Você está na página 1de 29

2002 Systeme Evolutif Limited

Version 1.0
Page 1
Version 1.0 2002 Systeme Evolutif Ltd Slide 1
Risk-Based Testing
Paul Gerrard
Technical Director, Systeme Evolutif Limited
Systeme Evolutif Limited
3
rd
Floor, 9 Cavendish Place
London W1M 9DL, UK
Tel: +44 (0)20 7636 6060
Fax: +44 (0)20 7636 6072
email: paulg@evolutif.co.uk
http://www.evolutif.co.uk/
Version 1.0 2002 Systeme Evolutif Ltd Slide 2
Agenda
l I Why Risk-Based Testing?
l II Introduction to Risk-Management
l III Risk and Test Objectives
l IV Designing the Test Process
l V Illustrative Example from an RBT Prototype
l V1 Closing Comments, Q&A
l Heres the commercial bit:
This material is based on:
Risk-Based E-Business Testing, Gerrard and Thompson,
Artech House, 2002
Visit www.riskbasedtesting.com for more information.
2002 Systeme Evolutif Limited
Version 1.0
Page 2
Version 1.0 2002 Systeme Evolutif Ltd Slide 3
Paul Gerrard
Systeme Evolutif are a software testing consultancy specialising in E-Business testing, RAD,
test process improvement and the selection and implementation of CAST Tools. Evolutif are
founder members of the DSDM (Dynamic Systems Development Method) consortium,
which was set up to develop a non-proprietary Rapid Application Development method.
DSDM has been taken up across the industry by many forward-looking organisations.
Paul is the Technical Director and a principal consultant for Systeme Evolutif. He has
conducted consultancy and training assignments in all aspects of Software Testing and
Quality Assurance. Previously, he has worked as a developer, designer, project manager and
consultant for small and large developments. Paul has engineering degrees from the
Universities of Oxford and London, is Co-Programme Chair for the BCS SIG in Software
Testing, a member of the BCS Software Component Test Standard Committee and Former
Chair of the IS Examination Board (ISEB) Certification Board for a Tester Qualification
whose aim is to establish a certification scheme for testing professionals and training
organisations. He is a regular speaker at seminars and conferences in Europe and the US, and
won the Best Presentation award at EuroSTAR 95.
Version 1.0 2002 Systeme Evolutif Ltd Slide 4
Why Risk Based Testing?
2002 Systeme Evolutif Limited
Version 1.0
Page 3
Version 1.0 2002 Systeme Evolutif Ltd Slide 5
Requirements
Functional
Specification
Physical
Design
Program
Specification
User
Acceptance
Test
System
Test
Integration
Test
Unit
Test
V-Model
Is there ever a one-to-one relationship between baseline
documents and testing?
Where is the static testing (reviews, inspections, static
analysis etc.)?
Version 1.0 2002 Systeme Evolutif Ltd Slide 6
Traditional approach
Test stage Test stage Test stage Test stage
Consider
Schedule,
Environments,
Timescales etc.
Acceptance
System
Test
Unit Test
Methodology
Build and
Execute tests
Not again!
Not
focused
Not Done
Stakeholder
Involvement
Are these faults
really severe?
Too detailed
To understand
We have to
Trust them
2002 Systeme Evolutif Limited
Version 1.0
Page 4
Version 1.0 2002 Systeme Evolutif Ltd Slide 7
Problems with tradition
l Sequence of decisions
Stages responsibility capability objectives
l Guidance to developers and testers
None, except generic, text book mantras
demonstrate software meets requirements
l Input of stakeholders
Only when system/acceptance tests reveal problems
Far too late!
l Decision making
Timescale driven in early stages
Crisis driven towards the end
Unsatisfactory all round.
Version 1.0 2002 Systeme Evolutif Ltd Slide 8
Write
Requirements
Specify
System
Design
System
Test the
Requirements
Test the
Specification
Test the
Design
Unit
Test
Acceptance
Test
System
Test
Integration
Test
Install
System
Build
System
Build
Software
Write
Code
W-Model
2002 Systeme Evolutif Limited
Version 1.0
Page 5
Version 1.0 2002 Systeme Evolutif Ltd Slide 9
Risk-based testing
Plan
assess
product risks
define test
objectives
test techniques,
products to test
Stakeholder
Involvement
responsibility
estimation
process
Schedule
focused test
design and
execution
Implement
risk-based
test reporting
assess
product risks
Decide
Version 1.0 2002 Systeme Evolutif Ltd Slide 10
Risk-based test planning
l If every test aims to address a risk, tests can be
prioritised by risk
