Você está na página 1de 56

Energy Risk

Professional (ERP

)
Examination
Practice Exam 1
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material i
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
Introduction . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .1
ERP Practice Exam 1 Candidate Answer Sheet . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .3
ERP Practice Exam 1 Questions . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .5
ERP Practice Exam 1 Answer Sheet/Answers . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .21
ERP Practice Exam 1 Explanations . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .23
TABLE OF CONTENTS
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 1
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
INTRODUCTION
The ERP Exam is a practice-oriented examination. Its ques-
tions are derived from a combination of theory, as set forth
in the core readings, and real-world work experience.
Candidates are expected to understand energy risk man-
agement concepts and approaches and how they would
apply to an energy risk managers day-to-day activities.
The ERP Examination is also a comprehensive examina-
tion, testing an energy risk professional on a number of risk
management concepts and approaches. It is very rare that
an energy risk manager will be faced with an issue that can
immediately be slotted into just one category. In the real
world, an energy risk manager must be able to identify any
number of risk-related issues and be able to deal with them
efectively.
The ERP Practice Exam 1 has been developed to aid
candidates in their preparation for the ERP Examination in
November 2011. This practice exam is based on a sample
of actual questions from the 2009 ERP Examination and
is suggestive of the questions that will be in the 2011 ERP
Examination.
The ERP Practice Exam 1 contains 60 multiple choice
questions. Note that the 2011 ERP Examination will consist
of a morning and afternoon session, each containing 90
multiple choice questions. The practice exam is designed to
be shorter to allow candidates to calibrate their prepared-
ness for the exam without being overwhelming.
The ERP Practice Exam 1 does not necessarily cover
all topics to be tested in the 2011 ERP Examination. For
a complete list of topics and core readings, candidates
should refer to the 2011 ERP Examination Study Guide.
Core readings were selected in consultation with the Energy
Oversight Committee (EOC) to assist candidates in their
review of the subjects covered by the exam. Questions for
the ERP Examination are derived from these core readings
in their entirety. As such, it is strongly suggested that candi-
dates review all core readings listed in the 2011 ERP Study
Guide in-depth prior to sitting for the exam.
Suggested Use of Practice Exams
To maximize the efectiveness of the practice exams, candi-
dates are encouraged to follow these recommendations:
1. Plan a date and time to take the practice exam.
Set dates appropriately to give sufcient study/review
time for the practice exam prior to the actual exam.
2. Simulate the test environment as closely as possible.
Take the practice exam in a quiet place.
Have only the practice exam, candidate answer
sheet, calculator, and writing instruments (pencils,
erasers) available.
Minimize possible distractions from other people,
cell phones, televisions, etc.; put away any study
material before beginning the practice exam.
Allocate 2 minutes per question for the practice
exam and set an alarm to alert you when a total of
120 minutes have passed (or 2-60 minute sessions
with a break in between to simulate the actual exam
conditions). Complete the entire exam but note the
questions answered after the 120-minute mark.
Follow the ERP calculator policy. Candidates are only
allowed to bring certain types of calculators into the
exam room. The only calculators authorized for use
on the ERP Exam in 2011 are listed below, there will
be no exceptions to this policy. You will not be allowed
into the exam room with a personal calculator other
than the following: Texas Instruments BA II Plus
(including the BA II Plus Professional), Hewlett Packard
12C (including the HP 12C Platinum and the Anniversary
Edition), Hewlett Packard 10B II, Hewlett Packard 10B II+
and Hewlett Packard 20B.
3. After completing the ERP Practice Exam 1
Calculate your score by comparing your answer
sheet with the practice exam answer key. Only
include questions completed within the rst 200
minutes in your score.
Use the practice exam Answers and Explanations to
better understand the correct and incorrect answers
and to identify topics that require additional review.
Consult referenced core readings to prepare for
the exam.
Remember: pass/fail status for the actual exam is
based on the distribution of scores from all candi-
dates, so use your scores only to gauge your own
progress and level of preparedness.
Energy Risk
Professional(ERP

)
Examination
Practice Exam 1
Answer Sheet
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 3
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
a. b. c. d.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
a. b. c. d.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
Correct way to complete
1.
Wrong way to complete
1. 8 3
Energy Risk
Professional(ERP

)
Examination
Practice Exam 1
Questions
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 5
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
1. An electric power generator is offering the following four separate bids:
50 MW at USD 20 per MW
100 MW at USD 25 per MW
150 MW at USD 30 per MW
250 MW at USD 40 per MW
What would the market clearing price of electric power be if demand is 175 MW?
a. USD 40.00/MW
b. USD 26.25/MW
c. USD 32.72/MW
d. USD 30.00/MW
2. Devon is interested in creating a synthetic commodity by combining a forward contract with a zero-coupon
bond. What is the payoff required on the zero-coupon bond if the annual risk-free interest rate on a continuous
basis is 2% and the price of the commodity forward contract at time 0 is F0,T = USD 150 (where T = 1 year)?
a. USD 147
b. USD 150
c. USD 153
d. USD 156
3. The Senior Management of Cristal Crude Refinery is planning to build a new refinery complex in Indonesia
that includes a coker. Which of the following is true about the new refinery?
a. The refinery is a hydroskimming refinery.
b. The refinery is classified as a simple refinery.
c. The refinery is best suited for processing heavy crude oil.
d. The refinery will produce nearly as much residual fuel as gasoline.
4. Which of the following statements regarding the transportation of petroleum products is correct?
a. Natural gas liquids like ethane, ethane-propane mixtures and LPGs are commonly transported by
dedicated pipeline.
b. Contamination is usually an issue when butane is transported via the same pipeline as gasoline and diesel.
c. Ethane-propane mixtures are seldom transported via pipeline.
d. Natural gasoline is typically transported through its own dedicated pipeline.
6 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
5. Which of the following best describes a royalty payment?
a. An amount equal to a percentage of the value of production paid by the holder to the State in cash
or in kind.
b. An amount paid by the contract holder to an independent agent for the right to exploit an asset.
c. The money collected by the site inspector.
d. A tax on production volume, independent of profits.
6. Which of the following energy forward contracts will have the greatest mark-to-market sensitivity to a single-
day price spike created by an unplanned outage at a large generation plant during the delivery period?
a. 5 x 16 contract for a week
b. On-peak contract for delivery over the entire month
c. Round-the-clock contract for delivery over a two-month period
d. A 5 x 8, 2 x 2 4 calendar year contract
7. Heinz provides risk management support to a multinational energy trading desk. His primary responsibility is
to inform the Chief Risk Officer about derivatives trades executed each day along with all trader risk limit
exceptions. Which of the following risk control categories best describes Heinzs primary responsibility?
a. Risk Reporting
b. Risk Review
c. Risk Assessment
d. Risk Control
8. Jim Johnson is studying issues associated with electricity options. Which of the following statements regarding
electricity options is correct?
a. Option models (i.e. Black-Scholes) can be modified to handle electricity as well as financials
b. The use of convenience yield compensates for electricity price spikes
c. Asian options are popular among electricity risk managers because of to their averaging feature
d. The no-arbitrage argument can be applied to electricity in order to value derivatives
9. A power plant enters into a natural gas contract that has a take-or-pay value of 85% and a swing value of
20%. If the contract specifies delivery of 120 MWh of natural gas equivalent, what is the minimum amount of
gas that must be purchased under the terms of the contract?
