Escolar Documentos
Profissional Documentos
Cultura Documentos
CLIENT:
JOB:
HALDOR
TOPSOE
I-MA-9525.05-5124-000-TPI-001
UFN - V
1500 MTPD AMMONIA PLANT
AREA:
5124
TITLE:
SHEET
C.C.
1 of
55
9525.05
GE-PGI/IETQ/IEUFN-V
INDEX OF REVISIONS
REV.
FIRST ISSUE
FINAL ISSUE
REV. 0
REV. A
REV. B
REV. C
REV. D
REV. E
REV. F
REV. G
REV. H
DATE
16/11/11 20/01/12
DESIGN
UNF V
UNF V
EXECUTION A.D.M.
M.C
CHECK
A.A.
A.A
APPROVAL
A.M.
A.M.
THE INFORMATION CONTAINED IN THIS DOCUMENT IS PETROBRAS PROPERTY AND MAY NOT BE
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
2/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
THIS FORM IS PART OF STANDARD PETROBRAS N-381 REV. J ENGLISH ANNEX A SHEET 01/08
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
3/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
20/01/2012
16/11/2011
REV.
DATE
STATUS
M. CARINCI
A.ALTAMURA
A.MAGARINI(L.DE GAETANO
A.DE MICHELE
A.ALTAMURA
A.MAGARINI(L.DE GAETANO
WRITTEN BY
(name & visa)
CHECKED BY
(name & visa)
APPROV./AUTHOR. BY
(name & visa)
DOCUMENT REVISIONS
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
4/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
INDEX
1
INTRODUCTION...................................................................................................5
1.1
1.2
PROCESS DESCRIPTION...................................................................................8
2.1
2.2
2.3
Design Condition................................................................................................10
Cooling Water System........................................................................................10
Control and Interlock Description........................................................................12
3.1
3.2
3.2.1
3.2.2
3.2.3
3.2.4
3.2.5
3.2.6
3.3
3.3.1
3.3.2
3.3.3
3.3.4
3.3.5
3.3.6
3.4
3.4.1
3.4.2
3.4.3
General............................................................................................................... 14
General plant inspection.....................................................................................14
Equipment inspection and cleaning....................................................................15
Piping Inspection................................................................................................19
Electrical Equipment Inspection.........................................................................20
Instrumentation Preparation...............................................................................21
Heating, Ventilation Air Conditioning Equipment................................................21
Telecommunications...........................................................................................22
Cleaning of Piping and Equipment.....................................................................22
General............................................................................................................... 22
Water Flushing...................................................................................................23
Air Blowing..........................................................................................................24
Steam Blowing....................................................................................................25
Chemical Cleaning.............................................................................................25
Lubrication Systems Flushing.............................................................................25
Leak Test............................................................................................................ 25
General Procedure.............................................................................................25
Tightness Test.....................................................................................................26
Leak Repairs / Tightening...................................................................................26
NORMAL START-UP..........................................................................................27
4.1
4.2
4.2.1
4.2.2
4.2.3
Start Up Preparation...........................................................................................27
Start Up Sequence.............................................................................................27
Main operation:...................................................................................................27
Operating description.........................................................................................28
Start-up of cooling water system........................................................................29
5.1
5.2
5.3
5.4
5.5
General............................................................................................................... 31
Feedstock...........................................................................................................31
Products............................................................................................................. 31
Process Variables...............................................................................................31
Analytical procedures for sampling.....................................................................32
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
5/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
6.1
6.2
6.2.1
6.2.2
Shutdown Preparation........................................................................................33
Shutdown Sequence (cold shutdown)................................................................33
Main operation:...................................................................................................33
Operating Description:........................................................................................33
7.1
7.2
7.3
7.4
7.5
Power failure.......................................................................................................35
Instrument Air Failure..........................................................................................36
Presence of Hydrocarbons.................................................................................36
Presence of Ammonia........................................................................................36
Excess of Chemical............................................................................................36
PLANT SAFETY.................................................................................................38
8.1
8.1.1
8.1.2
8.1.3
8.1.4
8.2
8.2.1
8.2.2
8.3
8.3.1
8.4
REFERENCE DOCUMENTATION......................................................................53
9.1
9.2
9.3
9.4
9.5
9.6
9.7
PFD.................................................................................................................... 53
PID...................................................................................................................... 53
Basis of Design...................................................................................................53
Data Sheets........................................................................................................54
Cause and effect Diagrams................................................................................55
Interlock Narrative...............................................................................................55
Fire and gas Layout............................................................................................55
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
6/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
INTRODUCTION
This operating instruction manual outlines the principles of operating the Cooling
Water System (UNIT 5124 OSBL) for the 1,500 MTPD ammonia plant UFN-V of
Petrobras, in Uberaba, Brazil.
Special attention has been paid to the principles of start-up, normal operation and
shutdown (normal as well as emergency shutdowns).
This manual should be used as the basis for the establishment of detailed operating
instructions, which should be prepared as part of the detailed engineering.
The Cooling Water System includes all the equipment required to produce and
distribute cooling water to the users of Nitrogen Fertilizer UNIT V (UFN V). This
system consists of an Open Circuit
Cooling Water System through which the hot cooling water return from the users is
cooled by a induced draft Cooling Tower.
The objective of this system is to provide the Plant with an uninterruptible supply of
cooling water to cool streams in the process, utilities & offsite units.
Equipment No.
B-5124001 A/B/C/D
Equipment description
Cooling Water Pump
B-5124002 A/B
BBC-5124001
TR-5124001
Cooling Tower
UQ-5124001
UQ-5124002
UQ-5124003
UQ-5124004
UQ-5124005
UT-5124001
Process Theory
The objective of this system is to provide the Plant with an uninterruptible supply of
cooling water to cool streams in the process, utilities & offsite units.
The Cooling Water System is normally fed by filtered water coming from Dual Media
Filtration Package (UT-5121002) via Cooling Water make-up Pump (B-51210013A/B)
as make-up of Cooling Water Circuit
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
7/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
8/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Emergency Diesel Generator will supply power to Emergency Cooling Water Pump in
case of power failure.
