Technical Specification
7.1.1 Type-A LAN Switch
7.8 RACK
7.8.1 Wall Mounted 12 U(21 inches Height)
Racks EIA-310-D standards
7.8.2 Floor Mounted 42 U( 72 inches Height)
Racks EIA-310-D standards
Moreover, it should contain following additional feature:
a) Separate runway for top and bottom cable runs.
b) Superior ventilation
c)At least four AC fans for cooling
d) Single front perforated doors or sealed glass door with
force cooling.
e) Duel/ single flash mount doors.
f) Sub-distribution board including ground bar, AC
distribution.
g) Vertical cable organizer, 8 cable rings.
h)PDU should have at least 8 unit C13 &2 units C19
connectivity.
7.12 Documentation
7.13.3 Training The bidder shall provide necessary training facilities to the BTCL
personnel in order to enable running the equipment purchased
under this contract.
The bidder shall provide training at BTCL premises
a) Number of BTTB Engineer : 6(six)
b) Number of minimum working days : 8 (Eight) days for
wireless control system and 10 (ten) days for server and
switch system.
c) Per diam charge to BTTB Executive : BD Taka 600 (six
hundred) per day per person
7.13.4 Maintenance The bidder at his own cost shall provide full
Support Service up maintenance support service for all equipment and
to Warranty period service covered by this purchase up to the end of
warranty period.
The maintenance support service shall cover at list (but
not limit to) the following service
1. Response in the shortest possible time during any call
by BTCL.
2. Help to solve different software and hardware problems
related to proper O&M of the equipment or
modification/ addition/ deletion of any feather/ service.
3. Advice BTCL about different aspects of O&M, system
dimensioning, expansion etc.
4. Transfer of technology to BTCL personnel.
5. This support shall only be limited to the operational and
maintenance activities. The bidder shall separately quote
for this. Repair and replacement of hardware covered by
warranty shall be included in the hardware cost.
7.13.5 Testing and Before acceptance of the install system/ equipment, BTCL
Commissioning representatives shall carryout , on site, detailed test of all
equipment to ascertain there inter-working ability with relevant
equipment of the other manufacturers, working reliability, and
concurrence to agree technical and other specifications, inventory
checking of installed equipment etc. such test shall be termed as
“Acceptances Test(AT) “ . Prior to commitment of such test, the
contractor shall submit a proposed procedure for the AT to be
subsequently passed by the Project Director. A joint team of
BTCL engineers and bidder’s engineers will do the AT.
BTCL shall start such test within one month after receipt of the
request . The bidder may , upon agreement by the both party,
offer AT for any part or part of the total work . such request for
partial AT may also be asked for by BTCL.
The bidder shall be totally responsible for arrangement of all
equipment, consumables, test gears and measuring equipment for
the AT. All cost for materials and service shall be quote and
failure to quote shall be considered that the bidder propose to
provide this service totally “Free of Charge” to BTCL.
The bidder’s engineer shall be liable to make necessary
arrangement complete any kinds of tests requested by BTCL AT
members during AT procedure .