Escolar Documentos
Profissional Documentos
Cultura Documentos
FOREWORD
Power is an essential infrastructural requirement for the overall economic development of the
country. The demand for power has been growing steadily and it is our endeavour to achieve our objective of
supplying power to all on demand by 2012, keeping in view the sustainable development needs of the
country.
On request from Andhra Pradesh Electricity Regulatory Commission, CEA has carried out a
comprehensive study and analysis of the forecasted demand for power to be adopted for the power
procurement plan of Andhra Pradesh as consultancy work. An assessment of the reserve margin and
generating capacity addition required to attain LOLP of at least 1% in the A.P. System has also been carried
out.
Andhra Pradesh has been experiencing both peak and energy shortages of varying magnitude for the
past 5 years. With a view to meet these shortages through capacity addition, the first step was to make
accurate demand projections for Andhra Pradesh. After a detailed analysis and studying of the various
alternatives it is opined that the methodology adopted by the 16th EPS Committee to forecast demand is a time
tested one giving fairly accurate results and should be relied upon to make future forecasts. 16 th EPS demand
forecasts should, therefore, be the minimum requirements for power planning. However, as a sensitivity
analysis, studies have also been carried out for demand variations of +/- 5% in both peak and energy
requirements of 16th EPS as well as APTRANSCO demand projections furnished by APERC.
The detailed Planning studies carried out by CEA indicate that besides stringent efforts towards
timely implementation of programmed 10th Plan projects, additional projects totaling to a capacity of about
1300 MW need to be identified for giving benefits during the 10th Plan. Additionally, A.P. should review
their decision and avail benefit from Neyveli Ext. and Kaiga Unit as also to continue the contract with
GRIDCO, Orissa.
I would like to place on records the excellent efforts made by Shri S. Ramar, Chief Engineer in
preparation of this Report and the excellent work done by the team of outstanding engineers - Shri M.L.
Gupta, Director supported by Smt. Neerja Mathur, Director and ably assisted by Smt. P.E. Kamala, Asstt.
Director. Excellent secretariat support has been provided by Shri Vijay Bhushan, Personal Assistant and
meritorious work has been done by Shri Jai Prakash, Draftsman in preparation of cover design as well as
general layout of the Report.
The report in the present form has been brought out due to the guidance, encouragement and
motivation provided by Shri R.V.Shahi, Secretary (Power) and Shri H.L. Bajaj, Chairman, CEA who have
been a source of continuous inspiration throughout the preparation of this Report. It is also hoped that
interaction with the APERC will also continue in future.
March , 2003
New Delhi (V.S. VERMA)
MEMBER (PLANNING)
APERC 1 CEA
Power Requirement of Andhra Pradesh
EXECUTIVE SUMMARY
APERC estimated the future demands of AP based upon the trends of past
consumption data. The Consultants of APTRANSCO had applied econometric
models for making future projections. The forecasts made by CEA in the report
of 16th EPS are based upon the most reliable and practiced End use/partial end
use techniques. The forecasts of CEA’s Electric Power Survey have stood the
test of time.
16th EPS demand projections are perspective in nature and take into account
the past consumption in various sectors, foreseeable changes in the pattern of
consumption and projected growth and surveys.
While making any demand forecast for power planning, merits, demerits,
limitations, availability of realistic data and ground realities have to be given
due consideration.
The demand met and energy consumed are restricted figures in view of
power shortages of varying magnitude in the past. Accordingly, projections
made on historical trend of past consumption without corrections for shortages
would not be a true representation of future demands.
It was brought out and agreed during discussions with APERC that the 17th
EPS studies have been started and completion of studies would take
considerable time. The present analysis of demands in AP shall be carried out
by adopting the projections of the 16th EPS.
The State of Andhra Pradesh had witnessed power shortages of varying magnitude
in terms of energy and peak load during the period 1995-96 to 2001-02.. An analysis of
energy shortages and peak deficit has been carried out up to the year 2001-02 based upon
the actual energy data during these years.
Summary of energy and peak shortages in the state of Andhra Pradesh, Southern
region and on All India basis is given below. These figures are based upon the data
APERC 2 CEA
Power Requirement of Andhra Pradesh
reported by the concerned state agencies etc. It is also very likely that the indicated
shortages are on the lower side due to various reasons including those of regulatory
measures.