Cooling Tower Basin (BBC-5124001)
The Cooling Tower Basin (BBC-5124001) is divided into three main sections:
the first one is located below the cells and it has the function of receiving the
water dripping from the cell packing. It is provided with partitions for independent
operation of the cells (a sluice gate allows the isolation of each cell for
maintenance during the operation of the remaining ones);
the second one collects the water coming from all the cells, routing it to the
suction bay of the pumps;
the third section represents the suction bay of the Cooling Water Pump
(B5124001A/B/C/D) and Emergency Cooling Water Pump (B-5124002A/B)
The suction bay is deeper than the rest of the basin to guarantee optimal
hydraulics of the pumps; a pair of suction screens will be provided at each
entrance of the pumping bay to prevent access of suspended material into the
system.
The Cooling Tower make-up will be sent to Cooling Tower Basin (BBC-5124001)
and the flow is automatically adjusted to maintain a constant water level inside
basin.
The design of the pump suction basin shall be in accordance with the
recommendations of Hydraulic Institute Standards (HIS).
Chemical Dosing Packages (UQ-5124001/5124002/5124003/5124004/5124005)
The Cooling Water will be chemically treated to protect the equipment from scale and
corrosion and to avoid bacteriological growth: chemical treatment will be performed
and optimized by Chemical Supplier based on cooling water characteristics.
The chemicals receiving, storage and handling area will be located on a paved area
provided with a shelter and partial walls for direct sunlight protection. The paving shall
be foreseen with anti-acid covering and curb: curbs dimension shall be adeguate to
contain the largest chemical storage inventory.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
9/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
PROCESS DESCRIPTION
The Cooling Water System is an Open Evaporative Circuit: the cooling tower is
induced draft counter flow type. The cells are installed on top of the common Cooling
Tower Basin in-line configuration.
The Cooling Tower is used to reduce the temperature of the cooling water return by
the mechanism of evaporating cooling and the exchange of sensible heat. Return
water will be distributed in the cooling tower where it will fall through the fill and cool
by evaporation.
Induced draft will be achieved by fans, which will move air through water to promote
evaporation.
The discharge air exits the top of the cell.
Drift eliminators will be provided to minimize liquid water carry over and prevent from
fallout around the tower itself. The Cooling Tower drift eliminator will be designed to
limit drift load to a maximum of 0.005% of the design cooling water flow rate to limit
water losses.
Cooled water is collected under the tower in a concrete basin (BBC-5124001) which
collect the water from all the cells and routes it to the suction buy of the pumps. Each
pump has an independent suction pit interconnected to the common, which has an
opening provided with two (2) screens. The screens, in series arrangement, will allow
the first screen to be cleaned while the other one will be in line. Suitable access
facilities and manual lifting device will be provided to enable the screens to be
cleaned outside the cooling water pumps basin.
Normally the Cooling Water Basin is drained to Rainy Sewer; in case of NH 3
contamination the basin draining shall be diverted to Oily Sewer.
Make-up water, replacing system losses (evaporation, drift losses and blow down), is
composed of filtered water coming from Cooling Water Make-up Pump (B-5121013
A/B),boiler blow down coming from Unit 5131, condensate from CO2 Compressor and
Air Compressor Inter stage from Unit 3211. The minimum liquid level (LL) in the
cooling towers basin will be sufficient to provide cooling water pumps flooded in all
conditions.
As evaporation occurs, dissolved solids build up in the water. By removing blow down
and adding filtered water as make-up water, the dissolved solids level in the water can
be maintained and the cycles of concentration can be controlled.
Blow down flow depends on conductivity level in the circulating cooling water and is
controlled with
Blow down control valves. Blow downstream is normally sent to Rainy Sewer.
Four (4) horizontal centrifugal (three main, one spare) Cooling Water Pump (B5124001 A/B/C/D) allow water circulation in the Cooling Water Supply circuit; while the
Emergency Cooling Water
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
10/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Pump (B-5124002A/B) guarantee the cooling water supply to the critical machines
inside the Plant during normal operation and in case of power failure. Cold water
recirculation line is provided on the common discharge of the Cooling Water Pump in
order to run the pumps at their rated point independently from the cooling water
request of the Plant, spilling back water into the common section of the cooling tower
basin.
The Side-stream Filters (UT-5124001) are provided to reduce the suspended solids
in the circulating water so reducing also the chemical consumption and the suspended
solids in the circulating water; they are fed from the discharge line of the Cooling
Water Pumps (B-5124001 A/B/C/D) and are designed to treat a portion of the design
circulating cooling water flow. Filtered water coming from the package is sent back to
the common section of the tower basin.
Side Stream Filters will be self-cleaning siphon type and the effluent coming from the
backwashing will be collected into a dedicated basin from which the effluent shall be
sent to Rainy Sewer together with blow downstream.
To avoid biological growth, to protect the equipment from scale and corrosion
phenomena and to adjust the pH if necessary, the Cooling Water will be chemically
treated:
The injection of these chemicals is made through a deep pipe directly in the common
section of the Cooling Tower Basin.
The chemical dosage control will be performed through an automatic control system.
The packages UQ-5124001/5124002/5124003 are composed by a Porta-feed and
two dosing pump to inject the chemicals.
The packages UQ-5124004/5124005 will receive chemicals from centralized storage
system:
sodium hypochlorite make-up feed will be sent from Unit 5121 by means of B5121016A/B;
sulphuric acid make-up feed will be sent from Unit 5128 by means of B5128003A/B.
The main characteristics of the circulating cooling water are continuously monitored
through in-line analyzers: pH, conductivity, free chlorine and turbidity analyzers are
installed in the cooling water return.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
11/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Design Condition
The design of Cooling Water System shall be consistent with the overall plant
operating scenarios.
The design shall ensure the continuous supply of the produced streams in quantities
adequate for normal and abnormal operating conditions and also maintaining stable
product quality.
T
[C]
8.3
10
8
10
10
Feedstock characteristics:
The filtered water, used as make-up of Cooling Water, will be available with the
following characteristics:
Filtered Water (1)
Normal
Design
Pressure [kgf/cm2]
3.8
Temperature [C]
31
70
(1) Filtered Water as product water from Dual Media Filtration Package (UT-5121002).