l Its always going to take too long so
Some tests are going to be dropped
Some risks are going to be taken
l Proposal:
The tester is responsible for making the project aware of the
risks being taken
Only if these risks are VISIBLE, will management ever
reconsider.
2002 Systeme Evolutif Limited
Version 1.0
Page 6
Version 1.0 2002 Systeme Evolutif Ltd Slide 11
How much testing is enough?
l Enough testing has been planned when the
stakeholders (user/customer, project manager, support,
developers) approve:
l TESTS IN SCOPE
They address risks of concern and/or give confidence
l THE TESTS THAT ARE OUT OF SCOPE
Risk is low OR these tests would not give confidence
l The amount and rigour of testing is determined by
CONSENSUS.
Version 1.0 2002 Systeme Evolutif Ltd Slide 12
Introduction to Risk Management
2002 Systeme Evolutif Limited
Version 1.0
Page 7
Version 1.0 2002 Systeme Evolutif Ltd Slide 13
Some general statements about risk
l Risks only exist where there is uncertainty
l If the probability of a risk is zero or 100%, it is not a
risk
l Unless there is the potential for loss, there is no risk
(nothing ventured, nothing gained)
l There are risks associated with every project
l Software development is inherently risky.
Version 1.0 2002 Systeme Evolutif Ltd Slide 14
Cardinal Objectives
l The fundamental objectives of the system to be
built
l Benefits of undertaking the project
l Payoff(s) that underpin and justify the project
l Software risks are those that threaten the
Cardinal Objectives of a project.
2002 Systeme Evolutif Limited
Version 1.0
Page 8
Version 1.0 2002 Systeme Evolutif Ltd Slide 15
Three types of software risk
Project Risk
resource constraints, external
interfaces, supplier
relationships, contract
restrictions
Process Risk
variances in planning and
estimation, shortfalls in
staffing, failure to track
progress, lack of quality
assurance and configuration
management
Primarily a management
responsibility
Planning and the development process
are the main issues here.
Product Risk
lack of requirements stability,
complexity, design quality,
coding quality, non-functional
issues, test specifications.
Requirements risks are the most significant risks
reported in risk assessments.
Testers are mainly
concerned with
Product Risk
Version 1.0 2002 Systeme Evolutif Ltd Slide 16
Process
l Risk identification
what are the risks to be addressed?
l Risk analysis
nature, probability, consequences, exposure
l Risk response planning
pre-emptive or reactive risk reduction measures
l Risk resolution and monitoring
l Stakeholders should be involved at all stages.
2002 Systeme Evolutif Limited
Version 1.0
Page 9
Version 1.0 2002 Systeme Evolutif Ltd Slide 17
Assessing consequences (loss)
Severity Description Score
Critical business objective cannot be accomplished 5
High business objective undermined 4
Moderate business objectives are affected 3
Low slight effect on business 2
Negligible No noticeable effect 1
Version 1.0 2002 Systeme Evolutif Ltd Slide 18
Assessing probability (likelihood)
Probability Description Score
>80% almost certainly, highly likely 5
61-80% probable, likely, we believe 4
41-60% we doubt, improbable, better than even 3
21-40% unlikely, probably not 2
1-20% highly unlikely, chances are slight 1
2002 Systeme Evolutif Limited
Version 1.0
Page 10
Version 1.0 2002 Systeme Evolutif Ltd Slide 19
Risk exposure
l Risks with the highest exposure are those of
most concern
l Worst case scenarios drive concerns
l Risk EXPOSURE is calculated as the product of
the PROBABILITY and CONSEQUENCE of the
risk
l A simple notation is L
2
where L
2
= LIKELIHOOD x LOSS.
Version 1.0 2002 Systeme Evolutif Ltd Slide 20
What do the numbers mean?
l Sometimes you can use numeric assessments
We may have experience that tells us
Likelihood is high (it always seems to happen)
Loss is 50,000 (thats what it cost us last time)
l But often, we are guessing
Use of categories help us to compare risks
Subjective perceptions (never the same)
E.g. Developers may not agree with users on probability!
l Maybe you can only assign risk RAG numbers
RED, AMBER, GREEN
l The ability to compare is what is most important.
2002 Systeme Evolutif Limited
Version 1.0
Page 11
Version 1.0 2002 Systeme Evolutif Ltd Slide 21
The danger slope