Table - 1
♦ During the year 2001-02 in the state of Andhra Pradesh the energy shortages
were 8.5% with associated peak shortages of 19.9%. During the period 1995-96
to 2001-02, the State experienced energy deficit ranging from 22.1% to 6.5%
and peak deficit ranging from 26.7% to 9.3%.
♦ The Southern Region was also short of energy and power. Shortages ranging
from 20.6 to 7.4% in energy and 23.6% to 12.2% in peak demand were
experienced.
♦ The country as a whole was also short of energy and power. Shortages
ranging from 11.5% to 5.9% in energy and 18.3% to 11.3% in peak demand
were experienced.
DEMAND PROJECTIONS
Andhra Pradesh
An analysis of 16th EPS projections versus actual energy supplied and estimated
shortages during the last three years in the State of Andhra Pradesh as brought out at Table
2.10 indicate that the 16th EPS energy projections for the years 1999-2000 and 2000-01
were less by 3.54 % and 1.4 % respectively of the energy requirements and the same were
higher by 4.34% for the year 2001-02.
While comparing the 16th EPS forecasts with actual unrestricted requirements in the
system following aspects may also be kept in view:
a) The compounding average growth rate (CAGR) for the energy requirement
during period 1995-96 to 2001-02 works out to 4.68% on the basis of actual
APERC 3 CEA
Power Requirement of Andhra Pradesh
energy supplied and the estimated shortages. However during 1998-99 and 2001-
02 growth rates works out to 0.86% and 0.84% respectively over previous years.
These are not normal and are taken as exceptional. While the analysis of the
specific reasons for these lower growth rates is not under the purview of this
study, the CAGR actually works out to 6.87% if these two abnormal years are not
considered.
b) The abnormal growth in the year 1998-99 is also substantiated by the fact
that GDP growth in AP was –1.37 % in 1997-98 which would have affected the
energy consumed in the following year. The GDP growth rates in AP are in the
range of 6 to 9 % as per the information received from the Govt. of AP given at
Table 2.11. These growth rates would therefore need to be given due weightage in
case the industrial development has to keep pace with the GDP in the state.
c) It is pertinent to mention that during the year 2000-01 energy requirements
were almost matching with 16th EPS demand forecasts (1.4% variation). The
CAGR of 16th EPS is 6.44%, which is lower than CAGR of normal years.
d) Future projections therefore need to be based upon unrestricted requirement
in the system and not upon actual energy supplied as this would put serious
constraints on the future development and growth of the state.
The energy forecasted for the year 2001-02 as per 16th EPS were higher by 1.75%
for the Southern Region and by 1.22% on all India basis. In the other two years i.e. 1999-
2000 and 2000-01, sum of energy supplied and estimated shortages in Southern Region as
well as on All India basis were higher than the 16th EPS forecasts.
APTRANSCO Projections
During the year 1995-96 the agricultural sales are shown as 50% and the
same were brought down to 40% in 1996-97. This reduction in the agricultural
consumption was shifted to T&D losses in 1996-97. The T&D losses, which were
20% in 1995-96, were increased to 33% in 1996-97.
This reflects only change in the accounting of energy consumed in the AP
System and no change in the demand.
The reduced agriculture consumption which was recorded as 11757 MU in
1995-96 has been projected as 10,565 MU in 2007-08, thus showing an overall
decrease in agriculture consumption.
Analysis of per consumer agriculture consumption in 2007-08 indicates that
agriculture supply would be for 129 days per year for a period of 9 hours/day as
against informed requirement of about 180 to 200 days per year.
In view of the above analysis and the detailed methodology adopted for making
the projections by 16th EPS Committee, it is considered appropriate and prudent to
APERC 4 CEA
Power Requirement of Andhra Pradesh
adopt the 16th EPS demand forecasts for working out the power development
programme.
However, as a sensitivity analysis, studies have also been carried out for demand
variations of ± 5% in both peak and energy requirements of 16th EPS as well as
APTRANSCO projections furnished by APERC.
The above philosophy and the basis of the study was also agreed by APERC during the
discussion from 4th to 7th Feb 2003 at Hyderabad.
RESULTS OF STUDIES:
Under the 16th EPS demand projection scenario the AP System is expected
to operate at 5.81% LOLP and 2.2% ENS during the year 2006-07. In order to
achieve 1% LOLP, additional capacity of 1320 MW would be required over and
above the following programmed capacity addition during 10th Plan.