Component
pH
TSS [mg/L]
Normal
Maximum
7.35 (1)
Calcium
12
Magnesium
15
14,7
Sulphates
18
Chlorides
19,7
Bicarbonates
- della Magliana,
Silica
(as SiO2)
[mg/L]
13 68
TECHNIP
ITALY S.p.A.
- 00148
ROMA - Viale Castello
Free Chlorine
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
12/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
In the Cooling Water Basin will be also routed the following streams:
STREAM
Boiler Blowdown
Condensate from
CO2 Compressor
Condensate from
Air Compressor
Condition
Normal
Design
Normal
Design
Normal
Design
Pressure [kgf/cm2]
1.5
3.5
1.5
1.5
3.5
Temperature [C]
50
155
41
70
41
70
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
13/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
b)
Product characteristics:
Cooling Water characteristics, at Unit 5124 battery limits, are the following:
Norm.
Design
Cooling Water
Return
Norm.
Design
Pressure [kgf/cm 2]
(1)
Temperature [C]
31
70
Temperature [C]
41(4)
70
Ph
HOLD (3)
TDS
[mg/l]
500600
TSS
[mg/l]
50
(1)
(2)
(3)
(4)
5124-LIC-0001
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Logic
Block
Description
I-001
I-002
I-003
I-004
I-005
I-006
I-007
detected
Action
open 5124-XV-0007
Rev.
Page
14/56
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
15/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
16/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
3.2.1
General Inspection
A general inspection of tanks, vessels, drums, columns, reactors and exchangers
is made against the design drawings soon after erection. This check includes:
c.
Check that relevant lines and expansion joints are free to move in all
directions. Be sure shipping stops are removed on the expansion joints if any.
Check that the platforms and other structures will not interfere with the free
expansion of the equipment in any direction.
Check that instrument piping, electrical conduit and other equipment are in no
danger of bending.
Internal Inspection
Tanks, vessels, drums and columns will be inspected internally.
The bottom manhole should be left open in case tools or other materials are
accidentally dropped down.
Check that no scaffolding or trash remains in the vessel.
Internals must be inspected carefully and checked against the designs
documents to ensure that the installation was properly carried out. This check
should include:
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
17/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
d.
Cleaning
All tanks, vessels, columns, drums, basins, reactors, etc. have to be inspected
and cleaned if required, before final closure, boxing-up.
The final cleaning is witnessed by the precommissioning team, especially if the
relevant vessel has been integrated in a cleaning sequence.
In such case, it is normal practice that the equipment is finally closed/boxed-up
after inspection.
When the vessel is used as "collecting device", it must be finally closed only after
cleaning.
Vessels cleaning is normally done through different ways according to the
equipment materials and vessels service.
Equipment internal materials generally are the following:
Carbon steel;
Stainless steel;
Carbon steel lined with different coating material.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
18/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
f.
g.
h.
Final Inspection
After hydrotest, cleaning and dry-out as required, a final vessel inspection should
be done. When vessels have been shop-tested, they will not be further tested in
the field but may be included as part of a piping system test.
Carefully inspect for cleanliness. After the final inspection, immediately close,
after mutual agreement on "final closure / boxing-up" document.
Caution:
Before entering a vessel, the plant safety precautions should be observed. These
include sampling of vessel internal for toxic vapours and oxygen concentration,
wearing a safety harness and having an attendant outside the vessel. AN
UNATTENDED VESSEL SHOULD NEVER BE ENTERED.
Pumps
a. Initial Checking
The most critical period in the life of a pump is during its initial start and several
minutes immediately thereafter. Proper installation and start-up is essential for
trouble-free performance. Before the equipment is ever started it should be
checked as follows:
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
19/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Verify that bearings shafts are clean and properly lubricated. All bearings
should be flushed clean and the correct lubricant in the proper quantity must
be provided. Records for type of lubricant used and date of lubrication follow
up will be recorded;
Temporary strainers are provided for the suction of each pump to be installed
on the pump side of the suction block valves. These strainers should be
installed after the suction lines are flushed. These should be cleaned
frequently to keep lines free of foreign matter. The strainers should be
cleaned frequently by alternating pumps where possible. Except on severe
services which may require installation of fine mesh on both pumps A and B,
it is normally sufficient to equip only one pump with fine mesh (on all "A"
pumps for instance).
Consequently, the "A" pumps will be the ones preferentially started during
initial start-up. Then when temporary strainers are not anymore required they
should be removed and only the permanent strainer installed to prevent
further possible pump damage;
Pumps are not field hydrostatically tested.
b. Running Tests
When piping systems are sufficiently complete, means that a system or subsystem can be released from construction activity to precommissioning activity for
dynamic operations; some pumps will be put into operation to determine whether
they are in good mechanical condition and to verify proper installation of support
systems and test running. Keep in mind that medium other than the design fluid is
not always possible. Typical example is the case for LPG pumps when use of
water leads to adverse effect that may damage mechanical seals and introduce
water in the system where drastic drying is being implemented before start-up.
The circulating fluid for pump test running, when applicable, is often water. Due to
differences in specific gravity between water and the design fluid care must be
taken not to overload the motors on motor driven pumps. The amperage on motor
driven centrifugal pumps should be monitored. If the amount of current drawn is
too high the discharge valve should be throttled until the amperage drawn by the
motor is acceptable, keeping in mind that the pump minimum flow should always
be achieved.
Note:
Running test of pumps will be done when applicable only. The selection of the
pumps subject to running test with water will be done by the
precommissioning/commissioning group.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
20/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Electrical Motors
In conjunction with final inspection of the electrical construction work the following
testing and preparation is to be carried out in order to perform the initial run-in of
electrical motors for rotational check:
Open all circuit breakers and switches;
Check all bus bars to see that they are free of foreign material;
Check that all electrical equipment are connected to the equipment grounding
system in accordance with the drawings and specifications;
Check that the cables are correctly installed on the tray supports and that electrical
equipment is properly connected;
Check grounding systems for continuity and resistance;
Check piping systems with electrical bonding at flanges for continuity and
resistance;
Close both main transfer primary disconnect switches;
Close switchgear main circuit breakers;
Check voltmeter on switchgear for proper voltage;
3.2.2
Piping Inspection
Piping Sliding Support and Anchors
All comments applying to sliding supports on static equipment also apply to piping.
