Escolar Documentos
Profissional Documentos
Cultura Documentos
Foreword
Much has been written over the years about the challenge of providing shelter for households affected by crises, whether
they are human-made or result from natural events. In spite of the many reports commissioned by governments, donors,
independent experts, multilateral and international aid organizations that provide a variety of recommendations on issues
ranging from design to cost analysis methods, shelter remains one of the most controversial and challenging components of
sustainable recovery from disasters.
In recent years, the humanitarian community has looked inward, learning from their past experiences in providing emergency
shelter for the ever-increasing number of populations suffering from crises worldwide. The humanitarian reform process has
helped widen the community of practitioners, reinforced global and country-based coordination systems, and required the
agencies concerned to seek new and better means of ensuring integrated and robust humanitarian programming.
This publication is an example of a series of learning tools being produced to support improved response to crises. It has
been developed by the Emergency Shelter Cluster through a group of agencies within the cluster led by UN-HABITAT.
It contains summaries of a range of experiences applied in crisis situations, and an honest appraisal of their successes and
failures. From these, a number of key principles emerge.
One key principle is that the survivors of these crises must be given every opportunity to engage in their own recovery.
!EO=OPAN=BBA?PA@DKQOADKH@OODKQH@JKHKJCAN>APNA=PA@=OHE=>EHEPEAO1DEOD=OOECJEł?=JPEILHE?=PEKJOKJNA?KIIAJ@A@
approaches to post-disaster shelter and settlement responses, several of which are well illustrated in the case studies in this
publication.
A second principle is that without immediate strategic planning covering land use, tenure, livelihoods and critical services, in
addition to shelter options, there is a danger that temporary solutions become, de facto, permanent ones. As well as failing
to address the risks and vulnerabilities that may have contributed to the scale of the crisis, poor or inadequate programmatic
responses can increase shelter and settlement vulnerabilities. A number of the case studies illustrate these considerations.
A third principle follows from the above – that is, all change demands social mobilization, the involvement of the affected
population and the appropriate local authorities, and legal compliance. Immediate shelter solutions must therefore consider
long-term settlement issues, both for temporarily displaced populations and those who are able to return to the location of
PDAEN@=I=CA@KN@AOPNKUA@ODAHPANO1DA?QHPQN=H
OK?E=H=J@A?KJKIE?JKNIOKBPDAOLA?Eł?@EO=OPAN=BBA?PA@OK?EAPEAOIQOP
>ANAŃA?PA@EJODAHPAN=J@OAPPHAIAJPNAOLKJOAOPD=PI=ULKPAJPE=HHU>A?KIA@QN=>HA
N=PDANPD=JPN=JOEAJP
EJJ=PQNA+KJ
tent based emergency shelter solutions that are rapid and cost effective can also be culturally acceptable to the populations
they are designed for, in both the short term and over a longer period of recovery. This publication highlights a number of
such examples.
łJ=HLNEJ?ELHABKHHKSOBNKIPDAPDNAAKQPHEJA@=>KRA-QPPEJCLAKLHAĠOQNRERKNO=J@RE?PEIO
łNOP
LH=JJEJC=J@LNKCN=IIEJC
EJ=@R=J?A
?KJOE@ANEJCPDALKPAJPE=HKBHKJCANPANIOKHQPEKJO
=J@łJ=HHU
?NA=PEJCOL=?APK=@@NAOOH=J@=J@LNKLANPU>=OA@
losses following a crisis, all contribute to reducing demand on humanitarian capital while maximizing potential opportunities
for recovery.
1DANA=NAI=JUIKNAHAOOKJOEJPDEO>KKGPD=PSEHH>AKB>AJAłPPKPDANA=@AN,J>AD=HBKBKQN=CAJ?EAO
=J@EJ?KHH=>KN=PEKJ
with our interagency partners from the Emergency Shelter Cluster, we encourage the study and widespread use of these
lessons.
i
INTRODUCTION Acknowledgments
Acknowledgments
Project coordinated by UN-HABITAT on behalf of the Emergency Shelter Cluster: Esteban Leon, Joseph Ashmore
Edited by: Joseph Ashmore
Lead authors: Joseph Ashmore (Asia, LAC), Jon Fowler (Africa), James Kennedy (Sri Lanka, Cuny Center).
Authors (specific sections): Eddie Argenal (Peru - self-build transitional shelters), Milton Funes (Honduras), Dave Hodgkin
(Jogyakarta), Kurt Rhyner (Peru - community mobilisation).
Editiorial support: Seki Hirano
Special thanks: The authors would like to give special thanks to the following people for providing case study information,
editing drafts, and for providing the photographs:
Hassan Abdalla, Subhan Ahmadov, Eddie Argenal, Dyfed Aubrey, Lizzie Babister, Eric Baranick, Rick Bauer, Isaac Boyd, Joana
Cameira, Michelle Carter, Chris Cattaway, John Flomo, Tom Corsellis, Milton Funes, Valle Galan, Catherine-Lune Grayson,
Jens Grimm, Anamul Haque, John Howard, Cynthia Jones, Yasmin Keith-Krelik, Peter Krouwel, Unni Lange, Mark Lawler,
Dan Lewis, Manoucher Lolachi, Julia Macro, LeGrand Lee Malany, Bill Marsden, Tom McKnight, Jelena Milosevic, Douglas
Osmond, Paul Neale, Nicole Poirier, Anna Pont, Albert Reichert, Adelmo Risi, David Sanderson, Qurat Sadozai, Graham
Saunders, Hassan Noor Saadi, Anna Maria Sellari, Charles Setchell, Thierry Schweitzer, Alister Shields, Jo Da Silva, Joana
Sousa, Mikael Adri Budi Sulistyo, Wondwossen Teffera, Ombretta Tempra, Kim Williamson, Matthias Wohlfeil, Jake Zarins.
Additional thanks to the Cuny Center in Washington DC, USA for allowing access to the documents that have provided the
case studies in Section D.
A final thanks to all of the field staff who have worked so hard to make all of these projects possible.
Copyright notice:
The copyright for this booklet is retained by UN-HABITAT. Reproduction for non-profitable objectives is encouraged.
The copyright for the photographs remains with the photographers whose names are indicated on each photograph.
While every effort has been made to ensure the accuracy and completeness of the content of this book, no liability can be
accepted for any errors or omissions contained within it.
ii
Shelter Projects 2008 INTRODUCTION
Contents
Introduction
Foreword on behalf of the cluster i
Acknowledgments ii
Contents iii
Introduction iv
Overview of Case Studies v
Section A - Africa......................................................................................................................... 1
A.1 D.R. Congo - Goma - 2002 - Volcano - Distribution and technical support 2
"NEPNA= KJŃE?P =ILQLCN=@AO
A.3 Kenya - 2007- Flooding - Shelter and disaster mitigation 8
A.4 Kenya - 2008- Election violence - Transitional shelter kits 11
)E>ANE=&!-
/ABQCAAO0AHB>QEH@ODAHPANO
A.6 Mozambique- 2007- Cyclone - Shelter material packages and training 17
A.7 Rwanda - 2008 - Returns - Materials distribution and technical guidance 20
0KI=HE= EREH?KJŃE?P/AOAPPHAIAJP
!=NBQNĠKJCKEJC
KJŃE?P*=PANE=HO@EOPNE>QPEKJ
Section B - Asia............................................................................................................................ 29
B.1 Afghanistan - 2002 - Returns - Shelter construction 30
VAN>=EF=J KJŃE?P-AKLHA@EOLH=?A@2LCN=@AKB?KHHA?PERA?AJPNAO
B.3 India - Gujarat - 2001 - Earthquake - Non-food items and shelters 36
B.4 Indonesia - Aceh - 2004 - Tsunami and earthquake - Shelter or housing? 39
&J@KJAOE=
'KCU=G=NP="=NPDMQ=GA,RANREASKBPDANAOLKJOA
&J@KJAOE=
'KCU=G=NP="=NPDMQ=GA =OD=J@1N=JOEPEKJ=HODAHPAN
&J@KJAOE=
'KCU=G=NP="=NPDMQ=GA"IANCAJ?U=J@PN=JOEPEKJ=HODAHPAN
&JCQODAPE= KJŃE?P-AKLHA@EOLH=?A@ =ODBKNODAHPANDKOPB=IEHEAO
-=GEOP=J"=NPDMQ=GA,RANREASKBPDAA=NPDMQ=GANAOLKJOA
-=GEOP=J"=NPDMQ=GA1N=JOEPEKJ=HODAHPAN?KJOPNQ?PEKJ
-=GEOP=J"=NPDMQ=GA0DAHPANI=PANE=HO@EOPNE>QPEKJ
0NE)=JG= KJŃE?PNAPQNJO KNAODAHPAN
B.13 Sri Lanka - 2004 - Tsunami - Overview of the tsunami response 64
B.14 Sri Lanka - 2004 - Tsunami - Transitional shelter construction 66
Section C - Latin America and Caribbean............................................................................ 69
C.1 Honduras - 1998 - Hurricane Mitch - Transitional shelter 70
C.2 Peru - 2007- Earthquake - Overview of the response 73
C.3 Peru - 2007 - Earthquake - Community mobilisation 74
C.4 Peru - 2007 - Earthquake - Self-build transitional shelters 77
-ANQ"=NPDMQ=GA-NAB=>NE?=PA@PN=JOEPEKJ=HODAHPANO
Section D - Historical Case Studies........................................................................................ 83
D.1 Historical case studies - Overview - Case studies from the Cuny Centre 84
! &J@E= KJŃE?P/ABQCAAO#ENOP?=ILLH=JJEJCCQE@AHEJAO
D.3 Nicaragua- 1973 - Earthquake - Small Camp 89
! =JCH=@AOD KJŃE?P-AKLHA@EOLH=?A@0DAHPANQLCN=@AO
! $Q=PAI=H="=NPDMQ=GA*=PANE=HO@EOPNE>QPEKJ=J@PN=EJEJC
D.6 India - Andhra Pradesh - 1977 - Cyclone - Materials distribution and training 97
! 1D=EH=J@-KHEPE?=H?KJŃE?P/ABQCAA?=IL
D.8 Tonga - 1982 - Cyclone Isaac - Disaster mitigation 102
! 0Q@=J KJŃE?P-H=JJA@?=ILO
iii
INTRODUCTION Introduction
Introduction
The case studies in this book are While the number of people made Selection of case studies
of real shelter projects that have been newly homeless in 2007 was in excess Given the scale of emergency
EILHAIAJPA@ "=?D LNKFA?P EO OLA?Eł? KB IEHHEKJ
= OECJEł?=JP LNKLKNPEKJ shelter need every year, the case
to an individual context and is the of people are not able to return to studies in this book focus on imple-
outcome of local assessments and their place of origin for many years. mented projects rather than small-
monitoring. As a result, the total number of people scale trials or concepts that were
None of the case studies in displaced in the world has remained not implemented on any scale. There
roughly constant at approximately is also a regional bias towards Africa
this book should be directly 15 million refugees2 and a further and Asia, where the post-disaster and
copied. 25 million internally displaced people LKOP?KJŃE?PODAHPANJAA@O=NAH=NCAOP
Ġ&!-O
3.
Because these projects were imple- The case studies were selected
mented in diverse and often challenging according to the following criteria:
&!-AOPEI=PAO>UNACEKJĠ
Latin America and the Caribbean than beyond ‘throwing shelter relief items
in Africa, the Middle East and Asia. Africa 2 off the back of a lorry’ or delivering
Asia 20 shelters as a design or a product.
There are approximately 40 Latin America 1.5
million refugees and internally and Carribean
displaced people in the world - Ġ)
1DEOłCQNAS=ONA=?DA@>U?KI>EJEJC PDAłCQNABNKIPDA"IANCAJ?U"RAJPO!=P=>=OAĠDPPLġSSSAI@=P>A
BKNPDA
JQI>ANKBLAKLHAI=@ADKIAHAOOSEPDPDAłCQNAKBIEHHEKJJAS&!-OMQKPA@EJInternal displacement: Global overview of
trends and developments in 2007Ġ&JPANJ=H!EOLH=?AIAJP*KJEPKNEJC AJPNA
1DEOłCQNAAT?HQ@AOJASNABQCAAO
2. A refugee is a person who has crossed an international border and is unable to return through well-founded fear of
LANOA?QPEKJĠOAA2+% /Handbook for Emergencies
N@A@EPEKJ
BKN=BQHHAN@AłJEPEKJ
&!-O=NA>NK=@HU@AłJA@=OLAKLHASDKD=RA>AAJBKN?A@PKŃAAPDAENDKIAOOQ@@AJHUKNQJATLA?PA@HUEJH=NCAJQI>ANO
=O=NAOQHPKB=NIA@?KJŃE?P
EJPANJ=HOPNEBA
OUOPAI=PE?REKH=PEKJKBDQI=JNECDPOKNJ=PQN=HKNI=JI=@A@EO=OPANO=J@SDK
are within the territory of their country.
1DEO@=P=EOOKQN?A@BNKIPDA"IANCAJ?U"RAJPO!=P=>=OAĠDPPLġSSSAI@=P>A
KJ'QHU
iv
Shelter Projects 2008 INTRODUCTION
The case studies in this book cover Support the people affected Sphere standards and in-
a diversity of projects, from support 1DA łNOP =J@ I=EJ ABBKNP EJ =HH @E?=PKNO ĠJJAT
LNKRE@A ?KIIKJ
for families in collective buildings over responses is made by the people who standards on participation, initial as-
=JAECDPUA=NLANEK@ĠVAN>=EF=J
are themselves affected. Of the case sessment, monitoring and evaluation.
to emergency distributions of plastic studies listed in this book, the more
effective projects all had the close in- Supporting the people affected
sheeting within hours of an earthquake EO PDA łNOP LNEJ?ELHA KQPHEJA@ EJ PDA
Ġ'KCU=G=NP=
!AOLEPAPDALNKFA?PO volvement of the people affected, often
through existing community groups or guidelines of Transitional Settlement and
differences, there are many recurring Reconstruction after Natural Disasters
themes. Some of these themes are specially established committees.
ĠJJAT
discussed in the following pages.
Community
Transitional
Contracted
Household
Permanent
Technical
expertise
Shelter
Direct
Cash
!/ KJCK
(AJU=
/S=J@=
&J@E=Ġ$QF=N=P
v
INTRODUCTION Introduction
Settlement Options Phases of response Which is better: a high
The case studies illustrate support /AOLKJOAOPK@EO=OPANOKN?KJŃE?P=NA level of support for fewer
for disaster-affected people in a variety commonly split into the phases of: people or a lower level of
of settlements. These include host preparedness before the disaster; support for more people?
