA@>UPDAIQJE?EL=HEPU
@=I=CA  AOPEI=PA@ =P KRAN 20  HA=@ANODEL =O = LKKN B=IEHU 1DEO For the families who needed it,
>EHHEKJ EJĠAMQER=HAJPPK20 ?=PACKNU S=O ?KJłNIA@ >U = HK?=H EJOPNQ?PEKJ =J@ OQLANREOEKJ KJ ?KJ-
>EHHEKJ EJ  PANIO
 %KJ@QN=O S=O social organisation or other reliable OPNQ?PEKJ S=O LNKRE@A@  &J ?=OAO
the worst-affected country, although source. SDANA PDA B=IEHU D=@ HEIEPA@ ?=L=?EPU
+E?=N=CQ= $Q=PAI=H==J@"H0=HR=@KN to assist with construction labour,
0AHA?PA@ ?KIIQJEPEAO SANA =OGA@ PDA LNKCN=IIA LNKRE@A@ OQLLHAIAJ-
SANA=HOKOARANAHUABBA?PA@
PK LNKRE@A HEOPO KB PDA RQHJAN=>HA P=H?KJOPNQ?PEKJH=>KQN1DEOOQLLKNP
Before the disaster families, according to standard local ensured that the shelter was erected
Before the hurricane, the organi- ?NEPANE=BKNRQHJAN=>EHEPU MQE?GHU=J@?KNNA?PHU
O=PEKJ D=@ = LNKCN=IIA PK =OOEOP PDA
Database For the most elderly and disabled,
NACEKJ†O LKLQH=PEKJ PK LNAL=NA BKN
!QNEJC PDA LNKFA?P  PDA KNC=JEO=- all or most of the construction labour
=J@ IEPEC=PA @EO=OPNKQO ARAJPO 1DEO
tion maintained an electronic database BKN PDA ODAHPAN S=O LNKRE@A@ 4DANA
SKNGEJCNAH=PEKJODELSEPD?KIIQJEPEAO
KB =LLNKRA@ >AJAł?E=NEAO  @AP=EHO LKOOE>HA  PEI>AN BNKI PDA @AOPNKUA@
EJ PDA =NA= S=O RANU QOABQH EJ DAHLEJC
KB DKQOAODAHPAN HK?=PEKJ  B=IEHU DKQOA S=O NAQOA@ EJ PDA PAILKN=NU
PDA KNC=JEO=PEKJ SKNG SEPD PDA =Q-
IAI>ANO  HARAHO KB RQHJAN=>EHEPU Ġ=CA shelter.
PDKNEPEAOPKAJOQNAPD=PPDA>AJAł?E=NU
=J@ @EO=>EHEPEAO
 =J@ OP=PQO KB ODAHPAN
OAHA?PEKJ LNK?AOO S=O N=LE@  =??QN=PA ‘Though it is not a big space,
?KJOPNQ?PEKJ =J@ >AJAł?E=NU L=NPE?E-
=J@PN=JOL=NAJP
L=PEKJ 1DEO @=P=>=OA S=O HEJGA@ PK it feels like home for me,
AJAł?E=NUOAHA?PEKJ OUOPAIO BKN PN=?GEJC PDA @AHERANU KB my husband and children’.
1DAPN=JOEPEKJ=HODAHPANLNKCN=IIA materials and shelter construction
LNKCNAOO
 AJAł?E=NU EJ )=O NEO=O 
łNOP P=NCAPA@ PDA IKOP RQHJAN=>HA
families in communities under the Tegucigalpa
!AL=NPIAJPO KB #N=J?EO?K *KN=V=J
and Choluteca. Disabled and elderly
Photo: Milton Funes

Photo: Milton Funes


Photo: Milton Funes

Marking out the site for a shelter Prefabricating walls Shelter assembly using prefabricated walls

71
C.1 Honduras - 1998 - Hurricane Mitch - Transitional shelter LAC
Materials list
In addition to the materials listed List of tools needed to build 50 - 75
>AHKS  =LLNKTEI=PAHU I2 KB SKRAJ transitional shelters:

Funes
Milton Funes
NE>>KJ KB EJPANJ=PEKJ=H OLA?Eł?=PEKJ
Materials Quantity
LH=OPE? ODAAP S=O LNKRE@A@ >U PDA
Hole digger 10

Photo: Milton
donor organisation.
Manual saw 10

Photo:
Hammer 20
Materials Quantity Tin snips (tin scissors) 10
Timber 8 Plumb 10
Completing the frame 50mm x 100mm x 3m
Tape measure 10
Timber 4
50mm x 100mm x 3.6m Level 10
Timber 3 Staple gun 10
Logistics 50mm x 100mm x 4.3m
AJAł?E=NEAOOECJA@BKNPDAI=PANE=H Table saw 1
SDAJ EP S=O @AHERANA@ =J@ SANA NA- Timber 1 Portable saw 5
50mm x 100mm x 1.8m
OLKJOE>HA BKN PDA I=PANE=H†O OA?QNEPU Diamond saw blades 5
Timber 6
BNKIPD=PLKEJPKJS=N@1DEONAMQENA- 50mm x 50mm x 2.4m
ment was made clear to each family at
Timber 5
PDA KJOAP KB PDAEN EJRKHRAIAJP EJ PDA 50mm x 50mm x 4.3m
LNKCN=IIA
Timber
A senior staff member based in 25mm x 74mm x 2.4m
PDA?KQJPNUKBł?AS=ONAOLKJOE>HABKN Galvanized roof sheet 6

Photo: Milton Funes


PDALNK?QNAIAJP=J@PN=JOLKNPKBPDA 28 SWG - 0.8m x 2.7m
I=PANE=HONAMQENA@BKNPDALNKCN=IIA Galvanized roof sheet. 6
28 SWG – 0.8m x 1.8m
Ensuring that all materials were
LNK?QNA@ =J@ @AHERANA@ =??KN@EJC PK Nails 100mm 1.5kg
schedule was challenging. Nails 75mm 1.5kg
Nails 50mm 1.5kg
/KKłJC+=EHOII 288 Covering the roof
with corrugated iron
Staples 12mm 300
Diesel (to protect wood 2l
from termites)
‘Through this simple and
Photo: Milton Funes

Cement (42.5 kg bag) 2.5 bags


quickly installed structure we
Gravel 0.18m3
have been able to provide an
Sand 0.15m3
intimate family space for the
Plywood door / standard size 1
victims of the hurricane’.
Plywood sheet 1
(5mm x 1.2m x 2.2m) - Jose Aleman, carpenter
for corner reinforcements
Covering the frame working on the project
Photo: Milton Funes
Photo: Milton Funes

Although the preferred option was to build shelters on people’s own land, in
some cases it was necessary to build shelters on a temporary relocation site.

72
LAC Shelter Projects 2008 C.3

‘Once the basic shelters were built,


B=IEHEAO?=JLH=JKJPDAENBQPQNA
=J@SKNGKJPQNJEJCPDAENODAHPAN
EJPK=DKQOA FQOPHEGADQJ@NA@OKB
PDKQO=J@OKB-ANQRE=JOD=RA@KJA

Photo: Predes
KRANPDAUA=NO OP=NPEJCSEPD=
>=I>KKI=PDKQOA†

0AHA?PEKJKB>AJAł?E=NEAO Materials distributed


A public kitchen was the basis of Every selection was to be approved
PDA LNKFA?P I=J=CAIAJP &J PDA łNOP by the assembly of the kitchen group, Materials Quantity
stage it had 40 groups, each with a des- which was something like a ‘block Bamboo mats 10 mats
ignated responsible person. Most of committee’. 6 walls, 3 ceiling, 1 door
the groups were led by women. They Round poles (for columns) 12 poles
Technical solutions
became the centre of all project activi- 3" diameter, 3m long
In the coastal regions of Peru there
ties and organised frequent assemblies Round poles for beams and 11 poles
is a long tradition of constructing semi-
to discuss all aspects of the project and roof joists
permanent shelters using bamboo. In
take decisions. The whole project was 2.5" diameter, 3m long
the past, immigrants to Lima and other
conducted in close coordination with 1EI>ANBKNłTEJCPDAI=PO 7 beams
cities have established themselves with
the municipality.
simple structures, leading to the step- Reinforced plastic sheet 3m x 15m
Within days of the earthquake, by-step construction of a formal house. Nails 2", 3" and 4" 2.2 kg
the NGO was able to present the Wire 1 kg
While the bamboo mats are not
project ideas to the communities via
considered a formal construction Hinges 3 units
the ‘kitchen group’. Most opted into
material, the climate allows people to Lock 1 units
the project, while some decided to
live in such structures. Many of the dis-
wait for better offers. Some of those Implementation
aster-affected people had lived in struc-
who opted out were still waiting for Every family was responsible for
tures made from bamboo at some time
support eight months later. the construction of their shelter. This
in their lives.
1DA >AJAł?E=NEAO SANA ?DKOAJ allowed them to make adaptations
based on a list of criteria, including: dependent on available space, using
loss of shelter, family situation, vulner- materials that they had rescued.
ability, poverty, residency in the area, 1DALNAOAHA?PA@>AJAł?E=NEAOSANA
and willingness to build the structure. visited by the coordinators of the
community kitchens together with
somebody from the NGO or the
municipality to check whether they
complied with the following criteria:
Š People had to be occupiers of a
house on a plot of a land before the
earthquake.
Š Their plot had to be cleared of
debris in order to place the shelter on it.
Š One family member had received
instructions on how to build and had
participated in the construction of a
Photo: Predes

model structure.
 AJAł?E=NEAO SANA łNOP CERAJ
wooden poles and received the mats
only when the structure was properly
assembled. Materials were distributed
by the block coordinators. Most
1DALNKFA?PS=O>=OA@KJ?KIIQJEPUOKQLGEP?DAJO=O=OP=NPEJCLKEJPBKN families ended up digging a new latrine
social mobilisation. on their property.

75
C.3 Peru - 2007 - Earthquake - Community mobilisation LAC

Photo: Eddie Argenal

Photo: Predes
1N=JOLKNPEJCPDAI=POBKN=ODAHPANPKOEPA

Logistics and materials Building with these materials costs local market had a limited capacity to
The wooden poles and woven about 25% of what some other local deliver bamboo mats - an issue which,
bamboo mats were purchased from organisations spent on their provisional in the end, led to the ending of the
local production in the informal shelters made of timber or low-grade project.
market. Plastic sheeting and hardware galvanized sheeting. However, the
elements (nails, hinges, etc.) were
centrally purchased.
The materials were shipped to San
José, where the municipality provided
the football stadium and another
building as storage areas.
The trucks were unloaded by the
LKPAJPE=H>AJAł?E=NEAO1DAEILHAIAJP-
ing NGO organized and was responsi-

Photo: Predes
ble for the warehouse management.
The materials were given to the -DKPK(QNP/DUJAN
>AJAł?E=NEAO SDAJ PDAU LNAOAJPA@
vouchers issued by the coordinators.
#=IEHUODAHPAN>QEHP@QNEJCPDALNKFA?P
Photo: Predes
Photo Predes