Long straight runs of piping should be checked for bowing when up to temperature.
Bowing causes pipe overstressing and could result in pipe failure. The probable cause
for bowing is that the line is unintentionally anchored at each extremity and this should
be checked and corrected.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
21/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Spring Support
Inspection prior to Hydrostatic Testing
Check that the spring stops are installed. If the stop is not installed on the spring
support of a vapour line, the weight of water in the pipe during hydrostatic testing
could deform the spring. The characteristic of the spring would thus change and its
performance may not be as predicted. Pipe normally transporting water would not be
affected as the spring would be designed for the weight of water but rather than make
them an exception it is simpler to state that all spring supports have their stops
installed.
Inspection after Hydrostatic Testing
After draining the water and prior to any heating the spring stops should be removed.
If the stops are not removed, the springs will not flex with the pipe thermal growth and
nozzles will be over stressed resulting in possible damage.
After the spring stop is removed, check that the spring pointer is somewhere between
the hot and cold settings stamped on the support. The thermal growth of the pipe will
result in the spring being either compressed or stretched.
If the spring pointer is not between the hot and cold settings, the spring could become
fully compressed or stretched before the full load is imposed on it. At this point, the
spring would cease to function as such, resulting in nozzle over stressing with
possible damage.
3.2.3
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
22/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
3.2.4
Instrumentation Preparation
Before energizing field instrumentation and proceed to energized loop checks,
confirm that the following static checks are actually implemented:
Clean the instrument air supply headers by blowing with clean, dry air, and check
them for leak tightness before connecting to instruments;
Verify that pneumatic tubing is hooked up, that instrument air is available at the
instrument;
Check tubing from instruments to process piping and equipment for leak
tightness;
Check orifice plate bore diameters;
Install orifice plates after completion of testing, draining, flushing and cleaning of
lines;
Isolate or remove in line components for flushing and cleaning operations.
Reinstall and/or reconnect after completion of cleaning and flushing operations;
Verify correct positions and installation of inline instrumentation (control valve flow
direction and fail position, orifice plate installed in correct relation to flow etc.);
Perform all non-operating tests that ensure instrument operability: remove
shipping stops, check pointer travel, verify and adjust the instrument's capability
to measure, operate, stroke, etc. in the direction and manner required by the
process application (direct or reverse controllers, etc.);
Perform functional loop checks and demonstrate correct operation (a
precommissioning record sheet with the relevant loop diagram);
Fully pressurize and energize the transmitting and control signal systems by
opening process connections at primary sensors and regulators and by making
control mode settings for automatic operation of equipment as the process unit is
charged and brought on stream;
Check on the DCS the operability of the system and interfaces to other
subsystems.
3.2.5
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
23/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Telecommunications
Inspection of all telecommunication equipments is performed to ensure compliance
with specifications, drawings, Codes of Practice, regulations and manufacturer's
particular requirements. In general, inspections should ensure satisfactory jointing and
continuity of all conductors, satisfactory alignment and tightness of bolting,
acceptance levels of insulation, and a high standard of cleanliness.
Main telecommunication systems are:
Message switch system;
Radio communication system;
Telephone network.
3.3.1
General
Lines and equipments cleaning is intended to eliminate welds rods and slags,
abrasive dusts, oxides and in general other substances which might impede the
normal unit operation or damage the equipment (valves, pumps, compressors,
turbines, etc.). Cleaning is usually carried out either by hand cleaning for large
equipment and lines having a diameter higher than (or equal to) 24", by water
flushing, by air/steam blowing, chemical cleaning, etc.
The cleaning of lines and associated equipment will be treated during the construction
and precommissioning phases in two steps:
1.
2.
As a summary, only above (1) can be implemented at the hydraulic test stage of the
work. The cleaning (2), of course will be performed as soon as the site facilities allow
for it, the optimum being that both cleanings are implemented in sequence.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
24/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Water Flushing
Water flushing will be performed using clean water.
The following guidelines should be observed for flushing operations:
It should be stressed that brackish or salt water must not be used for piping
flushing. Demineralized water or condensate should be used for stainless steel
pipes.
Flush main headers first, then subheaders;
When practical, lines should always be flushed away from a vessel rather than into
a vessel. Any vessel that has been flushed or blown into should be opened and
manually cleaned following flushing;
Flushing should be preferentially from the highest elevation to the lowest elevation.
This restrain is not compulsory for blowing;
Vessels and systems should be vented when filling or emptying to prevent vacuum
pulling;
During flushing, maximum volume and velocity should be used to ensure through
cleaning, the rate of flushing medium should be regulated at the source;
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
25/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Air Blowing
Cleaning of circuits will be carried out by air blowing for lines and pieces of equipment
which have to be kept free from water and for some big piping (for reasons as:
unacceptable weight, or too large quantity of water would be required, or water
flushing not efficient).
By experience, the air blowing method is usually also extended and applicable to
small size lines, as this leads to good results and dry conditions are obtained rapidly.
Air blowing will be carried out with compressed air. Air blowing of a circuit should be
performed by using temporary connection with compressed air network, in a
continuous manner for small lines or by using vessels (drum, column, etc.,) as
holdup/buffer capacity to get a quick air release. The vessel will be pressurized with
compressed air, then the air will be released through the circuit (of course first, check
that design pressure of the vessels is in accordance with compressed air maximum
operating pressure). This design pressure is reminded in the specific procedure to be
applied to each system.
In some huge systems, it is sometimes not possible to use valves to blow the relevant
lines. In this case, a bursting disc or quick opening valves can be used to proceed to a
sudden depressurization (ensure that no equipment may be damaged).
This will be the case for some lines in the process unit and interconnecting mainly.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
26/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Piping system blowing will be considered completed when air at the exit point will
appear clear (the air has not to be orange dust colour).
3.3.4
Steam Blowing
Cleaning by steam blowing is carried out essentially for steam circuits. Due to
problems of expansion or draining of condensate, this type of cleaning is not used for
other circuits except for small parts and with the utmost care.