B=IEHEAO Ġ&JCQODAPE=
?KHHA?PERA emergency response;
?AJPNAO ĠVAN>=EF=J
>KPD NQN=H the recovery phase; and Self-build and contractor models
Ġ-=GEOP=J
=J@QN>=JĠ0KI=HE=
durable solutions. of construction
contexts, and planned and unplanned Many of the case studies include Different projects used different
?=ILOĠ=JCH=@AOD
!
shelter responses aimed at bridging ways of organising the labour required
the gap between emergency shelter to build shelters. The case studies in
&PS=ONAH=PERAHU@EBł?QHP and durable housing solutions. Housing Peru illustrate a mixture from self-build
PKłJ@?=OAOPQ@EAOKB programmes can take many years Ġ
PK OQLLKNPA@ OAHB>QEH@ Ġ
=L-
supporting host families. to complete, especially when imple- proaches, to contractors prefabricat-
mented on a large scale. The project ing shelter components that were then
Finding shelter with friends and EJ /S=J@= Ġ
EHHQOPN=PAO = DKQOEJC ANA?PA@>UDKIAKSJANOĠ
*=JUKB
relationsor by renting are common project that took two years to build the projects in this book provided car-
coping mechanisms for families who 220 houses. The speed of durable penters or masons to support self-build
have lost their house in a disaster. shelter construction can leave a gap, projects. In many projects, families were
%KSARAN
EP S=O @EBł?QHP PK łJ@ ?=OA with families in emergency shelter for provided with some money to either
studies of organisations providing many years. Transitional responses aim support them while building or to allow
support for hosting or rental arrange- to bridge this gap. them to employ others to build.
ments. Logistics and supply
A comparison of the strategies
Transitional settlement: displaced =@KLPA@ EJ ?AD Ġ
=J@ 0NE )=JG= In many projects, logistics and
populations ĠJJAT
Ġ
BKHHKSEJC PDA POQJ=IE EH- OQLLHU EOOQAO D=@ OECJEł?=JP EIL=?PO
lustrates how long housing can take to on both the design of shelters and
In most case studies, the timescale for implementation. The
land ownership was a complete in comparison to transitional
scale of some procurements was huge
@AłJEJCB=?PKNEJSD=P projects. However, as the case studies
ĠAC $QF=N=P Ġ
*=JU LNKFA?PO
types of shelter support note, in implementing the transitional
response there should be a vision of OQ?D =O PDA KJA EJ %KJ@QN=O Ġ
were offered. AILHKUA@OLA?Eł?ODAHPANHKCEOPE?OOP=BB
what is being transitioned to. Often,
Land ownership there is not follow-on funding or land to ensure that shelter projects were
Those without land are often E@AJPEłA@BKNLANI=JAJPDKQOAO implemented. Shelter staff had to work
among the most vulnerable people in closely with these staff members.
society. Approaches to land ownership Scale of programme
The responses illustrate the Assistance methods
varied between the case studies. For The case studies selected include:
AT=ILHA
EJ -ANQ Ġ
KNC=JEO=- challenge of whether to implement
high quality programmes for fewer giving money to host families,
tions built primarily only on the land of upgrading squatted communal blocks,
people who could offer proof of land people or poorer quality responses
to support more people. The case establishing an inter-agency pipeline of
title. Building lighter shelters allowed shelter items and constructing shelters
people to later move them. OPQ@EAOEJ-=GEOP=JĠ
EHHQOPN=PA
this challenge. One project delivered through both unpaid volunteers and
A more active approach to estab- materials to over 2% of the affected contractors.
lishing land for families is illustrated by population without support, while the &PS=O@EBł?QHPPKłJ@OQBł?EAJP@AP=EH
PDA?=OAOPQ@UEJ?AD
&J@KJAOE=Ġ
other project built transitional shelters on projects where families were given
after the tsunami, where the organisa- for 0.2% of the affected population. vouchers that they could redeem with
tion helped to negotiate land with title certain suppliers, although according to
deeds for entire villages. anecdotal evidence this type of project
has been successfully conducted. No
case studies were found of loans being
provided to support families through
By using transportable shelter the emergency or transitional phases
materials, transitional shelter of the response.
solutions can sometimes be found Other sectors
until land rights issues are resolved Many of the more effective projects
Photo IFRC
vi
Shelter Projects 2008 INTRODUCTION
(AU
Duration of natural disaster
!QN=PEKJKB?KJŃE?PKN@EOLH=?AIAJP
Duration of project
Africa
Asia
Latin America and Caribbean
C.3 Peru 2007 24 days Historical case studies
(AJU= 2 months
D.3 Nicaragua 1973 2 months
B.7 Indonesia, Jogyakarta 2006 2 months
C.4 Peru 2007 3 months
B.10 Pakistan 2006 3 months
A.9 Sudan 2004 3 months
B.12 Sri Lanka 2007 3 months
A.8 Somalia 2007 3 months
D.2 West Bengal 1971 4 months
C.1 Honduras 1998 4 months
B.11 Pakistan 2006 4.5 months
A.6 Mozambique 2007 5 months
A.5 Liberia 2007 6 months
C.5 Peru 2007 9 months
B.13 Sri lanka 2005 9 months
B.3 India, Gujarat 2007 10 months
D.6 India 1977 10 months
!/ KJCK 10 months
B.6 Indonesia, Jogyakarta 2006 10 months
D.9 Sudan 1985 1 year
(AJU=
!=@==> 1 year
D.5 Guatemala 1976 13 months
/S=J@= 14 months
/QOOE=
&JCQODAPE= 2 years
B.1 Afghanistan 2002 2 years
D.8 Tonga 1982 2½ years
D.4 Bangladesh 1975 3 years
B.4 Indonesia, Aceh 2004 3½ years
A.2 Eritrea 2004 10 years
B.2 Azerbaijan 1997 13 years
D.7 Thailand 1979 14 years
5
10
Pr
3
6 nth rt
9 nth
1 nth
ye
m t st
m s
m s
ye s
ye
oj
ye
o a
o
o
a
ec
ar
ar
rs
a
s
rs
Duration of project
Illustration of the duration of the case studies
vii
INTRODUCTION Introduction
Shelter design
For most projects, the design of
the shelters themselves was less chal-
lenging than the design and planning of
the shelter project.
Many projects that built shelters left
the design and construction of shelters
2
Shelter size
48m
population, consideration
The illustration below shows the
should be given to the
diversity of shelter-covered areas in
impact on dignity, health these case studies. These vary from
and well-being of the people 9m2Ġ
PKI2 Ġ
1DEOEO=NAOQHP
accommodated...’ of varying needs, permanency, budgets,
2
25m
24m
21m 2
7 people x 3.5m2
2
5m
2
6m 2
20m
20.
2
6 people x 3.5m2
18.
18m
2
16m
5 people x 3.5m2
5m 2
13.
2
12m
4 people x 3.5m2
2
11m
2
10m
Size of shelter
9m 2
3 people x 3.5m2
2 people x 3.5m2
1 person x 3.5m2
I I I I I I I I I I I I I I I I I I I I I I
C
B. Peru
C ndia
A. Hon
A. oz ras
A. om biq
C rit a
C Peru
B. Peru
B. Pak
Pak an
B. AJ an
A. Sri
!=
B. ud ka =>
B. Sri
B. fgh ka
B. ogy ista
ndo arta
A. / sia
ibe KJC
B. AJ
ndo
.3
.1
.5 re
.4
3
11
10 is
12 U=
13 an
1
7
6 ak n
4 U=
6 d
8 am
2 al ue
is
9 la @=
ne
5
ria K
ne
I
A lan
J an
I
I
M u
S
E i
( t
S n
!
L
(
/S si
=J a
a
@=
t
Case study
Chart showing sizes of the shelters in the case studies in comparison with the suggested allocation of 3.5m2 per person.
Note that smaller shelters are often constructed after assessment of local and host population standards, as well as what
is practically possible. Shelter size is not necessarily a good indicator of the quality of a shelter programme.
viii
Africa Shelter Projects 2008 A.1
3
A.1 D.R. Congo - Goma - 2002 - Volcano - Distribution and technical support Africa
HK?=H =NA= S=O @EBł?QHP PK RANEBU
OK to raise money for new furniture.
timber from fast-growing eucalyp- Disaster Risk Reduction (DRR)
PQO S=O OLA?EłA@ =J@ >KQCDP BNKI This shelter programme was im-
a number of different sources to plemented alongside a DRR project to
minimise potential local deforestation. support the Goma Volcano Observa-
tory’s hazard monitoring and a com-
munity-based early warning system.
4
A.2 "NEPNA=KJS=N@O KJŃE?P =ILQLCN=@AO Africa
PEKJO1AJP?=JR=OHEBAOL=JR=NEA@BNKI
BKQN UA=NO PK FQOP OET IKJPDO 1DEO /KKłJCġ )=UANO KB PAJP ?=JR=O
R=NE=PEKJ?=J>AATLH=EJA@>U@EBBANAJP plastic sheeting, grain sacks and straw
ODELIAJPO
SEPD OKIA PAJPO LNKRE@A@ I=PO SANA QOA@ =O NKKłJC I=PANE=HO
from emergency stocks, some ordered For those IDPs who did not possess
JAS =J@ OKIA @KJ=PA@ 0KIA ?=JR=O a tent, plastic sheeting was used as
samples could be torn by hand after =J KQPAN H=UAN SEPD KPDAN =R=EH=>HA
HAOOPD=J=UA=N-H=OPE?ODAAPEJCKBPAJ I=PANE=HO LH=?A@ KRAN PDA PKL PK
ripped in the wind, partly due to poor LNARAJPLH=OPE?ODAAPEJCBNKI@ACN=@EJC
People adapted their tents in many
S=UO łTEJCPA?DJEMQAO=J@=H=?GKBOQEP=>HA EJOPNKJCOQJHECDP
NKLA Walls: External walls were made of
Adaptations by IDPs
Many of the camp residents in the PDAO=IAI=PANE=H=OPDANKKłJC&JOE@A
An assessment made in 2002
$=OD=NG=NACEKJD=@LNAREKQOHUHERA@ the shelters, a ‘wall’ around 20cm high
NARA=HA@ PD=P I=JU >AJAł?E=NEAO D=@
EJDKQOAO?=HHA@DQ@JKO1DAOADKQOAO was built up around the edge using
I=@A OECJEł?=JP IK@Eł?=PEKJO PK
D=@DA=RUNKKBO=J@PDE?GS=HHO
SDE?D @KJGAU@QJCKNIQ@1DAS=HHOSANA
their shelters for two main reasons:
kept interiors cool during the hot day used as benches or beds and also
AIANCAJ?UODAHPANEPAIOLNKRE@A@PKK
=J@S=NI@QNEJCPDAJECDP LNKRE@A@OKIALNKPA?PEKJ=C=EJOPN=EJ
HEPPHA?KRANA@OL=?A=J@D=@PKKODKNP
=HEBAOL=J The roof of a hudno uses a lot of Partitions: Partitioned interior space
SKK@ PDA NKKB BN=IA EO ?KRANA@ >U S=O ?NA=PA@ >U D=JCEJC I=PANE=H KRAN
a) Space
IKNASKK@SEPD=H=UANKBIQ@KJPKL PEI>AN BN=IAO 0KIA B=IEHEAO =HOK
1DA OP=J@=N@ NAHEAB PAJP LNKRE@AO
The walls are generally made of stone, created separate areas for storing
only 16m2 KB ?KRANA@ OL=?A ĠAJKQCD
KBPAJQOEJCIQ@=OIKNP=N OPN=SBKN=JEI=HBAA@
BKN=B=IEHUKBBKQNLAKLHASEPDI2
LANLANOKJ
=J@I=JUH=NCAB=IEHEAOBAHP
PD=P PDAU SANA HEREJC EJ KRAN?NKS@A@
?KJ@EPEKJOUIK@EBUEJCPDAENODAHPANO
some IDPs managed to increase their
Photo: Joseph Ashmore
7
Africa Shelter Projects 2008 A.3
=IKJC=CAJ?EAOSKNGEJCEJ@EBBANAJPOA?PKNO
9
A.3 Kenya - 2007- Flooding - Shelter and disaster mitigation Africa
10
A.4 Kenya - 2007-2008 - Election violence - Transitional shelter kits Africa
Strengths and weaknesses (continued)
promoted sustainable return. roofs and doors had been looted.
8 Occupancy was not as high as hoped for, with some 8 The kit included spare sheets and plastic sheeting for
IDPs not ready to move back. the construction of latrines. These materials were often
8 +KP=HHKBPDAI=PANE=HO=NA=R=EH=>HAHK?=HHUEJOQBł?EAJP used to extend the roof instead.
quantities. Sourcing of materials needs to be reconsidered 8 0KIA >AJAł?E=NEAO OP=PA@ PD=P PDAU SKQH@ D=RA
before the project can be upscaled. preferred to have been given the cash value of the plastic
8 Only those whose houses had been completely so that they could buy local materials themselves to build
destroyed received the kit. Further attention needs to be the walls (cash grants are being considered for the post-
given to those whose houses are partly damaged, as many pilot phase).
12
Africa Shelter Projects 2008 A.4
location in Mtaragon to sensitize bene- ground at a depth of around 60cm. The Materials Quantity
ł?E=NEAO=OPKSD=PS=O>AEJCLNKRE@A@ poles supported a timber ring beam,
Walls
and to get feedback on the design. which in turn supported the timber
rafters onto which an iron sheet was Cedar posts 14 units
Local craftsmen and unskilled 9', 4" diameter
nailed.
labourers were recruited into ten Walling-polythene sheeting- 45 m2
teams and trained. Although not Walls were clad in plastic sheeting 1000g
planned, the teams were a 50-50 mix =J@ŃKKNOSANA?KILNAOOA@A=NPD1DA Cypres timber 2x3", 20 m
BNKIPDAAPDJE?CNKQLPD=PD=@ŃA@=J@ @KKNOSANAŃ=LOEJPDALH=OPE?ODAAPEJC 6 x 2m, 3 x 2m
the ethnic group that they felt threat- and weighted with timber battens. Ordinary nails 4" 2 kg
ened by. This side effect of the project The design was based on the ver- Roof
had a positive impact on peacebuild- nacular housing typically lived in by Cypess timber 2x3", 40 m
ing. The donor organisation directly IDPs prior to their displacement. 2 x 10m, 3 x 3m, 1 x 8m
procured the materials within Kenya This enabled IDPs to upgrade their Cypes timber 2x2" 41 m
and delivered them to the implement- shelters incrementally using materials 6.5 x 6m
ing agency’s warehouse in Nakuru. and methods that they were already CGI ridge covers-30g -1.5 m 4 units
The implementing agency then familiar with. The walls could be clad CGI sheets-30g 20 units
distributed the materials at three with timber, adobe or even brick and 2 x 0.9m
HK?=PEKJOAJAł?E=NEAO?KHHA?PA@PDAI cement. Cement could be used to Ordinary nails, 2kg 4", 2kg 4.5 kg
and took them to their plots up to EJ?NA=OAPDA@QN=>EHEPUKBPDAŃKKN 3", ½kg 2"
three kilometres away, using their own The use of plastic sheeting allowed /KKłJCJ=EHO 4 kg
transportation (either by hand, by shelters to be built and occupied Iron hoop 1 kg
donkey, or by tractor and trailer). RANU MQE?GHU
PDKQCD OKIA >AJAł?E=N- Tools
The kits also included the basic ies replaced the plastic sheeting walls
Stanely claw hammer 1 unit
tools necessary to build the shelter. immediately with adobe or reclaimed
building parts, such as doors or timber. Stanley woodcutting saw 1 unit
ĺ&IKRAN=J@QJ=>HA The plastic sheeting could then be sold Panga knife 1 unit
PKCAPPDAI=PANE=HOPK or used for temporary house exten- Hoe and handle 1 unit
>QEH@KJIUKSJ!AOLEPA sions, and provided waterproof storage Manaila thread 30m (roll) 1 unit
SD=PD=LLAJA@
&D=RA for seeds and fertilisers.
Measuring tape 1 unit
PK?KJPEJQAOP=UEJCDANA The use of regular frame and
AEJCIUH=J@&?=JJKP roof sections made the construction
NQJ=S=U&BARANU>K@U modular – it could be easily extended
can be assisted in the or adapted. The choice of materials ‘The prototypes built by
way I was, that would meant that there was no part of the local craftsmen in each
>ACNA=P-H=OPE?ODAAPEJC >QEH@EJC PD=P ?KQH@ JKP >A łTA@ KN project location enabled
EO,(
>QP&SKQH@D=RA replaced locally. structures to be tested and
LNABANNA@PEI>AN
=OEPO important feedback from
OPNKJCAN=J@?=JP>A *KOP >AJAł?E=NEAO ANA?PA@ PDAEN
>QEH@ANO=J@>AJAł?E=NEAO
>HKSJ=S=U- AJAł?E=NU shelters on exactly the same site as
to be incorporated into
their previous homes had been, so
Guidance was given by the local little site clearance or ground levelling PDAłJ=H@AOECJ–
craftsmen on how to put the shelter was required. Engineering coordinator
PKCAPDAN 1DA >AJAł?E=NEAO LNKRE@A@
Logistics and materials
the labour themselves and the houses
Materials were sourced in Kenya,
were normally completed within one
and chosen for their familiarity, durabil-
or two days.
ity and low cost. Timber was supplied
,RANKBPDA>AJAł?E=NEAOIAP by private forestries who were only
PDA RQHJAN=>EHEPU ?NEPANE= =J@ MQ=HEłA@ considered if they had government-
to have their houses built by the con- approved replanting projects in place.
struction teams. Plastic sheeting was made from recycled
Photo: Dyfed Aubrey
13
Africa Shelter Projects 2008 A.5
Strengths and weaknesses (continued)
- The project ran alongside water and sanitation and could be more clearly seen.
education programs, which was necessary to ensure that 8 Maintenance issues could have been considered further,
people had access to the services they needed in order to SEPDI=JU>AJAł?E=NEAO=OGEJCBKN?AIAJPBKNŃKKNEJC=J@
resettle. walls.
- 1DA?KJOPNQ?PEKJKBODAHPANOBKNRQHJAN=>HA>AJAł?E=NEAO 8 Technical supervision could have been more intensive
appeared to inspire other returnees to begin rebuilding from the beginning, as some construction work had to be
spontaneously, as it created a positive atmosphere of NA?PEłA@
recovery. 8 Donor-driven partnerships with community-based
- The project was better suited to a rural context than an organisations from previous projects had to be dropped
urban one, as community mobilisation was much easier in due to corruption and a lack of community involvement.