*=GEJC=>=OE?ODAHPAN

76
C.4 Peru - 2007 - Earthquake - Self-build transitional shelters LAC

Photo: Eddie Argenal


Rubble clearance Fabricating doors

0AHA?PEKJKB>AJAł?E=NEAO durability. Some shelters incorporated Implementation


Community leaders were initially reclaimed materials, particularly mud This shelter project was part of a
NAMQAOPA@ PK E@AJPEBU >AJAł?E=NEAO blocks and doors. However, higher- programme that included shelter, cash
1DAOA >AJAł?E=NU HEOPO SANA R=HE@=PA@ value reclaimed materials, such as for work, sanitation (where destroyed),
>UPDAłAH@=OOAOOIAJPPA=I EJ?HQ@EJC timber beams, were often stored by small grants for businesses and tran-
interviews to validate the selection families to be used in the future con- sitional classrooms for schools. The
of each family. Lastly, a community struction of permanent housing. cash-for-work project included debris
meeting was held to establish who was removal (employing 100 women for
The basic shelter design was arrived
to be included in the programme. two months) and payment for families
at by asking three carpenters in an
who could not build for themselves.
Most families had no formal land affected community to build a sample
The sanitation project included the
title, so shelters had to be easy to shelter. Members of the community
repair of destroyed latrines.
dismantle and remove if required. vetted the shelter design and a pilot
project was then implemented. The The project was implemented by a
Technical solutions ODAHPAN@AOECJS=OIK@EłA@@QNEJCPDA team consisting of one project manager
The shelter provided had an area of
pilot to improve labour productivity =J@=PA=IKBPAJłJ=HUA=NAJCEJAANEJC
18 m2 AJKQCDPKDKOP=B=IEHUKBłRA
=J@ ABł?EAJ?U EJ PDA QOA KB ?KJOPNQ?- student volunteers, each responsible
The shelter area was chosen based on
tion materials. It was expected that for the shelters of around 65 families.
Sphere indicators. The shelter itself
the shelter materials would be later
consisted of a timber pole-framed The project was conducted in close
reused in the construction of adobe
structure with a soil-cement mix as consultation with the local authorities.
houses (e.g. plastic sheeting used as a
ŃKKNEJC -H=OPE? ODAAPEJC ?KRANA@ PDA Before distribution of materials could take
water barrier in the clay roof) or that
timber structure and woven reed place, each family had to clear the debris
the shelter as a whole would be reused
mats were placed on top of the plastic from their damaged house into the street.
as a kitchen.
sheeting to increase insulation and
Photo: Eddie Argenal
Photo: Eddie Argenal

*=GEJCPDA?KJ?NAPAŃKKNOH=>

78
LAC Shelter Projects 2008 C.5

-DKPKOġ)A$N=J@*=H=JU
KILHAPA@ODAHPAN>QEHPKJPDANKKBKB=@=I=CA@DKQOA
0AHA?PEKJKB>AJAł?E=NEAO Technical solutions All tools needed by the homeowner
Communities were selected by The shelter design was a rectan- to build his/her shelter were supplied
analysing the gaps and noting that no gular, single-storey, 18m2 (3m x 6m), by the contractor and were left with
other organisations were working in wood-framed, shed-roofed building. the homeowner at the conclusion of
the areas. Families within communities The side covering was vertical, tongue- the programme as a home mainte-
were prioritised based on need and in- and-groove wood. Each panel was ap- nance tool kit.
dividual vulnerability. proximately 1cm thick and approxi- Implementation
mately 10cm wide. The shelter had one The initial contract was for 500
AJAł?E=NEAO JAA@A@ PK LNKRA
door and a large window on one long shelters. Costs rose 25% for subse-
ownership of land before qualify-
wall (at the front). The roof was a shed quent shelters, due to local cost esca-
ing for the project. The criteria were
style made with lightweight, corrugated lations.
later relaxed so that those awaiting
cement panels approximately 1m wide
KSJANODEL ?ANPEł?=PAO =O PDA NAOQHP KB The contractor set up a materials
and about ½cm thick. The roof panels
wills of deceased family members could manufacturing ‘factory’ in each project
were long enough to run the full width
qualify for the project without holding area. At this site, the contractor’s
KBPDANKKB1DAŃKKNEJCQOA@LNAAT-
PDABKNI=HH=J@KSJANODEL?ANPEł?=PAO employees (using some local labour)
isting concrete slabs.
Families who were at risk and ?QP LH=JA@=J@łJEODA@PDAS=HHBN=IA
Each house took approximately units. Only the contractor’s employees
relocated from the ‘no return zone’
eight hours to construct once the used power tools.
had to wait in temporary shelter on
prefabricated materials were trans-
squatted allocated land for over nine Families were responsible for
ported to the site. The idea was that all
months before they could be allocated rubble removal, site cleaning and
materials could be later reused.
land and qualify for a shelter. marking out the shelter location.

-DKPKOġ)A$N=J@*=H=JU

1DAN=SI=PANE=HOSANALNAL=NA@EJSKNGODKLOOAPQLEJPDA?KIIQJEPEAOSDANAODAHPANOSANAPK>A>QEHP

81
C.5 Peru - 2007 - Earthquake - Prefabricated transitional shelters LAC

Bill of quantities

-DKPKġ)A$N=J@*=H=JU
Item Quantity
Wood 68
(tongue and groove)
2.48m
Wood 43
(tongue and groove)
2.3m
Wood 10
(tongue and groove)
42cm
Wood 16
(tongue and groove)
32cm
Wood 16
KILHAPA@ODAHPAN>QEHPKJPDANKKBKB=@=I=CA@DKQOA (tongue and groove)
1.01m
Wood 70
&B PDA KH@ ŃKKN OH=> ?KQH@ JKP >A volunteers. The rest worked in the (tongue and groove)
reused, or there was no existing slab, community, helping with registration, 2.48m to 2.30m
the homeowner was required to land rights and other emerging issues. Nails 1kg
pour one. In some cases homeown-
ANO I=@A PDAEN ŃKKNO =BPAN ?KJOPNQ?-
Safety and Liability Wood strips 2
The contractor maintained control 3cm x 6cm x 3m
tion. Employees of the contractor and
of the cutting and assembly yard and Wall plates 3
trained community members provided
its employees, and controlled access to 6cm x 6cm x 2.5m
guidance and oversight for the mixing
hazardous places. Since the contractor
and pouring of concrete. Hinge, steel 2.5" 7
owned, controlled and supervised the
Homeowners transported the operation they were the main liable KNNQC=PA@NKKłJC 6 sheets
materials from the ‘factory’ to their entity. 3m x 1m
home. They then installed the tongue- Instructional manual 1
Each community established a safety
and-groove wall sheeting onto the Plastic tape 8
committee that controlled access to
six wall-framing panels. Company 1cm x 15cm
the cutting and framing site, as well
employees and trained community
as the assembly sites. In general, Screws 3
members then assembled the sided
community activities were provided
frames (two for the side walls and One toolkit was distributed per group
for youth and children to keep them
four for the front and back walls) with of workers.
entertained while their families were
assistance from company advisors.
building their shelters.
Families nailed the structures together
and added the doors and windows. Logistics
By delivering basic raw materials
Quality Control
(rough timber, tongue-and-groove wall
Supervision and quality control
sheeting and corrugated iron, cement
were done by the contractor’s staff.
panels, nails, etc.) to the building site,
The contractor had one engineer and
logistics requirements were reduced.
one project manager (who supervised),
Warehousing was also reduced, since
=J@ łRA OGEHHA@ SKNGANO SDK ?QP PDA
-DKPKġ)A$N=J@*=H=JU

non-value-added raw materials took


timber. The homeowners transported
up less space than fabricated material
the prefabricated shelter materials
components. Component costs were
and assembled them on site. The
reduced by directly employing people
only carpentry skill that homeowners
on site to fabricate them. These people
required was the ability to hammer a
did this work as only a part of their
nail and follow connection directions.
salary. Everything was fabricated as
Monitoring took place through needed on site and according to speci-
a team of approximately 30 volun- ł?=PEKJ 1DEO =LLNK=?D =HOK LNKRE@A@
teers, of whom 15 were active in the a ‘just-in-time’ inventory system, but
łAH@KJ=@=EHU>=OEO,BPDAOA łRAKN required the hiring of additional skilled
,JAKBPDALNKFA?P†OODAHPANOĠ>=?G
six worked with the contractor on a staff by the contractor. ground) and a shelter walled with reed
daily basis and mobilised community I=POĠBKNACNKQJ@

82
Historic Shelter Projects 2008 D

Section D
Historical Case Studies
From the Cuny Archive

D.4
D.2 Bangladesh
D.3 India KJŃE?P
Nicaragua KJŃE?P
Earthquake 1973 D.7
D.5 D.9 Thailand
Sudan D.6
Guatemala India, KJŃ?EP
Earthquake 1976 KJŃE?P
Andrah Pradesh
Cyclone 1977
D.8
Tonga
Cyclone 1982

83
D.1 Historical case studies - overview - Case studies from the Cuny Center Historic

D.1 Historical case studies - overview


Case studies from the Cuny Center
Summary
The main focus of this book has been on shelter responses after the year 2000. However, the loss of housing from
J=PQN=H@EO=OPANO=J@?KJŃE?P=J@PDAOQ>OAMQAJPJAA@BKNODAHPANEOJKP=JASLDAJKIAJKJ
This chapter includes case studies from the 1970s and 1980s taken from the Cuny Center in Washington DC,
201DAOA?=OAOPQ@EAO@K?QIAJPNAOLKJOAO@QNEJCSDE?DPDAłNOPCQE@AHEJAOQOA@>UDQI=JEP=NE=J=?PKNOPK@=USANA
developed.
Although some of these case studies are from responses that took place over forty years ago, many of the issues and
projects are similar and relevant to those being implemented today.

Need for guidance MQ=GAOEJ+E?=N=CQ=Ġ


$Q=PAI=H=
efforts must be community-focused
There are occasional records of
and take into account the community’s Ġ
=J@IQHPELHA@EO=OPANOEJ=JCH=-
shelter responses going back to the
own potential for self-help. Secondly, desh (1973-1975) to argue for shelter
18th century, but concerted efforts to
that above all else, shelter and settle- responses that helped affected com-
research and develop a best practise in
ment programmes must provide the munities build back better from day
PDAłAH@KJHUOP=NPA@EJPDAA=NHUO
>AJAł?E=NEAO SEPD OQBł?EAJP HARAHO KB one, using local labour and materials,
Indeed, the earliest modern guidelines
hygiene and remove public health risks and supported by locally adapted haz-
for shelter response for any humani-
to the greatest degree possible, as ard-mitigation construction training.
tarian organisation, dating from 1959,
this was the largest danger to human &B >AJAł?E=NEAO SANA PK >A NAHK?=PA@
IANAHUOQCCAOPA@łJ@EJC=IEHEP=NUOLA-
life after the occurrence of a disaster in camps, then the camps would have
cialist and following his advice when
or forced displacement. The develop- to be community focused, with the
it came to the spacing and grouping
ment of minimum standards for shelter shelters clustered into small neigh-
of tents in planned emergency settle-
KRAN PDA OQ>OAMQAJP PDENPU UA=NO  bourhood groups, and with space for
ments.
often expressed in numeric indicators, livelihoods and public activities.
Post-colonial civil wars, notably @ANERA@ BNKI PDEO JAA@ PK AMQEP=>HU Meanwhile, the development of
in Nigeria and Bangladesh (then East protect the health and hygiene of those new materials, such as plastic sheeting,
Pakistan), and a number of large-scale living in emergency and transitional and the increasing professionalisa-
A=NPDMQ=GAOEJPDAH=PAO=J@A=NHU shelter and settlements, with limited tion of logistics and communications
1970s, led to exponentially greater resources to support them. systems in humanitarian response
numbers of forcibly displaced popula-
First camp guidance allowed agencies the potential for a
tions and a correspondingly increased
1DA łNOP OAPO KB CQE@AHEJAO  @N=SJ more rapid, wider and larger response.
role for humanitarian organisations in
PDA łAH@ 4EPDKQP =@AMQ=PA CQE@=J?A  up by Fred Cuny in 1971, were for Lead agencies
EP >A?=IA MQE?GHU =LL=NAJP PD=P >=@HU shelters within the context of planned By the end of the 1970s and the
designed shelter and settlement pro- camps, but were based on the under- various crises in south-east Asia, the
grammes could cause more harm than standing that the development of a rapidly increasing number of agencies
good. camp was a process taking place over AJPANEJCPDAłAH@BKNPDAłNOPPEIAKN
an indeterminate length of time. The with little previous experience forced
By 1973, NGOs like Oxfam and guidelines divided the type of shelter advocates of best practice to change
CARE, researchers like Ian Davis, response into phases, depending upon their emphasis, in order to ensure
and consultants like Fred Cuny were whether the camp was subject to an that the ensuing chaos was not as big
engaged in developing comprehensive EJEPE=H AIANCAJ?U EJŃQT KB LKLQH=PEKJ  a disaster as the original emergency.
guidelines for humanitarian response whether the camp was being maintained From that point on there would be
and continued practical research into and services consolidated, or whether the inception of ‘lead agencies’ from
issues related to shelter. Many of the the camp was being upgraded and the UN that were clearly mandated
concepts that are now accepted as expanded for longer-term occupancy. with overall coordination and technical
standard practice today derive from
In the face of well-meaning but guidance. This would be facilitated by a
the research conducted in the 1970s
misguided attempts to create a perfect decisive change of guidelines emphasis,
by Cuny, Davis and their collaborators.
universal prefabricated shelter and towards universal, often numeric,
Overarching principles shelter design competitions conducted minimum standards against which all
The two sets of overarching prin- thousands of miles from any disaster, agencies’ performance could be held
ciples in the development of these it was important for Fred Cuny and accountable, but which at the same
CQE@AHEJAO SANA  łNOPHU  PD=P ?KIIQ- Ian Davis, with the support of various time ran the risk of failing to take into
nities must be supported in regaining NGOs and then the UN, to use their account needs for local adaptation.
sustainable livelihoods, and that all own experiences in responses to earth-