Steam blowing will be carried out as follows:
Before putting steam into the system, control valves, turbines meters, instruments,
vacuum ejector, and strainers should be removed or blinded off from the system. The
steam headers should be slowly warmed up, one header at a time, while expansion of
the line is observed. Special attention should be given to pipe support shoes.
Condensate must be drained manually to prevent steam hammering. The headers
should now be blown using a low pressure, high-velocity sweep as explained
hereafter.
When the headers are warm, the drain valves should be opened, blown vigorously for
a few moments before reclosing. Each lateral to heater, exchangers, or service lines
should be blown in the same manner, usually not more than one at a time.
Condensate lines may be cleaned in the same manner as steam lines, but close
observation of the pressure on the condensate line is necessary since the working
pressure and temperature of the condensate lines are generally lower than of the
steam headers. A temporary movable silencer could be used to avoid exceeding noise
level limitations during the steam blowing operation, if necessary. Nevertheless, this
minimizes the efficiency of the steam blowing and steam blowing without silencer is
preferable. (Coordination with people working in the vicinity is required).
When blowing of the steam system is completed, equipment that were removed prior
to the blowing can be reconnected. The system can then be preheated and placed in
service.
3.3.5
Chemical Cleaning
Some piping must be cleaned by chemicals when either the product can react with oil
left inside of the piping or in case it can lead to adverse effect to leave even very small
parts of debris inside the piping. Proper neutralizing and flushing of these systems
after the chemical cleaning are of utmost importance.
3.3.6
3.4.1
Leak Test
General Procedure
After hydrostatic pressure testing and flushing, a tightness test must be conducted to
check all flanges and fittings for leaks, especially those opened during hydrostatic
tests and flushing.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
27/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Unit should be isolated with blinds from every part containing hydrocarbons, nitrogen
or steam.
All the relief valves should be in place and their isolation block valves in the current
position. The flare header inside the unit is isolated from the flare header already
under hydrocarbon (if any) and is open to atmosphere (by means of a PSV
dismantled for instance) to prevent overpressure during the air leak test.
3.4.2
Tightness Test
Tightness test for the process units should be carried out with air (or nitrogen when
applicable and when air is prohibited) at the maximum allowable pressure which
doesn't exceed the design pressure of equipment (check design data). Soap solution
should be prepared for the tightness checking and all flanged connections checked
with soap. Bubbling indicates if tightening is required.
The pressure raise should be checked on manometers and recorded. The leaks
should be carefully located and tightened.
This pressure follow-up gives an indication on the tightness of the system.
Nevertheless, it does not prevent from leak test on each flange with soap.
Using soap solution check for any sign of soap bubbles being formed;
Pressure the system with air (or nitrogen) at the highest possible pressure
compatible with the IA/PA supply, without exceeding the normal operating pressure;
Check pressure over a length of time. If the test is not satisfactory, every flange and
connection must be inspected with soap solution. After correction of leaks, the test
will be repeated until satisfactory.
3.4.3
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
28/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
NORMAL START-UP
The operational sequence described below is not intended, nor should be used, to
train the operator or start up the plant. The following procedures can be used as a
guideline for developing final operating procedures during detailed engineering stage
of the project.
Start Up Preparation
This chapter describes the sequential operations to be performed in order to start-up
the Cooling Water Unit, assuming certain prerequisites be satisfied before actual unit
start-up can commence.
Prior to any unit start up, ensure that:
Any issue raised in the pre-start up safety readiness review has been addressed
and cleared
Trained and experienced field and control room operation personnel is mobilised
Upstream and downstream interconnected units and other entities (fire brigade,
laboratories personnel, etc) have been duly informed and positively confirmed the
readiness to start operations.
Administration buildings, workshops, warehouses and other building and other
support facilities are ready for service
2.
Full energization of the electrical network of the main SS and secondary SSs
3.
Energization of DCS and other systems such as ESD, F&G and other auxiliary
control and information system (e.g. MMS, machine PLC, etc.)
4.
5.
Telecommunication system
Start Up Sequence
4.2.1
Main operation:
In order to start-up the cooling water system several water treatment packages and
some upstream units should be put in service first.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
29/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
4.2.2
1.
2.
Before cooling water can be introduced in the cooling water basin, Raw Water
Unit 5121 should be started-up as it includes the filter. A filtered water should be
used as make-up water to account for evaporation and drift losses in the circuit
3.
Introduce the cooling water in the cooling tower basin until the correct level is
reached.
4.
Start the cooling water pumps progressively using the electric motor drivers
5.
6.
Put all controllers in auto mode. Now the cooling water is circulating to the users
Operating description
Preliminary checks:
All units connected to the Cooling system are not yet in service (positively isolated
through valves + spectacles + chain locks at battery limit).
Blind flanges lists are checked.
All utilities are available at battery limit and in service inside the unit as follow:
LP NITROGEN
INSTRUMENT AIR
PLANT AIR
POTABLE WATER
DEMINERALIZED WATER
RAW WATER
LP FLARE
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
30/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Verify that all pre-commissioning and commissioning activities have been carried
out.
Verify that electrical power and utilities are available.
4.2.3
Verify that normal start-up work permit has been issued. All other work permits
should be closed.
Close butterfly block valve upstream Control Valve LV-0001, Open by-pass
butterfly valve on Filtered water.
Make up water level into the cooling tower basin BBC-5124001 with filtered water
from B-5121013A/B .
Close 5124-HV-002 to 5124-HV-0011, open 5124-HV-0012 and bypassing the
tower cell through the 24 line directly to the basin to avoid any rust or dirty to foul
the cooling tower.
Open XV-0001 to XV-0006 on pump B-5124001A/B/C/D and B-5124002A/B
discharge and all butterfly valves
on pump B-5124001A/B/C/D and B5124002A/B suction to fill, as much as possible, the pipes by gravity.
Start cooling water circulation pump B-5124001A (B/C/D) and circulate water back
to the basin. (When starting the pump the headers are not completely filled and
operator to pay attention to the pump electric load (amperage). Eventually, and
for short time, maintain the pump discharge valve partially closed to control
absorbed Ampere and possible hammering that can damage the installation. In
this last case stop the pump and investigate).
Establish cooling water circulation through the supply and return headers.
