Você está na página 1de 1

Nu Flows unique nondestructive pipe lining technology was the solution the customer was looking for.

Our international partner, Nu Flow Ireland, rehabilitated a failing rainwater pipe underneath a popular
stadium at a fraction of the cost and time a traditional repipe would have taken.
Project: Use Nu Main to rehabilitate the rainwater
pipe without the need to shut down the stadium.
Customer: J. Sisk & Sons Ltd., a member of the SISK
Group and an international construction company.
Site: The Aviva Stadium in Dublin, Ireland, which
reponed its doors on May 14, 2010. With more than
51,000 seats, it is the third largest stadium in Ireland.
The original stadium (1872-2006) was the oldest
rugby union ground worldwide and oldest sports
stadium in Europe.
System: A 14 HDPE rainwater pipe that is a main
outlet for rainwater off the stands with very diffcult
access.
Problem: The rainwater pipe had problematic joints
causing blockages, back-ups and leaks. The customer
wanted to avoid cutting out and replacing the pipe.
Circumvention: If the customer had chosen a
traditional repipe, the busy stadium would have to be
shut down in order to fx the problematic areas, since
the pipe ran under the main stadium and into the
electrical supply room.
Solution: Nu Flow gained access above the electrical
room and was able to clean and fully reline the
problematic area within the pipe using a custom made
Nu Main liner. Nu Flows technicians carried out the
rehabilitation, saving the requirement of a costly
shutdown or repipe. The customer was pleased to
have found Nu Flows pipe rehabilitation solution that
fxed the problem in a fraction of the time, cost and
disruption to a tradition repair.
When we frst came across
this issue, our main fear was for
the electric supply room which
distributes all power to the areas
required within the stadium. Also,
being such a busy stadium for sports
and conferences, logistically to try
and cut out and replace this pipe
was a major problem. Thankfully
we came across Nu Flow and with
their knowledge and expertise, a
solution was found and concluded
at a fraction of time, costs and
disruption.
- Sean Farrell, Building Services Engineer,
J. Sisk & Sons Ltd.
Costly Shutdown Avoided for Aviva Stadium in Ireland
Where life interacts with infrastructure.
North America: 1-800-834-9597 | International: 1-905-433-5510
info@nufowtech.com | www.nufowtech.com

Você também pode gostar