84
Historic Shelter Projects 2008 D.1

1980s
Throughout the 1980s, the numbers =@AMQ=PANAOLKJOA(JKSHA@CAKB>AOP ments and extreme weather conditions
of refugees caught in protracted situa- LN=?PE?A=IKJC=HH=?PKNOS=O=LNANAM- attributable to global warming.
tions increased, while the willingness of uisite before the start of a programme, Experiences such as those in Aceh,
host governments to provide options rather than something that could be Indonesia following the 2005 tsunami
for permanent resettlement dimin- FQOP HA=NJA@ EJ PDA łAH@ 1DEO SKQH@ D=RAN=EOA@EILKNP=JPMQAOPEKJO=>KQP
EODA@1DA2+łNOPATLKQJ@A@=LKHE?U become the Sphere Project (www. the unintended effects of shelter
response of voluntary repatriation as sphereproject.org). responses in accelerating urban
the single preferred durable solution, migration and extending the sprawl of
Transitional shelter and
and decried camps as the option of the cities further into hazardous or en-
settlement
last resort. Under such circumstances, vironmentally fragile locations.
At the same time as the Sphere
the focus of those working on best
drafting process, other initiatives gave
practice in the shelter sector started
PDAODAHPANOA?PKNEPOłNOPOAPKBEJ@A-
to pay more attention to the political
LAJ@AJP  OA?PKNOLA?Eł? RK?=>QH=NU
aims to which settlements could be
since the 1970s. The shelter process
twisted. This was often based on their
for the affected communities and for
own experiences of witnessing un-
humanitarian organisations is now
sustainable camps being used as ‘pull
seen as having transitional phases, with
factors’ or to house hostage popula-
=J EJOEOPAJ?A PD=P PDA łNOP AIANCAJ?U
tions, in places like Sudan or the Horn
response must somehow demon-
of Africa.
strate support for the eventual durable
1990s and Sphere solution.
The crisis in Rwanda in 1994
Urban challenges
gave the impetus to many organisa-
The last four years have seen
tions to capitalise on the movement
moves to widen the accountability and
started in the early 1990s with the Red
predictability in all sectors of humani-
Cross Code of Conduct. This aimed
tarian response through the develop-
PK JKP KJHU OUOPAIEOA PDA MQ=HEP=PERA
ment of the Cluster System. But those
=J@ MQ=JPEP=PERA =OLA?PO KB IEJEIQI
years have also seen greater challenges
standards across all sectors including
brought closer to the spotlight.
shelter, but to also ensure the widest
possible awareness of those standards, In the last two years, the number of
and the maximum possible adherence people living in urban populations has
and buy-in among humanitarian or- reached 50% of the world’s population
ganisations. This was done in the re- BKNPDAłNOPPEIA =J@I=JUKBPDKOA=NA
alisation that in complex emergencies living in hazard-prone areas on marginal
the UN lead agency system could lands. This is especially relevant with
not always be relied upon to ensure the potential threat to coastal settle-

Fred Cuny
Fred Cuny trained as an urban planner in Cuny conceived humanitarian response as centred
the mid-1960s, and worked professionally with upon the affected communities, and serving to
disadvantaged communities in southern Texas, support them in a return to sustainable livelihoods.
before his experience as a pilot of small planes He advocated for camp designs that clustered
gained him a position working with relief agencies shelters into small communities, shelters made
during the Biafran War in 1970. Between 1971 of traditional materials that were built by the
and 1995, Cuny and Intertect, the consultancy refugees, and the training needed to ensure that
that he set up, worked with NGOs, the UN, and those shelters and houses would be built back safer
I=FKN@KJKNOEJ=JQI>ANKBDECDLNKłHA@EO=OPANO and hazard resistant. Cuny also advocated a holistic
Through all of these, Cuny sought to develop approach to humanitarian response and worked to
guidelines for best practice and to advance the combine shelter responses with those for water/
state of the art in humanitarian response. Cuny and sanitation, food security, livelihoods and public
&JPANPA?PSANANAOLKJOE>HABKNPDASNEPEJCPDAłNOP health. By the early 1990s, he was increasingly
ever set of camp planning guidelines, contributed involved in advocating for policy and intervention
to Shelter After Disaster =J@SNKPAIQ?DKBPDAłNOP OPN=PACEAOEJ?KJŃE?P=J@@EO=OPAN%AS=OGEHHA@EJ
draft of the Handbook for Emergencies. They were also Chechnya in 1995.
early advocates for the promotion of minimum
standards in humanitarian response, through
guidelines and manuals.