When the return water is clean, open 5124-HV-002 to 5124-HV-0011 and close
24 by-pass valve 5124-HV-0012 and establish circulation through the cooling
cells.
Make up level in cooling water basin as required.
When the circulation tower-Basin / pump / main header / back to tower is
stabilized:
- make up basin level to maximum
- as user start their internal cooling circulations the Ampere absorber by the
pump in operation will approach the nominal value as indicated in the pump
name plate.
- Start the other pump and make up level as required.
Open inlet butterfly valve on 5124-LV-0001 and close the relative by-pass
butterfly valve.
Commission in auto mode basin level control 5124-LIC-0001.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
31/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
32/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
The content of residual free chlorine in the cooling water return should be 0.3
ppm. Chlorine should be injected in water producing a solution which satisfies the
above requirement. Sodium Hypochlorite solution should be dosed at 1 ppm in
the circulating water, the solutions concentration being 20% minimum. A chlorine
analyzer and ph Analyzer are installed on the cooling water return header to
monitor water quality
The normal operating water level in the cooling tower basin should be kept 150
mm above low water level which in turn is 150mm above the top of the pumps.
This is automatically achieved by the level controller acting on the quantity of
required make-up water.
Feedstock
The Cooling Water Unit has been designed to provide all the users with treated
cooling water. Therefore the unit processes make-up water (filtered raw water from the
Raw Water Treatment - Unit 5121) and the products used in the injection packages
(chlorine, sodium hypochlorite, the corrosion inhibitor and the anti-scale/dispersant) to
produce circulated cooling water.
Products
The product of the unit is chemically conditioned cooling water.
Process Variables
The most important and critical variables for the Cooling water Unit are:
Cooling Water pH
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
33/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Cooling Water pH
The pH analyser is important to control the status of the cooling water regarding the
water corrosiveness.
Cooling Water Conductivity
This variable is essential to maintain the correct concentration of the cooling water.
This control open or close the water outlet to blow down.
Cooling Water Residual Chlorine
This parameter is essential to avoid biological growth.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
34/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
6.2.1
Main operation:
1. Switch off the cooling tower fans
2. Switch off the Cooling Water Pumps
3. Shutdown all water treatment packages
4. Drain all the cooling water circuit by emptying the cooling water basin and the sidestream filters back-wash basin
6.2.2
Operating Description:
Most of the maintenance works will be carried out one cell at time without stopping the
cooling water system.
Flow rate are reduced as user unit shutdown. During this phase CW return
temperature and CW supply pressure are monitored to decide when stopping cooling
fans and one by one of the circulation pumps. If necessary the pump left running can
recycle the water back to the basin through the recycle line. When it is expected a
plant total or partial shutdown it would be better to prevent low flow by preventive
opening of said by-pass in reason of the number of pump in service and, anyhow,
giving high attention to the amperage of the motor to avoid pup cavitation.
A good indication of pump extra capacity is given by the amperemeter of the electrical
motor. When the ampere absorption fall below 70% (Vendor to confirm) of the value
indicated in the name plate of the motor, the pump can be stopped.
Another control element is the total flow indicated by 5124-FI-0015. The number of
pumps in operation will be in accordance with the indicated flow.
Pressure indications are not too much helpful in deciding when one pump can be
stopped being the pump curve almost flat.Shutdown Sequence:
Confirm process units shutdown is completed.Confirm all users in utility units are
down.
Continue cooling water circulation until no more thermal load is present, that is
same temperature in supply and return.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
35/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
If necessary empty the cooling water basin and the side-stream filters back-wash
basin. If the basin does not drain completely by gravity use portable pumps
and/or ejectors.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
36/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Power failure
In case of power failure the four available pumps B.5124001A/B/C/D are down, one
Emergency Diesel Generator will supply power to Emergency Cooling Water Pump
(B-5124002 A/B). Emergency Cooling Water Pump (B-5124002 A/B), one (1)
operating and one (1) spare which has the purpose to ensure the cooling of the
equipment that must run even in case of power failure:
These equipments are:
-
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
37/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
5124-LV-0001, keep the last position, if it is open the basin will overflow, check
and control of basin level with manual by-pass.
5124-AV-0002, Cooling water blowdown valve is closed, cooling water supply can
be maintained for several hours considered the large capacity of the system.,
keep under control the 5124-AI-0002 value.
5124-FV-0020, the side stream filters should be put in stand by conditions to
avoid entertainments of filtering element when IA is restored.
Presence of Hydrocarbons.
There should be no hydrocarbons in the system. Any hydrocarbons arriving with the
CW return flow are gasiform, and it will be eliminate by the top of the tower. For this
reason all fans are provided explosion prof.
Presence of Ammonia
There should be no ammonia in the system. In case of presence of ammonia detected
by 5334-AI-0010 (on unit 5334) the cooling tower blow down has to be closed and the
problem will be investigated and checked.
Excess of Chemical
If the chemical exceeds the normal concentration, and it is out of the range of
tolerance, close the chemical, open Blow down valve 5124-AV-0002, drain the cooling
water to blow down as far as the concentration of chemical is acceptable. Re-open
the chemical to cooling water system and investigate the causes.
Automatic interlock operations
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
38/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
All
ESD
interlock
are
covered
in
the
following
table:
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
39/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
PLANT SAFETY
Introduction to Hazardous Material
On the basis of Health Safety Environmental (HSE) Guidelines for Nitrogenous
Fertilizer Production dated APRIL 30, 2007 by IFC (International Finance Corporation
Word Bank Group), the following chemical hazards are applicable to typical
nitrogenous fertilizer production processes.
Chemical Hazards
Toxic chemicals in the nitrogenous fertilizer facilities include ammonia, nitric acid
vapour, gaseous formaldehyde and urea or AN (Ammonium Nitrate) dust. Threshold
value associated with specific health effects can be found in the internationally
published exposure guidelines
Ammonia only is applicable in this case.
8.1.1
VALUE
Gas
94 psia
0.62
Evaporation point:
Not Available
Boiling point:
-33C
Freezing point:
-77.7C
pH :
Not Available
Specific gravity:
Not Available
Not Available
Solubility (H20):
Very soluble
Odor threshold:
Not Available
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
40/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
8.1.2
Hazards Identification
Acute risk:
Ammonia (NH3)
Apart of the flammable characteristic, NH3 can be classified as toxic by inhalation,
thus it exposes risk to personnel by acute exposure.