a. 24 MWh
b. 96 MWh
c. 102 MWh
d. 120 MWh
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 7
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
10. Consider the delta profile for at-the-money European call forward options on NYMEX crude oil. What is the
approximate delta value when the strike price is close to the forward price?
a. 0.00
b. 0.25
c. 0.50
d. 1.00
11. Which of the following is NOT a method for managing credit-risk exposure within energy markets?
a. Clearing OTC energy derivatives
b. Obtaining credit risk insurance
c. Purchasing commodity forward contracts
d. Securing a financial guarantee via an Irrevocable Standby Letter of Credit
12. Karachaganak, Kazakhstan is one of the largest gas condensate fields in the world, with proven reserves of
1.9 billion barrels of oil and 13 trillion cubic feet of gas. In 2004, the field produced about 220,000 barrels of
oil and 1.3 billion cubic feet of gas per day. What is the producing gas-oil ratio?
a. 4,300
b. 5,909
c. 6,842
d. 7,523
13. LNG suppliers must assure the quality of the gas from their LNG terminals in order to fulfill which of the
following specifications?
a. It is characteristic of the gas as it came from the reservoir.
b. It meets the sellers specifications.
c. It is free of methane.
d. It is consistent with the requirements of downstream gas customers.
8 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
14. Two manufacturing plants Factory Alpha and Factory Bravo are told by the government they each need
to reduce their greenhouse gas emissions. The target reductions and costs for each factory to meet this goal
are shown in the table below.
Alpha Bravo
Required emissions reductions 10 tons 10 tons
Cost of emissions reductions USD 120 per ton USD 40 per ton
Total cost of reductions USD 1,200 USD 400
Under an emissions trading scheme, Factory Alpha can pay Factory Bravo to reduce its emissions by an
additional 10 tons, in effect, buying the needed emissions credit from Bravo.
What will Bravos final emission reduction cost be if it charges Alpha USD 600 for the emissions credit?
a. USD 200
b. USD 600
c. USD 800
d. USD 1,000
15. A trader at XYZ Bank has been asked by a client who is a petroleum refiner client to quote the price on a
3-month crude oil forward contract. Given the following forward curve and discount factors for crude oil,
calculate the price of the 3 month forward contract.
Contract Price Discount Factor
Jan Contract USD 79.10/bbl 0.95
Feb Contract USD 85.60/bbl 0.92
Mar Contract USD 83.90/bbl 0.88
a. USD 80.37
b. USD 82.81
c. USD 75.91
d. USD 90.40
16. You have been asked by your supervisor to hedge a daily power option. Which is the most appropriate
contract to use to hedge the daily option?
a. Daily forward contract
b. Daily futures contract
c. OTC swap contract
d. Balance-of-the-month contract
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 9
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
17. Which of the following is NOT a disputable point in the performance of an energy commodity contract?
a. Credit ratings
b. Missed deliveries or deadlines
c. Poor commodity quality
d. Default on a debt
18. Which of the following statements is/are true about the impact of a Smart Grid?
I. A smart grid is a more flexible control system that maximizes the utility of existing transmission assets
and delays the need for creating new ones.
II. A smart grid provides better control of the transmission system allowing peaker plants to run during
periods of congestion
a. I only
b. II only
c. Both I and II are correct
d. Neither I or II are correct
19. Which of the statements below is/are an advantage of using Geometric Brownian motion (GBM) to model
electricity prices?
I. GBM is an industry standard that can be easily applied for efficient computer simulation
II. GBM is a stochastic process that captures the fat tails of price distributions
a. I only
b. II only
c. Both I and II are correct
d. Neither I or II are correct
10 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
20. Consider the following yields from a simple, complex, and very complex refinery. Each is processing the same
sour, heavy crude oil. Based on the output products listed, identify refineries X, Y, and Z by their complexity level.
Product Type\Refinery X Y Z
Gasoline 60 50 30
Jet Fuel 15 15 15
Distillate Fuel 25 25 20
Residual Fuel
Coke 5
Refinery Fuel 15 10 8
Gain (20) (5) (3)
a. X = simple, Y = complex, Z = very complex
b. X = simple, Y = very complex, Z = complex
c. X = complex, Y = simple, Z = very complex
d. X = very complex, Y = complex, Z = simple
21. Which facility type is usually considered the least desirable option for underground storage of natural gas
because of expense and operational constraints?
a. Depleted oil and gas fields
b. Aquifers
c. Salt caverns
d. Storage tanks
22. Consider a power grid where the average heat rate for combined cycle gas turbine plants using natural gas is
8,500 Btu/kWh. The price of natural gas is USD 5.00/MMBtu, and the price of electricity is USD 30.00/MWh.
What is the spark spread for this particular power grid?
a. USD 0.0125/kWh
b. USD 0.1250/kWh
c. USD -0.0125/kWh
d. USD -0.1250/kWh
23. Ann Kelly buys a long call at a strike of USD 50 and sells a long call at a strike of USD 75. She has purchased
which of the following structures?
a. Bull spread
b. Bear spread
c. Participating collar
d. Participating cap
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 11
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
24. Simone is interested in capturing large price swings in her energy portfolio and decides to use the delta-normal
approach to compute portfolio VaR. The delta-normal approach will be least likely to capture large price
changes in which of the following instruments?
a. Futures
b. Forwards
c. Swaps
d. Options
25. Which of the following statements regarding LNG project costs is correct?
a. The construction of liquefaction plant facilities typically represents the LNG chains most significant
capital investment.
b. LNG storage tank costs are independent of liquefaction plant location.
c. The cost of a liquefaction plant is considered part of the upstream costs.
d. One unusual aspect of LNG upstream and downstream development is that future additions to achieve
economies of scale are not planned due to the high cost of building LNG facilities.
26. A major hurricane has shut down drilling activity on hundreds of oil rigs across the Gulf of Mexico. The
resulting supply disruption has caused the cash (spot) price of WTI crude to spike above the price of longer
dated futures contracts. As a result the WTI contract is said to be trading in _____________.
a. backwardation
b. contango
c. short-term disequilibrium
d. extreme volatility
27. High pressure in subsurface reservoirs can cause a significant volume of natural gas to be dissolved in
underground crude oil reserves. Which of the following is the correct term for this build-up of gas?
a. Non-associated gas
b. Crude oil gas
c. Associated gas
d. Free gas
28. Which of the following geographic regions is the largest importer of coal?
a. Asia
b. Europe
c. Former Soviet Union
d. North America
12 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
29. Environmental impacts must be considered when evaluating the operating efficiency of an electric generation
facility. Using the information below calculate the economic impact of sulfur dioxide (SO2) in the cost of
producing each MWh of electricity at Acme Power Generation.
Heat rate is 8 MMBtu/MWh
SO2 price is USD 600 per ton (2,000 pounds/ton)
SO2 rate is 2.00 lbs per MMBtu
a. USD 2.40 per MWh
b. USD 8.25 per MWh
c. USD 9.60 per MWh
d. USD 4.80 per MWh
30. Andreas purchased a monthly 100 MW on-peak power call option for a month that has 20 business days. The
strike price is USD 75/MWh and the premium is USD 5/MWh. What would the gross settlement amount be if
Andreas exercised the call option in a month when the average on-peak power price was USD 85/MWh?
a. USD 160,000
b. USD 240,000
c. USD 320,000
d. USD 480,000
31. Which of the following is an example of basis risk?
a. The risk of a natural gas price spike during peak electricity demand for a gas fired power generation plant.
b. The risk of failure to comply with FERC financial reporting regulations.
c. The risk that a megawatt of electricity will cost USD 75 in Pennsylvania and USD 82.50 in New York.
d. The risk of the inability of a power generation plant to meet demand in a given market.