85
Historic 0DAHPAN-NKFA?PO D.2

Before the war


0I=HHAN NABQCAA ŃKSO EJPK 4AOP CQE@AHEJAOKB>=OE??=ILLH=JJEJCLNEJ- QLCN=@EJCKBODAHPANO=J@PDAJAA@BKN
AJC=H BNKI SD=P S=O PDAJ ?=HHA@ ?ELHAOS=OSNEPPAJH=PANPD=PUA=N IKNAOL=?A=J@O=JEP=PEKJB=?EHEPEAO
"=OP -=GEOP=J D=@ >AAJ ?KJPEJQKQO Š -D=OA &&ġ 1DAOA SANA ?=ILO SEPD
OEJ?A PDA EJEPE=H L=NPEPEKJ LANEK@ KB A?=QOA KB PDA ?KJPEJQKQO EJŃQT
IKNA OP=>HA LKLQH=PEKJO 1DAU D=@
 *=JU KB PDA NABQCAAO SANA KBNABQCAAOKRAN=JQI>ANKBIKJPDO
IKNAN=PEKJ=H@AOECJO0DAHPANI=PANE=HO
KBPDA%EJ@QIEJKNEPUEJ"=OP-=GEOP=J =J@PDAODAANOEVAKBPDA@EOLH=?AIAJP 
SANA @EOPNE>QPA@  >=OE? @N=EJ=CA =J@
%KSARAN BNKIPK NAOAJP- I=JU KB PDA ?=ILO MQE?GHU >A?=IA
O=JEP=PEKJ SANA ?KJOPNQ?PA@  =J@
IAJPOKRAN@EO?NEIEJ=PEKJ>UPDA4AOP KRAN?NKS@A@ *=PPANO SANA I=@A
NK=@S=UO =J@ LQ>HE? B=?EHEPEAO SANA
-=GEOP=JCKRANJIAJP?KJPEJQA@PKNEOA SKNOA >U ?DKHAN= KQP>NA=GO =J@ PDA
EILNKRA@ PPAJPEKJ S=O =HOK CERAJ
1DAU?=IAPK=DA=@EJPDA=BPANI=PD I=FKN ŃKK@EJC KB I=JU KB PDA ?=ILO
PK LNKRE@EJC KLLKNPQJEPEAO BKN >KPD
KBPDADKH= U?HKJAKB+KRAI>AN @QNEJCPDAN=EJUOA=OKJEJ0ALPAI>AN
HERAHEDKK@O=J@OK?E=H=?PEREPEAO
  SDANA PDA 4AOP -=GEOP=J CKR- /AL=PNE=PEKJ KB PDA I=FKNEPU KB PDA
Š -D=OA&&&ġ4EPDSAHHH=E@KQPNK=@O
ANJIAJP S=O =??QOA@ KB IEOI=J=C- NABQCAAO OP=NPA@ =BPAN PDA AJ@ KB PDA
=J@ >APPAN @N=EJ=CA  BK?QO IKRA@ PK
EJC PDA NAHEAB ABBKNP =J@ JACHA?PEJC S=N
DECDANOP=J@=N@ LQ>HE? B=?EHEPEAO =J@
PDA =BBA?PA@ LKLQH=PEKJO  @AOLEPA PDA 0AHA?PEKJKB>AJAł?E=NEAO PDA ?KJOE@AN=PEKJO KB ?NA=PEJC IKNA
B=?PPD=P=JAOPEI=PA@ LAKLHA (and assessment) LANI=JAJP OAPPHAIAJPO  EB NAMQENA@
SANA GEHHA@ 1DEO NAOQHPA@ EJ =J "=OP &J PDA H=NCAN ?=ILO  PDA ĺREHH=CAO† 4EPD = IKNA OP=>HA ?=IL LKLQH=PEKJ 
-=GEOP=J LKHEPE?=H L=NPU ĠPDA S=IE H=UKQPS=OQOA@PK=@RK?=PAPDAOAL=- @EBBANAJPREHH=CA=NA=O?KQH@>AQOA@BKN
)A=CQA
C=EJEJC=H=J@OHE@AI=FKNEPUEJ N=PEKJ KB %EJ@Q =J@ *QOHEI CNKQLO ?KKLAN=PERA ATLANEIAJPO KJ @EBBANAJP
!A?AI>AN SEPDEJ PDA O=IA ?=IL 1DANA SANA PULAO KB ODAHPAN KN ODAHPAN CNKQLEJCO 
?KJ?ANJO=>KQPAJOQNEJCAMQ=HOQLLKNP PK>AOP=@=LPPKPDANAOE@AJPO†JAA@O
!AIKJOPN=PEKJO BKN EJ@ALAJ@AJ?A
BKN>KPDCNKQLO &J =HH LD=OAO  PDA @AOECJ =EIA@ PK
SANAIAPSEPD=OARANA?N=?G@KSJ>U
4AOP -=GEOP=J IEHEP=NU BKN?AO  HA=@EJC 1DA EJD=>EP=JPO KB OKIA KB PDA D=RA PDA ODAHPANO CNKQLA@ EJPK OI=HH
PKPDA@A?H=N=PEKJKBEJ@ALAJ@AJ?AKJ OI=HHAN =J@ IKNA >=OE? -D=OA & =J@ @A?AJPN=HEOA@ REHH=CAO EJ KN@AN PK
*=N?D=J@PDANAOQHPEJCS=N -D=OA && ?=ILO SANA OAHA?PA@ PK >A OQLLKNP PDA NABQCAAO† OAHB=@IEJEO-
1DAS=NKJHUAJ@A@KJ?A&J@E= BA=NEJC IKRA@ PK PDA H=NCAN -D=OA &&& ?=ILO PN=PEKJ =OSAHH=OPK=E@@N=EJ=CA=J@
BQNPDAN @AOP=>EHEO=PEKJ BNKI I=OO SDAJ PDA łNOP ?=ILO SANA ?HKOA@ ?KJOPNQ?PEKJ KRAN QJARAJ H=J@ 1DA
EJŃQTAOKBNABQCAAO EJPANRAJA@KJPDA @KSJ @A?AJPN=HEO=PEKJKBOANRE?AO=HOKIA=JP
OE@AKB"=OP-=GEOP=J>APSAAJ=J@ PD=PPDANABQCAAOD=@CNA=PAN=??AOOPK
!A?AI>AN
Land rights / ownership PDKOAOANRE?AO NAOQHPEJCEJHAOOQJNAOP
)=PANNALKNPOOP=PA@PD=PPDA&J@E=J =J@CNA=PANDA=HPD>AJAłPO
After war breaks out CKRANJIAJPD=@>AAJ=PL=EJOPKEJOEOP
JAOPEI=PA@IEHHEKJB=IEHEAO =P QLKJPDAJKJLANI=JAJPJ=PQNAKBPDA 1DEOS=O=HOKPDAłNOPPEIAPD=PPDA
= LA=G N=PA KB PAJO KB PDKQO=J@O LAN ?=ILO  =J@ D=@ NAOPNE?PA@ PDA QOA KB ?HQOPANEJCKBODAHPANH=UKQPOEJPDEOS=U
@=U  ŃA@ EJPK 4AOP AJC=H EJ &J@E= ĺLANI=JAJP† ?KJOPNQ?PEKJ I=PANE=HO EJ D=@>AAJ=@RK?=PA@
*=JU =NNERA@ EJ OAHBOAPPHA@ ?=ILO EJ PDA ?=ILO BPAN PDA AJ@ KB PDA S=N  Implementation
PDA RE?EJEPU KB =H?QPP= 1DA $KRANJ- =J@PDAAOP=>HEODIAJPKBEJ@ALAJ@AJ?A 1DA?=IL?KJOPNQ?PEKJ=J@=@IEJ-
IAJPKB&J@E==J@PDA KNLKN=PEKJKB >U =JCH=@AOD  PDA CNA=P I=FKNEPU KB EOPN=PEKJS=OQJ@ANP=GAJ>UPDA&J@E=J
PDA EPUKB =H?QPP==OOECJA@H=J@BKN PDA NABQCAAO SANA NAL=PNE=PA@ RKHQJ- =QPDKNEPEAO=J@IQ?DKBPDASKNGS=O
?=ILO =J@PDA&J@E=JNIULNKRE@A@ P=NEHU %KSARAN  IKNA PD=J  IEHHEKJ @KJA>U&J@E=JNIUAJCEJAANO
>=OE?OQLLHEAO=J@=@IEJEOPN=PEKJ NABQCAAO ĠI=EJHU %EJ@QO
 ?DKOA PK
NAI=EJEJ&J@E=BASKBPDAKH@?=ILO  LNK?AOO S=O ARAJPQ=HHU EJEPE=PA@
JQI>ANKBPDA?=ILOSANAOLKJ- PK ?HKOA @KSJ OI=HHAN -D=OA & =J@
D=RAOEJ?A>AAJEJ?KNLKN=PA@EJPKPDA
P=JAKQOHU OAHBOAPPHA@ KPD ?=PACK- -D=OA&&?=ILOEJŃKK@A@=NA=O
ATL=J@EJCHK?=H?EPEAO =HPDKQCDPDAEJ-
NEAOKB?=ILOSANAKBPAJKJI=NCEJ=H
D=>EP=JPO†DKQOEJCNECDPO=NAQJ?HA=N &J PDA -D=OA &&& ?=ILO  SKNGODKLO
H=J@O =J@ EJ HKSHUEJC =NA=O LNKJA PK
ŃKK@EJC SANAOAPQLPKI=GA>=I>KKI=PPEJC
Technical solutions
BKN QOA EJ ODAHPAN ?KJOPNQ?PEKJ „
1DA +$, D=@ >AAJ EJRKHRA@ EJ 1DA ?KJOPNQ?PEKJ  QLCN=@EJC =J@
AJKQCDBKN ODAHPANOEJHAOOPD=J
LQ>HE?DA=HPD=J@S=PAN=J@O=JEP=PEKJ I=EJPAJ=J?AKBPDA?=ILOSANA@ERE@A@
KJAIKJPDEJKJA?=IL0KIAKBPDA
LNKFA?PO EJ PDA ?=ILO  =J@ D=@ =OGA@ EJPK PDNAA LD=OAO  SEPD PDA BKHHKSEJC
SKNGOSANA@KJA>UL=E@?KJPN=?PKNO 
= ?KJOQHP=JP PA=I PK @ARAHKL = IKNA AILD=OAOġ
>QPIQ?DKBPDAHK?=H?KJOPNQ?PEKJ=J@
?KILNADAJOERA OPN=PACU BKN ?=IL Š -D=OA &ġ 1DAOA SANA @AO?NE>A@ =O QLCN=@EJC S=O @KJA >U H=>KQN PA=IO
LH=JJEJC =J@ ?=IL @ARAHKLIAJP 1DA >AEJC PDAłNOPAIANCAJ?U?=ILO>QEHP KNC=JEOA@=NKQJ@PDAREHH=CAO
?KJOQHP=J?U SKNGA@ @ENA?PHU KJ PDA =P PDA OP=NP KB PDA EJŃQT  SEPD HEPPHA
EILHAIAJP=PEKJ KB R=NEKQO LNKFA?PO EJ LNEKNPDKQCDPCERAJPKOEPEJCKNB=?EHEPEAO Materials
PDA?=ILO N=JCEJCBNKIPDAOAPPEJCQL 0=JEP=PEKJ S=O KBPAJ LKKN  ODAHPANO 1DA łNOP ODAHPANO SANA I=@A
KBI=PANE=HOSKNGODKLOPK@N=EJ=CAAT- SANA RANU >=OE? =J@ B=?EHEPEAO SANA BNKI PD=P?D  >=I>KK =J@ NA?KRANA@
?=R=PEKJ1DAU=HOKEILHAIAJPA@?=IL EJ=@AMQ=PA 1DA IKOP LNAOOEJC EOOQAO I=PANE=HO )=PAN LD=OAO KB ODAHPANO
H=UKQP OPN=PACEAO BNKI SDE?D = OAP KB SANAPDA?KJOPNQ?PEKJKB@N=EJ=CA PDA EJ?HQ@A@LKHUPDAJAODAAPEJC=J@OKIA
?KNNQC=PA@PEJNKKłJCODAAPO =OSAHH=O

87
D.2 &J@E= KJŃE?P/ABQCAAO#ENOP?=ILLH=JJEJCCQE@AHEJAO Historic

Cuny Center

Clustered camp plan

PDA>=I>KKI=PPEJC1DAOASANAQOA@ -D=OA &&& ?=IL >AJAłPA@ BNKI EPO =NIU AJCEJAANO &ILKNPA@ I=PANE=HO
BKN NKKłJC  L=NPEPEKJO =J@ ŃKKNEJC EJ LNKTEIEPU PK =H?QPP= EJ PANIO KB SANAH=PAN=QCIAJPA@>UPDA>=I>KK
PDA ODAHPANO =J@ H=PNEJAO  =J@ BKN PDA PDA LNK?QNAIAJP KB EPO ?KJOPNQ?PEKJ I=PPEJCI=@AEJPDA?=ILSKNGODKLO
HEJEJCKB@N=EJ=CA?=J=HO I=PANE=HO 1DA =>EHEPU KB PD=P ?=IL PK
@ARAHKL N=LE@HU S=O =PPNE>QPA@ PK PDA
Logistics =QPDKNEPEAO† SEHHEJCJAOO PK ?KIIEP
1DA ?KJOPNQ?PEKJ KB PDA H=NCAN
BQHHPEIA LNKBAOOEKJ=H PA?DJE?E=JO =J@

88
D.3 Nicaragua - 1973 - Earthquake - Small camp Historic

Before the earthquake 0AHA?PEKJKB>AJAł?E=NEAO washing facilities. The latrines were


Large-scale urban migration during (and assessment) placed outside of all of the shelter
the 1960s had increased the popu- 1DA >AJAł?E=NU CNKQL =LLA=N PK clusters along the side of the camp.
lation of Managua from 170,000 to have been self-selected, having moved
The design also took into account
430,000 in the decade before the PK*=O=U=EJPDAłNOPBAS@=UO=BPANPDA
the possibility that the camp would
A=NPDMQ=GA1DEOHABP=@Ał?EPKB  earthquake.
exist into the longer term or would be
houses, with many additional people in Land rights / ownership upgraded into a permanent settlement.
substandard housing. More than 25% The site was designated as a camp Space was provided for the installation
of the national population were living by the government, who also provided of standard drainage and semi-perma-
in the capital city area. support with sanitation and other nent water and sewage facilities.
During the last months of 1972 services. The government decided to
rebuild Managua on its original site and
Implementation
Nicaragua had been experiencing a The tents were erected by the
drought. As a result, some aid organi- plan, in theory permitting families to
occupants of the camp, the US Army,
sations were already present in the return to their customary locations
and the Nicaraguan Boy Scouts, who
country at the time of the disaster. within the city. By the summer of
also worked together to install basic
1974, the Nicaraguan Boy Scouts,
Before the earthquake, the site for drainage.
who owned the site, were planning to
the camp had been the grounds for the bulldoze the remaining shelters and The extra space needed for the
Nicaraguan Boy Scouts, who retained evict the last few families. construction and deployment of the
formal ownership of the site during igloos also caused some displacement
its use for displaced families. The land Technical solutions of shelters from the original cluster
was already cleared for use and there Tents were provided by the
design.
were some facilities in place, such as a US Army within four weeks of the
number of permanent latrines, before disaster. However, these were seen One NGO provided camp manage-
PDAłNOP=NNER=HOKBA=NPDMQ=GA=BBA?PA@ as inadequate to last through the rainy ment support in the form of a reception
families. season. committee to assess the medical and
social needs of or new arrivals. In-
After the earthquake After four months, polyurethane
formation was distributed via notice
With more than 250,000 people igloos (previously used in Peru in 1970)
boards and a camp newspaper.
homeless, the national government SANA?KJOPNQ?PA@BKNPDA>AJAł?E=NEAO
made the decision to move many of by international staff using specialised There was no initial plan for the
the homeless to tent camps near the machines. delivery or upgrading of some facili-
city or in the outskirts. However, ties, so the NGOs had to negotiate
Although the internal shelter space
130,000 affected people chose instead with the government (not always with
of the igloos was larger than that of
to stay with extended family members. success)to extend water lines into
the tents, the igloos had much lower
each cluster, build shower units and
All other camps were laid out along occupancy rates. This was in part due
construct a septic tank. However, the
strict military lines. However, one to the lateness of the delivery, but also
question of waste incinerators was left
camp, the one at Coyotepe, Masaya, because the design was not one that
unresolved.
was designed by the NGO consult- related to standard housing shapes
ant Fred Cuny to be laid out in square BKNPDA>AJAł?E=NEAO1DAECHKKOSANA Logistics and materials
‘clusters’ of 16 shelters each, with not easily extendable or maintain- Delivery of both the tents and the
the explicit intention of providing the able, although there were reports of igloos came at a relatively late stage.
physical structures for community self- parts of the igloos being broken off to Permanent toilets previously con-
OQLLKNP 1DEO S=O PDA łNOP PEIA PD=P make materials for other shelters. The structed on the site were used, but
such a layout concept had ever been igloos were also criticised for being other permanent buildings were not. In
implemented and it has provided the Ń=II=>HA terms of the support and maintenance
basic template for all other cluster- of the camp, the site was located along
based designs since. The design also
Camp layout a main road 3km away from the town
PKKGEJPK=??KQJPłNA>NA=GO OA?QNEPU The camp was laid out using square of Masaya and 20km from the nearest
lighting and adequate public spaces for clusters of 16 shelters, with a central =ENłAH@ 1DA ?=IL NAI=EJA@ NAHE=JP
recreation and community activities. space for administrative buildings and on the delivery of food and water and
Meanwhile, many of the other camps social/recreation areas. The clusters removal of waste solids by truck.
experienced much lower occupancy were placed so that the camp could
be expanded after the initial construc- Materials Quantity
rates and early abandonment of
shelters. tion phase. This would allow the camp Phase I – Sears Co. 360
to have the capacity for up to 3,500 high-wall chalet tents
By the end of 1973, the vast people (700 shelters). The layout Phase II – Bayer Co. 310
majority of camp residents had left the was designed to accommodate either polyurethane igloos
camp, mostly to return to Managua. community or individual cooking and Latrines, water facilities, No data
lighting, also supplied

90
D.4 =JCH=@AOD KJŃE?P-AKLHA@EOLH=?A@0DAHPANQLCN=@AO Historic
Before the upgrading of the
camps
Hundreds of thousands of Urdu-
speaking Biharis migrated from eastern
India to what was then East Pakistan
during the partition period of 1948.
During the Bangladesh War of Inde-
pendence in 1971, the Biharis sided

Cuny Center
with the Government of Pakistan.
After the surrender and evacuation
of Pakistani armed forces, the Biharis
were left behind, declared to be enemy
citizens by the new Bangladesh govern-
ment, denied the right to resettle in
Pakistan by the Pakistan government,
and were rendered stateless.
During the 1972-1974 period, the
Biharis were displaced into camps,
often under force from the Bangladeshi
authorities. A number of those camps
were scattered on marginal lands on
the periphery of Dacca. In 1972, some
NGOs had given shelters or shelter
materials to the camps, but the camp
layouts were often poorly organised,
and the shelters themselves had not
been upgraded since that point.