Concentration threshold categorisation for TOXIC is the follow:
Skin Contact
Eye Contact
Inhalation
HEALTH EFFECTS:
Exposure Limits
Irritant
Mutagen
Synergistic Effects
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
41/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
EYE EFFECTS:
Mild concentrations of product will cause conjunctivitis. Contact with higher
concentrations of product will cause swelling of the eyes and lesions with a possible
loss of vision.
SKIN EFFECTS:
Mild concentrations of product will cause dermatitis or conjunctivitis. Contact with
higher concentrations of product will cause caustic-like dermal burns and
inflammation. Toxic level exposure may cause skin lesions resulting in early necrosis
and scarring.
INGESTION EFFECTS:
Since product is a gas at room temperature, ingestion is unlikely.
INHALATION EFFECTS:
Corrosive and irritating to the upper respiratory system and all mucous type tissue.
Depending on the concentration inhaled, it may cause burning sensations, coughing,
wheezing, shortness of breath, headache, nausea, with eventual collapse.
Inhalation of excessive amounts affects the upper airway (larynx and bronchi) by
causing caustic-like burning resulting in edema and chemical pneumonitis. If it enters
the deep lung, pulmonary edema will result.
Pulmonary edema and chemical pneumonitis are potentially fatal conditions.
8.1.3
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
42/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
INHALATION
PROMPT MEDICAL ATTENTION IS MANDATORY IN ALL CASES OF
OVEREXPOSURE. RESCUE PERSONNEL SHOULD BE EQUIPPED WITH SELFCONTAINED BREATHING APPARATUS.
Conscious persons should be assisted to an uncontaminated area and inhale fresh
air. Quick removal from the contaminated area is most important. Unconscious
persons should be moved to an uncontaminated area, given mouth-to-mouth
resuscitation and supplemental oxygen. Keep victim warm and quiet. Assure that
mucus or vomited material does not obstruct the airway by positional drainage.
8.1.4
8.2.1
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
43/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
All gases other than air are harmful to man when inhaled in sufficient concentrations.
Toxic gases may be classified as either asphyxiating or irritating.
Asphyxiating gases may cause death by replacing air in the lungs or by reacting with
the oxygen carried in the blood, for example: hydrogen sulphide, carbon monoxide,
smoke.
Irritating gases may cause injury or death not only by asphyxiation but also by both
internal and external burning, for example: chlorine, sulphur dioxide, hydrogen
fluoride.
To guard against inhalation of harmful gases, the operator should:
Secure a gas test certificate showing the gas conditions of the atmosphere
(vessel, etc.).
Avoid entering a confined space, which has not been purged and tested.
Provide ventilation.
Oxygen cylinder and masks set: give 100% protection regardless of the presence
of the toxic gas. Their disadvantage are that they can be used for a limited time
only and require skill in proper use.
Canister type masks: are full-face masks equipped with a cartridge containing
chemicals to remove the toxic component from the air breathed through the
canister. Different cartridges are supplied for different groups of toxic gases. This
type can only be used at low concentrations of toxic gas, so that the
concentration of oxygen in the filtered air is not below 18% by volume. A
disadvantage of this type is the relatively limited capacity of the cartridge. When
the chemicals are exhausted, the toxic gas will not be trapped and therefore the
wearer must leave the contaminated area.
Air line masks: are full-face masks into which fresh air is blown through a long
hose from a manually operated blower placed outside the hazardous area.
The masks can be used in any concentration of toxic gases, can be used for a long
time and permit relatively easy breathing.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
44/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Body protection
In order to limit the possibility of hazards, operators should be compelled to wear
suitable protective equipment, as follows:
8.2.2
Head protection: hard hats whenever working in the plant. These provide
protection from falling objects and against head injury in general.
Eye protection: while cleaning or purging a line with air, steam or inert gas, all
operators and supervisors must wear goggles or other safety equipment. Goggles
should be fitted to prevent splashes from entering the eye. Plastic shields with
facial protection should be used in addition to goggles when full face protection is
required.
Ear protection: in some parts of the plant (e.g. compressor room) personal
comfort or safety ear protection. This can take the form of ear plugs or ear muffs
provided individually or located in enclosed stations adjacent to high noise areas.
Personnel should be instructed to wear ear protection before they enter high
noise level areas.
Foot protection: sturdy footwear, preferably leather, with built-in steel toe cap.
When necessary, boots of chemical resistant material can be worn over safety
shoes.
Skin and hand protection: suits made of synthetic rubber or other approved
material when complete body protection is necessary. Gloves made of synthetic
rubber or other approved material should be worn to protect the hands. In case of
severe leaks only properly protected personnel should remain in the area.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
45/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
open flames;
automotive vehicles;
static electricity.
To extinguish fires,
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
46/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Deluge systems
Hydrants
Hose boxes
Fixed monitors (oscillating, manual and remote controlled)
Water extinguishers
Fire trucks (first intervention and foam trucks)
Foam
Carbon
Dioxide
Dry chemical
Clean Agent
WATER to extinguish paper and wood fires; to cool equipment, tanks, etc.; to
protect personnel against radiant heat; to extinguish small hydrocarbon fire;
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
47/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Stop flow of gas and liquid to equipment on fire, and depressurize to blow down
system, but keep a slight positive pressure inside the equipment. Where possible
inject snuffing steam.
If flame is extinguished but elate continues, gas may spread as an explosive
cloud which may re-ignite; follow as closely as possible unit emergency shutdown procedure.
Cool any endangered adjacent structure or equipment by water jet or mist.
Fight with appropriate extinguishing agent, bearing in mind that oil floating on
water can easily spread the fire. Use foam in such cases.
A way to extinguish a fire produced by a leak is to eject steam or nitrogen into the
fire through a temporary connection from the nearest possible location, after
cutting off the fire causing fluid.