32. Makati and Sons Heating Oil Company expects customer demand to average 2,200 gallons of heating oil
during the upcoming heating season. The company sells oil to customers using fixed price contracts and has
decided to store enough oil to meet average customer demand of 2,300 gallons. They have also purchased
call options to protect against the risk of a much colder than expected winter. What risk is the company
primarily seeking to hedge?
a. Volume Risk
b. Supply Risk
c. Credit Risk
d. Location Basis Risk
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 13
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
33. On June 20, Caufield Refining estimates it will need to purchase 40,000 barrels of crude on October 12.
Caufield decides to hedge price risk using a November NYMEX futures contract. The November futures price
on June 20 is USD 67.00/bbl. On October 12, Caufield is ready to purchase its required crude oil and closes
out the futures contract on that day; at this time the spot price is USD 70.10/bbl and the futures price is
USD 68.50/bbl. In this scenario, what is the effective price paid per barrel?
a. USD 68.50
b. USD 68.60
c. USD 70.10
d. USD 70.40
34. An oil field estimated to have 50 Mbbl of oil is classified as "P90." What does this classification indicate?
a. That there is a 90% probability the oil field will actually produce more than 50 Mbbl of oil.
b. That there is a 90% probability the oil field contains 50 Mbbl of oil.
c. That the oil field is 90% depleted.
d. That the oil field is determined to contain of 90% petroleum and 10% other material (e.g. natural gas).
35. Black Gold Co. is a firm specializing in the exploration, acquisition and drilling of new crude oil fields. Based
on these activities, Black Gold would best be described as what type of oil operation?
a. Independent
b. Integrated
c. Speculative
d. Wildcat
36. Which of the following is NOT considered a primary model for electricity trading arrangements?
a. Integrated model
b. Open access model
c. Wheeling model
d. Decentralized model
37. You have a portfolio of gas calls and puts that is gamma neutral. Which of the following trading strategies
would you implement to make your portfolio delta neutral?
a. Purchase a call option
b. Purchase a forward contract
c. Purchase either a call or a put option
d. By definition a gamma neutral portfolio is also delta neutral so no action is necessary
14 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
38. Steve Dolan is a power manager at Upstate Electric. He is negotiating a one-day contract to sell 100 MWh of
electricity at USD 55/MWh for a 24-hour period and has been asked to calculate the Value-at-Risk (VaR) for
the contract. If the daily volatility of electricity prices is 2%, what is the daily VaR on the contract assuming a
95% confidence interval?
a. USD 180
b. USD 3,447
c. USD 4,330
d. USD 5,412
39. Which of the following pricing relationships include the elements of convenience yield?
a. Spot price
b. Expected spot price
c. Strike price
d. Forward price
40. Wet gas refers to ______________.
a. Gas that has a high moisture content
b. Gas that has a heating value greater than methane.
c. Gas that has not been scrubbed of its sulfur impurities
d. None of the above
41. Given the following information, how much power capacity (in MWs) would load serving entities in a capacity
market be required to purchase to make the building of additional capacity economically viable?
Expected end-user peak load: 100 MW
Average end-user load: 90 MW
Percentage reserve margin: 10%
a. 10 MW
b. 110 MW
c. 100 MW
d. 99 MW
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 15
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
42. Which of the following statements is/are true regarding option valuation?
I. The intrinsic value of a call option is greatest when the value of the underlying is equal to the strike price
of the option.
II. The time value is the difference between the market quoted premium and the intrinsic value.
a. I only
b. II only
c. Both I and II
d. Neither I or II
43. Which of the following tests can be used to demonstrate that model errors are unbiased and normally distributed?
I. QQ plot
II. R-squared
III. Autocorrelation test
a. I and II
b. I and III
c. II and III
d. I, II and III
44. Which of the following statements about the storage of natural gas is/are correct?
I. Gas is stored to provide base load storage to meet seasonal demands.
II. Gas is stored to provide peak storage to smooth out the demand curve.
a. I only
b. II only
c. Both I and II
d. Neither I or II
45. Countries have varying policies regarding hydropower, with some countries making it a national policy to rely
on hydropower. From the options below, choose the one that correctly lists the four countries from highest-
to-lowest in terms of the ratio of hydropower-generated electricity to total national electricity generation:
a. Sweden, Norway, Brazil, Canada
b. Canada, Norway, Brazil, Sweden
c. Brazil, Canada, Sweden, Norway
d. Norway, Brazil, Canada, Sweden
16 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
46. Patel is managing a portfolio with 100 long puts on March peak forward power contracts. If the delta of the
put contracts is -0.4, what position in March peak forward power contracts does Patel need to create for the
combined portfolio to be delta neutral?
a. Short 40 March Peak Forward contracts
b. Long 40 March Peak Forward contracts
c. Short 60 March Peak Forward contracts
d. Long 60 March Peak Forward contracts
47. A producer holding a commodity is said to be _____ and could hedge by going _____ a forward contract.
a. Long, long
b. Long, short
c. Short, short
d. Short, long
48. A natural gas-fired power plant uses 15,200 MMBtu of gas to generate 2,000 MWh of electricity. What is the
heat rate for this power plant?
a. 0.131 MMBtu/MWh
b. 7.6 MMBtu/MWh
c. 30.4 MMBtu/MWh
d. 7,600 MMBtu/MWh
49. A 3-month natural gas option with a strike of USD 6.00 on an August contract is trading at a Black-implied
volatility of 45%. Another call option with the same contract specifications, with a strike of USD 6.50, is trading
at a Black-implied volatility of 50%, producing a volatility smile. Which of the following conclusions can be
made given the market information above?
a. The volatility smile tells us that the market is feeling good about the economy and prices are expected to
go higher.
b. The different volatilities for the two call options tell us that the lognormal Black model cannot capture
the true underlying price behavior with a single volatility measure.
c. A call option with the same contract specifications as the two options in the problem but with a strike of
USD 7.00 must therefore be trading at a Black-implied volatility of 55%.
d. The two options should have exactly the same volatility, and therefore this is a case of market arbitrage:
the USD 6.00 option is under-priced relative to the USD 6.50 option.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 17
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
50. Consider global proven recoverable coal reserves. Which of the following correctly lists the countries in order
of largest to smallest recoverable coal reserves?
a. United States, China, Russia, Australia, India
b. Russia, United States, India, China, Australia
c. United States, Russia, China, India, Australia
d. China, United States, Australia, Russia, India
51. Carsten needs to refine petroleum into high octane gasoline. Which process will he use?
a. Horizontal refining
b. Catalytic cracking
c. Distillation process
d. Vertical hydrolytic emersion
52. Which of the following processes refers to the refining of crude oil into separate fractions or cuts?
a. Distillation
b. Treatment
c. Blending
d. Conversion
53. A call swaption is exercised covering 6 months for 100,000 barrels of crude per month. The premium is
USD 1.00 per barrel and the strike price is USD 65 per barrel. During the ensuing six months the average
price is USD 70 per barrel. What is the net cash flow from the swaption?
a. USD 400,000
b. USD 500,000
c. USD 2,400,000
d. USD 3,000,000
54. A call option has a premium of USD 5 and a strike price of USD 28. What is the time value of the call option if
the current price of the underlying is USD 31?
a. USD 5
b. USD 3
c. USD 2
d. USD 0
18 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
55. Eloise, ERP, is the risk manager for a large natural gas company. The company uses a VaR model with a 95%
confidence level to measure risk exposure and compliance. If Eloise is concerned with the impact of extreme
events, she should:
a. Continue VaR testing at the 95% confidence level.
b. Move the VaR confidence level up to 97%.
c. Move the VaR confidence level down to 90%.
d. Implement stress testing to assess the impact of extreme events.