H
i
g
h
l
y

U
n
l
i
k
e
l
y

U
n
l
i
k
e
l
y

I
m
p
r
o
b
a
b
l
e

L
i
k
e
l
y

V
e
r
y

L
i
k
e
l
y

Critical
High
Moderate
Low
Negligible


W
h
e
r
e

w
e

w
a
n
t
to

m
o
v
e

a
ll
r
is
k
s
Version 1.0 2002 Systeme Evolutif Ltd Slide 22
Risk and Test Objectives
2002 Systeme Evolutif Limited
Version 1.0
Page 12
Version 1.0 2002 Systeme Evolutif Ltd Slide 23
Why use risks to define test
objectives?
l If we focus on risks, we know that bugs relating to the
selected mode of failure are bound to be important.
l If we focus on particular bug types, we will probably be
more effective at finding those bugs
l If testers provide evidence that certain failure modes
do not occur in a range of test scenarios, we will
become more confident that the system will work in
production.
Version 1.0 2002 Systeme Evolutif Ltd Slide 24
Defining a test objective from risk
l We turn around the failure mode or risk
l Risk:
a BAD thing happens and thats a problem for us
l Test objective:
demonstrate using a test that the system works without the
BAD thing happening
l The test:
execute important user tasks and verify the BAD things dont
happen in a range of scenarios.
2002 Systeme Evolutif Limited
Version 1.0
Page 13
Version 1.0 2002 Systeme Evolutif Ltd Slide 25
Risks and test objectives - examples
Risk Test Objective
The web site fails to function
correctly on the users client
operating system and browser
configuration.
To demonstrate that the application functions
correctly on selected combinations of
operating systems and browser version
combinations.
Bank statement details
presented in the client
browser do not match records
in the back-end legacy
banking systems.
To demonstrate that statement details
presented in the client browser reconcile with
back-end legacy systems.
Vulnerabilities that hackers
could exploit exist in the web
site networking infrastructure.
To demonstrate through audit, scanning and
ethical hacking that there are no security
vulnerabilities in the web site networking
infrastructure.

Version 1.0 2002 Systeme Evolutif Ltd Slide 26
Risk-based test objectives are usually
not enough
l Other test objectives relate to broader issues
contractual obligations
acceptability of a system to its users
demonstrating that all or specified functional or non-functional
requirements are met
non-negotiable test objectives might relate to mandatory rules imposed by
an industry regulatory authority and so on
l Risk assessment might miss something, or de-scope something
important
l Generic test objectives
catch all measure e.g. all requirements coverage
complete the definition of your test stages.
2002 Systeme Evolutif Limited
Version 1.0
Page 14
Version 1.0 2002 Systeme Evolutif Ltd Slide 27
Generic test objectives
Test Objective Typical Test Stage
Demonstrate component meets requirements Component Testing
Demonstrate component is ready for reuse in larger
sub-system
Component Testing
Demonstrate integrated components correctly
assembled/combined and collaborate
Integration testing
Demonstrate system meets functional requirements Functional System
Testing
Demonstrate system meets non-functional requirements Non-Functional System
Testing
Demonstrate system meets industry regulation
requirements
System or Acceptance
Testing
Demonstrate supplier meets contractual obligations (Contract) Acceptance
Testing
Validate system meets business or user requirements (User) Acceptance
Testing
Demonstrate system, processes and people meet
business requirements
(User) Acceptance
Testing

