a. Design the Shrinkage sheet using the following parameters 5 Marks 8.5 hour shift One 30 min Meal break Two 15 min Tea Break 50 Hours Paid training per year 60 Min weekly Outbound 10 holidays 8 Sick leaves 24 Paid Leave b. Using the Shrinkage determined in Part a and the following parameters determine the FTE Requirement: 5 Marks Working window: 24 by 7 Contact Type : Email Service Level :7 Day TAT (Working Days) AHT: 2363 Sec Weekly Volume 14364 Calls Occupancy: 85%
c. Design the Shrinkage sheet using the following parameters 5 Marks 9 hour shift One 45 min Meal Break Two 15 min Tea Break 15 min daily briefing 30 min weekly Coaching/Feedback 8 holidays 10 Sick leaves 32 Paid Leave
d. Using the Shrinkage determined in Part a and the following parameters determine the FTE Requirement & Projected Service Level: 10 Marks Working window: 24 by 7 Contact Type : Calls Service Level :95% in 20 Sec (Daily) AHT: 200 Sec Weekly Volume 115687 Calls Consistent Shift Start Team Size 10 Consecutive Weekly OFF Arrival Patter Attached Along with Erlang add-in. Test Scenario.xlsm
2. Draw the learning curve for following hiring with defined assumptions: 8 Marks a. Hiring
b. Training & LC Weeks
c. Throughput
d. Learning Curve
e. Base AHT 600 Sec Sample
3. Calculate following basis attached raw data: 8 Marks a. AHT (Weekly/Monthly) b. Service Level (Weekly/Monthly) c. Offer Rate(Weekly/Monthly) d. Absenteeism for Production Agents(Daily/Weekly/Monthly) AHT SL OFFER.xlsx Absenteeism.xlsx
4. Calculate the absolute & percentage impact on Capacity and revenue loss for following scenario: 6 Marks
a. Break+Trng Shrinkage of 18% b. Absenteeism of 17.5% c. Both of above together
Revenue Loss Calculation (Billing on Actual AHT, Per minute rate is $ .55)
Section B : Live Bean 1. Define WFM. Write the 4 basic capabilities of WFM. 2 Marks 2. Name 3 basic types of manual forecasting techniques 2 Marks 3. Name 2 main components for calculating agent workload 2 Marks 4. Name 3 one word terms which you think affects or is important for adherence 2 Marks 5. Name 2 different types of planned and unplanned absenteeism 2 Marks 6. Name 2 prime key Erlang C assumptions. 2 Marks 7. Match the following terminologies with the following statements:- 2 Marks (AHT, Shrinkage, Occupancy, SL, ASA, RTA) a. X % of calls answered in Y seconds b. The time for which people are paid during which they are not available to handle calls. c. Talk time + after call work time + hold time d. Real time management process for tracking and analysis e. The average delay of all calls averaged together including the calls that experienced no delay f. Percentage of time an agent is actually involved in call handling during the hour versus sitting in the idle state waiting for a call 8. Identify the following phrases falls in which of the two groups:- [full timers; part timers; contact staff; temporary staff; hours of operation; budgetary constraints; consistent shift start time; staggered shift start time; split weekly offs; consecutive weekly offs] A B Scheduling Limitations Scheduling Leverages
2 Marks 9. Which one of the following is not true about under-staffing implications:- 2 Marks a. Poor service to customers b. Lost revenue c. Lower productivity/occupancy d. Over worked staff
10. The two prime components of time series forecasting technique are:- 2 Marks a. Call volume and time b. Trend and seasonality c. Moving and weighted averages 11. The following makes the call centre staffing unique:- 2 Marks a. Random call arrivals b. Invisible queue c. Service expectations d. All the above 12. Calculate the weighted AHT of Queue X which has Group A and Group B types of calls Group A : 300 calls; 550 sec AHT Group B : 250 calls; 510 sec AHT 2 Marks 13. Calculate how many agents we require to schedule when the process requirement is of 90 FTEs and the expected shrinkage is 19%. (show formula along with answer) 2 Marks 14. If .240 is the annual trend what will be the monthly forecast trend rate? 2 Marks 15. Study the following data table and calculate daily forecast when the weekly forecast is 3689 calls. 2 Marks Mon Tue Wed Thu Fri Sat Sun Total Avg. Daily Total 330 353 345 318 383 289 269 2287
Section C : Excel
1. Create 2 levels of Dependent List basis raw data available in Sheet1 (Location, Process & Queue). 3 Marks 2. Transpose Data in Sheet2 using Indirect () & Transpose(). 3 Marks 3. Create a self expanding Validation list using Offset () (Sheet3). 3 Marks 4. Vlookup & Match Combination to pull value (Sheet4). 3 Marks 5. Vlookup, Match & Indirect Combination to pull value (Sheet5). 5 Marks 6. Find Duplicate Records using Countif () (Sheet6). 3 Marks 7. Fetch Unique records (Sheet6). 3 Marks Excel.xlsx