ID Task Name Duration Start Finish Predecessors Resource Names

1 110 KV works i n Ashok Leyl and Hosur uni t 2 & 2 A 176 days Mon 10/1/12 Fri 4/19/13
2 Purchase order stage 2 days Mon 10/1/12 Tue 10/2/12
3 Receipt of PO 1day Tue 10/2/12 Tue 10/2/124 ALL Hosur
4 Getting advance 1day Mon10/1/12 Mon10/1/12 ALL Hosur
5 Preparatory work 5 days Wed 10/3/12 Mon 10/8/12
6 Pooja work 1day Wed 10/3/12 Wed 10/3/123 SVEPL
7 Site surveyand marking coordinates 3days Thu10/4/12 Sun10/7/126 SVEPL
8 Cleaning of switchyard 1day Sun10/7/12 Mon10/8/127 SVEPL
9 Orderi ng work 14 days Tue 10/2/12 Wed 10/17/12
10 Vendor finalisation 7days Tue 10/2/12 Tue 10/9/124 SVEPL
11 Release of PO for suppliers 7days Tue 10/9/12 Wed 10/17/1210 SVEPL
12 Drawi ng stage 29 days Tue 10/2/12 Sun 11/4/12
13 Preparationof designdrawings 10days Tue 10/2/12 Fri 10/12/124 SVEPL
14 Receipt of drawings fromvendors 10days Wed 10/17/12 Mon10/29/1211 SVEPL
15 Scrutinyof drawings 5days Mon10/29/12 Sun11/4/1214 SVEPL
16 Ci vi l works 85 days Sun 11/4/12 Fri 2/8/13
17 Excavation 25days Sun11/4/12 Sun12/2/128,15 SVEPL
18 Foundation 60days Sun12/2/12 Fri 2/8/1317 SVEPL
19 Erecti on 20 days Fri 2/8/13 Mon 3/4/13
20 Structurals erection 10days Fri 2/8/13 Wed 2/20/1318 SVEPL
21 Equipment erection 10days Wed 2/20/13 Mon3/4/1320 SVEPL
22 Earthi ng works 40 days Fri 2/8/13 Tue 3/26/13
23 Excavationfor earthmat 10days Fri 2/8/13 Wed 2/20/1318 SVEPL
24 Earthflat laying 15days Wed 2/20/13 Sun3/10/1323 SVEPL
25 Earthmat termination 15days Sun3/10/13 Tue 3/26/1324 SVEPL
26 Cabl i ng 27 days Fri 3/15/13 Mon 4/15/13
27 Excavation 7days Fri 3/15/13 Fri 3/22/1332,39 SVEPL
28 Cable laying 10days Sun3/24/13 Wed 4/3/1327 SVEPL
29 Termination 10days Wed 4/3/13 Mon4/15/1328 SVEPL
30 Tray works 10 days Mon 3/4/13 Fri 3/15/13
31 Traysupport fabrication 5days Mon3/4/13 Sun3/10/1321 SVEPL
32 Trayerection 5days Sun3/10/13 Fri 3/15/1331 SVEPL
33 Transformer works 105 days Wed 10/17/12 Thu 2/14/13
34 Receipt of transformer at site 100days Wed 10/17/12 Fri 2/8/1311 SVEPL
35 Transformer erection 5days Fri 2/8/13 Thu2/14/1334 SVEPL
36 Ni trogen i nj ecti on system 125 days Wed 10/17/12 Sun 3/10/13
37 Receipt of equipment 100days Wed 10/17/12 Fri 2/8/1311 SVEPL
38 erection 25days Fri 2/8/13 Sun3/10/1337 SVEPL
39 Approval fromwater department for laying HT cable 30days Tue 10/2/12 Mon11/5/123SS ALL Hosur
40 TNEB 173 days Tue 10/2/12 Wed 4/17/13
41 Submissionof necessarydocuments byALL 1day Tue 10/2/12 Tue 10/2/123SS ALL Hosur
42 Submissionof application 5days Tue 10/2/12 Sun10/7/124 SVEPL
43 Registrationof application 40days Sun10/7/12 Thu11/22/1242 TNEB
44 Payment of EMDcharges 40days Thu11/22/12 Mon1/7/1343 ALL Hosur
45 Payment of developmental charges 40days Mon1/7/13 Thu2/21/1344 ALL Hosur
46 Executionof agreement 3days Thu2/21/13 Mon2/25/1345 ALL Hosur
47 110KV supplyreadiness 45days Mon2/25/13 Wed 4/17/1346 TNEB/SVEPL
48 CEIG 175 days Tue 10/2/12 Fri 4/19/13
49 Preparationof drawings 45days Tue 10/2/12 Thu11/22/124 SVEPL
50 Submissionof drawings 30days Thu11/22/12 Wed 12/26/1249 SVEPL
51 Getting approval for the same 60days Wed 12/26/12 Tue 3/5/1350 SVEPL
52 Arranging for inspection 15days Tue 3/5/13 Thu3/21/1351 SVEPL
53 Precomissioning and testing 2days Wed 4/17/13 Fri 4/19/1352,29,35,25,38,47 SVEPL
ALL Hosur
ALL Hosur
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
ALL Hosur
ALL Hosur
SVEPL
TNEB
ALL Hosur
ALL Hosur
ALL Hosur
TNEB/SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
SVEPL
Sep Oct Nov Dec J an Feb Mar Apr May
4thQuarter 1st Quarter 2nd Quarter
Timing plan must beread andunderstoodin conjunctionwith our Technical offer ENQ/ALH02/11-12/R17T dated12.09.12and commercial offer ENQ/ALH02/11-12/R17C dated 12.09.12