Version 1.0 2002 Systeme Evolutif Ltd Slide 28
Tests as demonstrations
l Demonstrate is most often used in test objectives
l Better than Prove which implies mathematical
certainty (which is impossible)
l But is the word demonstrate too weak?
it represents exactly what we will do
we provide evidence for others to make a decision
we can only run a tiny fraction of tests compared to what is
possible
so we really are only doing a demonstration of a small, sample
number of tests.
2002 Systeme Evolutif Limited
Version 1.0
Page 15
Version 1.0 2002 Systeme Evolutif Ltd Slide 29
But tests should aim to locate faults,
shouldn't they?
l The testers goal: to locate faults
l We use boundary tests, extreme values, invalid data,
exceptional conditions etc. to expose faults:
if we find faults these are fixed and re-tested
we are left with tests that were designed to detect faults,
some did detect faults, but do so no longer
l We are left with evidence that the feature works
correctly and our test objective is met
l No conflict between:
strategic risk-based test objectives and
tactical goal of locating faults.
Version 1.0 2002 Systeme Evolutif Ltd Slide 30
Testing and meeting requirements
l Risk-based test objectives do not change the
methods of test design much
l Functional requirements
We use formal or informal test design techniques as
normal
l Non-functional requirements
Test objectives are often detailed enough to derive
specific tests.
2002 Systeme Evolutif Limited
Version 1.0
Page 16
Version 1.0 2002 Systeme Evolutif Ltd Slide 31
Designing the Test Process
Version 1.0 2002 Systeme Evolutif Ltd Slide 32
Risk
Identification
Consult business, technical staff
Prepare a draft register of risks
Risk
Analysis
Risk
Response
Test
Scoping
Test Process
Definition
Discuss risks
Assign probability and consequence scores
Calculate exposure
Formulate test objectives, select test technique
Document dependencies, requirements, costs,
timescales for testing
Assign Test Effectiveness score
Nominate responsibilities
Agree scope of risks to be addressed by testing
Agree responsibilities and budgets
Draft the test process from the Test Process
Worksheet
Complete test stage definitions
Tester Activity
Workshop
Tester Activity
Review and Decision
Tester Activity
Master Test Planning process
2002 Systeme Evolutif Limited
Version 1.0
Page 17
Version 1.0 2002 Systeme Evolutif Ltd Slide 33
Test process worksheet
Failure Mode or
Objective
P
r
o
b
a
b
i
l
i
t
y

C
o
n
s
e
q
u
e
n
c
e

T
e
s
t
E
f
f
e
c
t
i
v
e
n
e
s
s

R
IS
K
N
u
m
b
e
r

P
r
o
t
o
t
y
p
i
n
g

I
n
f
r
a
s
t
r
u
c
t
u
r
e

S
u
b
-
S
y
s
t
e
m

A
p
p
l
i
c
a
t
i
o
n
S
y
s
t
e
m

N
o
n
-
F
u
n
c
t
i
o
n
a
l

T
e
s
t
s

U
s
e
r
A
c
c
e
p
t
a
n
c
e

O
p
e
r
a
t
i
o
n
a
l

A
c
c
e
p
t
a
n
c
e
(
B
T
S
)
L
i
v
e
C
o
n
f
i
d
e
n
c
e

C
u
s
t
o
m
e
r
L
i
v
e
T
r
i
a
l

Test Technique
Client Platform
1 Which browsers, versions and O/S platforms
will be supported, includes non-fr ames, non -
graphic browsers etc.)?
SS

2 New platforms: Web TV, Mobile Phones, Palm
Pilots etc.

3 Connection through commercial services e.g.
MSN, Compuserve, AOL
SS
4 Browser HTML Syntax Checking SS

5 Browser compatibility HTML Checking SS
6 Client configuration e.g. unusable, local
character sets being re jected by database etc.
SS
7 Client configuration: Client turns off graphics,
rejects cookies, Cookies time out, Client doesnt
have required plug-ins etc.
SS
8 Minimum suppo rted client platform to be
determined/validated
SS
Component Functionality
9 Client component functionality SS
10 Client web-page object loading SS