OI=HHANREHH=CAOSDANAPDA>AJAłPOPKPDASDKHA?KIIQJEPU
-DKPKġ'=GA7=NEJO
-DKPKġ'=GA7=NEJO
KILHAPA@DKQOAOBKNNAPQNJAAO
15
A.5 Liberia- 2007- IDPs, refugees - Self-build shelters Africa
-DKPKġ'=GA7=NEJO
workers. The sum was large enough to be
Implementation an incentive to get people involved, but
,J?A >AJAł?E=NEAO D=@ >AAJ OI=HHAJKQCDPKLNARAJP?KJŃE?PKRAN
selected and cooperation of the SDK >AJAłPA@ 1DA 20 BKN PDA
community was agreed upon through a materials was only paid once construc-
series of open meetings, a skilled local tion up to the roof was completed. Completed house
carpenter was chosen to lead the con- -=UIAJP KB PDA łJ=H 20 S=O Materials Quantity
struction of between one and three made upon occupancy rather than
houses. The carpenter would also act
3" nails 65 (0.3kg)
when the structure was completed.
as a community mobiliser to organise 4" nails 28 (0.3kg)
This was a lesson learned from
people to collect materials and provide previous projects, where payment had Hammer
labour for construction. been made upon structural comple- 7EJ?NKKłJCODAAPO 2 bundles
Progress was monitored by one of tion. The NGO was then unable to (0.66m x 2.4m)
łRA ODAHPAN OQLANREOKNO
=HH KB SDKI prevent occupancy of the structures Zinc nails L=?GAPO
had construction knowledge and skills. >UJKJ>AJAł?E=NEAO=BPANS=N@O
Door and frame 2
The supervisors were managed by Shelter supervisors marked out the
a shelter coordinator and a project Window and frame 2
agreed 25m2. A standard design was
director. proposed for a two-room construc- Hinges 4 pairs
Supervisors were expected to visit tion with a veranda. However, ben- Nails ĠGC
16
A.6 Mozambique- 2007- Cyclone - Shelter material packages and training Africa
Strengths and weaknesses (continued)
BQJ@EJCIA=JPPD=POKIA>AJAł?E=NEAO@E@JKPD=RAOQLLKNP required repetition of the messages.
for basic shelter needs for at least three weeks. 8 Local suppliers were sometimes unable to meet
8 Technical advice was not always implemented by the deadlines. This resulted in the project requiring an
>AJAł?E=NEAOHPDKQCD>AJAł?E=NEAO=PPAJ@A@PDAPN=EJEJC
extension. Delays were partly due to legal requirements
the construction may have been carried out by someone for supplier registration and payment of taxes by suppliers.
else or they had not been convinced by the advice. This
18
Africa Shelter Projects 2008 A.6
between families)
Metal wire (2kg)
Roof trusses (3)
Plastic sheeting
Wall poles (10)
(1 sheet)
19
A.7 Rwanda - 2008 - Returns - Materials distribution and technical guidance Africa
Tanzania
by June 2007.
Rwanda
Project target population:
469 households
Occupancy rate on handover:
All 220 shelters completed by August 2008 were occupied.
Shelter size
48 m2 (6m x 8m)
Summary
This project provided support to people of Rwandan origin expelled from Tanzania by providing
materials for house building, masons and providing shared services at the site of return. Communities
were mobilised by forming beneficiary associations in consultation with the local government. The
role of the associations was to collectivise the tasks required for house building.
Project timeline
6 6 6 06 h hs hs hs hs
20
0
20
0 00 20 ont t t nt ont
94 96 2 v m on on o
m m
19 19 ar ay y
Jul No 1 m m
M M 6 8 12 14
I I I I I I I I I I
re n to
or
47 ees om
re nda
Fir
Rw
Jo ania ed
50 anza
Ta for
to
te
Re
Se ph
De nts ex
Th
Se
int n
sid b
am
fug fr
igi
5,0 re Ta
co as
,00 se an nt
co
0, ni
nz m
st
st an er
tu
ird
T
cla of pel
a
an Rw
rn
nd e b
nd
ph
00 tur nza
0 be d al
da an
ra R led
sb
re gi
as
tio wa
n
ph eg
ph
Rw ne nia
tu ns
ee
ge dan
eg
e
as ins
as
n: nd
rn
an d to
no s fl
in
ee
eb
nd
all an
ee
da
cid ee
nd
eg
ille
s
n
e.
ins
s
ga
l
20
Africa Shelter Projects 2008 A.7
21
A.7 Rwanda - 2008 - Returns - Materials distribution and technical guidance Africa
those of different physical abilities, as The associations were supported Logistics and materials
well as able people. >U=CAJ?UłAH@SKNGANOSDK@A=HPSEPD Some materials were transported
questions and resolved problems. directly to the site and distributed
Each association produced the
to each plot. Other materials of high
necessary materials to build houses Technical solution
value or requiring special storage were
for all the families in its group. They After approval of the house design
stocked in a nearby warehouse and
produced the clay bricks needed by the Ministry of Infrastructure, the
distributed on demand.
(1,800 for a house; 200 for a latrine), building of houses was monitored by
dug latrines, de-barked timbers to be the agency, with inspections made by AJAł?E=NEAO SANA EJRKHRA@ EJ PDA
used for construction and cleared and local authority representatives. quality control of materials and were
levelled sites. Associations were regis- responsible for ensuring the security of
The design is based on local building
tered with the local authority and all the warehouse.
traditions but with some upgrading,
work was unremunerated.
such as cement plastering. Materials Quantity
‘Nobody is vulnerable! Each house provides 48m of 2 I) Foundation
You can always give covered living space (6m x 8m) and has Twine for setting out 2 balls
something to your com- four rooms and one corridor with two Cement 2.5 sacks
munity!’ -Slogan of the mobi- doors. A foundation of hardcore, sand
Plastic sheeting for roof 0.2 roll
lisation teams in the returnee and cement is laid for each house and
communities the exterior of the mud-brick walls is Hardcore 10 m3
coated in ‘rough-cast’ – a mixture of Sand 5m3
Through the collectivisation of cement and other materials to provide II) Walls
tasks it was possible to build houses protection against the weather. Brick mould 1 piece
for all members of the community.
This would not have been possible if The roof is made of galvanised Plastic sheeting for water 1 piece
families had worked alone. Materials NKKłJCODAAPEJC=J@=@@EPEKJ=HNKKłJC Timber planks 5.5 pieces
that could not be produced were sheets were used for the guttering. Breeze blocks 8 pieces
provided: cement, foundation stones, Each house is equipped with a Poles for scaffolding 4 pieces
sand, construction wood, doors and rainwater catchment system, storing Mud bricks (20 x20x35 cm) 1800
windows, roof sheeting, as well as tools up to 1.2 cubic metres of water. The
and other non-food items. Materials III) Roof
system follows the local design and
were provided at the appropriate stage Poles for truss 26 pieces
uses cement layers cast together over
of construction. a reed mould. Local technicians were Nails 15cm 3 kg
Before house building began, the hired to produce the mould and others Nails 12cm 3 kg
agency contracted skilled masons to make the cement layers. Nails 10cm 3 kg
to build latrines, each shared by two To reduce the fuelwood used for Nails 6cm 2 kg
households. Once the latrines were cooking, the agency has developed a /KKłJCJ=EHO 3 kg
completed and the necessary con- stove design in collaboration with the /KKłJCODAAPO 29 pieces
struction materials were produced, Kigali Institute for Science and Technol-
house building could begin. Strip iron - for binding 18 pieces /
ogy. The stove can be built out of local joints 1.5m each
Although no other shelter materials and has greatly improved fuel IV) Exterior
materials were provided for the tran- ABł?EAJ?U
LNKPA?PEJCPDA?KIIQJEPUO Cement 3 sacs
sitional period between arrival in the natural resources from deforestation.
Doors 2 pieces
new villages and construction of new Planned shared services
houses, the agency supported initial Windows 4 pieces
In its third phase, the project is
livelihood recovery with a distribution V) Other
now concentrating on the following
of seeds and food rations. shared services: /KKłJCODAAPOBKNCQPPAN 2 pieces
The construction of each house IQHPELQNLKOA ?KIIQJEPU
was overseen by a skilled mason hired centre to be shared with surround-
by the agency and paid a total of US$ ing villages. It is intended be a
EJłRAEJOP=HIAJPOBKNA=?DDKQOA semi-open hangar accommodating up
Each household appointed one person to 300 people with storage rooms
from the household to be an assistant for materials and products of local
to the mason, who monitored the workshops.
attendance and contribution of the
assistant. In return for providing their A day centre for children whose
labour, the ‘assistants’ learned basic L=NAJPOSKNGA@EJPDAłAH@O
construction skills as well as improving KNADKHAO =NA =HOK LH=JJA@ PK
their physical living conditions. improve access to clean water.
22
A.8 0KI=HE= EREH?KJŃE?P/AOAPPHAIAJP Africa
24
Africa Shelter Projects 2008 A.8
Photo: J. Ashmore
*=JUKBPDAOEPAOEJEPE=HHUKBBANA@SANANAFA?PA@>A?=QOAPDAUSANAB=NBNKIKOO=OK=J@LKOOE>HAHERAHEDKK@O1DAłRAOAHA?PA@OEPAOSANA
donated following requests for land made during Ramadan.
occupied their site, preferring instead KJPN=?PKNO SANA QOA@ PK PN=?A The cost for the second phase
PK NAJP KQP PDA JAS =??KIIK@=PEKJ NK=@O BKN PDA JAS OAPPHAIAJP =J@ S=O 20 LAN DKQOEJC QJEP 1DEO
KN HA=RA PDA DKQOA AILPU
SDEHA PDA ?KJJA?P EP PK PDA IQJE?EL=H S=PAN excluded agency staff costs and food-
occupancy rate on project completion OQLLHU1DEO=HOK>AJAłPA@PDKOAHEREJC BKNSKNG ?KJPNE>QPEKJO >QP EJ?HQ@A@
BNKI&!-B=IEHEAOS=O =HKJC PDA NKQPA KB PDA JAS S=PAN all other logistics, administrative and
LELAO J KJCKEJC OKH=NLKSANA@ I=PANE=H?KOPO
The selection process, managed
OPNAAPHECDPEJCLNKFA?PS=O=HOKOP=NPA@
by the multi-representative Bossaso Logistics and materials
PKS=N@OPDAAJ@KBPDALNKFA?P
selection committee, began in *=PANE=HO SANA LNK?QNA@ HK?=HHU
0ALPAI>AN &!- >AJAł?E=N- LHKPS=OLNKRE@A@SEPDEJPDAOAP- SEPD?KJPN=?PKNONAOLKJOE>HABKNPDAEN
EAO SANA OAHA?PA@ >U LNEH
>QP tlement for each family to construct KSJLNK?QNAIAJP
=CNAAIAJPKJQN>=JLKKN>AJAł?E=NEAO PDAEN KSJ DKQOA
SEPD OQLLKNP BNKI
Bill of quantities
S=OJKPNA=?DA@QJPEH+KRAI>AN PDA?KJOKNPEQI
1DA BKHHKSEJC P=>HA ODKSO PDA >EHH
Before selecting individual families, 1SK@EBBANAJP=CAJ?EAOEILHAIAJP- KBMQ=JPEPEAOBKN-D=OAKBPDALNKFA?P
PDA &!- OAPPHAIAJPO SEPD PDA SKNOP A@PDA?KJOPNQ?PEKJKBPDADKQOEJC =RAN=CA@BKN=OEJCHAQJEPĠOKIAQJEPO
ODAHPAN ?KJ@EPEKJO SANA E@AJPEłA@ QJEPOEJPSKLD=OAOQOEJC?KJPN=?PKNO SANA ?KNJAN QJEPO N=PDAN PD=J BNAA-
0AHA?PEKJ?KIIEPPAAOSANABKNIA@EJ 1DA łNOP LD=OA PKKG łRA IKJPDO =J@ OP=J@EJC
A=?D KB PDAOA OAPPHAIAJPO =J@ SANA involved the construction of foun-
P=OGA@SEPDLQPPEJCBKNS=N@EJ@ERE@Q=H @=PEKJO
>KQJ@=NU S=HHO
O=JEP=PEKJ Materials Quantity
DKQOADKH@O SDK D=@ HERA@ EJ KOO=OK ĠODKSAN
PKEHAPO=J@OALPE?LEPO
=J@= Hollow concrete blocks 281 pieces
BKNIKNAPD=JOETUA=NO
SEPDJKłTA@ ITIŃKKNOH=>-D=OA?KOP20 (150 mm x 390 mm x 180
mm)
=OOAPO=J@=PHA=OPPDNAA?DEH@NAJ*KNA
LANDKQOEJCQJEP
@AP=EHA@ ĺRQHJAN=>EHEPU ?NEPANE= SANA Cement for mortar and 5 bags
The second phase began after concrete ring beam
rejected due to the complexity of
>AJAł?E=NU OAHA?PEKJ S=O ?KILHAPA Sand for mortar and concrete 1 tonne
0KI=HEB=IEHUOPNQ?PQNA=J@PDAH=?GKB ring beam
=J@ PKKG PDNAA IKJPDO
łJEODEJC EJ
E@AJPEł?=PEKJ@K?QIAJPO
!A?AI>AN 1DA >AJAł?E=NU Aggregate / ballast for ring 0 tonnes
0AHA?PEKJ HEOPO SANA I=@A LQ>HE? families moved onto their plot, living in beam concrete
PK =HHKS PEIA BKN ?KILH=EJPO PK >A =PAILKN=NUPAJPHEGAODAHPANLNKRE@A@ Y8 bars (12m long) for ring 4 pieces
EJRAOPEC=PA@ ĠKJA KB PDA OAPPHAIAJPO >U=JKPDAN=CAJ?UQJPEHPDASKNGS=O beam
produced a list that excluded an ethnic ?KILHAPA@ 1DA PAILKN=NU ODAHPANO R6 rings (6m long) for ring 2 pieces
IEJKNEPU
1DA łJ=H OAHA?PEKJ KB PDA SANAH=PANQOA@=O=@@EPEKJ=HNKKIOKN beam
&!- B=IEHEAO S=O I=@A PDNKQCD BKNOPKN=CA 6x1 white wood for form 12 metres
work
a lottery broadcast on local TV and
#KK@ BKN SKNG BKN = I=TEIQI KB 28-gauge galvanised 14 pieces
N=@EK
SDE?DS=O@AAIA@=B=ENIAPDK@
@=UO S=O LNKRE@A@ PK >AJAł?E=N- corrugated iron sheets
>U>AJAł?E=NEAO
ies for the construction period, along Structural grade 150 x 50 18 m
SEPD20PKDENA=I=OKJĠB=IEHEAO (6' x 2') timber roof rafters
‘Compared to the shelter OKIAPEIAO @E@ I=OKJNU SKNG PDAI- Structural Grade 75 x 50 27 m
I had before, I can now OAHRAO
SEPDPA?DJE?=HOQLLKNP
=J@GALP (3' x 2') timber roof purlins
say that my life has im- PDAIKJAU
1DAI=EJ=CAJ?ULNKRE@A@ /KKłJCJ=EHO 1 kg
proved 100 percent. The technical support in the form of cash
resettlement programme Ordinary wire nails 1 kg
BKNOGEHHA@H=>KQN=J@AILHKUIAJPKB=
was completely transpar- BKNAI=JBKNOQLANREOEKJ
Steel single doors
(0.8m x 2m)
1 set
ent and well done’.