Cuny Center
In 1974-75, local police forced some
of the Biharis into new camp sites. This
had the initial effect of making NGOs
reluctant to support the camps, in case
they were seen as supporting the gov-
ernment policies. This attitude only
changed after April 1975, after storms Site plans before and after upgrade
had caused major damage to some
camps. After the upgrading of the 0AHA?PEKJKB>AJAł?E=NEAO
camps (and assessment)
The Intertect consultancy had been
There continued to be very minor People were largely self-selected
working with US university research-
technical issues with the structures by arriving at the camp. All families in
ers on the development of emergency
themselves. These issues, such as the the camp were eligible for the new
shelter designs and implementation
angle and placement of the windows, ODAHPANO OOAOOIAJPO KB >AJAł?E=NU
processes since late 1973. In 1975,
SANA A=OEHU łT=>HA >U PDA K??QL=JPO satisfaction (and the reasons for any
they were given donor assistance to
However, it was noted that the families dissatisfaction) were included in the
@ALHKUODAHPANLNKPKPULAOEJPDAłAH@
did little if anything to improve or LNKFA?P†OłJ=HNALKNPKB,?PK>AN
After that, Intertect persuaded NGOs
adapt their shelters. Members of the consultancy team
working in three different camps to
made further assessments in 1977.
use their designs for shelters, camp Later assessments showed that
layout and construction processes. =HPDKQCD PDA >AJAł?E=NEAO SANA Land rights / ownership
CAJAN=HHU O=PEOłA@ SEPD PDAEN JAS The Bihari camp residents continue
The aims of the research project
shelters, the A-frame design made to be stateless (recent rulings give the
had been to design shelters that:
EP @EBł?QHP PK I=GA ATPAJOEKJO KN option of Bangladeshi citizenship only
Š would be sustainable and resistant additions. There were also complaints to later-born generations) and do not
to hazard; that although the A-frame was highly own the land.
Š could be constructed by the resistant to high winds, it also reduced
>AJAł?E=NEAOĢ the head height.
Technical solutions
Š SKQH@ EJOPNQ?P PDA >AJAł?E=NEAO Multi-family shelters were designed
&J CAJAN=H  PDA H=?G KB >AJAł?E=NU using bamboo poles, palm thatch,
in hazard-resistant design through the
participation in the design process was matting and jute rope. The design was
construction process; and
seen in the reduced sense of ownership that of an A-frame with cross-bracing,
Š could be made in large numbers,
or responsibility after occupancy. which had performed best in strong-
and could be made out of low-cost,
local materials. wind tests back in the US.

92
Historic Shelter Projects 2008 D.4

The shelters built in the camps also


D=@N=EOA@ŃKKNOPKLNKPA?PPDAB=IEHEAO
BNKIŃKK@EJCOI=HHJQI>ANKB=HPAN-
native models were made with varying
lengths and for varying numbers of
families.
The consultant recognised that
most post-natural disaster situa-
tions generally required single-family
shelters that could be built on each

Cuny Center
family’s plot. But it was felt that in the
planned camps for the Biharis, with
very limited amounts of space, the
multiple-family shelters were appropri-
ate. The same basic design principles
could be used for single-family shelters
if required.
The layout of the camps was
based upon small U-shaped clusters of
ODAHPANO1DAOASANAH=PANOEILHEłA@PK
square clusters in some camps. Space
within the U was intended for the use
of women, particularly those observing
purdah. The areas outside the U shape,
along the access routes through the
camp, were intended for use by the
men. In this way, the public men’s area
was also intended to be made available
for workshops or other livelihoods ac-
tivities, and also gave each community

Cuny Center
more control over the public space
nearest their shelter cluster. Washing
and cooking areas were contained
within each cluster.

Shelter design details


Implementation
Two prototypes of the shelter were previously designed in the US were
>QEHPEJPDAłAH@QJ@ANPDAOQLANREOEKJ too cumbersome and too detailed.
of the university/consultant team and
The work teams preferred to
were occupied by refugee families.
be trained verbally, but this slowed
Based on observations of environmen-
down the rate of construction. This
tal issues, minor changes in structure
meant that large-scale production of
were made. After further consulta-
the shelters would be impossible or
tions with camp stakeholders (local
would have to rely on large numbers of
CKRANJIAJP KBł?E=HO  +$,O  ?=IL
PN=EJANO=J@OQLANREOKNO"RAJPQ=HHU ŃEL
residents), the upgrading was started in
?D=NPO SEPD OEILHEłA@ CN=LDE?O SANA
phases, with sections of the camp being
also developed for use in the project.
upgraded in rotation.
It was estimated that it would take
Logistics and materials
The basic materials were provided
a multi-person team two days to build
to the refugees by the humanitar-
one shelter, with different small teams
ian organisations. All materials were
assembled to take charge of different si-
available locally.
multaneous tasks. However, problems
were encountered in instructing the
U-shaped community block plans work teams in both the design and the
construction techniques. The manuals

93
Historic Shelter Projects 2008 D.5

Before the earthquake


During the preceding decade,
Guatemala City and other urban areas
had seen rapid increases in population,
with many of the new arrivals living
in hazardous areas on steep slopes at
the edges of the city. Even in the rural
areas, many had built their houses out
of adobe, often with heavier tile roofs,
without the inclusion of seismic-resist-
ant features.
Prior to the earthquake, a number
of smaller INGOs, as well as local
community-based organisations, had
been active in development pro-
grammes (but not necessarily shelter-
related) in the affected areas. While
PDA KBł?E=H H=JCQ=CA KB PDA ?KQJPNU EO
Spanish, many of those in the rural
affected areas had limited command of
this language and preferred to commu-
nicate in local Mayan dialects.
After the earthquake
The earthquake struck the Central
Highlands of Guatemala, killing 23,000
people and leaving more than a million
homeless. Some 58,000 houses were
destroyed in Guatemala City and
163,000 in the rural areas.
&JEPE=H KBł?E=H NAHEAB ABBKNPO SANA
further hampered by the number of

Cuny Center
roads and rivers blocked by landslides.
The emergency response from the US
and other governments was swift, with
5,000 tents transported to Guatemala
City within seven hours of the earth-
Sketch showing earthquake-resistant techniques bracing
quake.
As equally rapid as the external The international NGO in question Land rights / ownership
response was the rate at which affected partnered with a regionally-based Many of the affected population
families started building impromptu NGO that already had ongoing pro- were squatters in peri-urban areas
shelters themselves. Around 50,000 grammes in Guatemala (it was im- who often built back on traditional
ODAHPANOSANA>QEHPSEPDEJPDAłNOP plementing the earthquake shelter sites with no guarantee of tenure.
hours of the disaster. Although this programme), in order to accelerate At least one researcher involved in
meant that much of the affected popu- programming and ensure incorpora- the programme counselled against
lation were quickly under shelter, it led tion of local knowledge. wholesale rationalisation of the street
to a rapid increase in the price of cor- systems in those areas, because it
NQC=PA@C=HR=JEOA@ENKJNKKłJCODAAPO 0AHA?PEKJKB>AJAł?E=NEAO
would mean depriving many families of
There were additional concerns that Four affected rural areas were
their customary plots. Land holdings in
this would cause scarcity for the re- assigned to the NGOs by the national
rural areas may also have been tradi-
construction effort and cause the government. A partial registration of
tional for the most part, but this issue
materials to be too expensive for many >AJAł?E=NEAO S=O DAHLA@ >U =J EILHA-
was not as acute in those areas.
of the affected people. menting partner and the fact that local
cooperatives were already present in Technical solutions
A?=QOA KB PDA DECDLNKłHA J=PQNA the area. In some areas there were In light of the scale of the self-build-
of the disaster many organisations EOOQAOKB?KILAPEPEKJBKN>AJAł?E=NEAO ing of shelters, the NGOs in question
SEPDKQP LNEKN łAH@ ATLANEAJ?A OAJP KN KB >AJAł?E=NEAO OSEP?DEJC +$,O made a decision to support these
personnel to the disaster. The govern- when others appeared with free dis- efforts by distributing construction
ment was generally unable to enforce tributions or other attractive options. materials, supported with technical
coordination between organisations. training.

95
D.5 Guatemala- 1976 - Earthquake - Materials distribution and training Historic

At the beginning of the programme, the programme. The choice of the


a total of 67 separate recommenda- materials that were distributed and
tions for seismic-resistant features resold through the cooperatives was
were drawn up by a consultant for also geared towards seismic-resistant
the NGO as the basis for the training construction.
programme. The intention was that
even if not all of the recommendations
Logistics and materials
The corrugated galvanised iron
were followed, the house would still
sheets were imported from El Salvador.
be substantially safer. There was some
Some 95,000 sheets were bought and
disagreement, as some NGO staff
Cuny Center

NAOKH@ >U PDA +$, @QNEJC PDA łNOP


thought that the list of recommenda-
six months of the programme. Funds
tions was too comprehensive and was
recovered from the resales were even-
>AEJC QOA@ PKK OPNE?PHU EJ PDA łAH@
tually used to expand the operation.
Some thought that a smaller number
Construction materials were sold
of recommendations might support a
0GAP?DODKSEJCOPNQ?PQN=HNKKłJC through local, pre-existing cooperative
details H=NCANJQI>ANKB>AJAł?E=NEAO
societies. This was intended to raise
The programme had six key pillars: The NGO created four different PDA LNKłHA =J@ @ARAHKL PDA ?=L=?EPU
model houses, although the families of those cooperatives, but concerns
Š Salvage materials from destroyed
eventually built a wider range of were voiced a few years later that this
or damaged homes;
adapted designs. A booklet was also had ended up overstretching their ca-
Š Use indigenous materials (apart
developed and over 100,000 copies L=?EPEAO=J@ŃKSKBBQJ@O
BNKIPDANKKłJC
Ģ
were eventually distributed as an
Š Mount an extensive educational
element of training programmes.
programme;
Š Build a model house in each Implementation
community using techniques (such as 1DA >AJAł?E=NEAO SANA LNKRE@A@
the introduction of timber and barbed- with information and training on seis-
wire bracing) that would ensure safety mic-resistant construction, using local
the next time; materials and technologies (demon-
Š Use the model house as a focus of strated by the model houses). But the
further educational activity; responsibility for the design and for
Š Distribute the corrugated galva- reconstruction remained entirely with
JEOA@ENKJNKKłJCODAAPO=POQ>OE@EOA@ PDA>AJAł?E=NEAOPDAIOAHRAO
prices through the cooperatives.
The local cooperatives distrib-
Construction materials were sold
uted the corrugated galvanised iron
at subsidised prices to ensure that the
and other materials and also become
people had a true need of the materials,
the focal points for the training pro-
to reduce the sense of dependency and
grammes.
to spread meagre budget resources to
a wider population. There were limits In many affected communities,
to the amount of each article that model houses were built using local
each family could buy, in order to limit labour, as directed by the NGO and
hoarding or speculation. in coordination with village master
Cuny Center

craftsmen. Once these craftsmen,


A full set of housing materials,
masons and carpenters had been
EJ OQBł?EAJP MQ=JPEPU =J@ R=NEAPU PK
trained they were then employed
build a whole house, was sold through
to train a series of apprentices while
the local cooperatives. But the main
working on the reconstruction of the
material, which was imported and dis-
houses in the community. ,LPEKJOBKNNKKłJCI=PANE=HOPEHAO 
PNE>QPA@>UPDA+$, S=OPDANKKłJC
sheets. The thicker 26- or 28-gauge Unfortunately, many of the trained L=HIHA=RAO PD=P?D ?KNNQC=PA@ENKJ
sheets were preferred over the 30- or masons found better-paid jobs in the
35-gauge sheets. (Note: With standard cities and left the rural work pro-
wire gauge and corrugated iron sheet, grammes. Eventually, a local company
the higher the gauge, the thinner the had to be engaged and supported
sheet.) to take on the work for that part of