56. Which of the following Greeks measures the sensitivity of an options price to changes in the underlying
instruments implied volatility?
a. Delta
b. Gamma
c. Theta
d. Vega
57. Akiko, an ERP, is pricing a daily transportation deal between Henry Hub and Houston Ship Channel using the
mean-reverting Ornstein-Uhlenbeck process to model gas prices. In order to calculate the at-the-money
(ATM) implied volatilities for Henry Hub and Houston Ship Channel Akiko will need to do which of the following?
a. Calculate the correct volatilities since the implied volatilities from a Black-Scholes calculation are not the
same volatilities used in the Ornstein-Uhlenbeck process.
b. Scale the implied volatilities by 365250 since it is a daily deal.
c. Roughly estimate implied volatilities. Nothing else needs to be done.
d. Scale the implied volatilities by 250365 since it is a daily deal.
58. The Cost of Alternative Transportation method of establishing pipeline shipping rates involves comparison
against the costs of alternative forms of product transportation such as ship, barge, rail, and truck. Assuming
the cost of shipping 1,000 bbl of crude from Tucson, AZ to St. Louis, MO via truck is USD 25/bbl, and by rail
is USD 21/bbl, what would be the appropriate charge for transporting 1,000 bbl of crude by pipeline?
a. USD 23.00 USD 25.00/bbl
b. USD 19.50 USD 21.00/bbl
c. USD 24.50 USD 25.50/bbl
d. USD 21.00 USD 22.50/bbl
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 19
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
59. Hydroelectric projects are not being pursued in many developed nations despite the fact they are an
emissions-free source of power. What is the primary reason most developed countries are not building
hydroelectric plants?
a. National environmental regulations make the construction of new hydro projects extremely difficult
b. Without a global cap-and-trade emissions scheme, it is less-expensive to build fossil fuel-powered
generation plants
c. Government incentives favor renewable projects like wind and solar over hydroelectric plants
d. Most developed nations have already largely exploited their hydroelectric potential
60. Which of the following statements regarding oil sands production are true?
I. Extracting oil sands on a large scale has significant environmental impacts.
II. Mining and in-situ operations in oil sands use a significant amount of water.
III. Large tailing ponds are created in the production of oil sands and their management is one of the main
challenges for the industry.
a. Statement I
b. Statement III
c. Statements I and III
d. All are correct
Energy Risk
Professional(ERP

)
Examination
Practice Exam 1
Answers
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 21
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
a. b. c. d.
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
16.
17.
18.
19.
20.
21.
22.
23.
24.
25.
26.
27.
28.
29.
30.
31.
32.
a. b. c. d.
33.
34.
35.
36.
37.
38.
39.
40.
41.
42.
43.
44.
45.
46.
47.
48.
49.
50.
51.
52.
53.
54.
55.
56.
57.
58.
59.
60.
Correct way to complete
1.
Wrong way to complete
1. 8 3
Energy Risk
Professional(ERP

)
Examination
Practice Exam 1
Explanations
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 23
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
1. An electric power generator is offering the following four separate bids:
50 MW at USD 20 per MW
100 MW at USD 25 per MW
150 MW at USD 30 per MW
250 MW at USD 40 per MW
What would the market clearing price of electric power be if demand is 175 MW?
a. USD 40.00/MW
b. USD 26.25/MW
c. USD 32.72/MW
d. USD 30.00/MW
Correct answer: a
Reading reference: Making Competition Work in Electricity, Hunt, Chapter 2, p. 170.
Explanation: Answer a is correct. Use the price quoted for 250 MW: apply this amount (USD 40) to any
demand level between 150 and 250 MW.
2. Devon is interested in creating a synthetic commodity by combining a forward contract with a zero-coupon
bond. What is the payoff required on the zero-coupon bond if the annual risk-free interest rate on a continuous
basis is 2% and the price of the commodity forward contract at time 0 is F0,T = USD 150 (where T = 1 year)?
a. USD 147
b. USD 150
c. USD 153
d. USD 156
Correct answer: b
Reading reference: Fundamentals of Derivatives Markets, McDonald, Chapter 6, p.171.
Explanation: Answer b is correct because, in creating a synthetic, we enter into a commodity forward con-
tract and purchase a zero coupon bond equaling e-rt* F0,T, this value is USD 147. The payoff is USD 150. The
total payoff in formula form is: ST F0,T + F0,T, or the payoff on the forward + the payoff of the zero bond.
Answer a is incorrect because it is the investment, at time 0, in the zero bond.
24 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
3. The Senior Management of Cristal Crude Refinery is planning to build a new refinery complex in Indonesia
that includes a coker. Which of the following is true about the new refinery?
a. The refinery is a hydroskimming refinery.
b. The refinery is classified as a simple refinery.
c. The refinery is best suited for processing heavy crude oil.
d. The refinery will produce nearly as much residual fuel as gasoline.
Correct answer: c
Reading reference: Petroleum Refining in Nontechnical Language, 3rd Edition, Leffler: Chapter 20.
Explanation: The presence of a coker defines this as a very complex refinery; very complex refineries usually
make their best margins in processing heavy crude, which the coker allows them to break down into more desir-
able light petroleum products. Very complex refineries produce little or no residual fuel oil. By comparison,
hydroskimming refineries are classified as simple refineries that do not include cokers and usually cannot prof-
itably refine heavy crude. Since you know your refinery includes a coker, this means that answer b is correct.
4. Which of the following statements regarding the transportation of petroleum products is correct?
a. Natural gas liquids like ethane, ethane-propane mixtures and LPGs are commonly transported by
dedicated pipeline.
b. Contamination is usually an issue when butane is transported via the same pipeline as gasoline and diesel.
c. Ethane-propane mixtures are seldom transported via pipeline.
d. Natural gasoline is typically transported through its own dedicated pipeline.
Correct answer: a
Reading reference: Fundamentals of Natural Gas Processing, Kidnay and Parish, Chapter 12, p. 261.
Explanation: Answer a is correct; LPGs are typically transported through their own product-specific pipelines.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 25
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
5. Which of the following best describes a royalty payment?
a. An amount equal to a percentage of the value of production paid by the holder to the State in cash
or in kind.
b. An amount paid by the contract holder to an independent agent for the right to exploit an asset.
c. The money collected by the site inspector.
d. A tax on production volume, independent of profits.
Correct answer: a
Reading reference: Oil, Gas Exploration and Production, Institut Francais: Chapter 3, p. 198-200.