Giving the families the oppor- Double leaf-steel window 1 set
PQJEPU PK OAHA?P PDAEN KSJ I=OKJ (1m x 1m )
Technical solutions ĠN=PDAN PD=J BKHHKSEJC PDA SEODAO KB White wash 4 bags
This project provided the infra- PDA HK?=H =QPDKNEPEAO SDK S=JPA@ PDA Brushes for whitewashing 2
structure for a serviced community SDKHA ?KJOPNQ?PEKJ LNK?AOO ?KJPN=?P- Bamboo/rope for ceiling mats As
OAPPHAIAJP
SAHH EJPACN=PA@ SEPD PDA A@ KQP
IA=JP PD=P PDAU D=@ CNA=PAN required
host population, and support to IDPs MQ=HEPU ?KJPNKH KRAN PDA SKNG @KJA
BKNPDA>QEH@EJCKBEJ@ERE@Q=H@SAHHEJCO =J@ =HHKSA@ PDA =CAJ?U PK =RKE@ PDA
SEPDEJPDAOAPPHAIAJP LNK>HAIOKB=PAJ@ANEJCLNK?AOO
25
Africa 0DAHPAN-NKFA?PO A.9
=L=NPE=HL=?G=CASANA=OOQIA@PK>A >AJAł?E=NEAOSKQH@QOAEPAIOPK?NA=PA
=>HAPKOQLLHUIEOOEJCI=PANE=HOPDAI- ODAHPANOIA=JPPD=POKIA>AJAł?E=NEAO
OAHRAO
SDE?D I=U JKP D=RA =HS=UO SKQH@D=RAD=@PKOKQN?A?KJOPNQ?PEKJ
>AAJPDA?=OA I=PANE=HOPDAIOAHRAO1DAOAI=UD=RA
>AAJ ATLAJOERA
KN
EJ PDA ?KHHA?PEKJ
U QCQOP
KB PDA >AJAł?E=N-
KBLKHAO
D=RAAJP=EHA@PDAO=IANEOGO
Unloading a lorry of relief items
EAOSANANA=?DA@SEPDĺłNOPPEAN+#&O
PKLANOKJ=HOA?QNEPUPD=PI=JUSKIAJ
?KILNEOEJC LH=OPE? ODAAPEJC
>H=JGAPO
B=?A@SDAJ?KHHA?PEJCSKK@BKNBQAH
27
A.9 !=NBQNĠKJCKEJC
KJŃE?P*=PANE=HO@EOPNE>QPEKJ Africa
,PDANJKJBKK@EPAIOSANALQN?D=OA@
EJ(D=NPKQIKN+U=H=
Shelter items in the NFI
basket
+KPAġ,PDANEPAIO
OQ?D=OO=JEP=-
PEKJ EPAIO
SANA =HOK OQLLHEA@ EJ PDA
Emergency shelters JKJBKK@ EPAI >=OGAP
>QP =NA JKP
EILHAIAJP=PEKJ KB PDA LELAHEJA 1DA
LNK?AOO S=O OQLLKNPA@ >U OARAN=H HEOPA@DANA
@KJKNO =J@ PDA łJ=H =HHK?=PEKJ KB NA-
‘Coordination with all of Materials Quantity
OLKJOE>EHEPUS=OQJ@ANP=GAJ>UPDA2+
the agencies was key. We H=JGAPO 2
KQJPNU1A=I1DAKNC=JEO=PEKJKBPDA
held weekly meetings in
(D=NPKQI=J@PDAłAH@ -H=OPE?ODAAP
LELAHEJAS=OOLHEPEJPKPSKI=EJL=NPOġ ĠITI
=OQLLHUL=NP=J@=LNKCN=IIAL=NP
and set up information-
sharing systems such as a /KLA I
#KN PDA OQLLHU L=NP KB PDA website. No one had an -KHAO LH=JJA@
>QP
LNKCN=IIA
KJA 2+ =CAJ?U S=O excuse for not knowing JKP@EOPNE>QPA@
JKIEJ=PA@ BKN LNK?QNAIAJP
SDE?D what was going on!’ 0HAALEJCI=P 2
SKQH@>A@EOPNE>QPA@=OB=N=O=?AJPN=H- - Coordinator
EOA@ S=NADKQOA ĠPDKQCD PDEO LNK?AOO
28
Asia Shelter Projects 2008 B
Section B
Asia
B.8
&JCQODAPE=
KJŃE?P
B.1
Afghanistan
B.2 KJŃE?PNAPQNJO
Azerbaijan
KJŃE?P
-=GEOP=J
"=NPDMQ=GA
B.3
India
"=NPDMQ=GA
B.10
0NEH=JG=
KJŃE?PNAPQNJO
0NEH=JG= B.4
1OQJ=IE Indonesia, Aceh
"=NPDMQ=GA=J@POQJ=IE
&J@KJAOE=
'KCU=G=NP=
"=NPDMQ=GA
29
Asia Shelter Projects 2008 B.1
31
B.1 Afghanistan - 2002 - Returns - Shelter construction Asia
Photo:Øyvind Nordlie
Implementation
The shelter programme is
based on a four-stage process:
Stage I: Planning - Allocation
of shelter per region/province/
@EOPNE?P
>Q@CAPEJC
E@AJPEł?=PEKJ KB
implementing partners, establishment
of materials supply contracts. Completed shelters
Photo:Øyvind Nordlie
32
B.2 VAN>=EF=J KJŃE?P-AKLHA@EOLH=?A@2LCN=@AKB?KHHA?PERA?AJPNAO Asia
buildings and schools was adopted. the greatest problem in the buildings.
Other common problems included
Criteria for the selection of
shortage of water, leaking roofs and
public buildings for inclusion in the
@=ILJAOOO=NAOQHP
LH=OPANEJC
ŃKKNO
programme were adjusted throughout
and ceilings in toilets and bathrooms
the project period. However, the main
were damaged in most buildings.
criteria remained unchanged: at least
70% of building inhabitants had to be A typical repair of a public building
Bathrooms before and after upgrade IDPs; other organisations could not involved:
have previously worked in the building;
Context rehabilitation of the shared areas
and the building had to be in exception-
1DA ?KJŃE?P EJ +=CKNJK(=N=>=GD - toilets, bathrooms, washing rooms,
ally bad condition.
between Azerbaijan and Armenia in the kitchens and corridors;
early 1990s led to over 500,000 people &J EPO łNOP UA=NO Ġ
PDA infrastructure repairs - electricity,
becoming internally displaced and a project prioritised hostels located sewerage, water and sewerage pipes;
further 200,000 becoming refugees. next to each other and that shared a repair of roofs;
Around half of the internally displaced common yard. Such locations made installation of new water heaters,
people moved to urban areas, most of repair works easier and reduced costs. sinks, stoves, faucets, showers, light
them to the capital, Baku. Letters from local or central authori- bulbs, circuit breakers, switchboards,
ties, as well as applications from the windows and doors;
In Baku, many people moved into residents, were also considered in the installation of electricity
dilapidated, overpopulated public selection process. transformers (this was not costly but
buildings, most of which were origi- served a large number of IDPs).
nally student residence halls and dor- The willingness of the building
mitories. The buildings were designed residents to work with the NGO
with rooms intended for one person, S=O PDA @A?EOERA B=?PKN EJ PDA łJ=H The most durable output of the
JKP BKN B=IEHEAO KB łRA KN IKNA 1DA selection. Inhabitants had to be willing project was the provision of electric-
kitchens and bathrooms were shared. In to volunteer to help with repairs, and ity systems (including transformers and
some cases the buildings were without to clean corridors and shared areas. In switchboards) and new roofs.
water supply or sanitation. This was in some cases, works had to be suspended
The project was not always success-
PDA ?KJPATP KB = OECJEł?=JP CNKSPD EJ QJPEHPDA?KIIQJEPU=CNAA@PKBQHłHPDA
ful in solving problems with the water
wealth in Baku, in part due to the oil NGO’s conditions.
supply. A durable solution would have
industry. +KP ARANUKJA >AJAłPA@ AMQ=HHU required dealing with the malfunctions
The temporary shelter solutions from the project. Although similar outside the building, which was beyond
BKQJ@ BKHHKSEJC PDA ?KJŃE?P H=OPA@ works were performed in most of the the scope of the project. Cooking
longer than was expected. Many of buildings, several of them were only stoves and taps in the rehabilitated
PDKOA @EOLH=?A@ BKHHKSEJC PDA ?KJŃE?P partially rehabilitated (only roof or buildings had short lifespans because
electricity) for a variety of reasons. many people used them.
Photo: Predes
Azerbaijan
buy-in and participation in the project.
This was believed to be instrumental in lock their rooms and keep them as a
creating a feeling of ownership and in storage space.
Rhyner
the further maintenance and upkeep of Obviously, the families who could
Kurt NRC
the rehabilitated buildings. afford to leave the public buildings
were those who managed to establish Photo:
some livelihoods and were relatively
Photo
35
Asia Shelter Projects 2008 B.3
After the earthquake to have introduced some inclusion (as ‘What the international
The earthquake struck the State of well as exclusion) errors.
NGO saw as normal
Gujarat on 26 January 2001, and par-
Technical solutions professional procedures, the
ticularly affected the district of Kutch
A low-cost shelter design was local organisation saw as
and its neighbouring areas.
developed using low 1m walls and a
meaningless bureaucracy. The
News of the earthquake spread bamboo-framed and grass-thatched
rapidly through the international media. roof. With time it was recognised international NGO had bent
Local communities, the Central and that there was a need to preserve the its own rules in favour of the
State governments, the defense forces, CN=OOBKN=JEI=HBK@@AN
OKPDANKKłJC local NGO to such an extent
donors, and international and national material was replaced with locally PD=P KQN łJ=J?E=H ?KJOQHP=JP
NGOs all responded to the emergency. produced Mangalore clay tiles.
became highly concerned…
Within one week, a network The dimensions of the shelters But ultimately there is no
of 22 local organisations, including de- built were approximately 4m x 2½m. doubt that the international
velopmentally minded architects, had Although this provided a covered area
formed a partnership agreement with of only 10m2 for a family, these dimen- NGO's real achievement in
an international organisation. Members sions were carefully selected to focus the Gujarat response was its
of this local network had been working on earthquake safety. A larger span link with local NGOs and the
on low-cost construction technolo- SKQH@D=RANAMQENA@OECJEł?=JPHUIKNA temporary housing project’.
gies prior to the earthquake and were materials to ensure the same level of – Evaluation by the Disasters
able to act as an effective coordination safety.
mechanism. During the earthquake
Emergency Committee (the donor)
The distribution of construction
their focus was on:
materials was phased to ensure that
interim, transitional shelter buildings were built safely:
(it would not be possible to build
First, a shallow foundation was Working with partners
permanent shelter to meet the needs
built. When this was complete the The way in which the international
of all affected families within a year and
cement for the walls was distributed. NGO was able to work in partner-
PAJPO SANA JKP @QN=>HA AJKQCD PK łHH
Walls then had to be built. When ship with a strong local network of
the gap);
PDAOASANA?KILHAPA
S=HHO=J@NKKłJC NGOs was one of the strengths of this
examples of low-cost and safe
materials were distributed. project. However, the relationship at
public buildings.
After the initial shelters were built, times became strained, in part due to
&J PDA łNOP SAAGO KB PDA NAOLKJOA
EOOQAOSANABKQJ@SEPDPDANKKłJC=J@ the different working methods and the
the focus was on the distribution of
an upgrade programme was required. speed at which the working relation-
non-food items.
This involved distributing four pieces ship was set up.
0AHA?PEKJKB>AJAł?E=NEAO of bamboo (1½m long ) to brace the
The initial assessment was rapid and roof. The international NGO had
@AłJA@OKIA?NQ?E=HJAA@O%KSARAN
internal rules and donor requirements
The distributions of materials were for paperwork and processes for ac-
it relied on individual competence and accompanied by the training of local
was not standardised. countability. The local organisations
masons and carpenters, to mobilise the saw much of this as overly bureaucratic.
The criteria and procedures for communities and raise their awareness These organisational differences were
PDA OAHA?PEKJ KB >AJAł?E=NEAO BKN NAHEAB of seismic-resistant construction. A sig- compounded by high staff turnover.
distribution in the communities were JEł?=JP=IKQJPKBSKNGS=ONAMQENA@
JKP =HS=UO ?HA=NHU @AłJA@ 1DAU SANA to ensure that people correctly braced Many of the procedures, logistical
commonly left to the subjective inter- their shelters and to explain that once =J@ łJ=J?E=H ?KJPNKHO SANA HKKOAJA@
pretation of the village-level workers braced, the buildings would be stronger However, the shelter programme
and the communities. Although this and safer. was very effective according to both
=HHKSA@=@ACNAAKBŃATE>EHEPU
EPEOHEGAHU internal and external evaluations.
37
B.3 India - Gujarat - 2001 - Earthquake - Non-food items and shelters Asia
38
B.4 Indonesia - Aceh - 2004 - Tsunami and earthquake - Shelter or housing Asia
Before the tsunami Throughout the response and developed in each district.
The Indonesian state of Aceh is a reconstruction, government housing
As part of the agreements
densely forested state in the north of policy had a strong impact on the
reached with the communities, the
the island of Sumatra. The majority of response. Policy required that the
łNOP OAIEPEI>ANA@ ODAHPANO
SDE?D
the population live along the coast and shelters that were built create a
had provided transitional shelter
the main access is by sea or along the minimum covered area of 36m2. The
for as long as two years, were
coastal roads. KJHU KBł?E=H PN=JOEPEKJ=H NAOLKJOA
upgraded at the NGO’s expense
was the building of transitional living
Aceh has had intermittent periods centres, also known as ‘barracks’.
KB ?KJŃE?P OEJ?A &J *=U
Photo: Predes
These were long, timber-framed
the government of Indonesia declared and panelled buildings on stilts with
martial law in the province. As a plywood separation between families.
NAOQHPKBPDA?KJŃE?PPDANAS=OHEIEPA@
involvement of non-governmental Technical solutions
organisations in the province. Traditional coastal Achinese
Road
once all shown twohad
shelters yearsbeen
aftercompleted.
the tsunami.
shelters are entirely made of local ??AOOS=OEJEPE=HHU@EBł?QHP=HKJCIQ?D
After the tsunami timber and have thatched roofs. They of the west coast of Aceh.
The earthquake that struck on 26 are often on stilts to keep them off
December 2004 was one of the largest the ground. More recent construction
ever recorded and damaged many of has a concrete plinth and low brick
the larger concrete-framed buildings Who builds?
walls, with a timbered superstructure Planning of the programme started
in Aceh. The ensuing tsunami caused built on top. The roof is covered in
extensive damage in many of the approximately six weeks after the
corrugated iron. tsunami, as a community-led con-
countries in the Indian Ocean. The
province of Aceh was the worst hit, This project began building semi- struction programme to build shelters
due to its proximity to the earthquake permanent shelters based on local similar to those that many families had
and because the majority of the popu- designs. These had concrete and brick before the disaster. The programme
lation live in low-lying coastal areas. foundations and low brick walls, and sensibly aimed to build skills and ca-
were topped with timber frames, pacities within the villages, create live-
Following the tsunami, the majority a corrugated iron roof and timber lihood opportunities and cultivate a
of emergency shelter needs were met panels. higher level of ownership by encourag-
EJ PDA łNOP SAAGO >U PDA &J@KJAOE=J ing self-build approaches.
military, Indonesian organisations and About ten months after the
>AJAł?E=NEAO PDAIOAHRAO 1DEO S=O tsunami, the house model changed to a The scale of the construction in
due to logistical challenges and the reinforced concrete-framed structure ?ADS=OOECJEł?=JPHUCNA=PANPD=JD=@
fact that foreign access was limited with brick walls and a wood-framed ever before been experienced in the
by infrastructure damage and travel roof. It included over 50 separate com- region, requiring over 109,000 houses
restrictions resulting from the ongoing ponents, as well as toolkits. This was from a building industry that had only
?KJŃE?P 0DAHPAN S=O LNKRE@A@ EJ seen as ‘building back better’, although built a fraction of that number. As
collective tents, existing buildings, there were some safety concerns time passed and villagers started to
individual family tents, by use of plastic where builders had taken shortcuts. regain their livelihoods, NGOs found
sheeting and by families moving inland EPD=N@ANPKłJ@=SKNGBKN?ABNKIPDA
1DEO LNKFA?P S=O >=OA@ EJ łRA villages.
to where the damage was not as bad. distinct districts, with different
designs and implementation methods
*=JULAKLHA>QEHPPDAENKSJODAHPANOQOEJCNA?H=EIA@I=PANE=HO
40
Asia Shelter Projects 2008 B.5
Bamboo being bound with string Electric power drills used to drill holes in
the bamboo so that it can be pegged
Photos: IFRC
Prefabrication of a wall panel Connecting a vertical post to Foundation pads cast with bamboo to
the foundation connect them to the frame
43
B.6 Indonesia, Jogyakarta - 2006 - Earthquake - Overview of the response Asia
44
B.6
B6 Jogyakarta - 2006 - Earthquake - Cash and transitional shelter Asia
Community-built shelter
AJAł?E=NEAO SANA OPNKJCHU AJ-
couraged to follow the design, but not
compelled to. In some cases people
ECJKNA@ KN IK@EłA@ PDA @AOECJ
OQ?D
Photo: IFRC
as in Delingo, a remote community
Photo: IFRC
with widespread construction skills
and local construction resources.