96
D.6 India - Andhra Pradesh - 1977 - Cyclone - Materials distribution and training Historic
Before the cyclone
The affected population was pre-
dominantly rural, farming rice and
keeping livestock to supplement their
income. The affected areas were all
low lying and were intensively culti-
vated.
The vast majority of the popula-
tion lived in houses made of tradi-
tional materials. Common materials
were bamboo and palmyra leaf thatch
(made from a certain type of palm
tree). Before the cyclone there had

Cuny Center
>AAJ KBł?E=H AJ?KQN=CAIAJP PK I=GA
houses ‘pukka’ - made using reinforced
concrete. Pukka housing was also
preferred by much of the population
and displayed a higher social status. Safer shelter techniques - strapping columns to beams
Some of the faith-based and local to do so. There was also pressure from day to tend their farms.
organisations that were involved in the the government and from international
Tensions rose over the course
emergency response had been working donors (and from within some organi-
of the response, due to the different
in the area since at least 1969. Many of sations) to start construction imme-
levels of support given to communities
the larger international organisations diately, using outside contractors or
affected by the tidal wave and those
were new to the area. non-local volunteer forces if necessary.
affected by the high winds. Additional
After the cyclone It was recognised that the tidal tensions arose between communi-
The cyclone created two different wave had left dangerous levels of ties who had made agreements with
areas of damage: an area damaged by salinity in many of the communities’ different aid organisations, which had
a six-metre tidal wave that travelled L=@@U łAH@O  =J@ PD=P PDA CNA=PAN different types of programme method-
as far as 24km inland at its furthest need was to recover what was left ologies.
point; and an area damaged by high of the previous rice crop, and then
The NGO initially targeted the most
winds reaching over 270km/h, all along PK QJ>HK?G ENNEC=PEKJ ?=J=HO =J@ ŃQOD
vulnerable members of each village for
a 50km stretch of coastline. KQPPDAL=@@UłAH@O0KIABA=NA@PD=P
the materials distribution, asking the
the large labour force needed for the
In the areas affected by the wind local Rotary Club to work with the
immediate construction of concrete
alone, many of the materials from villages to select 20 of the most vul-
housing would divert efforts from the
the destroyed houses were still lying nerable households from each village,
agricultural efforts and, in doing so,
nearby. About 90% of the surviving according to agreed-upon criteria.
block long-term recovery. Therefore,
population very quickly built their a two-pronged strategy was advocated Land rights / ownership
own shelters using this material and and involved: Affected communities were aided
removed the need for ‘emergency’ on their customary locations, although
shelter support. Š OQLLKNPEJCPDA>AJAł?E=NEAOEJPDAEN
some agencies constructed shelters in
own reconstruction, and on a schedule
In the areas affected by the tidal the early stages of the emergency in
of their own choosing, through the
wave almost all of the original housing grid patterns near the affected villages,
distribution of materials and technical
materials had been washed away, so without full consideration for land
support; and
the survivors were in need of shelter ownership questions. By December
Š encouraging the adaptation of
materials. 1977, the local government was
the reconstruction schedule to the
EJOEOPAJP PD=P PDKOA SDK D=@ ŃA@ PK
The local government distributed agricultural calendar.
the towns or cities at the beginning of
poles and palmyra thatch during the the emergency should be strongly en-
łNOPBAS@=UO SEPD=E@=CAJ?EAOFKEJEJC 0AHA?PEKJKB>AJAł?E=NEAO couraged to return to their villages and
in later. The NGOs had started pro- Lack of capacity by the local govern-
not remain permanently in the towns.
gramming in the health and medical ment, combined with the large number
sectors, but quickly changed their focus of newly created organisations looking Technical solutions
to shelter. to help and ‘adopting’ random villages, Basic kits of traditional materials
I=@A >AJAł?E=NU OAHA?PEKJ LNK>HAI- were distributed to the communities.
The local government requested atic. Selection was also made more It was recognised that in some cases
that the humanitarian organisations complex by the fact that some commu- distribution would have to be timed to
construct pukka housing for all ben- nities were displaced into local towns take into account both the agricultural
Ał?E=NEAO =J@ KBBANA@  I=P?DEJC or large villages, but were still travelling work cycle and the time needed to
funding to all organisations who chose back to their original locations every cure the bamboo for construction.

98
Historic Shelter Projects 2008 D.6

The architect hired by the NGO


felt that because parts of the roof had
actually blown off, this had reduced the
internal wind pressure and had saved
the larger structure of many of these
types of houses during the cyclone.
Implementation
Direct implementation was done by

Cuny Center
the families themselves, with technical
assistance from local carpenters. The
>AJAł?E=NEAOSANA=HOKNAOLKJOE>HABKN
shelter quality and for any adaptations
of their shelter. The NGO, and later
ARTIC, provided technical information
PDNKQCD @ENA?P łAH@ REOEPO  PN=EJEJC KB
local carpenters, the development of
Shelter design elevation showing cross-bracing booklets and posters, and in one case
The initial construction efforts consultation with the various organisa- the production of a short play to impart
were evaluated three weeks into the tions, but also produced booklets on important construction messages.
programme. Based on the evaluations, safer housing construction for local Logistics and materials
improvements and additions were distribution. Similar sets of materials were initially
made (cross-bracing and the protec- provided by the local government in
The design of the model house that
tion of the housing posts below ground PDAłNOPOP=CAOKBPDAAIANCAJ?U1DEO
PDA+$,LNKRE@A@PKPDA>AJAł?E=NEAO
level) in the guidelines and prototypes. delivery was taken over by the NGOs,
was square, with a pyramid-shaped roof
Based on the interest of a wide of a 45-degree slope to be both wind- and was augmented with the materials
range of shelter actors and the local resistant and to allow water runoff (bamboo, metal straps) necessary to
government, an Appropriate Recon- from the palmyra thatch. A ring beam make the shelters cyclone resistant.
struction Training and Information and aluminium strips to bind the joints One of the arguments for delaying the
Centre (ARTIC) was established were added to the cross-bracing. The reconstruction was that the materials
to give advice and conduct evalua- wooden posts were treated for infes- used in traditional construction were
tions for the various ongoing shelter tation and rot and were sunk 1m into strongest or best for use as construc-
programmes. ARTIC was funded and the ground. The palmyra thatch was tion materials. In the case of bamboo,
supported by a loose consortium attached to the roof using traditional this would have needed to be bought
of major INGOs and local partners. sewing methods, despite the sewing some weeks in advance and then cured
ARTIC not only worked directly in materials’ lack of great strength. before use.
Materials list
The following list shows the main
materials provided and the ones that
were of most value in the construc-
tion of adequate and cyclone-resistant
structures.

Materials
Wood posts
Bamboo bracing
Wood roof frame
-=HIUN=HA=BNKKłJCI=PANE=H
Metal binding straps
Plastic sheeting (used to protect
wood posts below ground level)
Cuny Center

Connection detail

99
Historic 0DAHPAN-NKFA?PO D.7

Before the opening of the camp !AOLEPA PDA H=PAN LKLQH=PEKJ LNAREKQO NAHEAB KLAN=PEKJO SANA JKP
1DA EJR=OEKJ KB =I>K@E= >U 3E- NA@Q?PEKJ KB PDA (D=K&!=JC ?=IL  NALA=PA@
APJ=IAOA BKN?AO EJ !A?AI>AN   PDA EJEPE=H EJ?NA=OAO EJ LKLQH=PEKJ D=@ 1DNKQCD NACEKJ=H SKNGODKLO SEPD
PDAAO?=H=PEKJKBłCDPEJC>APSAAJ3EAP- LKOA@ OARANA ?D=HHAJCAO BKN ?KJPNKH PDA?KJOQHP=JP=J@KPDANOEJ PDEO
J=IAOA=J@(DIAN/KQCABKN?AO=BPAN KB PDA ?=ILO ,RAN?NKS@EJC =J@ I=JQ=H BKNIA@ PDA OP=NPEJC LKEJP BKN
'QJA=J@B=IEJAEJ,?PK>AN  PDA DECDPQNJKRAN J=PQNA KB ?=IL PDAłNOP@N=BPKBPDA2+% /Handbook
?=QOA@=I=OOEJŃQTKBNABQCAAO=?NKOO NAOE@AJPO?=QOA@PDA?=ILPK@AO?AJ@ for Emergencies
PDA >KN@AN EJPK 1D=EH=J@  LA=GEJC =P EJPKREKHAJ?A=J@PK>A?KIAATPNAIAHU
A?=QOA KB PDA H=?G KB OL=?A  PDA
=LLNKTEI=PAHUIEHHEKJLAKLHAEJH=PA @EBł?QHPPKCKRANJ=PPEIAO
ODAHPANO SANA ?KJOPNQ?PA@ =O IQHPE
=J@A=NHU
0AHA?PEKJKB>AJAł?E=NEAO B=IEHU HKJCDKQOAO  QOEJC I=EJHU PN=@E-
1DA 1D=E CKRANJIAJP S=O EJEPE=HHU 1DAI=OOJQI>ANOKBPDAEJŃQT=J@ PEKJ=H I=PANE=HO Ġ>=I>KK =J@ PD=P?D

