Locate unit on distance more than 10m from the well Shut in Master valve on a Christmas tree Shut in valve on gas or oil line from the well Take off the plunge from the Christmas tree Install wellhead adapter Install jean-beam on the Christmas tree and anchor Remark: place jean-beam on the opposite side of slickline unit Install transmission system for the rig up of raisers and pull out sequences of jean-beam and anchor them Assemble the whole BOP composition planned for the test above Christmas tree and check it on the attested pressure The test must take at least 15min Unwind the wire from drum and pass it through slickline stuffing box Before RIH check the well using the available weight to the depth of memory gauge test Remark: The well must be absolutely clear to the depth of the test If the well is not clear the instrumentation must be carried out Connect the string with wire according to the instruction NG3021045 String design must be according to the wellhead pressure Rig up BOP composition with the string in and mount it on the Christmas tree Ratify ZERO for the string Open the Master valve slowly to provide equalization pressures in the well and BOP equipment above the Christmas tree Conduct PT test according to the deigned program
Version 3.1 Prepared by Milan Ivic Well Testing Engineer Date: 11/08/2008 P/N 0318.0000
AFTER THE TEST
After the test ends POOH the string into the BOP composition Remark: The whole string must be above BOP preventer Shut the Master valve Open the bleeding valve on raiser and bleed off the pressure Disassemble the whole BOP composition on the ground after disconnection from the Christmas tree Cut 1.5m from the end of wire Uninstall jean-beam and pick up the whole equipment Leave the rig site in the state as it was before the test