Total 4214.7
*since already commissioned
Additionally AP should review their decision and avail benefits from Central
sector stations of Neveyli Ext. and Kaiga, and continue the contract with GRIDCO,
Orissa.
5% increase in peak demand and energy requirement from the 16th EPS
projections results in worse LOLP & ENS. In this scenario the system is expected to
operate at 10.77% LOLP and 6.16% ENS during the year 2006-07. In order to
achieve 1% LOLP, additional capacity of 2200 MW would be required over and
above the programmed committed capacity of 10th Plan.
APERC 6 CEA
Power Requirement of Andhra Pradesh
A study has been carried out without the benefits of Vemagiri, Gautimi, J’
Padu Ext. and Konaseema CCGT projects and demand projections as per
APTRANSCO. This Study has indicated that up to the year 2003-04, the AP
System would have LOLP below 1 % ( LOLP of 0.78% and ENS 0.193%.).
During the years 2004-05 to 2006-07 the LOLP would be in the range of 2.2% to
3.4% and ENS in the range of 3.96 % to 7.6 %.
An analysis has been done of the expected utilisation of Vemagiri, Gautimi, J’ Padu
Ext. and Konaseema CCGT projects for different demand scenarios and considering
normative and improved outage rates for these units. The results are as follows:
Table - 2
Reduction in 1000 GWh of hydro energy would also not call for any
additional generating capacity over and above the programmed capacity of 10 th plan
on this account.
APERC 7 CEA
Power Requirement of Andhra Pradesh
RECOMMENDATIONS
16th EPS forecasts shall be the minimum requirements for power planning.
Reserve Margin of 30% in terms of rated capacity over peak demand or 29% of net
capacity would give 1% LOLP and less than 0.15% ENS for the AP system.
Possibility of advancing the schedule of commissioning of projects due in 11th Plan like
Vijaywada VII Unit (660 MW) may be seriously considered.
The decision of APTRANSCO of not utilsing the benefits from Kaiga (58 MW
allocated AP share) and Neyveli Ext.(113 MW allocated AP share) should be reviewed.
It may also not be in national interest in the long run to avoid absorption of nuclear
generation from energy security angle and to reduce the shortages under 16th EPS
demand scenario..
The APTRANSCO projections are not representative of future need based growth.
This will have adverse affect on the power development and availability programme for
AP in general and country as a whole.
It would be advised that action on all the above issues is initiated on priority so that the
commitment of the Ministry of Power, Government of India to achieve the mission
‘Power on Demand to all by year 2012’ is fulfilled.
APERC 8 CEA
Power Requirement of Andhra Pradesh
CHAPTER 1
BACKGROUND
(i) Forecasted demand for power to be adopted for the power procurement plan
of the APTRANSCO.
(ii) Assessment of reserve margin and generating capacity requirement to attain
LOLP of less than 1% in the AP System.
1.2 The material/information made available by APERC during the first meeting was
examined in the CEA and another round of discussion was held by Shri ML Gupta,
Director and Mrs. P.E. Kamala, Asstt. Director with the officers of APERC and
APTRANSCO from 4th to 7th February, 2003 at Hyderabad. The broad assumptions made
by APTRANSCO to arrive at capacity requirement corresponding to 1% LOLP, the details
of SYPCO model available with APTRANSCO and assumptions made for making demand
projections and capacity planning were discussed at length.
1.3 Based upon the information made available by APERC and APTRANSCO, studies
have been carried out by CEA and the results of the studies alongwith analysis, conclusion
and recommendations are brought out in this report.
APERC 9 CEA
Power Requirement of Andhra Pradesh
CHAPTER 2
DEMAND FORECAST
Basically two demand forecasts are available for the State of Andhra Pradesh.
2.1.1 Central Electricity Authority makes projections for requirement of electricity for
drawing up power programme in the country on regional and state level basis under a
system of periodic power surveys. The latest forecast made by CEA is as per the report of
16th Electric Power Survey Committee, September, 2000. The 16th EPS Committee was
constituted in March, 1998 and under its terms of reference detailed demand projections
were made up to 2004-05 and perspective demand was projected upto 2016-17. The
Report by the EPS Committee was submitted to CEA in December, 1999 and was finalised
on 24th May, 2000 based upon the discussions with the representatives of Ministry of Power
, Planning Commission, State Utilities, TERI etc.