The volunteers/supervisors were
A completed transitional shelter built A transitional shelter built on the site of essential to guide and support good
through cash grants a destroyed house construction. The more the volunteers
SANA ?KJł@AJP =J@ AJC=CA@ EJ PDA
Design process process, the more the construction
AJAł?E=NUOAHA?PEKJ
This project aimed to empower followed the design and was of
Small cash grants were given out via
community members to rebuild their OQBł?EAJP MQ=HEPU 3=NE=PEKJO SANA JKP
traditional mutual support mechanisms
lives, starting with the construction of problematic as long as the general
to neighbourhood groups to buy tools
a transitional shelter. The transitional principles were followed and the
and basic materials to build temporary
shelter design was developed through essential points (such as building size,
shelters.
an understanding of locally available O=BA?KJJA?PEKJO
AP?
SANAO=PEOłA@
Meetings were held with each materials, community needs and the Delay in project startup
group to discuss the project and to capacity and objectives of the organi- The organisation was initially
sign a contract with the community. In sation. hesitant to give cash directly to ben-
order to participate, each neighbour-
It took one month for the design Ał?E=NEAO &B PDANA D=@ >AAJ MQE?GAN
hood (20-50 houses) had to form a
process, one month for community institutional support for the project, it
shelter committee that had to include
preparation and demonstration could have been scaled up faster and
a head of the group, a treasurer (who
shelters, and one week to build 740 reached more people.
had to be a woman) and a secretary.
The positions could not be held by ‘model’ houses through a public com- Community knowledge
HK?=HKBł?E=HOKNPDAENB=IEHUIAI>ANO petition. Community levels of knowledge
The competition involved three about the use of bamboo varied. The
The committee was responsible
categories and offered prize money more urbanised the environment,
BKN PDA OAHA?PEKJ KB >AJAł?E=NEAO
that went to the neighbourhood for: the lower the level of traditional
who could be anyone currently living
knowledge in the community, which
in a tent or under a tarpaulin, with the most number of houses; led to a lower quality of bamboo con-
a house unsuitable for habitation. the most beautiful houses; and struction.
Priority was given to vulnerable people the involvement of women.
such as widows, orphans, disabled The rural mountainous commu-
people, pregnant women, the sick The programme was rolled out nities recovered relatively quickly,
and the elderly. Funds were delivered over seven months, with 12,250 despite higher levels of damage from
through group bank accounts in three shelters built in 761 communities. the earthquake and higher levels of
to four instalments. The community Shelters cost under US$ 200 per unit. general poverty. One of the reasons
contributed labour and materials for this was that many locals had
recovered from the rubble. worked in the construction industry
prior to the earthquake.
Photo IFRC
46
Asia Shelter Projects 2008 B.7
Community training lasted up to As per the requirements of the
one week. During this time the vol- cluster-wide transitional shelter
unteers and the community built the design, untreated bamboo was used
łNOP ODAHPAN PKCAPDAN
SEPD OQLLKNP- (which deteriorates after two years).
ing media (a step-by-step guide, an in- If treated bamboo had been integrated
Photos: IFRC
formative video about using bamboo in into the programme, the shelter
construction, safe construction adver- structures could have been safely used
PEOAIAJPO =J@ = >KKGHAP
3KHQJPAANO in communities for up to 25 years.
lived in the communities in a tent or
Transporting bamboo mats to a Resource management
transitional shelter and worked with
construction site The shelter programme built
the communities every day.
Implementation partners 12,250 transitional shelters that used
Throughout this project, the or- Working with volunteers allowed more than 100 culms of bamboo per
ganisation worked with national vol- a large-scale programme to be set up. shelter, using a total of more than 1.2
unteers, two local universities, un- The volunteers were often enthusias- million culms of bamboo.
dergraduate architecture students, tic and very willing to help, but some
To avoid deforestation of the
a training team, NGO facilitators/ D=@=HKSHARAHKB?KJł@AJ?AKNATLA-
bamboo stock, this project could have
trainers, an implementation team, and rience. This led to some challenges in
set up purchasing control mechanisms
a bamboo expert with experience in ensuring adequate quality control.
to manage the bulk procurement of
3AJAVQAH= =J@ #HKNAO
=J@ ?KIIQJE- 3KHQJPAANO SANA L=E@ = OI=HH bamboo that controlled quality, en-
ties in Jogyakarta and Central Java. stipend and supported with cooking vironmental impact, procurement
The local universities were involved AMQELIAJP
OHAALEJC CA=N =J@ łAH@ methods and treatment of the bamboo.
and helped to: OQLLKNP SAAGHU NAŃA?PERA HA=NJEJC It would have also been possible to
training session was held. allocate money to reforestation pro-
develop technical inputs for shelter grammes.
design and messages; The Shelter Cluster design
develop posters, pamphlets, guidelines included seismic Materials Quantity
t-shirts, etc.; resistance, lasting up to two Bamboo mats 10 mats
train students to deliver 'build years, using materials that 6 walls, 3 ceiling, 1 door
back better' messages under staff Round poles (for columns) 12 poles
supervision; and
could be recycled and that 3' diameter, 3m long
set up mobile construction clinics. cost under US$ 200. Round poles (for beams 11 poles
and roof joists)
Ongoing use of shelters 7.5cm diameter, 3m long
The local media also got involved,
reinforcing best practice shelter and In the densely populated area of 1EI>ANBKNłTEJCPDAI=PO 7 beams
construction messages on the radio, Klaten, the transitional shelters were /AEJBKN?A@LH=OPE?ODAAP ITI
television and in print. eventually demolished to make room Nails 2.2 kg
for permanent housing. 5cm, 7.5cm and 10cm
‘Achieving good recovery and In the rural areas, the majority Wire 1 kg
risk reduction outcomes in of the transitional shelters were still Hinges 3 units
shelter is not about building being used after permanent shelters Lock 1 units
structures. It is about building were built, but for purposes such as
trust with communities’. storage sheds, shelter for cattle and
- Recovery coordinator for the livestock, or for small restaurants.
programme
47
Asia Shelter Projects 2008 B.7
Distribution - plastic sheeting At the request of local communi- and equipment for cleanup and
The organisation implementing this ties and in support of the local self-help reconstruction; and
project was one of the few agencies tradition of ‘gotong royong’, all distri- a shortage of clean sleeping mats.
with full-functioning capacity at the butions occurred at the community
time of the earthquake. It started its level instead of the individual level. All
needs assessments and distributions The rush by affected families to re-
łNOP @EOPNE>QPEKJO PAJ DKQNO =BPAN PDA
were conducted by local implementing construct permanent houses raised a
earthquake.
partners. Communities were responsi- number of advocacy concerns. These
As rain was falling each night there included issues about the quality
>HABKN>AJAł?E=NUOAHA?PEKJ
was an urgent need for shelter, but of construction, health and safety,
supplies were too limited to supply Because local NGOs conducted treatment of the asbestos within the
one tarpaulin per family. all distributions and evaluations, the rubble and the construction of shelters
amount of human resources that the in precarious positions.
A broader distribution through
international NGO itself had to deploy
local partners was conducted. Each The emergency programme was
was extremely limited. At its peak
REHH=CA S=O LNKRE@A@ SEPD OQBł?EAJP followed by an Enhanced Emergency
EP AILHKUA@ KJHU OET ODAHPANOLA?Eł?
tarpaulins to ensure that the sick, the Shelter programme, which provided:
staff, and focused its resources more
weak, the young and the elderly were
on logistics and partnership support. woven bamboo wall sheeting
=@AMQ=PAHU QJ@AN ?KRAN &J PDA łNOP
Expansion of the emergency (gedek) to affected communities to
days, villages joined tarpaulins together
shelter programme AJOQNA PD=P A=?D B=IEHU D=@ OQBł?EAJP
to form large communal shelters that
Early analysis of the progress of material to build walls for their
housed the whole village at night (up
community recovery showed: emergency shelter;
to ten times the expected number of
combined community toolkits for
>AJAł?E=NEAO
the use of tarpaulin for both clean-up and reconstruction; and
As funds and capacity from other NKKłJC=J@S=HHEJC
NAOQHPEJCEJHEIEPA@ sleeping mats.
organisations arrived, the project undercover space;
S=O NA@Q?A@ PK =J EJłHH LNKCN=IIA
OQBł?EAJP NA?H=EI=>HA PEI>AN It also launched an advocacy
returning to previously assisted villages for temporary shelter framing, but and public outreach programmes to
and supplying 48m2 of plastic sheeting EJOQBł?EAJPI=PANE=HBKNS=HH?H=@@EJCĢ address safety and health issues.
per family (two 6m x 4m sheets). a pressing need for tools
Photos: Dave Hodgkin
?KHHA?PERAODAHPAN>QEHP>U>AJAł?E=NEAOQOEJC@EOPNE>QPA@LH=OPE?P=NL=QHEJO
49
B.7
B7 Jogyakarta - 2006 - Earthquake - Emergency and transitional shelter Asia
Transitional shelter grants the emergency shelter distributions. Cluster members as a part of shelter
O=łJ=HL=NPKBPDAKNC=JEO=PEKJO These were based on a tender process material distributions. In total, four
emergency shelter programme, a that resulted in a cost of US$ 100-300 batches of 20,000 posters each were
programme was started to support per shelter. distributed to the disaster-affected
the transition into temporary housing. population.
As well as housing 2,000 families
The transitional shelter programme and improving the capacity of a The public outreach working group
was conducted in accordance with the number of local partners, this went on to develop a range of public
Emergency Shelter Cluster guidelines programme produced a range of outreach and advertising materials to
that had been developed locally well-documented transitional shelter promote safe reconstruction.
following the earthquake. solutions as potential examples for
further expansion or adoption by
‘The best we can do as other agencies.
Materials Quantity
shelter managers, is to be "IANCAJ?UODAHPANLNKCN=IIA
responsive and adaptive to Public outreach and advocacy Plastic tarpaulin 20-30 per
1DA łJ=H =OLA?P KB PDEO LKOP ITI sub-village
the changing needs of the earthquake shelter response was (200-300 families)
affected community;providing a public outreach and advocacy EJłHHLNKCN=IIA
minimalist but strategic and programme, where the organisation Plastic tarpaulin 1 per family
incremental inputs into the provided technical advice to the Shelter ITI
Grants were provided to build transitional shelters. Many different and innovative designs were built.
50
B.8 /QOOE=
&JCQODAPE= KJŃE?P-AKLHA@EOLH=?A@ =ODBKNODAHPANDKOPB=IEHEAO Asia
9 +K ARE?PEKJ KB &!-O @QNEJC PDA SEJPAN IKJPDO KB 8 1DADECDJQI>ANKB>AJAł?E=NEAOEJ@EBBANAJP@=P=>=OAO
=J@SANANALKNPA@ NAMQENA@=JEJPAJOERARANEł?=PEKJLNK?AOO
9 +K =>QOA @QNEJC ?=OD @EOPNE>QPEKJ KN =JU OA?QNEPU 8 Implementation of the 2nd phase during the following
EJ?E@AJPOK??QNNA@@AOLEPA=N=PDANPAJOAOA?QNEPUOEPQ=PEKJ SEJPAN S=O ATLKOA@ PK OARANA BN=Q@ =PPAILPO
=O OKIA
9 1DA LNKCN=IIA O HARAH KB PN=JOL=NAJ?U =?DEARA@ DECD EJ@ERE@Q=HO D=@ I=JELQH=PA@ KBł?E=H @K?QIAJPO EJ KN@AN
=??ALP=J?A=IKJC>AJAł?E=NEAO=J@HK?=H=QPDKNEPEAO IAAPPDAAHECE>EHEPU?NEPANE=%KSARAN
PDABN=Q@QH=JP?=OAO
9 Professional cooperation with the Russian postal SANA OKNPA@ KQP =J@ ATLAHHA@ BNKI PDA >AJAł?E=NU HEOPO
OANRE?AĠ&JCQOD>N=J?D
=HHKSA@BKN=PEIAHU=J@=??QN=PA >ABKNAL=UIAJPS=ONAHA=OA@
cash disbursement. 8 In view of the scope of the project (the entire Republic of
9 1DAOECJEł?=JPEJŃQTKBHEMQE@?=ODOQLLKNPA@PDAHK?=H &JCQODAPE=
=JAR=HQ=PEKJKBPDALNKFA?PS=ONA?KIIAJ@A@
A?KJKIU to reveal detailed information about its effects and impact.
52
Asia Shelter Projects 2008 B.8
53
Asia 0DAHPAN-NKFA?PO B.9
Destroyed rural houses (left, centre) and urban houses (right) in Kashmir
Self-built shelters in Kashmir built using reclaimed materials only ten days after the earthquake
Above, assorted model shelters built in the North-West Frontier Province and Kashmir. Note that not all of these models (e.g. the domed
ODAHPAN@AOECJEJPDA?AJPNA
SANA?QHPQN=HHU=??ALP=>HA
OQBł?EAJPHU@QN=>HAKNOL=?EKQOAJKQCDBKNLAKLHAPKHERAEJ
55
B.10
B.10 Pakistan - 2005 - Earthquake - Transitional shelter construction Asia
Villagers collected their shelter There was a warehouse for each
GEPO=PPDAL=NGKBł?A1DA=IKQJPKB LNKFA?P =NA= *=PANE=HO SANA PDAJ
materials included in each kit depended transported to the villages; from there
upon the family size. There was a it was the responsibility of villagers to
PKKHGEPBKNARANUłRAB=IEHEAO carry them to construction sites.
After some initial issues with The shelters after two years
shelters not being completed, the After two years, nearly half of the
NKKłJC I=PANE=HO
EJ?HQ@EJC PDA IKOP shelters were still standing in their
valuable part of the kit, the corrugated original position. Of those that had
iron, were distributed only upon com- been removed, one was reassembled
pletion of the frame. in the summer pastures. Shelters were
commonly removed to make space
Most of the shelters were con-
for the ‘permanent’ house or to reuse
structed by a team of two to four
the materials. The corrugated iron and
workers in less than one week. The
the timber were the most commonly
LNKFA?P LNKRE@A@ =J =HHK?=PEKJ KB łRA
reused materials.
‘person days’ of payment for the con-
struction of each shelter. In practice, Materials Quantity
the technical assistance teams ended Polypropylene sand 350
up constructing many of the shelters. bags
Progress was periodically halted by
Wire 14g/PP strips ¼ roll
deteriorating weather conditions, par- 20 x 6mm
ticularly in early January.
Polypropylene 6 rolls
1DAI=FKN?KJOPN=EJPOEJPDAEILHA- string
IAJP=PEKJKBPDALNKFA?PSANANAH=PA@ Corrugated iron 16
to the procurement and transporta- sheets
tion of materials and the weather con- 2.74m x 0.99m
ditions. The corrugated iron sheeting, Iron ridge sheets 6.7m
SDE?D S=O QOA@ =O PDA NKKłJC BKN Nails 5kg
ODAHPANO
S=O @EBł?QHP PK LNK?QNA EJ
the required quantity. A tender for
Salvaged timber was also used for the
sheeting was placed in November
NKKłJCBN=IA
but suppliers were not able to deliver.
Eventually it was imported from India,
1KKHGEPO SANA OD=NA@ >APSAAJ łRA
which required high-level negotiations
families and contained: an adze
to relax the import restrictions into
(woodworking axe) with handle, a cold
Pakistan for Indian materials.
chisel, a 1.3 m crowbar, a hacksaw
with 20 blades, a 2kg hammer, a claw
Photo Kurt Rhyner
Logistics and materials hammer, 10m of transparent hose,
For much of the duration of the three needles, a pick with handle,
LNKFA?P LANEK@
NK=@ =??AOO PK PDA pliers, a 400mm handsaw, a shovel, a
LNKFA?POEPAOS=O>HK?GA@>UH=J@OHE@AO I P=LA IA=OQNA =J@ =J =@FQOP=>HA
As a result, materials had to be driven wrench.
to Muzaffarabad and then airlifted to
PDAOEPA1DAłJ=HOP=CAKBPN=JOLKNP=-
tion was by donkey and by foot.
