TEST SCHEDULE
Document No TD/ENG/NIB-Broadband/Multiplay/TS
No of Pages. 18
Issue No. 01
No of Pages:
Issued by:
D fI
INDEX
Multiplay Network Diagram Page 2
PART A- GENERIC TEST SCHEDULE Page 3 - 9
1. PRE-SWITCH ON TESTS Page 3-4
2. POST-SWITCH ON TESTS Page 5 to 7
2.1 CHECK OF BROADBAND NETWORK GATEWAY Page 5
2.3 CHECK OF RPR LAN SWITCH (T-I & T-II) Page 6
Page - 1 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Abbreviations
• Core Components
– BNG (Broadband Network Gateway)
– RPR (Resilient Packet Ring)
– OC LAN (Other City LAN)
• Access Components
– DSLAM
– CPE
Page - 2 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Page - 3 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Software CDs
16. Check for A/T of Transmission Refer relevant EI Ensure that the media is
media to be used A/Ted. Obtain certificate
from the Installer.
Note: The BOM verification of all the network elements including Servers, UPS, Battery in the
nonvalidation sites viz Noida, Chennai also needs to be carried out as part of the AT schedule.
Page - 4 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Page - 5 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
SL GUIDELINES/Expected
NAME OF TEST REFERENCE
NO. Results
1. Check for Redundancy for As per Annexure III
Power Supply Test No. 1
2. Check for Redundancy for As per Annexure III
Processor Test No. 2
3. Power ON As per Annexure III Printout of Boot process
Test No. 3 in hard copy or soft copy
4. Log In and Log Out As per Annexure III
Test No. 4
5. Check date and time setting As per Annexure III
Test No. 5
6. Check log details As per Annexure III
Test No. 6
7. Backup and Restoration As per Annexure III
Test No. 7
8. Check of restoration by As per Annexure III
system reboot
Test No. 8
9. Check of Alarms As per Annexure III
Test No. 9
10. Check of Software Version As per Annexure III
Test No. 10
11. System User management As per Annexure III
functions for different levels Test No.11
12. Check of proper working for GE As per Annexure III FE is Applicable only for
& FE ports Test No. 12 T-I
13. Check of working & automatic As per Annexure III Ensure that there is no
changeover of RPR RING Test No. 13 interruption of
service/traffic.
14 Test on VLAN As per Annexure III Numbers of VLAN
Test No. 14 configuration for various
services to be verify.
15 Check for MAC addresses As per Annexure III
Test No. 15
16. Checking of power levels of Refer respective
optics vendor’s manual
Page - 6 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Console Cable
BNG with
Redundant PC
Power Supply
Module
Procedure 1. Connect the BNG with the power supply units. Switch ON both
power inputs to the BNG using MCB’s.
2. Attach a PC to the management port of the BNG.
3. Ping the Management IP of the BNG from the PC.
4. Switch off one power supply of BNG, by switching off one MCB in
PDP or using the switch, on the power supply unit. Ping will not be
disturbed.
5. Switch on the power supply and repeat this process with the
other power supply as well.
Results Passed Failed
Remarks Redundancy of the Power supply Modules Tested
CARD / XCRP
CARD / XCRP PC
Console Cable
BNG
Page - 7 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Procedure
1) Connect a laptop/PC to the BNG using console
2) Login using Username and Password
3) Check the status of the Controller Cards
4) Connect the GE port of the card to the L3PE (or to PC
through Converter if Network not available)
5) Configure the BNG port with an IP Address and the L3PE /
PC with another IP of the same subnet.
6) Start a ping L3PE / PC to the BNG.
7) Using the console login issue the command “reload switch-
over” in BNG
8) The ping will continue after switch-over
Note:
Primarily XCRP in slot no 7 is master and that in slot number 8 is
slave. To test the failover mechanism use the following command:
reload switch-over
Now XCRP in slot 8 is the master and that in slot 7 is the slave.
Results Passed Failed
Switchover between the master and slave supported
Remarks
Page - 8 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Cross Cable
BNG
PC
Page - 9 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Page - 10 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Console Cable
BNG
PC
Console Cable
BNG
PC
Page - 11 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Cross Cable
BNG
PC ( TFTP
Server)
Page - 12 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Console Cable
BNG
PC
Page - 13 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Eg:
[local]Redback>context ip-dial
[ip-dial]Redback>show ip pool
Results Passed Failed
Check the IP Pools and also info like available addresses and
Remarks
reserved addresses from the pool.
CARD / XCRP
CARD / XCRP PC
Console Cable
BNG
Page - 14 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
ANNEXURE II TEST PROCEDURE FOR RPR T-I & T-II LAN SWITCH
Page - 15 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Page - 16 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
Test Item:13 Check of working & automatic change over of RPR RING
Procedure
pc1 pc2
R0_a R0_b
Page - 17 -
TECHNICAL & DEVELOPMENT CIRCLE ACCEPTANCE TESTING SCHEDUL
JABALPUR (BROADBAND MULTIPLAY)
4. Check L2 Unicast Forward state Table and query the port status
5. Observe the MAC addresses
Page - 18 -