Explanation: A royalty is an amount equal to a percentage of the value of production, paid by the holder to
the State in cash or in kind. It is effectively a tax directly proportional to the value of production, that is, a tax
on turnover, and independent of profits. The amount of the royalty depends not only on the percentage
applying, but also on a number of other parameters which must be carefully specified.
6. Which of the following energy forward contracts will have the greatest mark-to-market sensitivity to a single-
day price spike created by an unplanned outage at a large generation plant during the delivery period?
a. 5 x 16 contract for a week
b. On-peak contract for delivery over the entire month
c. Round-the-clock contract for delivery over a two-month period
d. A 5 x 8, 2 x 2 4 calendar year contract
Correct answer: a
Reading reference: Energy Risk, Pilipovic: Chapter 7, p. 173-179.
Explanation: A forward contract for delivery over a number of days is valued as a weighted average of the
daily forward prices, be it the on-peak, off-peak, or round-the-clock prices given the contract specifications.
Hence, a price spike expected to occur for just one of the days in the period will have the greatest impact on
the shorter time period of delivery. That would make answer a the best answer above. Additionally, on-peak
markets (5 x 16) tend to be more volatile than the round-the-clock markets (7 x 24), which further tend to be
more volatile than the off-peak markets (5 x 8,2 x 24). Hence, in this regard, a is also the best answer.
26 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
7. Heinz provides risk management support to a multinational energy trading desk. His primary responsibility is
to inform the Chief Risk Officer about derivatives trades executed each day along with all trader risk limit
exceptions. Which of the following risk control categories best describes Heinzs primary responsibility?
a. Risk Reporting
b. Risk Review
c. Risk Assessment
d. Risk Control
Correct answer: a
Reading reference: Energy Markets: Price Risk Management and Trading, Tom James; Chapter 10, p. 183-84.
Explanation: Reporting derivatives positions to upper management is a duty that falls under the reporting
(communications) category of risk control; it is an important aspect of risk management because if upper
management is not informed of derivative usage the effects on the company can be devastating. Daily
reporting of derivative positions is not the same as an in-depth internal review of a company's finances or an
audit, thus b is not the correct answer; nor do the reporting duties fall under the risk assessment or manage-
ment control categories.
8. Jim Johnson is studying issues associated with electricity options. Which of the following statements regarding
electricity options is correct?
a. Option models (i.e. Black-Scholes) can be modified to handle electricity as well as financials
b. The use of convenience yield compensates for electricity price spikes
c. Asian options are popular among electricity risk managers because of to their averaging feature
d. The no-arbitrage argument can be applied to electricity in order to value derivatives
Correct answer: c
Reading reference: Fundamentals of Electricity Derivatives, Kaminski, Chapter 2, p.64.
Explanation: Answer c is correct according to the authors Asian options are gaining in popularity among
electricity managers for this reason.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 27
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
9. A power plant enters into a natural gas contract that has a take-or-pay value of 85% and a swing value of
20%. If the contract specifies delivery of 120 MWh of natural gas equivalent, what is the minimum amount of
gas that must be purchased under the terms of the contract?
a. 24 MWh
b. 96 MWh
c. 102 MWh
d. 120 MWh
Correct answer: c
Reading reference: Managing Energy Risk: An Integrated View on Power and Other Energy Markets, Burger,
Graeber, and Schindlmayer, Chapter 4, p. 166-177.
Explanation: The take-or-pay percentage refers to the percentage of the contract that must be paid for
whether the importer wants to take delivery of the gas or not. For this contract, the minimum that must be
paid for is 85% x 120 MWh = 102 MWh.
10. Consider the delta profile for at-the-money European call forward options on NYMEX crude oil. What is the
approximate delta value when the strike price is close to the forward price?
a. 0.00
b. 0.25
c. 0.50
d. 1.00
Correct answer: c
Reading reference: Energy Derivatives: Pricing and Risk Management, Clewlow and Strickland; Chapter 9, p. 166.
Explanation: Answer c is correct. For at-the-money options, where the strike price is close to the forward
price the delta is approximately 0.5.
11. Which of the following is NOT a method for managing credit-risk exposure within energy markets?
a. Clearing OTC energy derivatives
b. Obtaining credit risk insurance
c. Purchasing commodity forward contracts
d. Securing a financial guarantee via an Irrevocable Standby Letter of Credit
Correct answer: c
Reading reference: Energy Markets: Price Risk Management and Trading, James: Chapter 16, p. 319-21.
Explanation: Methods for managing credit-risk exposure include: master netting; collateralization; financial
guarantees; credit insurance; credit derivatives; assignment; and clearing OTC energy derivatives. The
purchase of commodity futures is a hedging strategy.
28 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
12. Karachaganak, Kazakhstan is one of the largest gas condensate fields in the world, with proven reserves of
1.9 billion barrels of oil and 13 trillion cubic feet of gas. In 2004, the field produced about 220,000 barrels of
oil and 1.3 billion cubic feet of gas per day. What is the producing gas-oil ratio?
a. 4,300
b. 5,909
c. 6,842
d. 7,523
Correct answer: b
Reading reference: Norman J. Hyne. Nontechnical Guide to Petroleum Geology, Exploration, Drilling, and
Production, 2nd Edition (Tulsa, OK: PennWell, 2001): Chapter 1, p. 11.
Explanation: Answer B is correct. The definition of producing gas-oil ratio requires gas production (in cubic
feet) to be divided by oil production (in barrels). Thus, GOR = (1,300,000,000 cf)/(220,000 bbl) = 5,909.
Note that the gas-oil ratio of the proved reserves is computed as (13 Tcf)/(1.9 Bbbl) = 6,842 which denotes a
field with oil (condensate) and gas production.
13. LNG suppliers must assure the quality of the gas from their LNG terminals in order to fulfill which of the
following specifications?
a. It is characteristic of the gas as it came from the reservoir.
b. It meets the sellers specifications.
c. It is free of methane.
d. It is consistent with the requirements of downstream gas customers.
Correct answer: d
Reading reference: LNG: A Nontechnical Guide, Tusiani and Shearer, Chapter 7, p. 180.
Explanation: Answer d is correct. The quality of the gas that comes from an LNG import terminal must be
consistent with the requirements of downstream gas customers or meet the specifications of the intercon-
nected gas transmission lines, which vary by region and by country.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 29
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
14. Two manufacturing plants Factory Alpha and Factory Bravo are told by the government they each need
to reduce their greenhouse gas emissions. The target reductions and costs for each factory to meet this goal
are shown in the table below.
Alpha Bravo
Required emissions reductions 10 tons 10 tons
Cost of emissions reductions USD 120 per ton USD 40 per ton
Total cost of reductions USD 1,200 USD 400
Under an emissions trading scheme, Factory Alpha can pay Factory Bravo to reduce its emissions by an addi-
tional 10 tons, in effect, buying the needed emissions credit from Bravo.
What will Bravos final emission reduction cost be if it charges Alpha USD 600 for the emissions credit?
a. USD 200
b. USD 600
c. USD 800
d. USD 1,000
Correct answer: a
Reading reference: Energy and Emissions Markets: Collision or Convergence?, James and Fusaro; Chapter 3,
p. 31-32.