Photos: Albert Reichart
Photo Albert Reichart
Inside one of the transitional shelters Building one of the transitional shelters
58
B.11
B.11 Pakistan - 2005 - Earthquake - Shelter materials distribution Asia
0AHA?PEKJKB>AJAł?E=NEAO earthquake damage to roads meant
Within one week of the earthquake, that many people incurred costs in
I=FKNłAH@KBł?AOSANAOAPQLEJ=CD getting to the distribution points and
and Muzaffarabad, the two operational transporting materials home. This was
hubs for relief operations in Pakistani- by far the largest cause of dissatisfac-
controlled Kashmir. The programmes tion with the distribution process.
were in rural areas, selected on the
Corrugated iron became a much
basis of the level of damage and
sought-after commodity in distribu-
coverage by other organisations.
tions. A combination of the cost of the
The initial lists of people who iron and the very low incomes of many
should qualify for support were affected families meant that a distribu-
provided by community leaders. A tion of corrugated iron was equivalent
built shelter is unlikely to kill people in of the toolkits due to time pressures;
the varying skills and capacities of Plastic sheet 6m x 4m 1
the event of further aftershocks and
building collapse. affected populations to use the tools; Stove with exhaust pipes 1
the variable security surrounding Jerry can 20l 1
Toolkits containing basic carpentry Bagh;
and earthmoving tools, as well as nails Jackets – 1 large, 1 medium, 1
lack of support to help people use
=J@IAP=HOPN=LLEJCBKNQOA=OłTEJCO
1 small
their tools to rebuild; and
were developed through a limited but the inconsistent quality of tools. Plastic shoes – I large, 1
rapid community consultation. The Implementation 1 medium, 1 small
time pressure was such that orders Although distribution points were Cookset: 3 pots, 6 large 1
for large numbers of kits could be selected with the consent of community plates, 6 small plates, 6
rapidly placed, leading to cost and representatives and communities were spoons, 1 knife, 2 mugs
logistics savings. The idea of delivering JKPEłA@SAHHEJ=@R=J?A
PDAPANN=EJ=J@
60
B.12 0NE)=JG= KJŃE?PNAPQNJO KNAODAHPAN Asia
62
Asia Shelter Projects 2008 B.12
provided all materials, apart from
locally sourced sand. All other materials
were procured in Trincomalee, the
JA=NAOPH=NCALKNP1DAI=FKNEPUKBPDA
PEI>ANS=O?K?KJQPPEI>ANP=GAJBNKI
OQOP=EJ=>HUI=J=CA@OKQN?AO1DA>AJ-
Ał?E=NEAO SANA CERAJ OI=HH CN=JPO PK
pay for the transportation of materials
from the central distribution site.
After the project
63
Asia Shelter Projects 2008 B.13
The shelter strategy allowed for many different shelter designs. Over 70,000 transitional shelters were built.
65
Asia Shelter Projects 2008 B.14
Before the tsunami The metal frames also meant that
Many families had built houses the shelters could be relocated and
on customary plots in ribbon settle- reused if necessary, unlike shelters
67
B.14 Sri Lanka - 2004 - Tsunami - Case study: Transitional shelter construction Asia
Materials list
Material Quantity
take sand from the beaches, but this Umbrella nails 0.2kg
was counter to government bans and G.I. ridge sheet - 0.9m x 1
also had a potentially negative impact 2.4m
on the environment. In some cases,
communities were given small grants In July and August 2005, basic elec-
to buy sand from local suppliers. trical wiring (one plug socket and one
The construction of the shelters was not
HECDP OK?GAP
=J@ NKKłJC EJOQH=PEKJ =@EBł?QHPLNK?AOO
were added.
68
LAC Shelter Projects 2008 C
Section C
Latin America and
Caribbean
C.1
Honduras
Hurricane 1998
C.2 - C.5
Peru
Earthquake 2007
69
LAC Shelter Projects 2008 C.1
Marking out the site for a shelter Prefabricating walls Shelter assembly using prefabricated walls
71
C.1 Honduras - 1998 - Hurricane Mitch - Transitional shelter LAC
Materials list
In addition to the materials listed List of tools needed to build 50 - 75
>AHKS
=LLNKTEI=PAHU I2 KB SKRAJ transitional shelters:
Funes
Milton Funes
NE>>KJ KB EJPANJ=PEKJ=H OLA?Eł?=PEKJ
Materials Quantity
LH=OPE? ODAAP S=O LNKRE@A@ >U PDA
Hole digger 10
Photo: Milton
donor organisation.
Manual saw 10
Photo:
Hammer 20
Materials Quantity Tin snips (tin scissors) 10
Timber 8 Plumb 10
Completing the frame 50mm x 100mm x 3m
Tape measure 10
Timber 4
50mm x 100mm x 3.6m Level 10
Timber 3 Staple gun 10
Logistics 50mm x 100mm x 4.3m
AJAł?E=NEAOOECJA@BKNPDAI=PANE=H Table saw 1
SDAJ EP S=O @AHERANA@ =J@ SANA NA- Timber 1 Portable saw 5
50mm x 100mm x 1.8m
OLKJOE>HA BKN PDA I=PANE=HO OA?QNEPU Diamond saw blades 5
Timber 6
BNKIPD=PLKEJPKJS=N@1DEONAMQENA- 50mm x 50mm x 2.4m
ment was made clear to each family at
Timber 5
PDA KJOAP KB PDAEN EJRKHRAIAJP EJ PDA 50mm x 50mm x 4.3m
LNKCN=IIA
Timber
A senior staff member based in 25mm x 74mm x 2.4m
PDA?KQJPNUKBł?AS=ONAOLKJOE>HABKN Galvanized roof sheet 6
Although the preferred option was to build shelters on people’s own land, in
some cases it was necessary to build shelters on a temporary relocation site.
72
LAC Shelter Projects 2008 C.3
Photo: Predes
KRANPDAUA=NO
OP=NPEJCSEPD=
>=I>KKI=PDKQOA
model structure.
AJAł?E=NEAO SANA łNOP CERAJ
wooden poles and received the mats
only when the structure was properly
assembled. Materials were distributed
by the block coordinators. Most
1DALNKFA?PS=O>=OA@KJ?KIIQJEPUOKQLGEP?DAJO=O=OP=NPEJCLKEJPBKN families ended up digging a new latrine
social mobilisation. on their property.
75
C.3 Peru - 2007 - Earthquake - Community mobilisation LAC
Photo: Predes
1N=JOLKNPEJCPDAI=POBKN=ODAHPANPKOEPA
Logistics and materials Building with these materials costs local market had a limited capacity to
The wooden poles and woven about 25% of what some other local deliver bamboo mats - an issue which,
bamboo mats were purchased from organisations spent on their provisional in the end, led to the ending of the
local production in the informal shelters made of timber or low-grade project.
market. Plastic sheeting and hardware galvanized sheeting. However, the
elements (nails, hinges, etc.) were
centrally purchased.
The materials were shipped to San
José, where the municipality provided
the football stadium and another
building as storage areas.
The trucks were unloaded by the
LKPAJPE=H>AJAł?E=NEAO1DAEILHAIAJP-
ing NGO organized and was responsi-
Photo: Predes
ble for the warehouse management.
The materials were given to the -DKPK(QNP/DUJAN
>AJAł?E=NEAO SDAJ PDAU LNAOAJPA@
vouchers issued by the coordinators.
#=IEHUODAHPAN>QEHP@QNEJCPDALNKFA?P
Photo: Predes
Photo Predes
*=GEJC=>=OE?ODAHPAN
76
C.4 Peru - 2007 - Earthquake - Self-build transitional shelters LAC
*=GEJCPDA?KJ?NAPAŃKKNOH=>
78
LAC Shelter Projects 2008 C.5
-DKPKOġ)A$N=J@*=H=JU
KILHAPA@ODAHPAN>QEHPKJPDANKKBKB=@=I=CA@DKQOA
0AHA?PEKJKB>AJAł?E=NEAO Technical solutions All tools needed by the homeowner
Communities were selected by The shelter design was a rectan- to build his/her shelter were supplied
analysing the gaps and noting that no gular, single-storey, 18m2 (3m x 6m), by the contractor and were left with
other organisations were working in wood-framed, shed-roofed building. the homeowner at the conclusion of
the areas. Families within communities The side covering was vertical, tongue- the programme as a home mainte-
were prioritised based on need and in- and-groove wood. Each panel was ap- nance tool kit.
dividual vulnerability. proximately 1cm thick and approxi- Implementation
mately 10cm wide. The shelter had one The initial contract was for 500
AJAł?E=NEAO JAA@A@ PK LNKRA
door and a large window on one long shelters. Costs rose 25% for subse-
ownership of land before qualify-
wall (at the front). The roof was a shed quent shelters, due to local cost esca-
ing for the project. The criteria were
style made with lightweight, corrugated lations.
later relaxed so that those awaiting
cement panels approximately 1m wide
KSJANODEL ?ANPEł?=PAO =O PDA NAOQHP KB The contractor set up a materials
and about ½cm thick. The roof panels
wills of deceased family members could manufacturing ‘factory’ in each project
were long enough to run the full width
qualify for the project without holding area. At this site, the contractor’s
KBPDANKKB1DAŃKKNEJCQOA@LNAAT-
PDABKNI=HH=J@KSJANODEL?ANPEł?=PAO employees (using some local labour)
isting concrete slabs.
Families who were at risk and ?QP
LH=JA@=J@łJEODA@PDAS=HHBN=IA
Each house took approximately units. Only the contractor’s employees
relocated from the ‘no return zone’
eight hours to construct once the used power tools.
had to wait in temporary shelter on
prefabricated materials were trans-
squatted allocated land for over nine Families were responsible for
ported to the site. The idea was that all
months before they could be allocated rubble removal, site cleaning and
materials could be later reused.
land and qualify for a shelter. marking out the shelter location.
-DKPKOġ)A$N=J@*=H=JU
1DAN=SI=PANE=HOSANALNAL=NA@EJSKNGODKLOOAPQLEJPDA?KIIQJEPEAOSDANAODAHPANOSANAPK>A>QEHP
81
C.5 Peru - 2007 - Earthquake - Prefabricated transitional shelters LAC
Bill of quantities
-DKPKġ)A$N=J@*=H=JU
Item Quantity
Wood 68
(tongue and groove)
2.48m
Wood 43
(tongue and groove)
2.3m
Wood 10
(tongue and groove)
42cm
Wood 16
(tongue and groove)
32cm
Wood 16
KILHAPA@ODAHPAN>QEHPKJPDANKKBKB=@=I=CA@DKQOA (tongue and groove)
1.01m
Wood 70
&B PDA KH@ ŃKKN OH=> ?KQH@ JKP >A volunteers. The rest worked in the (tongue and groove)
reused, or there was no existing slab, community, helping with registration, 2.48m to 2.30m
the homeowner was required to land rights and other emerging issues. Nails 1kg
pour one. In some cases homeown-
ANO I=@A PDAEN ŃKKNO =BPAN ?KJOPNQ?-
Safety and Liability Wood strips 2
The contractor maintained control 3cm x 6cm x 3m
tion. Employees of the contractor and
of the cutting and assembly yard and Wall plates 3
trained community members provided
its employees, and controlled access to 6cm x 6cm x 2.5m
guidance and oversight for the mixing
hazardous places. Since the contractor
and pouring of concrete. Hinge, steel 2.5" 7
owned, controlled and supervised the
Homeowners transported the operation they were the main liable KNNQC=PA@NKKłJC 6 sheets
materials from the ‘factory’ to their entity. 3m x 1m
home. They then installed the tongue- Instructional manual 1
Each community established a safety
and-groove wall sheeting onto the Plastic tape 8
committee that controlled access to
six wall-framing panels. Company 1cm x 15cm
the cutting and framing site, as well
employees and trained community
as the assembly sites. In general, Screws 3
members then assembled the sided
community activities were provided
frames (two for the side walls and One toolkit was distributed per group
for youth and children to keep them
four for the front and back walls) with of workers.
entertained while their families were
assistance from company advisors.
building their shelters.
Families nailed the structures together
and added the doors and windows. Logistics
By delivering basic raw materials
Quality Control
(rough timber, tongue-and-groove wall
Supervision and quality control
sheeting and corrugated iron, cement
were done by the contractor’s staff.
panels, nails, etc.) to the building site,
The contractor had one engineer and
logistics requirements were reduced.
one project manager (who supervised),
Warehousing was also reduced, since
=J@ łRA OGEHHA@ SKNGANO SDK ?QP PDA
-DKPKġ)A$N=J@*=H=JU
82
Historic Shelter Projects 2008 D
Section D
Historical Case Studies
From the Cuny Archive
D.4
D.2 Bangladesh
D.3 India KJŃE?P
Nicaragua KJŃE?P
Earthquake 1973 D.7
D.5 D.9 Thailand
Sudan D.6
Guatemala India, KJŃ?EP
Earthquake 1976 KJŃE?P
Andrah Pradesh
Cyclone 1977
D.8
Tonga
Cyclone 1982
83
D.1 Historical case studies - overview - Case studies from the Cuny Center Historic
84
Historic Shelter Projects 2008 D.1
1980s
Throughout the 1980s, the numbers =@AMQ=PANAOLKJOA(JKSHA@CAKB>AOP ments and extreme weather conditions
of refugees caught in protracted situa- LN=?PE?A=IKJC=HH=?PKNOS=O=LNANAM- attributable to global warming.
tions increased, while the willingness of uisite before the start of a programme, Experiences such as those in Aceh,
host governments to provide options rather than something that could be Indonesia following the 2005 tsunami
for permanent resettlement dimin- FQOP HA=NJA@ EJ PDA łAH@ 1DEO SKQH@ D=RAN=EOA@EILKNP=JPMQAOPEKJO=>KQP
EODA@1DA2+łNOPATLKQJ@A@=LKHE?U become the Sphere Project (www. the unintended effects of shelter
response of voluntary repatriation as sphereproject.org). responses in accelerating urban
the single preferred durable solution, migration and extending the sprawl of
Transitional shelter and
and decried camps as the option of the cities further into hazardous or en-
settlement
last resort. Under such circumstances, vironmentally fragile locations.
At the same time as the Sphere
the focus of those working on best
drafting process, other initiatives gave
practice in the shelter sector started
PDAODAHPANOA?PKNEPOłNOPOAPKBEJ@A-
to pay more attention to the political
LAJ@AJP
OA?PKNOLA?Eł? RK?=>QH=NU
aims to which settlements could be
since the 1970s. The shelter process
twisted. This was often based on their
for the affected communities and for
own experiences of witnessing un-
humanitarian organisations is now
sustainable camps being used as ‘pull
seen as having transitional phases, with
factors’ or to house hostage popula-
=J EJOEOPAJ?A PD=P PDA łNOP AIANCAJ?U
tions, in places like Sudan or the Horn
response must somehow demon-
of Africa.
strate support for the eventual durable
1990s and Sphere solution.
The crisis in Rwanda in 1994
Urban challenges
gave the impetus to many organisa-
The last four years have seen
tions to capitalise on the movement
moves to widen the accountability and
started in the early 1990s with the Red
predictability in all sectors of humani-
Cross Code of Conduct. This aimed
tarian response through the develop-
PK JKP KJHU OUOPAIEOA PDA MQ=HEP=PERA
ment of the Cluster System. But those
=J@ MQ=JPEP=PERA =OLA?PO KB IEJEIQI
years have also seen greater challenges
standards across all sectors including
brought closer to the spotlight.
shelter, but to also ensure the widest
possible awareness of those standards, In the last two years, the number of
and the maximum possible adherence people living in urban populations has
and buy-in among humanitarian or- reached 50% of the world’s population
ganisations. This was done in the re- BKNPDAłNOPPEIA
=J@I=JUKBPDKOA=NA
alisation that in complex emergencies living in hazard-prone areas on marginal
the UN lead agency system could lands. This is especially relevant with
not always be relied upon to ensure the potential threat to coastal settle-
Fred Cuny
Fred Cuny trained as an urban planner in Cuny conceived humanitarian response as centred
the mid-1960s, and worked professionally with upon the affected communities, and serving to
disadvantaged communities in southern Texas, support them in a return to sustainable livelihoods.
before his experience as a pilot of small planes He advocated for camp designs that clustered
gained him a position working with relief agencies shelters into small communities, shelters made
during the Biafran War in 1970. Between 1971 of traditional materials that were built by the
and 1995, Cuny and Intertect, the consultancy refugees, and the training needed to ensure that
that he set up, worked with NGOs, the UN, and those shelters and houses would be built back safer
I=FKN@KJKNOEJ=JQI>ANKBDECDLNKłHA@EO=OPANO and hazard resistant. Cuny also advocated a holistic
Through all of these, Cuny sought to develop approach to humanitarian response and worked to
guidelines for best practice and to advance the combine shelter responses with those for water/
state of the art in humanitarian response. Cuny and sanitation, food security, livelihoods and public
&JPANPA?PSANANAOLKJOE>HABKNPDASNEPEJCPDAłNOP health. By the early 1990s, he was increasingly
ever set of camp planning guidelines, contributed involved in advocating for policy and intervention
to Shelter After Disaster
=J@SNKPAIQ?DKBPDAłNOP OPN=PACEAOEJ?KJŃE?P=J@@EO=OPAN%AS=OGEHHA@EJ
draft of the Handbook for Emergencies. They were also Chechnya in 1995.
early advocates for the promotion of minimum
standards in humanitarian response, through
guidelines and manuals.