2.1.2 The methodology adopted for making the demand forecast is based upon partial end
use techniques and trend analysis for various sectors/categories of consumers. The other
highlight of 16th EPS are:
• The actual data of electricity consumption and T&D losses is given up to the
year 1997-98.
• The detailed forecasts on sectoral basis is given up to the year 2004-05.
• The load mix is analyzed in terms of LT load and HT load.
2.1.4 The micro level forecast for each category of consumption prepared by the Sectt. of
the Committee for every State Utilities/licencees were discussed. In case of Andhra
APERC 10 CEA
Power Requirement of Andhra Pradesh
Pradesh, these discussions were held with the representatives of APTRANSCO before
finalisation. The projected energy requirement for the State as per 16 th EPS corresponds to
a growth rate of 6.44% per annum compounded for the period 2000-01 to 2006-07 against
the corresponding past restricted growth rate of 7.69% during 1994-95 to 2000-01.
2.1.5 The demand forecast made by 16th EPS for the State of Andhra Pradesh are given in
Table-2.1.
TABLE-2.1
DEMAND FORECAST AS PER 16th EPS
Year Energy Requirement Peak Load
GWh MW
2001-02 50493 8234
2002-03 53711 8759
2003-04 57121 9315
2004-05 60633 9888
2005-06 64486 10516
2006-07 68797 11219
16th EPS has given the actual consumption of energy in the Andhra Pradesh under
11 categories for the period 1993-94 to 1997-98. Summary of category-wise consumption
in AP is given at Table-2.2 and the graphs of growth rates in each category are given at
Graph 2.1 given below. It could be seen that there is no consistent trend of growth in the
Sectoral consumption for making projections. In view of this, any projections made on the
basis of past consumption would give wrong projections.
Table2.2
SUMMARY OF CATEGORYWISE FORCAST FOR ANDHRA PRADESH
APERC 11 CEA
Power Requirement of Andhra Pradesh
It is seen from the above analysis that in view of large variations in the growth rates in
various sectors, trends in past consumption can not be used for making future projections.
GRAPH 2.1
GRAPHS SHOWING GROWTH RATES OF ACTUAL CONSUMPTIONS IN VARIOUS SECTORS
(1994-95 TO 1997-98)
YEAR YEAR
40.0 20.0
30.0 10.0
20.0 0.0
10.0 -10.0 1994-95 1995-96 1996-97 1997-98
0.0 -20.0
1994-95 1995-96 1996-97 1997-98 -30.0
YEAR -40.0
YEAR
40.0 20.0
GROWTH RATE
20.0
10.0
0.0
(%)
0.0
1994-95
-20.0 1995-96 1996-97 1997-98
-10.0 1994-95 1995-96 1996-97 1997-98
-40.0
-60.0 -20.0
YEAR YEAR
7.0
GROWTH RATE
10.0 6.0
5.0
5.0 4.0
3.0
(%)
0.0
2.0
-5.0 1994-95 1995-96 1996-97 1997-98 1.0
0.0
-10.0 1994-95 1995-96 1996-97 1997-98
YEAR YEAR
RAILWAY TRACTION
25.0
GROWTH RATE (%)
20.0
15.0
10.0
5.0
0.0
APERC 1994-95 12
1995-96 1996-97 1997-98 CEA
YEAR
Power Requirement of Andhra Pradesh
2.2.1 A study of the Load-Mix of constrained scenario for the period 1990-91 to 2000-01
indicates that under the reforms process the share of irrigation (Agriculture) in total sales
has been brought down in one year from about 50% in 1995-96 to about 40% in 1996-97
and this quantum of energy has been transposed from sales to T&D losses as Commercial
Loss Component. Therefore, the T&D losses, which were around 20% up to 1995-96, have
been hiked to about 33% in 1996-97 and further to about 35% in 2000-01. Thus terming
the average growth rates with administrated sales figures of recent past (1996-97 to 2000-
01) as representative of future is not proper.
Thus it may be seen from the above that the agriculture consumption for the
forecasted periods by APTRANSCO is under estimated.
2.3.1 A comparison between 16th EPS forecasts and that of APTRANSCO has been made
in the table 2.3 given below. The captive demand and energy have been deducted from the
projections of APTRANSCO to bring them at par with 16th EPS forecasts.