11 Custom-built infrastructure component
functionality
SS
12 COTS component functionality SS

13 HTML page content checking - spelling, HTML
val idation
SS
System/Application functionality

14 End -t o-end system functionality CC
15 Loss of context/persistence between
transactions
SS CC

Version 1.0 2002 Systeme Evolutif Ltd Slide 34
Using the worksheet - risks
l Failure Mode or Objective column
failures/risks
requirements for demonstrations
mandatory/regulatory/imposed requirements
l Probability of the problem occurring
l Consequence of failure
l Test Effectiveness - if we test, how likely would
the problem be detected?
2002 Systeme Evolutif Limited
Version 1.0
Page 18
Version 1.0 2002 Systeme Evolutif Ltd Slide 35
Creating the worksheet
l Create a template sheet with initial risks and objectives
based on experience/checklists
l Cross-functional brainstorming
stakeholders or technically qualified nominees
might take all day, but worth completing in one session to
retain momentum
l If you cant get a meeting, use the specs, then get
individuals to review.
Version 1.0 2002 Systeme Evolutif Ltd Slide 36
Illustrative Example from an RBT
Prototype
2002 Systeme Evolutif Limited
Version 1.0
Page 19
Version 1.0 2002 Systeme Evolutif Ltd Slide 37
Test products through the lifecycle
initial risk
assessment
test
objectives
test
stages
test process
definition
master test
planning
test plan/
procedures
test specification
test log
test execution
release risk
assessment
test results analysis
today
Planne
d
end
Progress through the test plan
R
e
s
i
d
u
a
l

R
i
s
k
s
start
Version 1.0 2002 Systeme Evolutif Ltd Slide 38
Risk
detail
This is the risk
detail it is one
row of the test
process
worksheet
An example
screen from the
RBT prototype
application.
2002 Systeme Evolutif Limited
Version 1.0
Page 20
Version 1.0 2002 Systeme Evolutif Ltd Slide 39
From risks to test objectives
initial risk
assessment
test
objectives
Version 1.0 2002 Systeme Evolutif Ltd Slide 40
2002 Systeme Evolutif Limited
Version 1.0
Page 21
Version 1.0 2002 Systeme Evolutif Ltd Slide 41
Test stage - key attributes
Test Objectives The objectives of this stage of testing based on the
risks to be addressed and the generic objectives for
the test stage.
Component(s) under Test The architectural components, documents,
business processes to be subjected to the test.
Baseline Document(s) defining the requirements to be met
for the components under test (to predict expected
results).
Responsibility Groups responsible for e.g. preparing tests,
executing tests and performing analysis of test
results.
Environment Environment in which the test(s) will be performed.
Entry Criteria Criteria that must be met before test execution may
start.
Exit Criteria Criteria to be met for the test stage to end.
Techniques/tools Special techniques, methods to be adopted; test
harnesses, drivers or automated test tools to be
used.
Deliverables Inventory of deliverables from the test stage.

Version 1.0 2002 Systeme Evolutif Ltd Slide 42
Test stage definition
initial risk
assessment
test
objectives
test
stages
2002 Systeme Evolutif Limited
Version 1.0
Page 22
Version 1.0 2002 Systeme Evolutif Ltd Slide 43
Test stage definition 2
Version 1.0 2002 Systeme Evolutif Ltd Slide 44
Test stage definition 3
2002 Systeme Evolutif Limited
Version 1.0
Page 23
Version 1.0 2002 Systeme Evolutif Ltd Slide 45
Test stage definition 4
Test stage definition
includes the required
items to create an IEEE
829 format test plan.
Version 1.0 2002 Systeme Evolutif Ltd Slide 46
Master Test Planning
initial risk
assessment
test
objectives
test
stages
test process
definition
master test
planning
2002 Systeme Evolutif Limited
Version 1.0
Page 24
Version 1.0 2002 Systeme Evolutif Ltd Slide 47
Master Test Plan glues it all together
Version 1.0 2002 Systeme Evolutif Ltd Slide 48
Example
test stage
Project: Sample IT Project
Test Stage: LSI Large Scale Integration
Description The System-Tested application will be tested in conjunction with
associated systems that it must integrate with.
Features To Be Tested The Sample IT Application will be tested in conjunction with the
Banking Interface and the Electronic Mail Interface. The following
features are in scope:
- payment processing
- payments exceptions
- electronic mail notifications (all types).
Features Not To Be Tested Integration with legacy Financial Accounting system FTBS is out of
scope for this project.
Item Pass Fail Criteria: Messages are triggered as predicted.
Data transfer performed in a synchonised way.
Data reconciles across integrated systems.
Suspend/Resume Criteria Testing will be suspended if it is not possible to perform the basic
data transfers:
- payments
- exceptions
- electronic mail notifications.
Test Deliverables: LSI Test Plan
LSI Test Procedures
LSI End of Phase Report
Object Under test Sample IT Application
Banking Interface
Electronic Mail interface.
Test Objectives:
Technique: System Integration Test
Risk: R07 Demonstrate system and banking systems integrate.
Organisation: Joint Customer and Supplier Activity
Environment: ACCTEST
Name: Evolutif Test
Estimate: 120 days
Dependencies: Assume functional system testing is complete tothe degree that the
key billing functions operate with stubbed-out interfaces.
Timescale: 40 days
Test stage
definition
example
stage objectives
technique
organisation
object under test
environment
etc. etc.
2002 Systeme Evolutif Limited
Version 1.0
Page 25
Version 1.0 2002 Systeme Evolutif Ltd Slide 49
Ongoing risk assessment
initial risk
assessment
test
objectives
test
stages
test process
definition
master test
planning
test plan/
procedures
test specification
test log
test execution
release risk
assessment
test results analysis
today
Planne
d
end
Progress through the test plan
R
e
s
i
d
u
a
l