85
Historic 0DAHPAN-NKFA?PO D.2
87
D.2 &J@E= KJŃE?P/ABQCAAO#ENOP?=ILLH=JJEJCCQE@AHEJAO Historic
Cuny Center
PDA>=I>KKI=PPEJC1DAOASANAQOA@ -D=OA &&& ?=IL >AJAłPA@ BNKI EPO =NIU AJCEJAANO &ILKNPA@ I=PANE=HO
BKN NKKłJC
L=NPEPEKJO =J@ ŃKKNEJC EJ LNKTEIEPU PK =H?QPP= EJ PANIO KB SANAH=PAN=QCIAJPA@>UPDA>=I>KK
PDA ODAHPANO =J@ H=PNEJAO
=J@ BKN PDA PDA LNK?QNAIAJP KB EPO ?KJOPNQ?PEKJ I=PPEJCI=@AEJPDA?=ILSKNGODKLO
HEJEJCKB@N=EJ=CA?=J=HO I=PANE=HO 1DA =>EHEPU KB PD=P ?=IL PK
@ARAHKL N=LE@HU S=O =PPNE>QPA@ PK PDA
Logistics =QPDKNEPEAO SEHHEJCJAOO PK ?KIIEP
1DA ?KJOPNQ?PEKJ KB PDA H=NCAN
BQHHPEIA LNKBAOOEKJ=H PA?DJE?E=JO =J@
88
D.3 Nicaragua - 1973 - Earthquake - Small camp Historic
90
D.4 =JCH=@AOD KJŃE?P-AKLHA@EOLH=?A@0DAHPANQLCN=@AO Historic
Before the upgrading of the
camps
Hundreds of thousands of Urdu-
speaking Biharis migrated from eastern
India to what was then East Pakistan
during the partition period of 1948.
During the Bangladesh War of Inde-
pendence in 1971, the Biharis sided
Cuny Center
with the Government of Pakistan.
After the surrender and evacuation
of Pakistani armed forces, the Biharis
were left behind, declared to be enemy
citizens by the new Bangladesh govern-
ment, denied the right to resettle in
Pakistan by the Pakistan government,
and were rendered stateless.
During the 1972-1974 period, the
Biharis were displaced into camps,
often under force from the Bangladeshi
authorities. A number of those camps
were scattered on marginal lands on
the periphery of Dacca. In 1972, some
NGOs had given shelters or shelter
materials to the camps, but the camp
layouts were often poorly organised,
and the shelters themselves had not
been upgraded since that point.
Cuny Center
In 1974-75, local police forced some
of the Biharis into new camp sites. This
had the initial effect of making NGOs
reluctant to support the camps, in case
they were seen as supporting the gov-
ernment policies. This attitude only
changed after April 1975, after storms Site plans before and after upgrade
had caused major damage to some
camps. After the upgrading of the 0AHA?PEKJKB>AJAł?E=NEAO
camps (and assessment)
The Intertect consultancy had been
There continued to be very minor People were largely self-selected
working with US university research-
technical issues with the structures by arriving at the camp. All families in
ers on the development of emergency
themselves. These issues, such as the the camp were eligible for the new
shelter designs and implementation
angle and placement of the windows, ODAHPANO OOAOOIAJPO KB >AJAł?E=NU
processes since late 1973. In 1975,
SANA A=OEHU łT=>HA >U PDA K??QL=JPO satisfaction (and the reasons for any
they were given donor assistance to
However, it was noted that the families dissatisfaction) were included in the
@ALHKUODAHPANLNKPKPULAOEJPDAłAH@
did little if anything to improve or LNKFA?POłJ=HNALKNPKB,?PK>AN
After that, Intertect persuaded NGOs
adapt their shelters. Members of the consultancy team
working in three different camps to
made further assessments in 1977.
use their designs for shelters, camp Later assessments showed that
layout and construction processes. =HPDKQCD PDA >AJAł?E=NEAO SANA Land rights / ownership
CAJAN=HHU O=PEOłA@ SEPD PDAEN JAS The Bihari camp residents continue
The aims of the research project
shelters, the A-frame design made to be stateless (recent rulings give the
had been to design shelters that:
EP @EBł?QHP PK I=GA ATPAJOEKJO KN option of Bangladeshi citizenship only
would be sustainable and resistant additions. There were also complaints to later-born generations) and do not
to hazard; that although the A-frame was highly own the land.
could be constructed by the resistant to high winds, it also reduced
>AJAł?E=NEAOĢ the head height.
Technical solutions
SKQH@ EJOPNQ?P PDA >AJAł?E=NEAO Multi-family shelters were designed
&J CAJAN=H
PDA H=?G KB >AJAł?E=NU using bamboo poles, palm thatch,
in hazard-resistant design through the
participation in the design process was matting and jute rope. The design was
construction process; and
seen in the reduced sense of ownership that of an A-frame with cross-bracing,
could be made in large numbers,
or responsibility after occupancy. which had performed best in strong-
and could be made out of low-cost,
local materials. wind tests back in the US.
92
Historic Shelter Projects 2008 D.4
Cuny Center
family’s plot. But it was felt that in the
planned camps for the Biharis, with
very limited amounts of space, the
multiple-family shelters were appropri-
ate. The same basic design principles
could be used for single-family shelters
if required.
The layout of the camps was
based upon small U-shaped clusters of
ODAHPANO1DAOASANAH=PANOEILHEłA@PK
square clusters in some camps. Space
within the U was intended for the use
of women, particularly those observing
purdah. The areas outside the U shape,
along the access routes through the
camp, were intended for use by the
men. In this way, the public men’s area
was also intended to be made available
for workshops or other livelihoods ac-
tivities, and also gave each community
Cuny Center
more control over the public space
nearest their shelter cluster. Washing
and cooking areas were contained
within each cluster.
93
Historic Shelter Projects 2008 D.5
Cuny Center
roads and rivers blocked by landslides.
The emergency response from the US
and other governments was swift, with
5,000 tents transported to Guatemala
City within seven hours of the earth-
Sketch showing earthquake-resistant techniques bracing
quake.
As equally rapid as the external The international NGO in question Land rights / ownership
response was the rate at which affected partnered with a regionally-based Many of the affected population
families started building impromptu NGO that already had ongoing pro- were squatters in peri-urban areas
shelters themselves. Around 50,000 grammes in Guatemala (it was im- who often built back on traditional
ODAHPANOSANA>QEHPSEPDEJPDAłNOP plementing the earthquake shelter sites with no guarantee of tenure.
hours of the disaster. Although this programme), in order to accelerate At least one researcher involved in
meant that much of the affected popu- programming and ensure incorpora- the programme counselled against
lation were quickly under shelter, it led tion of local knowledge. wholesale rationalisation of the street
to a rapid increase in the price of cor- systems in those areas, because it
NQC=PA@C=HR=JEOA@ENKJNKKłJCODAAPO 0AHA?PEKJKB>AJAł?E=NEAO
would mean depriving many families of
There were additional concerns that Four affected rural areas were
their customary plots. Land holdings in
this would cause scarcity for the re- assigned to the NGOs by the national
rural areas may also have been tradi-
construction effort and cause the government. A partial registration of
tional for the most part, but this issue
materials to be too expensive for many >AJAł?E=NEAO S=O DAHLA@ >U =J EILHA-
was not as acute in those areas.
of the affected people. menting partner and the fact that local
cooperatives were already present in Technical solutions
A?=QOA KB PDA DECDLNKłHA J=PQNA the area. In some areas there were In light of the scale of the self-build-
of the disaster many organisations EOOQAOKB?KILAPEPEKJBKN>AJAł?E=NEAO ing of shelters, the NGOs in question
SEPDKQP LNEKN łAH@ ATLANEAJ?A OAJP KN KB >AJAł?E=NEAO OSEP?DEJC +$,O made a decision to support these
personnel to the disaster. The govern- when others appeared with free dis- efforts by distributing construction
ment was generally unable to enforce tributions or other attractive options. materials, supported with technical
coordination between organisations. training.
95
D.5 Guatemala- 1976 - Earthquake - Materials distribution and training Historic
96
D.6 India - Andhra Pradesh - 1977 - Cyclone - Materials distribution and training Historic
Before the cyclone
The affected population was pre-
dominantly rural, farming rice and
keeping livestock to supplement their
income. The affected areas were all
low lying and were intensively culti-
vated.
The vast majority of the popula-
tion lived in houses made of tradi-
tional materials. Common materials
were bamboo and palmyra leaf thatch
(made from a certain type of palm
tree). Before the cyclone there had
Cuny Center
>AAJ KBł?E=H AJ?KQN=CAIAJP PK I=GA
houses ‘pukka’ - made using reinforced
concrete. Pukka housing was also
preferred by much of the population
and displayed a higher social status. Safer shelter techniques - strapping columns to beams
Some of the faith-based and local to do so. There was also pressure from day to tend their farms.
organisations that were involved in the the government and from international
Tensions rose over the course
emergency response had been working donors (and from within some organi-
of the response, due to the different
in the area since at least 1969. Many of sations) to start construction imme-
levels of support given to communities
the larger international organisations diately, using outside contractors or
affected by the tidal wave and those
were new to the area. non-local volunteer forces if necessary.
affected by the high winds. Additional
After the cyclone It was recognised that the tidal tensions arose between communi-
The cyclone created two different wave had left dangerous levels of ties who had made agreements with
areas of damage: an area damaged by salinity in many of the communities’ different aid organisations, which had
a six-metre tidal wave that travelled L=@@U łAH@O
=J@ PD=P PDA CNA=PAN different types of programme method-
as far as 24km inland at its furthest need was to recover what was left ologies.
point; and an area damaged by high of the previous rice crop, and then
The NGO initially targeted the most
winds reaching over 270km/h, all along PK QJ>HK?G ENNEC=PEKJ ?=J=HO =J@ ŃQOD
vulnerable members of each village for
a 50km stretch of coastline. KQPPDAL=@@UłAH@O0KIABA=NA@PD=P
the materials distribution, asking the
the large labour force needed for the
In the areas affected by the wind local Rotary Club to work with the
immediate construction of concrete
alone, many of the materials from villages to select 20 of the most vul-
housing would divert efforts from the
the destroyed houses were still lying nerable households from each village,
agricultural efforts and, in doing so,
nearby. About 90% of the surviving according to agreed-upon criteria.
block long-term recovery. Therefore,
population very quickly built their a two-pronged strategy was advocated Land rights / ownership
own shelters using this material and and involved: Affected communities were aided
removed the need for ‘emergency’ on their customary locations, although
shelter support. OQLLKNPEJCPDA>AJAł?E=NEAOEJPDAEN
some agencies constructed shelters in
own reconstruction, and on a schedule
In the areas affected by the tidal the early stages of the emergency in
of their own choosing, through the
wave almost all of the original housing grid patterns near the affected villages,
distribution of materials and technical
materials had been washed away, so without full consideration for land
support; and
the survivors were in need of shelter ownership questions. By December
encouraging the adaptation of
materials. 1977, the local government was
the reconstruction schedule to the
EJOEOPAJP PD=P PDKOA SDK D=@ ŃA@ PK
The local government distributed agricultural calendar.
the towns or cities at the beginning of
poles and palmyra thatch during the the emergency should be strongly en-
łNOPBAS@=UO
SEPD=E@=CAJ?EAOFKEJEJC 0AHA?PEKJKB>AJAł?E=NEAO couraged to return to their villages and
in later. The NGOs had started pro- Lack of capacity by the local govern-
not remain permanently in the towns.
gramming in the health and medical ment, combined with the large number
sectors, but quickly changed their focus of newly created organisations looking Technical solutions
to shelter. to help and ‘adopting’ random villages, Basic kits of traditional materials
I=@A >AJAł?E=NU OAHA?PEKJ LNK>HAI- were distributed to the communities.
The local government requested atic. Selection was also made more It was recognised that in some cases
that the humanitarian organisations complex by the fact that some commu- distribution would have to be timed to
construct pukka housing for all ben- nities were displaced into local towns take into account both the agricultural
Ał?E=NEAO =J@ KBBANA@ I=P?DEJC or large villages, but were still travelling work cycle and the time needed to
funding to all organisations who chose back to their original locations every cure the bamboo for construction.
98
Historic Shelter Projects 2008 D.6
Cuny Center
the families themselves, with technical
assistance from local carpenters. The
>AJAł?E=NEAOSANA=HOKNAOLKJOE>HABKN
shelter quality and for any adaptations
of their shelter. The NGO, and later
ARTIC, provided technical information
PDNKQCD @ENA?P łAH@ REOEPO
PN=EJEJC KB
local carpenters, the development of
Shelter design elevation showing cross-bracing booklets and posters, and in one case
The initial construction efforts consultation with the various organisa- the production of a short play to impart
were evaluated three weeks into the tions, but also produced booklets on important construction messages.
programme. Based on the evaluations, safer housing construction for local Logistics and materials
improvements and additions were distribution. Similar sets of materials were initially
made (cross-bracing and the protec- provided by the local government in
The design of the model house that
tion of the housing posts below ground PDAłNOPOP=CAOKBPDAAIANCAJ?U1DEO
PDA+$,LNKRE@A@PKPDA>AJAł?E=NEAO
level) in the guidelines and prototypes. delivery was taken over by the NGOs,
was square, with a pyramid-shaped roof
Based on the interest of a wide of a 45-degree slope to be both wind- and was augmented with the materials
range of shelter actors and the local resistant and to allow water runoff (bamboo, metal straps) necessary to
government, an Appropriate Recon- from the palmyra thatch. A ring beam make the shelters cyclone resistant.
struction Training and Information and aluminium strips to bind the joints One of the arguments for delaying the
Centre (ARTIC) was established were added to the cross-bracing. The reconstruction was that the materials
to give advice and conduct evalua- wooden posts were treated for infes- used in traditional construction were
tions for the various ongoing shelter tation and rot and were sunk 1m into strongest or best for use as construc-
programmes. ARTIC was funded and the ground. The palmyra thatch was tion materials. In the case of bamboo,
supported by a loose consortium attached to the roof using traditional this would have needed to be bought
of major INGOs and local partners. sewing methods, despite the sewing some weeks in advance and then cured
ARTIC not only worked directly in materials’ lack of great strength. before use.
Materials list
The following list shows the main
materials provided and the ones that
were of most value in the construc-
tion of adequate and cyclone-resistant
structures.
Materials
Wood posts
Bamboo bracing
Wood roof frame
-=HIUN=HA=BNKKłJCI=PANE=H
Metal binding straps
Plastic sheeting (used to protect
wood posts below ground level)
Cuny Center
Connection detail
99
Historic 0DAHPAN-NKFA?PO D.7
Before the opening of the camp !AOLEPA PDA H=PAN LKLQH=PEKJ LNAREKQO NAHEAB KLAN=PEKJO SANA JKP
1DA EJR=OEKJ KB =I>K@E= >U 3E- NA@Q?PEKJ KB PDA (D=K&!=JC ?=IL
NALA=PA@
APJ=IAOA BKN?AO EJ !A?AI>AN
PDA EJEPE=H EJ?NA=OAO EJ LKLQH=PEKJ D=@ 1DNKQCD NACEKJ=H SKNGODKLO SEPD
PDAAO?=H=PEKJKBłCDPEJC>APSAAJ3EAP- LKOA@ OARANA ?D=HHAJCAO BKN ?KJPNKH PDA?KJOQHP=JP=J@KPDANOEJ
PDEO
J=IAOA=J@(DIAN/KQCABKN?AO=BPAN KB PDA ?=ILO ,RAN?NKS@EJC =J@ I=JQ=H BKNIA@ PDA OP=NPEJC LKEJP BKN
'QJA=J@B=IEJAEJ,?PK>AN
PDA DECDPQNJKRAN J=PQNA KB ?=IL PDAłNOP@N=BPKBPDA2+% /Handbook
?=QOA@=I=OOEJŃQTKBNABQCAAO=?NKOO NAOE@AJPO?=QOA@PDA?=ILPK@AO?AJ@ for Emergencies
PDA >KN@AN EJPK 1D=EH=J@
LA=GEJC =P EJPKREKHAJ?A=J@PK>A?KIAATPNAIAHU
A?=QOA KB PDA H=?G KB OL=?A
PDA
=LLNKTEI=PAHUIEHHEKJLAKLHAEJH=PA @EBł?QHPPKCKRANJ=PPEIAO
ODAHPANO SANA ?KJOPNQ?PA@ =O IQHPE
=J@A=NHU
0AHA?PEKJKB>AJAł?E=NEAO B=IEHU HKJCDKQOAO
QOEJC I=EJHU PN=@E-
1DA 1D=E CKRANJIAJP S=O EJEPE=HHU 1DAI=OOJQI>ANOKBPDAEJŃQT=J@ PEKJ=H I=PANE=HO Ġ>=I>KK =J@ PD=P?D
NAHQ?P=JP PK DKOP PDA NABQCAAO BPAN PDALKHEPE?=HLNAOOQNAOATANPA@>UPDA #ENANAP=N@=JPS=HH>K=N@S=OQOA@BKN
A=NHUEJ?E@AJPOSDANA
NABQCAAO 1D=E=QPDKNEPEAO=J@PDA(DIAN/KQCA PDAOE@AOKBPDAHKJCDKQOAO=J@BKNPDA
SANANAPQNJA@PK =I>K@E=
PDA1D=E @E@ JKP LANIEP >AJAł?E=NU OAHA?PEKJ EJPANJ=H @EREOEKJO >APSAAJ EJ@ERE@Q=H
=QPDKNEPEAO =CNAA@ PK LANIEP ?=ILO QLKJ =NNER=H /AOAPPHAIAJP LNK- B=IEHEAO%KSARAN
PDEO@E@JKPNAIKRA
EJ JEJA HK?=PEKJO EJ PDA >KN@AN =NA= CN=IIAO =J@ PN=JOBANO EJŃQAJ?A@ PDA LNK>HAIO?=QOA@>UH=?GKBLNER=?UKN
%KSARAN
PDAU EJOEOPA@ KJ ?HKOA OAHA?PEKJKBSDKH=PANHABPPDA?=IL ?KIIQJE?=>HA@EOA=OA
?KJPNKH KB =??AOO =J@ PDA @AHERANU KB
Land rights / ownership #KNPDAIKOPL=NP
PDAH=NCANHKJC-
OANRE?AOPKPDA?=ILO
=J@KJPDA>=OE?