Persons not actually participating in the operations of the unit or in the fire fighting
are not allowed to be present in the area.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
48/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Hose Boxes
Hose boxes shall be installed near each hydrant. Each hose box consists of red steel
cabinet containing four hoses having 2 1/2" diameter and 15 meters length and one
adjustable straight/fog nozzle.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
49/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
detection of toxic vapours in all zones where they may appear and accumulate
automatic warning at control room, fire station, plant gate and or other location
deemed to emergency response action.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
50/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Administration building
Alarm only
Maintenance Shop
Alarm only
Laboratory
Alarm only
Activation of any one detector shall initiate an alarm relevant to the subject area, and
shall send signal to the Central Master Fire and Gas Alarm Panel (CMFGAP) located
on Control Room .
Manual Call Point (MCP)
Manual call points are provided throughout the plant areas, connected in a various
loops, relevant to the various units.
The manual call points are installed so that the maximum travelling distance is no
more than 60 meters from any point as per NFPA standard.
Activation of any one manual call point shall send signal to the Central Master Fire
and Gas Alarm Panel (CMFGAP) located on Control Room for alarm only.
Manual call points are, also, installed inside the following buildings:
Warehouse
Maintenance shop
Administration
Laboratory.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
51/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Electric Substations
Alarm only
Laboratory
Alarm only
Warehouse
Alarm only
Maintenance shop
Alarm only
Administration building
Alarm only
Area below false floor of technical rooms of Control building - Alarm and Clean agent
discharge
Gas Detection and Alarm
This paragraph covers location of equipment and devices to be installed for
combustible and toxic gas detection and alarm purpose.
Toxic (NH3) gas detectors, electrochemical cell type , are located strategically over the
process units.
In addition toxic gas detectors are installed in the suction duct of control room air
conditioning.
The signals coming from toxic gas detectors shall be send to the Central Master Fire
and Gas Alarm Panel (CMFGAP ) located on Control Room for alarm and for
activation of relevant optical / acoustical alarm located in field, the signals coming
from the detectors installed in the suction ducts of air conditioning are able to stop the
air suction.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
52/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
To close the fresh air suction of air conditioning system ( after reception of the
relevant gas detectors alarm ) for control building and electric substations.
g) To send grouped signals to the mimic type annunciator panels located one in
the fire station, one in the main guard house.
h) To send single alarms and common alarms (summarized per process area) to
the DCS.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
53/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
For Fire and gas location refer to Fire and Gas Layout: 2417-3200-DW-1950-01.
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
54/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
REFERENCE DOCUMENTATION
PFD
2417-3200-PFD-0010-02
I-DE-9525.05-3200-943-TPI-002
2417-5124-PFD-0010-01
I-DE-9525.05-5124-943-TPI-001
2417-5124-PID-0031-01-
I-DE-9525.05-5124-944-TPI-001
Cooling Tower
2417-5124-PID-0031-02-01
I-DE-9525.05-5124-944-TPI-002
Cooling Tower
2417-5124-PID-0031-03-01
I-DE-9525.05-5124-944-TPI-003
Cooling Pump
2417-5124-PID-0031-04-01
I-DE-9525.05-5124-944-TPI-004
Cooling Tower
2417-5124-PID-0031-05-01
I-DE-9525.05-5124-944-TPI-005
2417-5124-PID-0031-06-01
I-DE-9525.05-5124-944-TPI-006
CW Chemical treatment
2417-5124-PID-0031-07-01
I-DE-9525.05-5124-944-TPI-007
CW Chemical treatment
2417-5124-PID-0031-08-01
I-DE-9525.05-5124-944-TPI-008
CW Chemical treatment
2417-5124-PID-0031-09-01
I-DE-9525.05-5124-944-TPI-009
2417-5124-PID-0031-51-01
I-DE-9525.05-5124-940-TPI-001
2417-5124-PID-0031-52-01
I-DE-9525.05-5124-940-TPI-002
2417-5124-PID-0031-53-01
I-DE-9525.05-5124-940-TPI-003
I-MD-9525.05-5124-941-TPI-001
Basis of Design
PID
Basis of Design
2417-5124-JSD-0001.01
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
55/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
Data Sheets
2417-5124-SP-0271.01
I-FD-9525.05-5124-563-TPI-001
2417-5124-SP-0212-01
I-ET-9525.05-5124-561-TPI-001
2417-5124-SP-0310-01
I-FD-9525.05-5124-440-TPI-001
2417-5124-SP-0910-01
I-FD-9525.05-5124-311-TPI-001
2417-5124-SP-0910-02
I-FD-9525.05-5124-311-TPI-002
2417-5124-SP-4046-01
I-FD-9525.05-5124-642-TPI-001
2417-5124-SP-4046-02
2417-5124-SP-4046-03
2417-5124-SP-4046-04
2417-5124-SP-4046-05
I-FD-9525.05-5124-642-TPI-002
DATA
SHEET
FOR
MECHANICAL
DRAFT
WET
COOLING TOWERS - COOLING
TOWER - TR-5124001
DATA
SHEET
FOR
CENTRIFUGAL
PUMP
COOLING WATER PUMP - B5124001AD
DATA
SHEET
FOR
CENTRIFUGAL
PUMP
EMERGENCY
COOLING
WATER PUMP - B-5124002A/B
DATA SHEET FOR CHEMICAL
DOSING
SYSTEMS
CORROSION
INHIBITOR
&
DISPERSANT
TREATMENT
PACKAGE - UQ-5124001
DATA SHEET FOR CHEMICAL
DOSING
SYSTEMS
CORROSION
INHIBITOR
&
ANTI-SCALE
TREATMENT
PACKAGE - UQ-5124002
I-FD-9525.05-5124-642-TPI-003
I-FD-9525.05-5124-642-TPI-004
I-FD-9525.05-5124-642-TPI-005
Project N
Unit
Document Code
2417
5124
ML 901
Serial N
Rev.
Page
56/56
I-MA-9525.05-5124-000-TPI-001
PETROBRAS
1500 MTPD AMMONIA PLANT UFN-V
UBERABA (BRAZIL)
I-MD-9525.05-5000-800-TPI-002
Interlock Narrative
I-DE-9525.05-3200-947-TPI-002
Interlock Narrative
2417-5000-SP--0000-04
I-DE-9525.05-5000-947-TPI-001