It could be seen from the table given below that APTRANSCO projections are
lower than 16th EPS projections ranging from 5.4 % to 14.6 %.
APERC 13 CEA
Power Requirement of Andhra Pradesh
Table 2.3
There could be several methods of projecting power demands apart from historical
and econometric modeling etc. While selecting the methodology , objective of the forecast,
data base available and its spatial distribution has to be kept in mind. End-use method is
another method internationally recognised as an accurate yet mathematically simple
method of projecting power demands. This is a BOTTOM-UP exercise against the TOP-
DOWN approach of econometric method. This method does not necessarily require a
time-series data base, which is a basic necessity of other two methods, referred above. The
end-use method has also a distinct advantage of dovetailing the effect of changes in policy
decision on any particular sector of consumption. This method has been adopted and
evolved in CEA and a combination of trend and end-use method which has come to be
known as “Partial End-use Method” and is being used for forecasting State/sub-
State/System-wise power demands for the National Power Survey Committee set by Govt.
of India from time to time. This has proved to be a time tested method giving fairly
accurate forecast for a country like India where planning is being done from States upward.
It was agreed with APERC that the review of the various methodology would not
be carried out in this Report and recommendations would only be made in respect of
demand forecast to be adopted for the expansion plan of APTRANSCO.
APERC 14 CEA
Power Requirement of Andhra Pradesh
Estimates of future demands based upon past consumption has been made by
APERC. The Consultants of APTRANSCO had applied econometric models for making
future projection. 16th EPS forecasts are based upon End use/partial end use techniques.
2.4.1 Analysis of availability and shortages both in terms of energy and peak demand in
respect of Andhra Pradesh, Southern Region and All India basis is given in the Tables
below:
Table 2.4
POWER SUPPLY POSITION (ENERGY IN MU)
ANDHRA PRADESH
Table 2.5
POWER SUPPLY POSITION (ENERGY IN MU)
SOUTHERN REGION
Table 2.6
POWER SUPPLY POSITION (ENERGY IN MU)
ALL INDIA
APERC 15 CEA
Power Requirement of Andhra Pradesh
Variation of growth rate of energy requirement and Energy availability for the
period 1995-96 to 2001-02 for A.P, Southern region and all India is given in graph 2.2
Table 2.7
POWER SUPPLY POSITION (PEAK IN MW)
ANDHRA PRADESH
Table 2.8
POWER SUPPLY POSITION (PEAK IN MW)
SOUTHERN REGION
Table 2.9
POWER SUPPLY POSITION (PEAK IN MW)
ALL INDIA
2.4.2 It can be seen that Andhra Pradesh has felt energy shortages ranging from 22.1% to
6.5% in the period 1995-96 to 2001-02 and the southern region as a whole has also felt
shortages during this period in the range of 20 .6% to 7.4% . The energy shortages on All
India basis range from 11.5% to 5.9% for the same period. Similarly the shortages were
experienced in peak demand-met in AP, Southern Region and All India. A comparative
APERC 16 CEA
Power Requirement of Andhra Pradesh
chart of shortages both in energy and peak demand for the three systems examined are
given at Graph 2.3.
Graph 2.2
GR OF AP ER GR OF AP EA
10.00
16.00
9.00
8.00 14.00
7.00 12.00
6.00
10.00
5.00
8.00
4.00
6.00
3.00
2.00 4.00
1.00 2.00
0.00 0.00
1 2 3 4 5 6 1 2 3 4 5 6
8.00
GR OF SR ER GR OF SR EA
12.00
7.00
10.00
6.00
5.00 8.00
4.00 6.00
3.00
4.00
2.00
2.00
1.00
0.00
0.00
1 2 3 4 5 6
1 2 3 4 5 6 AVAILABILITY 87925
REQUIREMENT 105590
8.00
GR OF ALL-INDIA ER
GR OF ALL-INDIA EA
9.00 7.00
8.00
6.00
7.00
5.00
6.00
4.00
5.00
4.00 3.00
3.00 2.00
2.00
1.00
1.00
0.00
0.00 1 2 3 4 5 6
1 2 3 4 5 6 AVAILABILITY REQUIREMENT 389721
354045
APERC 17 CEA
Power Requirement of Andhra Pradesh
Graph 2.3
% ENERGY DEFICIT
25.0
20.0
A.P.