Explanation: By making the deal with Factory Alpha, Factory Bravos total cost of reductions will be USD 200
(answer A). Bravo will now have to reduce their emissions by 20 tons, at USD 40 per ton; this will cost Bravo
USD 800. Bravo will receive a payment from Alpha of USD 600, making their final costs USD 200
(800 600 = 200).
30 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
15. A trader at XYZ Bank has been asked by a client who is a petroleum refiner client to quote the price on a
3-month crude oil forward contract. Given the following forward curve and discount factors for crude oil,
calculate the price of the 3 month forward contract.
Contract Price Discount Factor
Jan Contract USD 79.10/bbl 0.95
Feb Contract USD 85.60/bbl 0.92
Mar Contract USD 83.90/bbl 0.88
a. USD 80.37
b. USD 82.81
c. USD 75.91
d. USD 90.40
Correct answer: b
Reading reference: Markus Burger, Bernhard Graeber, and Gero Schindlmayr. Managing Energy Risk:
Integrated View on Power and Other Energy Markets (West Sussex, England: John Wiley & Sons, 2007):
Chapter 2, p. 50.
Explanation: Answer b is correct, the equation is as follows:
16. You have been asked by your supervisor to hedge a daily power option. Which is the most appropriate
contract to use to hedge the daily option?
a. Daily forward contract
b. Daily futures contract
c. OTC swap contract
d. Balance-of-the-month contract
Correct answer: d
Reading reference: Fundamentals of Electricity Derivatives, Kaminski: Chapter 2, p. 60, 70.
Explanation: Most power markets, except perhaps the Nord Pool, do not have liquid markets for daily
forward or futures contracts, so it is best to use a balance-of-the-month contract as a surrogate for daily
forward/futures contracts to hedge daily options. The balance-of-the-month price is the price of power
delivered every day from today until end of current month.
Q1 Contract =
79.1 * 0.95 + 85.6 * 0.92 + 83.9 * 0.88 227.729
0.95 + 0.92 + 0.88 2.75
= 82
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 31
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
17. Which of the following is NOT a disputable point in the performance of an energy commodity contract?
a. Credit ratings
b. Missed deliveries or deadlines
c. Poor commodity quality
d. Default on a debt
Correct answer: a
Reading reference: Fundamentals of Electricity Derivatives, Kaminski; Chapter 12, p. 348-9.
Explanation: Answer a is correct. Events and disputes that may come up with a physical contract include
force majeure, the quality of the commodity being delivered, default on a debt, missed payments, or missed
deliveries. Credit ratings are not created in a contract but rather via third parties.
18. Which of the following statements is/are true about the impact of a Smart Grid?
I. A smart grid is a more flexible control system that maximizes the utility of existing transmission assets
and delays the need for creating new ones.
II. A smart grid provides better control of the transmission system allowing peaker plants to run during
periods of congestion
a. I only
b. II only
c. Both I and II are correct
d. Neither I or II are correct
Correct answer: a
Reading references: US Department of Energy, The Smart Grid: An Introduction.
Explanation: Answer a is correct: statement I is true because newer technology will allow better rerouting of
excess power in constrained zones through underutilized transmission assets, while statement II is false
because through better utilization of transmission lines during congestion, peaker plants within congested
areas will not have to run just to meet the demand.
32 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
19. Which of the statements below is/are an advantage of using Geometric Brownian motion (GBM) to model
electricity prices?
I. GBM is an industry standard that can be easily applied for efficient computer simulation
II. GBM is a stochastic process that captures the fat tails of price distributions
a. I only
b. II only
c. Both I and II are correct
d. Neither I or II are correct
Correct answer: a
Reading reference: Energy and Power Risk Management: New Developments in Modeling, Pricing, and
Hedging, Eydeland & Wolyniec: Chapter 4, p. 161-2.
Explanation: Answer a is correct, Statement I is the only true statement as per the reading. Statement II is
false, the principal weakness of GBM (cited on p. 162) is that it does not allow the modeling of fat tails of
price distributions.
20. Consider the following yields from a simple, complex, and very complex refinery. Each is processing the same
sour, heavy crude oil. Based on the output products listed, identify refineries X, Y, and Z by their complexity level.
Product Type\Refinery X Y Z
Gasoline 60 50 30
Jet Fuel 15 15 15
Distillate Fuel 25 25 20
Residual Fuel
Coke 5
Refinery Fuel 15 10 8
Gain (20) (5) (3)
a. X = simple, Y = complex, Z = very complex
b. X = simple, Y = very complex, Z = complex
c. X = complex, Y = simple, Z = very complex
d. X = very complex, Y = complex, Z = simple
Correct answer: d
Reading reference: Petroleum Refining in Nontechnical Language, 3rd Edition, Leffler: Chapter 20, p. 196.
Explanation: d is correct. Refinery complexity refers to the capacity and type of processing units that com-
prise a refinery. Refinery complexity will increase when complex units with large capacity are added since
they have greater ability to convert (heavy) crude input into gasoline. For a given grade of crude oil (in this
case, medium sour, heavy), as the complexity of the refinery increases the gasoline yield increases and the
residual fuel yield decreases (the residual fuel stream is being converted to gasoline).
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 33
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
21. Which facility type is usually considered the least desirable option for underground storage of natural gas
because of expense and operational constraints?
a. Depleted oil and gas fields
b. Aquifers
c. Salt caverns
d. Storage tanks
Correct answer: b
Reading reference: Fundamentals of Natural Gas Processing, Kidnay and Parrish: Chapter 12, p. 257.
Explanation: B is correct. Aquifers are considered the least desirable underground storage facility for several
reasons the geology of the aquifer is usually not well understood, infrastructure (wells, pumps, compres-
sors, etc.) is unavailable at the site, greater injection pressures mean higher operating cost, gas will need to
be dehydrated, and more stringent environmental regulations will be in place.
22. Consider a power grid where the average heat rate for combined cycle gas turbine plants using natural gas is
8,500 Btu/kWh. The price of natural gas is USD 5.00/MMBtu, and the price of electricity is USD 30.00/MWh.
What is the spark spread for this particular power grid?
a. USD 0.0125/kWh
b. USD 0.1250/kWh
c. USD -0.0125/kWh
d. USD -0.1250/kWh
Correct answer: c
Reading reference: Vincent Kaminski (ed). Managing Energy Price Risk, Chapter 3, p.120.
Explanation: Answer c is correct, the calculation is as follows:
Spark Spread = Output Price Input Price
Output Price = USD 30/MWh x 1MWh/1000kWh = USD 0.03/kWh
Input Price= 8500 Btu/kWh x USD 5/1,000,000Btu = USD 0.0425/kWh
Therefore, the Spark Spread = -0.0125
34 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
23. Ann Kelly buys a long call at a strike of USD 50 and sells a long call at a strike of USD 75. She has purchased
which of the following structures?
a. Bull spread
b. Bear spread
c. Participating collar
d. Participating cap
Correct answer: a
Reading reference: Managing Energy Price Risk, Kaminski, Chapter 2, p.60.
Explanation: Answer a is correct since, a bull spread is comprised of buying a long call and selling the upside
by selling a long call at a higher strike price (than the purchased long call).