NAHQ?P=JP PK DKOP PDA NABQCAAO BPAN PDALKHEPE?=HLNAOOQNAOATANPA@>UPDA #ENANAP=N@=JPS=HH>K=N@S=OQOA@BKN
A=NHUEJ?E@AJPOSDANA NABQCAAO 1D=E=QPDKNEPEAO=J@PDA(DIAN/KQCA PDAOE@AOKBPDAHKJCDKQOAO=J@BKNPDA
SANANAPQNJA@PK =I>K@E= PDA1D=E @E@ JKP LANIEP >AJAł?E=NU OAHA?PEKJ EJPANJ=H @EREOEKJO >APSAAJ EJ@ERE@Q=H
=QPDKNEPEAO =CNAA@ PK LANIEP ?=ILO QLKJ =NNER=H /AOAPPHAIAJP LNK- B=IEHEAO%KSARAN PDEO@E@JKPNAIKRA
EJ JEJA HK?=PEKJO EJ PDA >KN@AN =NA= CN=IIAO =J@ PN=JOBANO EJŃQAJ?A@ PDA LNK>HAIO?=QOA@>UH=?GKBLNER=?UKN
%KSARAN  PDAU EJOEOPA@ KJ ?HKOA OAHA?PEKJKBSDKH=PANHABPPDA?=IL ?KIIQJE?=>HA@EOA=OA
?KJPNKH KB =??AOO =J@ PDA @AHERANU KB
Land rights / ownership #KNPDAIKOPL=NP PDAH=NCANHKJC-
OANRE?AOPKPDA?=ILO =J@KJPDA>=OE?
1D=E =QPDKNEPEAO @AOECJ=PA@ PDA DKQOAO EJ (D=K&!=JC SANA H=E@ KQP
=J@ OQLLKOA@HU PAILKN=NU J=PQNA KB
?=ILOEPA=J@PDA?=IL=@IEJEOPN=PEKJ EJ L=N=HHAH 0KIA NA@Q?PEKJ KB OL=?A
PDKOA?=ILO
=OOECJA@ EJ@ERE@Q=H LHKPO PK NABQCAAO S=O=?DEARA@PDNKQCD=ĺ?DA?GAN>K=N@†
1DA NABQCAA LKLQH=PEKJ D=@ >AAJ HH NECDPO KB K??QL=J?U SANA QJ@AN- H=UKQP  SEPD >HK?GO KB KLAJ OL=?A
OARANAHU PN=QI=PEOA@ >U BKQN UA=NO KB OPKK@PK>AJKJLANI=JAJP4DAJ=HH PDNKQCDKQPPDA?=IL1DEO=HOK=HHKSA@
BKN?A@@EOLH=?AIAJP CAJK?E@A B=IEJA PDA ?=ILO ?HKOA@   NAL=PNE=PEKJ BKN=@@EPEKJ=HODAHPANO EBNAMQENA@&J
=J@=NIA@EJR=OEKJ S=O OQLLKNPA@ PDNKQCD 2+>=?GA@ PDA 0=GAK ATPAJOEKJO  PDA HKJCDKQOAO
LNKCN=IIAO=EIEJCBKNH=J@CN=JPO=J@ SANACNKQLA@EJPKBKQNPKAECDPDKQOAO
,B PDA JEJA ?=ILO  AECDP SANA EJ-
LNKRE@EJCHAC=H=@RE?A =NKQJ@ OI=HH EJPANJ=H OMQ=NAO 1DAOA
PANJ=HHU ?KJPNKHHA@ @ENA?PHU >U PDA
SANA EJPAJ@A@ =O LNER=PA KQP@KKN
(DIAN /KQCA =NIU KN EPO =BłHE=PAO Standards manual
OL=?A KN RACAP=>HA C=N@AJO BKN A=?D
1DA ?=IL =P (D=K&!=JC  DKSARAN   LKHE?U =J@ OP=J@=N@O EILHAIAJ-
CNKQLEJC KB NABQCAAO )=PAN ODAHPANO
S=O PDA KJHU KJA QJ@AN ?HA=N 1D=E P=PEKJI=JQ=HS=O@N=BPA@BKNPDA2+
SANA =HOK EILNKRA@ >U >QEH@EJC PDAI
CKRANJIAJP =QPDKNEPU  =@IEJEOPANA@ >U?KJOQHP=JPO@QNEJCPDAH=OPIKJPDO
KJ OPEHPO  PK =RKE@ ŃKK@EJC @QNEJC PDA
>U PDA 2+ )A=@ANO KB PDA NABQCAA KB  =J@ LQ>HEODA@ EJ @N=BP >EJ@AN
N=EJUOA=OKJ
CNKQLO LNAOAJPA@ PDAIOAHRAO PK PDA BKNI>U'=JQ=NU1DA?=ILOEPAO
?=IL=@IEJEOPN=PEKJ=PPDAKLAJEJCKB =J@ OANRE?AO L=NP KB PDA I=JQ=H D=@ Implementation
PDA?=IL AECDP EJEPE=H L=NPO BK?QOA@ KJ S=PAN 1DAKNC=JEO=PEKJ=OOECJA@=JQI>AN
=J@O=JEP=PEKJEOOQAO =J@KJAL=NPKJ KB +$,O PK QJ@ANP=GA PDA @EBBANAJP
!QA PK PDA OEVA  OLAA@ =J@ DECD
DKQOEJC =J@ ?KJOPNQ?PEKJ &P AILD=- LD=OAOKB?=IL?KJOPNQ?PEKJ QLCN=@EJC
LNKłHA J=PQNA KB PDA AIANCAJ?U  PDA
OEOA@ IEJEIQI JQIANE? OP=J@=N@O  =J@I=EJPAJ=J?A QOEJCPDAI=JQ=H=O=
2+D=@PK?KLASEPD=N=LE@ATL=JOEKJ
=HKJCSEPD?HA=NHU@AłJA@FK>NKHAO=J@ CAJAN=HCQE@A1DANABQCAAOPDAIOAHRAO
KBEPOKSJOP=BB=J@PDA=NNER=HKBH=NCA
NAOLKJOE>EHEPEAOSEPDEJPDA?=IL SANANAOLKJOE>HABKNPDA?KJOPNQ?PEKJ
JQI>ANOKB+$,O I=JUSEPDKQPLNEKN
KBPDAENKSJODAHPANO
ATLANEAJ?AEJPDAłAH@A?=QOAKBPDA &ILHAIAJPEJC=CAJ?EAOEJPDA?=IL
R=NE=>EHEPUKBPDAATLANEAJ?AKBPDA2+ SANAPK>ADAH@=??KQJP=>HAPKPDAOA Logistics and materials
=J@+$,OP=BB =?KJOQHP=J?UłNIS=O OP=J@=N@OPDNKQCDNKQPEJA=OOAOOIAJPO 1DA>=OE?I=PANE=HOSANALNKRE@A@
DENA@PK@ARAHKL=I=JQ=HKBOP=J@=N@O QJ@ANP=GAJ >U PDA 2+ 1DA OP=PA@ PK PDA NABQCAAO >U PDA DQI=JEP=NE=J
*=JU KB PDKOA LKHE?EAO =J@ OP=J@=N@O CK=HOBKNPDAI=JQ=HSANAġ KNC=JEO=PEKJO
SANAEILHAIAJPA@=PPDA(D=K&!=JC
Š 1KAJOQNAPD=P=HHOANRE?AOIAAP= Materials list
=J@0=GAK?=ILO
>=OE?IEJEI=HHARAHKBMQ=HEPUĢ 1DA BKHHKSEJC EO = L=NPE=H HEOP KB
After the opening of the camp Š 1K AJOQNA PD=P =HH OANRE?AO =NA PDA I=PANE=HO QOA@ BKN PDA IQHPEQJEP
KPD ?=ILO KLAJA@ EJ ,?PK>AN- LNKRE@A@EJ=QJEBKNII=JJANĢ ODAHPANO
+KRAI>AN  =J@ MQE?GHU łHHA@ Š 1K LNKRE@A PDA >=OE? EJBKNI=PEKJ
PK ?=L=?EPU (D=K&!=JC ?=IL S=O Materials
JA?AOO=NU PK OQ??AOOBQHHU EILHAIAJP
EJEPE=HHU EJPAJ@A@ PK >A PAILKN=NU  2+% /OP=J@=N@OĢ =I>KKLKHAO
DKQOEJC LAKLHA SDK SKQH@ >A PDAJ Š 1K OP=J@=N@EOA NKQPEJAO =J@ PK -H=OPE?ODAAPEJC
PN=JOBANNA@ PK KPDAN ?=ILO  NAL=PNE- B=?EHEP=PANALKNPEJC=J@IKJEPKNEJCĢ
=PA@  KN NAOAPPHA@ EJ KPDAN ?KQJPNEAO /KLAKNSENA
Š 1KLNKRE@A=CQE@ABKNPDKOASDK
1DA ?=IL =HOK >A?=IA = ?KHHA?PEKJ D=RA D=@ JK LNEKN ATLANEAJ?A EJ PDA 1D=P?DĠL=HI

LKEJPBKNPDKOASDKD=@>AAJEJFQNA@ łAH@Ģ=J@ #ENANAOEOP=JPS=HH>K=N@O


@QNEJCPDA?KJŃE?P Š 1K AJOQNA PD=P PDA IEOP=GAO KB
1EI>ANŃKKNEJC

101
Historic Shelter Projects 2008 D.8

Before the cyclone Small Projects Land rights / ownership


Tonga consists of 170 islands, 36 The implementing organisation, #KN PDA IKOP L=NP  >AJAł?E=NEAO
of which are inhabited. Approximately in cooperation with the Government built back on their customary land.
two-thirds of its population of 95,000 of Tonga and a major internation-
al donor, started their programme
Technical solutions
people live on one main island group. The villages were left to decide
three weeks after the cyclone. The
Tonga is exposed to a number of whether there were any proposals
project was intended as a form of
hazards (earthquakes, volcanic eruption for which they would like to apply
‘Quick Impact Project’. It was called
and tsunamis) of which cyclones are for funding. Staff worked with the
the Small Projects Disaster Assistance
the most common, striking once every villages to prepare the actual technical
Programme and had a shelter and set-
1.6 years on average. Cyclone Isaac proposals.
tlements focus.
was declared by the Tongan authori- Responsibility for all construction
ties to have been the worst disaster The uneven speed of progress in
and for the construction quality of the
in Tongan history, in part because of the completion of some projects meant
Small Projects was left explicitly to the
the magnitude of the destruction of PD=PPDALNKCN=IIA@E@JKPłJEODQJPEH
>AJAł?E=NEAO
housing, public buildings and livestock the end of June the following year. The
(95% of livestock were killed in some Small Projects programme was already Because most villagers were
places), but also because of the pro- on the ground before the emergency. able to quickly build basic shelters,
portion of damage caused to the more The consultants employed to create a and because they were applying as a
heavily populated island of the capital shelter strategy were also involved in a village, the proposals were often for
city, Tongatapu. broader project of disaster mitigation communal facilities in the village, or
BKNDKQOEJCEJPDA0KQPD-=?Eł? CNKQLO KB OPNQ?PQNAO PD=P >AJAłPA@
The emergency response was con- the shelter and settlement recovery as
strained by the large number of islands, Disaster mitigation strategy
a whole. These included restorations
the dispersed nature of the popula- For some time prior to Cyclone
of village fences, showers, kitchens
tion and limited communications. It Isaac, the same international donor
and toilets, as well as community food
emerged after the cyclone that there D=@ =HOK >AAJ BQJ@EJC PDA łNOP OP=CAO
gardens. Other projects, not directly
had been no comprehensive govern- of a shelter-focused disaster prepar-
related to shelter, included the resto-
ment disaster mitigation or disaster edness study for all of the anglophone
ration of poultry units, water tanks and
response programme in place. 0KQPD-=?Eł?EOH=J@O-=NPOKBPDAOPQ@U
a wind tower.
OLA?Eł?PK1KJC=SANAPDAJSNEPPAJEJ
Repeated cycles of disaster and direct reference to the cyclone and a Disaster mitigation strategy
short-term emergency response had draft was released in April 1982. This The consultant realised that most
contributed to a lack of disaster- then informed studies for the other traditional houses were built and main-
preparedness and disaster-mitigation islands. The consultant continued to tained incrementally by the families.
planning. The repeated disasters had work with the same donor and with Outside support, whether it was
both forced resources to be used for research organisations until 1984 to materials or information, often arrived
emergency response and had damaged produce guidelines for other South while the recovery and reconstruction
the local population’s capacity for self- -=?Eł??KQJPNEAO process was already underway. The fact
reliance. that this process was often ongoing
0AHA?PEKJKB>AJAł?E=NEAO when Tonga was faced with the next
Public buildings were designed
Small Projects The size of many
using seismic and cyclone codes from disaster led the consultant to develop
small islands and the prior stationing of
Australia and New Zealand, but these a series of illustrated information
the implementing organisation’s staff
were not applied to private housing. booklets that advocated:
allowed information about the Small
The modernisation of some of the Š self-reliance and self-build
Projects programme to be delivered
housing stock in the prior decade had techniques for the affected families;
to each community by word of mouth.
also seen many houses built with badly Š use of traditional techniques and
Villages made proposals as a whole and
OA?QNA@IAP=HNKKłJCODAAPO locally available materials;
each village’s proposal was assessed by
After the cyclone the implementing organisation. The Š last-minute strengthening measures
Relief agencies and the armed national government was informed of applicable to both transitional and
forces of Australia, New Zealand =HH @A?EOEKJO  JQI>AN KB łAH@ REOEPO permanent housing; and
and other countries worked quickly to each village were made during the Š the incorporation of hazard-
to bring food supplies, medicine and projects to monitor for quality and resistant measures into the repair
other support to the affected popula- speed of progress. of disaster-damaged housing, as few
tion. The largest immediate concern houses were torn down and built anew
While it was designed primarily for
was the widespread destruction of from scratch.
the Government of Tonga, the strategy
livestock and crops. While 1,000 The guidelines had to take into
for disaster mitigation and prepared-
tents and tarpaulins were delivered in account the wide range of hazards
ness was also intended to be accessible
PDA łNOP BAS @=UO  I=JU B=IEHEAO D=@ that were possible in Tonga. The main
to the country’s entire population.
already started the rebuilding process. guidelines concerned strengthening

103
D.8 Tonga - 1982 - Cyclone Isaac - Disaster mitigation Historic

The site was visited and the proposal


was checked to ensure that it answered
a cyclone-related problem, was within
a maximum of US$ 5000 and met
other criteria.