R
i
s
k
s
start
Version 1.0 2002 Systeme Evolutif Ltd Slide 50
Risk-based test reporting
today
Planned
end
residual risks
of releasing
TODAY
Progress through the test plan
R
e
s
i
d
u
a
l

R
i
s
k
s
start
all risks
open at
the start
2002 Systeme Evolutif Limited
Version 1.0
Page 26
Version 1.0 2002 Systeme Evolutif Ltd Slide 51
Benefits of risk-based test reporting
l Risk of release is known:
On the day you start and throughout the test phase
On the day before testing is squeezed
l Progress through the test plan brings positive results
risks are checked off, benefits available
l Pressure: to eliminate risks and for testers to provide
evidence that risks are gone
l We assume the system does not work until we have
evidence guilty until proven innocent
l Reporting is in the language that management and
stakeholders understand.
Version 1.0 2002 Systeme Evolutif Ltd Slide 52
Benefit & objectives based test
reporting
Open
Closed
R
i
s
k
s
Open
Open
Closed
Closed
Open
O
b
j
e
c
t
i
v
e
O
b
j
e
c
t
i
v
e
O
b
j
e
c
t
i
v
e
O
b
j
e
c
t
i
v
e
B
e
n
e
f
i
t
B
e
n
e
f
i
t
B
e
n
e
f
i
t
B
e
n
e
f
i
t
B
e
n
e
f
i
t
Benefits available for release
O
b
j
e
c
t
i
v
e
B
e
n
e
f
i
t
Closed
2002 Systeme Evolutif Limited
Version 1.0
Page 27
Version 1.0 2002 Systeme Evolutif Ltd Slide 53
Benefits of benefit-based test
reporting
l Risk(s) that block every benefit are known:
On the day you start and throughout the test phase
Before testing is squeezed
l Progress through the test plan brings positive results
benefits are delivered
l Pressure: to eliminate risks and for testers to provide
evidence that benefits are delivered
l We assume that the system has no benefits to deliver
until we have evidence
l Reporting is in the language that management and
stakeholders understand.
Version 1.0 2002 Systeme Evolutif Ltd Slide 54
How good is our testing?
l Our testing is good if it provides:
Evidence of the benefits delivered
Evidence of the CURRENT risk of release
At an acceptable cost
In an acceptable timeframe
l Good testing is:
Knowing the status of benefits with confidence
Knowing the risk of release with confidence.
2002 Systeme Evolutif Limited
Version 1.0
Page 28
Version 1.0 2002 Systeme Evolutif Ltd Slide 55
Closing Comments
Version 1.0 2002 Systeme Evolutif Ltd Slide 56
Risk-based test approach: planning
l RBT approach helps stakeholders:
They get more involved and buy-in
The have better visibility of the test process
l RBT approach helps testers
Approval to test against risks in scope
Approval to not test against risks out of scope
Clearer test objectives upon which to design tests
l RBT approach helps developers
Specifies their responsibility for testing in detail
No hiding place.
2002 Systeme Evolutif Limited
Version 1.0
Page 29
Version 1.0 2002 Systeme Evolutif Ltd Slide 57
Risk-based test approach: execution
and reporting
l RBT approach helps stakeholders:
They have better visibility of the benefits available
and the risks that block benefits
l RBT approach helps management:
To see progress in terms of risks addressed and
benefits that are available for delivery
To manage the risks that block acceptance
To better make the release decision.
Version 1.0 2002 Systeme Evolutif Ltd Slide 58
Risk-Based Testing
Close
Any Questions?
document templates can be found at
http://www.riskbasedtesting.com/

Você também pode gostar