24. Simone is interested in capturing large price swings in her energy portfolio and decides to use the delta-normal
approach to compute portfolio VaR. The delta-normal approach will be least likely to capture large price
changes in which of the following instruments?
a. Futures
b. Forwards
c. Swaps
d. Options
Correct answer: d
Reading reference: Energy Risk Management: A Non-technical Introduction to Energy Derivatives, Leppard;
Chapter 4, p. 200-205.
Explanation: d is correct. Since the delta-VaR method is a linear approximation, it works well only if a given
portfolio is linear or close to linear. The term linear portfolio means that it consists of products that depend
linearly on the risk factor changes. For example, a portfolio consisting of futures, forward and swaps is a lin-
ear portfolio. On the other hand, if there are many options in the portfolio it may be far from being linear. In
fact, an energy portfolio is expected to be very nonlinear, especially if there are many asset-type deals (e.g.
storage, generation, load service, and so on). In this case, linear approximation may be missing big changes in
the portfolio values due to nonlinearity. Hence, delta-VaR method may yield inaccurate results for an energy
portfolio consisting of options, since they are not linear instruments.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 35
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
25. Which of the following statements regarding LNG project costs is correct?
a. The construction of liquefaction plant facilities typically represents the LNG chains most significant
capital investment.
b. LNG storage tank costs are independent of liquefaction plant location.
c. The cost of a liquefaction plant is considered part of the upstream costs.
d. One unusual aspect of LNG upstream and downstream development is that future additions to achieve
economies of scale are not planned due to the high cost of building LNG facilities.
Correct answer: a
Reading reference: LNG: A Nontechnical Guide, Tusiani: Chapter 11, p. 301.
Explanation: Answer a is correct; it is generally the most significant capital item. Answer b is incorrect, since
storage tank costs are dependent on location, as well as, total production, distance from market and tank
system design. The cost of a liquefaction plant are downstream, therefore, answer c is incorrect. Answer d is
incorrect, since future additions are anticipated and undertaken if sufficient reserves are present.
26. A major hurricane has shut down drilling activity on hundreds of oil rigs across the Gulf of Mexico. The
resulting supply disruption has caused the cash (spot) price of WTI crude to spike above the price of longer
dated futures contracts. As a result the WTI contract is said to be trading in _____________.
a. backwardation
b. contango
c. short-term disequilibrium
d. extreme volatility
Correct answer: a
Reading reference: Risk Management in Commodity Markets, Geman: Chapter 2, p. 11.
Explanation: Answer a is correct. A market in backwardation (inverted market) is characterized by cash
(spot) prices that are higher than longer dated futures contracts. In contrast, a market in contango is charac-
terized by an upward sloping forward price curve.
36 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
27. High pressure in subsurface reservoirs can cause a significant volume of natural gas to be dissolved in
underground crude oil reserves. Which of the following is the correct term for this build-up of gas?
a. Non-associated gas
b. Crude oil gas
c. Associated gas
d. Free gas
Correct answer: c
Reading reference: Nontechnical Guide to Petroleum Geology, Exploration, Drilling, and Production, Hyne:
Chapter 1, p. 11.
Explanation: b is correct. Because of high pressure in the subsurface reservoir, a considerable volume of
natural gas can be dissolved in crude oil. The formation, dissolved or solution gas/oil ratiois the cubic feet
of natural gas dissolved in one barrel of oil in that reservoir under subsurface conditions. The volume meas-
urements are reported under surface conditions. In general, as the pressure of the reservoir increases with
depth, the amount of natural gas that can be dissolved in crude oil increases. When crude oil is lifted up a
well to the surface, the pressure is relieved, and the natural gas, called solution gas, bubbles out of the oil.
The producing gas-oil ratio (GOR) of a well is the number of cubic feet of gas the well produces per barrel
of oil. Non-associated natural gas is gas that is not in contact with oil in the subsurface. A non-associated
gas well produces almost pure methane. Associated natural gas occurs in contact with crude oil in the
subsurface. It occurs both as gas in the free gas cap above the oil and gas dissolved in the crude oil.
28. Which of the following geographic regions is the largest importer of coal?
a. Asia
b. Europe
c. Former Soviet Union
d. North America
Correct answer: a
Reading reference: Producing Liquid Fuels from Coal: Prospects and Policy Issues, Bartis; Chapter 2, p. 6.
Explanation: The chief importers of coal are Asian nations bordering the Pacific Ocean, including Japan,
South Korea and China, making a the correct choice.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 37
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
29. Environmental impacts must be considered when evaluating the operating efficiency of an electric generation
facility. Using the information below calculate the economic impact of sulfur dioxide (SO2) in the cost of
producing each MWh of electricity at Acme Power Generation.
Heat rate is 8 MMBtu/MWh
SO2 price is USD 600 per ton (2,000 pounds/ton)
SO2 rate is 2.00 lbs per MMBtu
a. USD 2.40 per MWh
b. USD 8.25 per MWh
c. USD 9.60 per MWh
d. USD 4.80 per MWh
Correct answer: d
Reading reference: James and Fusaro, Energy and Emissions Markets, Chapter 3.
Explanation: Answer d is correct: 8 * 2 *(1/2000) *USD 600 per ton = 4.80. a is incorrect:
8 *2*(1/4000) *USD 600 = USD 2.40 per MWH (use of 4,000 for lbs per ton), B is incorrect; just a guess,
b is Incorrect: use of 1,000 lbs per ton.
30. Andreas purchased a monthly 100 MW on-peak power call option for a month that has 20 business days. The
strike price is USD 75/MWh and the premium is USD 5/MWh. What would the gross settlement amount be if
Andreas exercised the call option in a month when the average on-peak power price was USD 85/MWh?
a. USD 160,000
b. USD 240,000
c. USD 320,000
d. USD 480,000
Correct answer: c
Reading reference: Managing Energy Price Risk, Kaminski: Chapter 2, p. 46.
Explanation: The correct answer is c: the payoff does not include the amount of premium (32,000 MWH x
USD 85 - USD 75). Payout is max (St k,0) x Q, wherein Q = quantity. a is incorrect, because it includes the pre-
mium cost of USD 160,000 (i.e. 32,000 MWH x USD 5). b is incorrect, because it assumes all-hours of 48,000
MWH and premium cost (48,000 MWH x USD 85 - USD 75-USD 5). d is incorrect, because it assume all-hours
of 48,000 MWH (48,000 MWH x USD 85 -USD 75). Assumes candidates will know on-peak power call option
means for 16 hours per day.
38 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
31. Which of the following is an example of basis risk?
a. The risk of a natural gas price spike during peak electricity demand for a gas fired power generation plant.
b. The risk of failure to comply with FERC financial reporting regulations.
c. The risk that a megawatt of electricity will cost USD 75 in Pennsylvania and USD 82.50 in New York.
d. The risk of the inability of a power generation plant to meet demand in a given market.
Correct answer: c
Reading reference: Energy Risk, Pilipovic: Chapter 2, p. 32.
Explanation: Answer c is correct. Decentralization introduces geographic basis risk, which is unique to ener-
gies. In financial markets,todays dollar is worth a dollar anywhere in the country. In energy markets, price
depends on location. A megawatt of electricity is priced according to delivery point; the same holds true for
natural gas. Location is a fundamental driver of price. Pilipovic defines basis risk as the difference in prices
between identical products but in two different markets.