1D=E =QPDKNEPEAO @AOECJ=PA@ PDA DKQOAO EJ (D=K&!=JC SANA H=E@ KQP
=J@ OQLLKOA@HU PAILKN=NU J=PQNA KB
?=ILOEPA=J@PDA?=IL=@IEJEOPN=PEKJ EJ L=N=HHAH 0KIA NA@Q?PEKJ KB OL=?A
PDKOA?=ILO
=OOECJA@ EJ@ERE@Q=H LHKPO PK NABQCAAO S=O=?DEARA@PDNKQCD=ĺ?DA?GAN>K=N@
1DA NABQCAA LKLQH=PEKJ D=@ >AAJ HH NECDPO KB K??QL=J?U SANA QJ@AN- H=UKQP
SEPD >HK?GO KB KLAJ OL=?A
OARANAHU PN=QI=PEOA@ >U BKQN UA=NO KB OPKK@PK>AJKJLANI=JAJP4DAJ=HH PDNKQCDKQPPDA?=IL1DEO=HOK=HHKSA@
BKN?A@@EOLH=?AIAJP
CAJK?E@A
B=IEJA PDA ?=ILO ?HKOA@
NAL=PNE=PEKJ BKN=@@EPEKJ=HODAHPANO
EBNAMQENA@&J
=J@=NIA@EJR=OEKJ S=O OQLLKNPA@ PDNKQCD 2+>=?GA@ PDA 0=GAK ATPAJOEKJO
PDA HKJCDKQOAO
LNKCN=IIAO=EIEJCBKNH=J@CN=JPO=J@ SANACNKQLA@EJPKBKQNPKAECDPDKQOAO
,B PDA JEJA ?=ILO
AECDP SANA EJ-
LNKRE@EJCHAC=H=@RE?A =NKQJ@ OI=HH EJPANJ=H OMQ=NAO 1DAOA
PANJ=HHU ?KJPNKHHA@ @ENA?PHU >U PDA
SANA EJPAJ@A@ =O LNER=PA KQP@KKN
(DIAN /KQCA =NIU KN EPO =BłHE=PAO Standards manual
OL=?A KN RACAP=>HA C=N@AJO BKN A=?D
1DA ?=IL =P (D=K&!=JC
DKSARAN
LKHE?U =J@ OP=J@=N@O EILHAIAJ-
CNKQLEJC KB NABQCAAO )=PAN ODAHPANO
S=O PDA KJHU KJA QJ@AN ?HA=N 1D=E P=PEKJI=JQ=HS=O@N=BPA@BKNPDA2+
SANA =HOK EILNKRA@ >U >QEH@EJC PDAI
CKRANJIAJP =QPDKNEPU
=@IEJEOPANA@ >U?KJOQHP=JPO@QNEJCPDAH=OPIKJPDO
KJ OPEHPO
PK =RKE@ ŃKK@EJC @QNEJC PDA
>U PDA 2+ )A=@ANO KB PDA NABQCAA KB =J@ LQ>HEODA@ EJ @N=BP >EJ@AN
N=EJUOA=OKJ
CNKQLO LNAOAJPA@ PDAIOAHRAO PK PDA BKNI>U'=JQ=NU1DA?=ILOEPAO
?=IL=@IEJEOPN=PEKJ=PPDAKLAJEJCKB =J@ OANRE?AO L=NP KB PDA I=JQ=H D=@ Implementation
PDA?=IL AECDP EJEPE=H L=NPO BK?QOA@ KJ S=PAN 1DAKNC=JEO=PEKJ=OOECJA@=JQI>AN
=J@O=JEP=PEKJEOOQAO
=J@KJAL=NPKJ KB +$,O PK QJ@ANP=GA PDA @EBBANAJP
!QA PK PDA OEVA
OLAA@ =J@ DECD
DKQOEJC =J@ ?KJOPNQ?PEKJ &P AILD=- LD=OAOKB?=IL?KJOPNQ?PEKJ
QLCN=@EJC
LNKłHA J=PQNA KB PDA AIANCAJ?U
PDA
OEOA@ IEJEIQI JQIANE? OP=J@=N@O
=J@I=EJPAJ=J?A
QOEJCPDAI=JQ=H=O=
2+D=@PK?KLASEPD=N=LE@ATL=JOEKJ
=HKJCSEPD?HA=NHU@AłJA@FK>NKHAO=J@ CAJAN=HCQE@A1DANABQCAAOPDAIOAHRAO
KBEPOKSJOP=BB=J@PDA=NNER=HKBH=NCA
NAOLKJOE>EHEPEAOSEPDEJPDA?=IL SANANAOLKJOE>HABKNPDA?KJOPNQ?PEKJ
JQI>ANOKB+$,O
I=JUSEPDKQPLNEKN
KBPDAENKSJODAHPANO
ATLANEAJ?AEJPDAłAH@A?=QOAKBPDA &ILHAIAJPEJC=CAJ?EAOEJPDA?=IL
R=NE=>EHEPUKBPDAATLANEAJ?AKBPDA2+ SANAPK>ADAH@=??KQJP=>HAPKPDAOA Logistics and materials
=J@+$,OP=BB
=?KJOQHP=J?UłNIS=O OP=J@=N@OPDNKQCDNKQPEJA=OOAOOIAJPO 1DA>=OE?I=PANE=HOSANALNKRE@A@
DENA@PK@ARAHKL=I=JQ=HKBOP=J@=N@O QJ@ANP=GAJ >U PDA 2+ 1DA OP=PA@ PK PDA NABQCAAO >U PDA DQI=JEP=NE=J
*=JU KB PDKOA LKHE?EAO =J@ OP=J@=N@O CK=HOBKNPDAI=JQ=HSANAġ KNC=JEO=PEKJO
SANAEILHAIAJPA@=PPDA(D=K&!=JC
1KAJOQNAPD=P=HHOANRE?AOIAAP= Materials list
=J@0=GAK?=ILO
>=OE?IEJEI=HHARAHKBMQ=HEPUĢ 1DA BKHHKSEJC EO = L=NPE=H HEOP KB
After the opening of the camp 1K AJOQNA PD=P =HH OANRE?AO =NA PDA I=PANE=HO QOA@ BKN PDA IQHPEQJEP
KPD ?=ILO KLAJA@ EJ ,?PK>AN- LNKRE@A@EJ=QJEBKNII=JJANĢ ODAHPANO
+KRAI>AN =J@ MQE?GHU łHHA@ 1K LNKRE@A PDA >=OE? EJBKNI=PEKJ
PK ?=L=?EPU (D=K&!=JC ?=IL S=O Materials
JA?AOO=NU PK OQ??AOOBQHHU EILHAIAJP
EJEPE=HHU EJPAJ@A@ PK >A PAILKN=NU
2+% /OP=J@=N@OĢ =I>KKLKHAO
DKQOEJC LAKLHA SDK SKQH@ >A PDAJ 1K OP=J@=N@EOA NKQPEJAO =J@ PK -H=OPE?ODAAPEJC
PN=JOBANNA@ PK KPDAN ?=ILO
NAL=PNE- B=?EHEP=PANALKNPEJC=J@IKJEPKNEJCĢ
=PA@
KN NAOAPPHA@ EJ KPDAN ?KQJPNEAO /KLAKNSENA
1KLNKRE@A=CQE@ABKNPDKOASDK
1DA ?=IL =HOK >A?=IA = ?KHHA?PEKJ D=RA D=@ JK LNEKN ATLANEAJ?A EJ PDA 1D=P?DĠL=HI
101
Historic Shelter Projects 2008 D.8
103
D.8 Tonga - 1982 - Cyclone Isaac - Disaster mitigation Historic
Cuny Center
A clear agreement on the division of
responsibilities was drawn up between
the organisation and the village. The
organisation was to procure the
Tieing techniques Bracing techniques materials, while the village would pick
up the materials from the local depot
and would take responsibility for con-
struction.
One challenge involved ensuring
that the villages understood what the
materials would be used for. This issue
became more central in villages where
Cuny Center
the leadership structures were not
clear.
Disaster mitigation strategy
The studies and the illustrated guide-
Preventing uplift due to strong winds Preventing uplift due to strong winds lines were made available to the
Tongan government. Other consult-
ants developed similar illustrated
guidelines that were published as sup-
plements in a local newspaper.
Logistics and materials
Cuny Center
104
D.9 0Q@=J KJŃE?P-H=JJA@?=ILO Historic
ABKNAPDAEJŃQT
1DANA D=@ >AAJ KJCKEJC ?KJŃE?P
between the Ethiopian government
=J@ NA>AH CNKQLO łCDPEJC BKN EJ@A-
pendence for the provinces of Eritrea
and Tigray since the 1970s. Many
NABQCAAO BNKI PDA ?KJŃE?P IKRA@ PK
0Q@=J!QNEJC
PDA?KJŃE?P
combined with drought across many
countries in Africa to create a major
famine. There were no early warning
programmes or adequate stockpiles
until after September 1984.
ABKNA
OQBł?EAJP BKK@ D=@
been supplied into Tigray from Sudan.
Cuny Center/UNHCR
By mid-1984 the Relief Society of
Tigray, a national civil relief organisa-
tion, stated that the famine had reached
crisis levels and that they would lead
Tigrayans out of Tigray and into Sudan,
where they could receive aid.
Initial camps in Sudan were
sometimes located adjacent to the Block plan
sites of older permanent refugee set-
tlements. In early December 1984, 0AHA?PEKJKB>AJAł?E=NEAO arrivals from each village.
it was realised that there were not There was no selection per se. As This cluster, block and sector
enough water resources for these the refugees arrived in the camps in hierarchy was derived from the
camps. A decision was taken to look more or less intact village groups, it Handbook for Emergencies, which had
for sites that would support larger was possible to work with the village been made available two years before
numbers of refugees. Even then, not leaders and social structures to identify PDA ?NEOEO 0Q@=JOLA?Eł? RANOEKJ KB
all camps had adequate clean water for vulnerable members. PDAD=J@>KKGOLA?Eł?S=O?NA=PA@
many months. Waterborne disease, Land rights / ownership As the main emphasis was placed
alongside measles and malnutrition in There were no permanent land on water supply, sanitation and the
new arrivals, became the chief cause of rights given to refugees. In fact, the logistics of food and medicine, the
death in the camps. government of Sudan insisted that basic shelter was often a traditional
Although the Sudanese had new refugees would not be granted tukul tent made out of branches,
welcomed hundreds of thousands of permanent residency. although there were some distribu-
refugees for resettlement from Ethiopia Technical solutions tions of other shelter materials. The
over the previous two decades, the Once decisions had been made to government’s insistence that the
O?=HA KB PDA JAS EJŃQTAO
=J@ PDA transfer some of the refugees from in- camps were to be short term often
fact that Sudan itself was suffering a adequate camps, the new camps were prevented the use of any more durable
drought, caused a reversal of policy in set up following a hierarchy of blocks shelter materials, even if the resources
the Sudanese government. Even when of buildings. This started with a cluster had been available.
this decision was overturned, the gov- of shelters based on the size of each Implementation
ernment indicated that they did not ATPAJ@A@B=IEHU1DAOA?HQOPANO?KQH@ The Relief Society of Tigray would
ATLA?P PDA NABQCAAO PK NAI=EJ EJ PDA be grouped together to form a block often lead the Tigrayans into Sudan in
long term. that would follow the size of a single entire village groups. In some cases,
BPANPDAłNOPEJŃQT village. A number of blocks would form the society would also participate in
NGOs began searching for suitable a sector of a camp. the transfer of groups from one of
sites for new camps. Between April Importantly, the number of clusters PDAłNOP?=ILOPK=OA?KJ@?=ILSEPD
and June 1985, 55,000 refugees were in a block was not predetermined, but better facilities.
able to return to Ethiopia. But this still was dependent upon the number of Materials
left 258,000 new Ethiopian refugees in ATPAJ@A@ B=IEHEAO ?KIEJC BNKI A=?D Pressure from the Govern-
eastern Sudan, in addition to 120,000 REHH=CAEJ1ECN=U1KPDAATPAJPLKOOE>HA
ment of Sudan meant that use of any
Chadian refugees in the west of the services such as health units and sup- ‘permanent’ materials was avoided.
country, 700,000 ‘old’ Ethiopian plementary feeding centres were de- Although there were distributions of
refugees and increasing numbers of in- centralised throughout the camps. plastic sheeting, many of the refugees
ternally displaced Sudanese. Space was left in each block for late
106
Historic Shelter Projects 2008 D.9
Cuny Center\UNHCR
there were some severe delays in the
provision of materials, but these were
caused by poor pre-planning, lack of
stockpiling and internal organisational
issues, as much as by lack of physical
infrastructure.
Sector plan
107
Annex -
108
Shelter Projects 2008 Annex
Further reading
Key shelter-related documents
Websites
www.humanitarianreform.org
The home page of the project to establish clusters as a coordination mechanism. Includes the Emergency Shelter Cluster and Early
Recovery Cluster home pages, which contain further reading on the cluster approach as well as on technical issues.
www.reliefweb.int
Up-to-date information on complex emergencies and natural disasters, as well as an archive of information, field reports and
situation reports from emergencies since 1996.
http://ochaonline.un.org
1. UNDRO Shelter after disasters
2. Transitional settlements
3. Guiding Principles on Internally Displaced.
Corsellis, T. and Vitale, A. (2005). Transitional Settlement: Displaced Populations, Oxfam Publishing, United Kingdom.
Guidelines aimed at strategic planners and implementers of settlement responses. Considers settlement options for displaced populations.
Available online: www.shelterlibrary.org
IFRC/Oxfam (2007). Plastic sheeting: A guide to the specification and use of plastic sheeting in humanitarian relief.
A guide to the use and specification of plastic sheeting in humanitarian operations.
Available online: www.plastic-sheeting.org
Norwegian Refugee Council/The Camp Management Project (2008). The Camp Management Toolkit.
A comprehensive field manual for camp management agencies and stakeholders involved in camp operations.
Available online: www.nrc.no/camp
The Sphere Project (2004). The Humanitarian Charter and Minimum Standards in Disaster Response.
Sets out what people affected by disasters have a right to expect from humanitarian assistance. Includes shelter and settlement
planning, with standards, indicators and checklists.
Available online: www.sphereproject.org
UNDRO (now UN/OCHA) (1982). Shelter after Disaster: Guidelines for Assistance.
Guidelines and description of shelter provision in all aspects of natural disasters, from preparedness to reconstruction.
Available online: www.sheltercentre.org (www.reliefweb.int/library/documents/2003/undro-shelter-jul82.htm)
UN/OCHA (2008). Transitional Settlement and Reconstruction after Natural Disasters, field edition.
Guidelines aimed at strategic planners and implementers of settlement responses. Considers settlement issues for people affected by
disasters as well as assitance methods to support them in their reconstruction.
Available online: www.shelterlibrary.org
109