15.0
SOUTHERN
10.0 REGION
ALL INDIA
5.0
0.0
1995-96 1996-97 1997-98 1998-99 1999-00 2000-01 2001-02
YEAR
% DEFICIT IN PEAK
30.0
25.0
20.0
15.0
10.0
A .P.
5.0
0.0 SOUTHERN
1995-96 1996-97 1997-98 1998-99 1999-00 REGION
A LL INDIA
YEAR
The above analysis shows that country, as a whole, Southern Region and Andhra
Pradesh have experienced energy and peak shortages of varying magnitude.
APERC 18 CEA
Power Requirement of Andhra Pradesh
2.5.1 A comparison has been made between demand forecast made by 16th EPS and total
energy requirement considering the energy supplied and shortages in Andhra Pradesh,
Southern Region and All India. Details are furnished in Table 2.10. It could be seen that
during the year 1999-2000 and 2000-01 the 16th EPS energy projections for Andhra
Pradesh were lower by 3.5% and 1.4% respectively while it was higher by 4.3% in the
year 2001-02. This trend was followed in Southern Region as well as on All India basis.
Table - 2.10
SOUTHERN REGION
1999-00 125356 116358 9371 125759 7.73 -0.32
2000-01 133845 123677 10623 134300 7.59 -0.3
2001-02 142980 128095 12421 140516 11.62 1.75
ALL INDIA
1999-00 466066 450594 29836 480430 3.43 -2.98
2000-01 496266 467400 39816 507216 5.82 -2.2
2001-02 529013 483350 39187 522537 7.10 1.22
a) The compounding average growth rate (CAGR) for the energy requirement
during period 1995-96 to 2001-02 for AP works out to 4.68%. However,
1998-99 and 2001-02 are abnormal years showing growth rate of 0.86% and
0.84% over previous years. The CAGR works out to 6.87% if these two
abnormal years are not considered.
b) During the year 2000-01 energy requirements of AP were almost matching
with 16th EPS demand forecasts (1.4% variation). The CAGR of 16th EPS is
6.44%, which is lower than CAGR of normal years.
Shortages in the previous years had affected the actual growth in the last years.
Had there been adequate supply available the growth would have been maintained and the
estimated projections of 16th EPS would have been achieved. This gives strong indication
that 16th EPS projections should be used for planning to arrive at need based capacity
addition. However, scenarios corresponding to the projections of 16th EPS reduced by 5%
and increased by 5% have also been considered as a sensitivity study.
APERC 19 CEA
Power Requirement of Andhra Pradesh
2.5.3 GSDP/GDP Growth Rates of Andhra Pradesh and All India at constant (1993-
94) Prices.
The GDP growth rates of Andhra Pradesh and all India at constant (1993-94) prices
are given in the Table 2.11 below.
Table 2.11
GSDP/GDP Growth Rates of Andhra Pradesh and All India
at constant (1993-94) Prices.
From the above table it may be concluded that the GDP growth in AP was –1.37 %
in 1997-98, which would have affected the energy consumed in the following year. The
GDP growth rates in the AP may be considered in the range of 6 to 9 % which would
require same order growth of electricity.
APERC 20 CEA
Power Requirement of Andhra Pradesh
CHAPTER 3
3.1 As of date total captive power generation in the State of Andhra Pradesh using
diesel, coal and other fuels is 1313 MW. It is expected that the industrial load will be
repatriated to the grid due to incentive given by APERC in the tariff for HT industrial
consumers and the same has been considered by APTRANSCO in their projections
Currently, APTRANSCO projects its requirement considering the captive load and
captive generating capacity in the system. During the discussions held with the officials of
APTRANSCO it was noted that the capacity utilisation of captive power plants is
considered at 40% and its availability is taken as 90% for LOLP calculation. This is not
appropriate from the modelling point of view as far as considering the captive power plants
available for 90% of the time in the system. These captive power plants would by and
large meet the demand of H.T. consumers when the grid supply is not available. However,
in the above referred assumption made by APTRANSCO it gives an effect that 90% of
time the captive plants are available to meet any demand in the system restricted by hours
of operations to yield 40% capacity factor.
In view of the above, it is recommended that captive demand and captive plants
should be kept outside the simulation runs of the Andhra Pradesh system.