Cuny Center
A clear agreement on the division of
responsibilities was drawn up between
the organisation and the village. The
organisation was to procure the
Tieing techniques Bracing techniques materials, while the village would pick
up the materials from the local depot
and would take responsibility for con-
struction.
One challenge involved ensuring
that the villages understood what the
materials would be used for. This issue
became more central in villages where

Cuny Center
the leadership structures were not
clear.
Disaster mitigation strategy
The studies and the illustrated guide-
Preventing uplift due to strong winds Preventing uplift due to strong winds lines were made available to the
Tongan government. Other consult-
ants developed similar illustrated
guidelines that were published as sup-
plements in a local newspaper.
Logistics and materials
Cuny Center

Small Projects In some of the


small projects, the NGO was able to
ask a village to show how much con-
struction material they already had and
were willing to use in the project. The
Lateral bracing Wind resistance techniques
resulting project budget was then used
to meet the shortfall.
In some projects the implementing
organisation was not able to survey
the available construction resources
beforehand and they therefore made
Cuny Center

a more comprehensive budget. Some


materials (e.g. timber, thatch) could
be sourced locally, but many other
materials had to be brought to the
different islands, making projects
0=BAS=HH?H=@@EJCłTPQNA 0=BANKKBłTPQNA longer to implement. The implement-
ing organisation was able to buy scarce
against both cyclones and earthquakes, reducing damage, repair and upgrading. materials duty free at the government
focusing on the binding of roofs to wall store, which saved an estimated 27%
The graphics guidelines were also
posts and the binding of ring beams in costs.
accompanied by other documents that
and reinforcement of joints.
focused on the setting up of permanent
The guidelines included the disaster preparedness capabilities
planting of bushes in front of houses within government structures.
Cuny Center

to protect them from objects blown


by high winds. The most important
Implementation - Small
Projects
element was the realisation that post- Proposals for each project were
disaster mitigation measures would be received on a rolling basis; approval
implemented both before and after took about three weeks in each case.
repeating disasters, as part of a cycle of Use of diagonal bracing

104
D.9 0Q@=J KJŃE?P-H=JJA@?=ILO Historic
ABKNAPDAEJŃQT
1DANA D=@ >AAJ KJCKEJC ?KJŃE?P
between the Ethiopian government
=J@ NA>AH CNKQLO łCDPEJC BKN EJ@A-
pendence for the provinces of Eritrea
and Tigray since the 1970s. Many
NABQCAAO BNKI PDA ?KJŃE?P IKRA@ PK
0Q@=J!QNEJC PDA?KJŃE?P
combined with drought across many
countries in Africa to create a major
famine. There were no early warning
programmes or adequate stockpiles
until after September 1984.
ABKNA   OQBł?EAJP BKK@ D=@
been supplied into Tigray from Sudan.

Cuny Center/UNHCR
By mid-1984 the Relief Society of
Tigray, a national civil relief organisa-
tion, stated that the famine had reached
crisis levels and that they would lead
Tigrayans out of Tigray and into Sudan,
where they could receive aid.
Initial camps in Sudan were
sometimes located adjacent to the Block plan
sites of older permanent refugee set-
tlements. In early December 1984, 0AHA?PEKJKB>AJAł?E=NEAO arrivals from each village.
it was realised that there were not There was no selection per se. As This cluster, block and sector
enough water resources for these the refugees arrived in the camps in hierarchy was derived from the
camps. A decision was taken to look more or less intact village groups, it Handbook for Emergencies, which had
for sites that would support larger was possible to work with the village been made available two years before
numbers of refugees. Even then, not leaders and social structures to identify PDA ?NEOEO  0Q@=JOLA?Eł? RANOEKJ KB
all camps had adequate clean water for vulnerable members. PDAD=J@>KKGOLA?Eł?S=O?NA=PA@
many months. Waterborne disease, Land rights / ownership As the main emphasis was placed
alongside measles and malnutrition in There were no permanent land on water supply, sanitation and the
new arrivals, became the chief cause of rights given to refugees. In fact, the logistics of food and medicine, the
death in the camps. government of Sudan insisted that basic shelter was often a traditional
Although the Sudanese had new refugees would not be granted tukul tent made out of branches,
welcomed hundreds of thousands of permanent residency. although there were some distribu-
refugees for resettlement from Ethiopia Technical solutions tions of other shelter materials. The
over the previous two decades, the Once decisions had been made to government’s insistence that the
O?=HA KB PDA JAS EJŃQTAO  =J@ PDA transfer some of the refugees from in- camps were to be short term often
fact that Sudan itself was suffering a adequate camps, the new camps were prevented the use of any more durable
drought, caused a reversal of policy in set up following a hierarchy of blocks shelter materials, even if the resources
the Sudanese government. Even when of buildings. This started with a cluster had been available.
this decision was overturned, the gov- of shelters based on the size of each Implementation
ernment indicated that they did not ATPAJ@A@B=IEHU1DAOA?HQOPANO?KQH@ The Relief Society of Tigray would
ATLA?P PDA NABQCAAO PK NAI=EJ EJ PDA be grouped together to form a block often lead the Tigrayans into Sudan in
long term. that would follow the size of a single entire village groups. In some cases,
BPANPDAłNOPEJŃQT village. A number of blocks would form the society would also participate in
NGOs began searching for suitable a sector of a camp. the transfer of groups from one of
sites for new camps. Between April Importantly, the number of clusters PDAłNOP?=ILOPK=OA?KJ@?=ILSEPD
and June 1985, 55,000 refugees were in a block was not predetermined, but better facilities.
able to return to Ethiopia. But this still was dependent upon the number of Materials
left 258,000 new Ethiopian refugees in ATPAJ@A@ B=IEHEAO ?KIEJC BNKI A=?D Pressure from the Govern-
eastern Sudan, in addition to 120,000 REHH=CAEJ1ECN=U1KPDAATPAJPLKOOE>HA  ment of Sudan meant that use of any
Chadian refugees in the west of the services such as health units and sup- ‘permanent’ materials was avoided.
country, 700,000 ‘old’ Ethiopian plementary feeding centres were de- Although there were distributions of
refugees and increasing numbers of in- centralised throughout the camps. plastic sheeting, many of the refugees
ternally displaced Sudanese. Space was left in each block for late

106
Historic Shelter Projects 2008 D.9

lived in self-built tukul tents, made from


tree branches, grass thatch and cloth.
Logistics
Access to the camp helped with
logistics. The most important paved
highway in Sudan, connecting Port
Sudan with Khartoum, ran through the
camps areas. A major train line also ran
adjacent to the highway for part of the
time, and airports capable of handling
large jets or C-130s were available at
towns used as logistics hubs.
Most materials had to be imported
using UN mechanisms, apart from in-
dividual shelter materials scavenged by
the refugees. During the emergency,

Cuny Center\UNHCR
there were some severe delays in the
provision of materials, but these were
caused by poor pre-planning, lack of
stockpiling and internal organisational
issues, as much as by lack of physical
infrastructure.

Sector plan

‘[The design] had several major


advantages. First, it enabled the
relief agencies to train a cadre of
health workers from each village.
In the event that people decided
to return to Tigray (which many
of them did several months after
arriving in the camp), the skills
and training the workers had
acquired would be taken back
to the village with them. Second,
it provided camp administra-
tors with a simple way to reunite
families. When anyone entered
Sudan, they simply had to tell
the relief authorities what Ti-
grayan village they were from;
they could be transferred to the
camp where the people from
that village were located. Family
NAQJEł?=PEKJ?KQH@PDAJ>AD=J-
dled on a self-help basis. Finally,
camp administrators were pre-
Cuny Center/UNHCR

sented with an intact community


organization with which to work,
facilitating activities which re-
MQENA@JKPEł?=PEKJKNKNC=JEV=-
tion of the refugees.’- Fred Cuny
Camp plan

107
Annex -

108
Shelter Projects 2008 Annex

Further reading
Key shelter-related documents
Websites
www.humanitarianreform.org
The home page of the project to establish clusters as a coordination mechanism. Includes the Emergency Shelter Cluster and Early
Recovery Cluster home pages, which contain further reading on the cluster approach as well as on technical issues.

www.reliefweb.int
Up-to-date information on complex emergencies and natural disasters, as well as an archive of information, field reports and
situation reports from emergencies since 1996.

http://ochaonline.un.org
1. UNDRO Shelter after disasters
2. Transitional settlements
3. Guiding Principles on Internally Displaced.

Corsellis, T. and Vitale, A. (2005). Transitional Settlement: Displaced Populations, Oxfam Publishing, United Kingdom.
Guidelines aimed at strategic planners and implementers of settlement responses. Considers settlement options for displaced populations.
Available online: www.shelterlibrary.org

IFRC/Oxfam (2007). Plastic sheeting: A guide to the specification and use of plastic sheeting in humanitarian relief.
A guide to the use and specification of plastic sheeting in humanitarian operations.
Available online: www.plastic-sheeting.org

Norwegian Refugee Council/The Camp Management Project (2008). The Camp Management Toolkit.
A comprehensive field manual for camp management agencies and stakeholders involved in camp operations.
Available online: www.nrc.no/camp

The Sphere Project (2004). The Humanitarian Charter and Minimum Standards in Disaster Response.
Sets out what people affected by disasters have a right to expect from humanitarian assistance. Includes shelter and settlement
planning, with standards, indicators and checklists.
Available online: www.sphereproject.org

UNDRO (now UN/OCHA) (1982). Shelter after Disaster: Guidelines for Assistance.
Guidelines and description of shelter provision in all aspects of natural disasters, from preparedness to reconstruction.
Available online: www.sheltercentre.org (www.reliefweb.int/library/documents/2003/undro-shelter-jul82.htm)

UN/OCHA (2008). Transitional Settlement and Reconstruction after Natural Disasters, field edition.
Guidelines aimed at strategic planners and implementers of settlement responses. Considers settlement issues for people affected by
disasters as well as assitance methods to support them in their reconstruction.
Available online: www.shelterlibrary.org

UN/OCHA (1998). Guiding Principles on Internal Displacement.


Identifies the rights and guarantees for the protection of internally displaced people. Relevant to forced displacement and protection
and assistance during displacement, as well as during return or resettlement and reintegration.
Available online: www.shelterlibrary.org

UNHCR (2007). Handbook for Emergencies, UNHCR, 3rd ed.


A managers' guide to setting up emergency operations for large-scale influxes. Provides advice on how to tackle various aspects of the
emergency response.
Available online: www.unhcr.ch

109

Você também pode gostar