As per the information available during the discussions the existing bio-gas capacity
in the AP System is about 82.8 MW and 47.6 MW capacity is planned for additions in
2002-03 and 46.9 MW during 2003-04.
Though it has not been the practice to consider non-conventional capacity along
with conventional power projects for power planning but for the present studies the
benefits have been considered as these capacities are committed for benefits in the AP
system. APTRANSCO is buying power from these plants as per signed PPA’s at 70 %
PLFs.
APERC 21 CEA
Power Requirement of Andhra Pradesh
CHAPTER 4
4.2 For the purposes of these studies, EGEAS model based upon probabilistic approach
has been applied to evaluate the system performance. The two reliability indices are briefly
explained below.
Loss of Load Probability (LOLP) is defined as the average number of days or hour
over a specific period, normally a year, during which the demand exceeds generating
capacity. There is no standard value of LOLP and the targeted LOLP varies from country
to country. For example, in the United States, the targeted value of LOLP is 1 day in 10
years. In Europe, the targeted value of LOLP varies from country to country from 1 day in
1 year to 1 day in 15 years. In India, LOLP of 1% i.e. 3.65 days in a year is adopted for
regional planning to assess the capacity requirements on long term basis.
APERC 22 CEA
Power Requirement of Andhra Pradesh
Energy Not Served is the expected amount of Energy Not Supplied due to outages
in the long run and is expressed in units of energy or as a percentage of the total energy
demand during a specified period. Since two or more alternative scenarios of generation
expansion plans can have same level of LOLP but different values on ENS, a cost value is
assigned to ENS in the Objective Function called as cost of energy Not Served. Recent
value of cost of ENS adopted in the planning studies has been of the order of Rs.4 per unit.
APERC 23 CEA
Power Requirement of Andhra Pradesh
CHAPTER 5
STUDIES AND ANALYSIS
Following listed projects totaling to 4214.7 have been considered as committed for
the purpose of Studies
Total 4214.7
*since already commissioned
The total capacity available for benefits is 13060.7 MW by 2006-07 after phasing out
imports of 400 MW from Gridco, Orissa.
APERC 24 CEA
Power Requirement of Andhra Pradesh
Considering above capacities the APTRANSCO system has been evaluated for the
following four demand scenarios.
5.4.1 The results of the studies in terms of LOLP, ENS and Reserve Margin for the four
scenarios is tabulated below.
Table 5.1
SCENARIO A: 16th EPS Demand Forecast
It could be seen from above that under the 16th EPS demand projection, the AP
System is expected to operate at 5.81% LOLP and 2.2% ENS during the year 2006-07.
In order to achieve 1% LOLP, additional capacity of 1320 MW would be required over
and above programmed capacity of 10th Plan.
APERC 25 CEA
Power Requirement of Andhra Pradesh
Table 5.2
th
SCENARIO B: 16 EPS Demand Forecast reduced by 5%
5% reduction in peak demand and energy requirement from the 16th EPS projections
is expected to meet the energy requirement with less than 0.15% ENS and LOLP would
be less than 1.5% during all the years except in the year 2006-07. Since the energy
requirements are by and large met under this scenario, it may not be pragmatic to
achieve 1% LOLP by adding additional capacity. This can be achieved by demand
management.
Table 5.3
th
SCENARIO C: 16 EPS Demand Forecast increased by 5%
It could be seen from above that under the scenario of 16th EPS demand projection
increased by 5%, the AP System is expected to operate at 10.77% LOLP and 6.16%
ENS during the year 2006-07. In order to achieve 1% LOLP, additional capacity of
2200 MW would be required over and above programmed capacity of 10th Plan.
Table 5.4
SCENARIO D: APTRANSCO Demand Forecast
5.4.2 Under APTRANSCO demand projections which are about 4.6 % to 15% lower
than 16th EPS demands, the expected LOLP are much lower than 1% and ENS is also very
much below 0.15% . This shows an over expanded system.
Since the four CCGTs namely Vemagiri, Gautimi, J’ Padu Ext. and Konaseema are
operating at extremely low PLFs , following studies have been carried out by dropping
them from the capacity expansion plan and the AP system is studied again.
The scenarios have been examined when the benefits of Vemagiri, Gautimi, J’ Padu
Ext. and Konaseema CCGTs have not been considered in the system and system
performance is evaluated for APTRANSCO projections. Up to year 2003-04 the system
give LOLP and ENS at accepted levels and shortages are indicated beyond 2004-05.
Summary of results is given below:
Table 5.5
This Study has indicated that up to the year 2003-04, the AP System would have
LOLP below 1 % ( LOLP of 0.78% and ENS 0.193%.). During the years 2004-05 to
2006-07 the LOLP would be in the range of 2.2% to 3.4% and ENS in the range of 3.96
% to 7.6 %. This indicates that one of the four CCGTs can be considered.
The energy supplied by the proposed system of expansion under four load
conditions is given below. It could be seen that in the year 2006-07 the system would
supply energy of 67283 GWh under 16th EPS demand conditions and would supply 58784
GWh under APTRANSCO projections. Thus there would be about 8500 GWh which
system is capable of supplying but would go unutilized.
APERC 27 CEA
Power Requirement of Andhra Pradesh
Table 5.6
The above Table indicates that proposed generation expansion plan is also
capable of meeting any eventuality arising out of additional rural supply and shortfall in
hydro generation in the system as explained below
APTRANSCO has proposed to the APERC that its energy requirement would be higher
by 1500 GWh, due to 24 hours supply to rural areas over and above the regulated supply to
agriculture consumers.
The proposed generating system can meet this requirement and no additional
generating capacity would be required. Moreover this situation of additional rural supply
is arising only under APTRANSCO projections
APTRANSCO has estimated that hydro generation may decrease by 1000 GWh per
year on account of diversion of water upstream to Srisailam.
Reduction in 1000 GWh of hydro energy would also not call for any additional
generating capacity
The expected plant load factor of each generating unit in the Andhra Pradesh
system is given at Annexure I to IV
It could be seen that expected utilisation of some of the generating units is much below the
accepted levels and is summarised in Table 5.7.
APERC 28 CEA
Power Requirement of Andhra Pradesh
Table 5.7
PLF’s of affected generating units under various demand scenarios:
APERC 29 CEA
Power Requirement of Andhra Pradesh
From the four studies carried out as above it was seen that 1% LOLP is achieved
corresponding to 29.5% Reserve Margin and 0.97% LOLP with 30% Reserve Margin.
Thus from the above it can be concluded that Andhra Pradesh System would
require around 30% Reserve Margin to arrive at rated installed capacity of the system.
The average net capacity of the Andhra Pradesh System has been assessed as 96.5% of the
rated capacity. Thus, in terms of net capacity the reserve margin may be adopted as 29%.
This value would undergo a change if the system load factor or availability of
generating units or hydro thermal mix is drastically changed.
APTRANSCO gives the reserve margin in terms of net capacity whereas in CEA
rated capacity is used in reserve margin calculations.
APERC 30 CEA
Power Requirement of Andhra Pradesh
CHAPTER 6
RECOMMENDATIONS
6.1 16TH EPS forecasts shall be the minimum requirements for power planning.
6.2 Reserve Margin of 30% in terms of rated capacity over peak demand or 29% of net
capacity would give 1% LOLP and less than 0.15% ENS for the AP system.
6.3 Work on programmed projects to be implemented in the 10th plan needs to be taken
up immediately on urgent basis with compressed time schedule so as to achieve the
commissioning in the 10th plan itself.
6.5 Possibility of advancing the schedule of commissioning of projects due in 11th Plan
like Vijaywada VII Unit (660 MW) may be seriously considered.
6.6 The decision of APTRANSCO of not utilsing the benefits from Kaiga (58 MW
allocated AP share) and Neyveli Ext.(113 MW allocated AP share) should be
reviewed. It may also not be in national interest in the long run to avoid absorption
of nuclear generation from energy security angle and to reduce the shortages under
16th EPS demand scenario..
6.7 The APTRANSCO projections are not representative of future need based growth.
This will have adverse affect on the power development and availability programme
for AP in general and country as a whole.
6.9 It would be advised that action on all the above issues is initiated on priority so that
the commitment of the Ministry of Power, Government of India to achieve the
mission ‘Power on Demand to all by year 2012’ is fulfilled.
Annexure - II Page 1 of 46
Annexure - II Page 3 of 46
APERC xl CEA
Power Requirement of Andhra Pradesh