32. Makati and Sons Heating Oil Company expects customer demand to average 2,200 gallons of heating oil
during the upcoming heating season. The company sells oil to customers using fixed price contracts and has
decided to store enough oil to meet average customer demand of 2,300 gallons. They have also purchased
call options to protect against the risk of a much colder than expected winter. What risk is the company
primarily seeking to hedge?
a. Volume Risk
b. Supply Risk
c. Credit Risk
d. Location Basis Risk
Correct answer: a
Reading reference: Surviving Energy Prices, Beutel, Chapter 3, p. 29-30.
Explanation: Answer a is correct, the heating oil company is concerned about a colder than expected winter,
but does not want to be stuck with an excess of inventory. Call options allow the company to purchase addi-
tional inventory at a set price should temperatures drop below normal, the options can expire unused if the
winter temperatures are at a normal level.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 39
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
33. On June 20, Caufield Refining estimates it will need to purchase 40,000 barrels of crude on October 12.
Caufield decides to hedge price risk using a November NYMEX futures contract. The November futures price
on June 20 is USD 67.00/bbl. On October 12, Caufield is ready to purchase its required crude oil and closes
out the futures contract on that day; at this time the spot price is USD 70.10/bbl and the futures price is
USD 68.50/bbl. In this scenario, what is the effective price paid per barrel?
a. USD 68.50
b. USD 68.60
c. USD 70.10
d. USD 70.40
Correct answer: b
Reading reference: Energy Markets: Price Risk Management, James: Chapter 13, p. 263.
Explanation: The effective price paid (in dollars per barrel) is the final spot price less the gain on the futures, or
70.10 1.50 = 68.60. This can also be calculated as the initial futures price plus the final basis, 67.00 + 1.60 = 68.60.
34. An oil field estimated to have 50 Mbbl of oil is classified as "P90." What does this classification indicate?
a. That there is a 90% probability the oil field will actually produce more than 50 Mbbl of oil.
b. That there is a 90% probability the oil field contains 50 Mbbl of oil.
c. That the oil field is 90% depleted.
d. That the oil field is determined to contain of 90% petroleum and 10% other material (e.g. natural gas).
Correct answer: a
Reading reference: Oil, Gas Exploration, and Production, Institut Francais; Chapter 3, p. 91.
Explanation: In 1997 the Society of Petroleum Engineers (SPE) and the World Petroleum Council formulated
and adopted standards of reserve definitions. Px is defined as a number such that there is an x% likelihood
that the true reserves exceed Px. For example, if the P10 of a field is 100 Mbbl, there is a 10% probability that
the actual size of the field exceeds 100 Mbbl. Thus, in this case, P90 indicates a 90% probability the oil field
will actually produce more than 50 Mbbl of oil. Other relevant classifications include P95, P50, P10 and P5.
40 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
35. Black Gold Co. is a firm specializing in the exploration, acquisition and drilling of new crude oil fields. Based
on these activities, Black Gold would best be described as what type of oil operation?
a. Independent
b. Integrated
c. Speculative
d. Wildcat
Correct answer: a
Reading reference: Fundamentals of Oil & Gas Accounting, Wright & Gallun; Chapter 1, p. 1.
Explanation: Independent oil and gas companies are typically described as companies primarily involved in
exploration and production (E&P) activities, as is Black Gold. Integrated oil and gas companies are usually
involved in at least one downstream activity as well as E&P activities.
36. Which of the following is NOT considered a primary model for electricity trading arrangements?
a. Integrated model
b. Open access model
c. Wheeling model
d. Decentralized model
Correct answer: b
Reading reference: Making Competition Work in Electricity, Hunt: Chapter 7, p. 127-9.
Explanation: Answer b is correct, by definition it is not one of the models.
37. You have a portfolio of gas calls and puts that is gamma neutral. Which of the following trading strategies
would you implement to make your portfolio delta neutral?
a. Purchase a call option
b. Purchase a forward contract
c. Purchase either a call or a put option
d. By definition a gamma neutral portfolio is also delta neutral so no action is necessary
Correct answer: b
Reading reference: Clewlow and Strickland: Chapter 9.3, p. 170.
Explanation: Answer b is correct. Call and put options have delta and gamma values. So the initial portfolio
would be constructed with calls and puts such that the gamma of the portfolio was zero. There is no guaran-
tee that the portfolio would also have zero Delta. Since forward contracts are linear, they only have delta and
no gamma. Consequently to ensure that a gamma neutral portfolio was also delta neutral, you would buy or
sell the right number of forward contracts to make it delta neutral.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 41
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
38. Steve Dolan is a power manager at Upstate Electric. He is negotiating a one-day contract to sell 100 MWh of
electricity at USD 55/MWh for a 24-hour period and has been asked to calculate the Value-at-Risk (VaR) for
the contract. If the daily volatility of electricity prices is 2%, what is the daily VaR on the contract assuming a
95% confidence interval?
a. USD 180
b. USD 3,447
c. USD 4,330
d. USD 5,412
Correct answer: c
Reading reference: Price Risk Management in the Energy Industry: The Value at Risk Approach, Mauro, Section 6.
Explanation: Answer c is correct: it is 100 x 55 x 24 x .02 x 1.64 = USD 4,330. Since the contract is for one
day, no time adjustment is needed. Answer a does not include 24 hours in the calculation 100 x 55 x .02 x 1.64
= USD 180; b assumes a time adjustment of 365 and does not use 24 in the calculation 100 x 55 x .02 x 1.64
x 365 = USD 3,447; d assumes a 98% confidence interval using 2.05 in the calculation 100 x 55 x 24 x .02 x
2.05 = USD 5,412
39. Which of the following pricing relationships include the elements of convenience yield?
a. Spot price
b. Expected spot price
c. Strike price
d. Forward price
Correct answer: d
Reading reference: Managing Energy Risk: A Nontechnical Guide to Markets and Trading, Wengler;
Chapter 6, p. 117.
Explanation: The forward price includes the cost of risk, cost of carry, cost of money and other factors included
within the concept of the convenience yield.
42 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
40. Wet gas refers to ______________.
a. Gas that has a high moisture content
b. Gas that has a heating value greater than methane.
c. Gas that has not been scrubbed of its sulfur impurities
d. None of the above
Correct answer: b
Reading reference: LNG: A Nontechnical Guide, Tusiani and Shearer, Chapter 3, p. 70.
Explanation: Answer b is correct. Wet gas contains a higher composition of higher-chain hydrocarbons such
as propane, butane, and condensates; it has a higher heating value relative to dry gas (methane).
41. Given the following information, how much power capacity (in MWs) would load serving entities in a capacity
market be required to purchase to make the building of additional capacity economically viable?
Expected end-user peak load: 100 MW
Average end-user load: 90 MW
Percentage reserve margin: 10%
a. 10 MW
b. 110 MW
c. 100 MW
d. 99 MW
Correct answer: b
Reading reference: Making Competition Work in Electricity, Hunt: Chapter 8, p. 166.
Explanation: Answer b is correct. Under the capacity obligation system, load serving entities are required to
purchase capacity tickets which require them to be able to cover a peak load, plus a reserve. The number of
tickets is determined by the formula of peak load, multiplied by (1+x) or the reserve margin percentage. In
the scenario above, this gives an answer of 110 MW.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 43
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
42. Which of the following statements is/are true regarding option valuation?
I. The intrinsic value of a call option is greatest when the value of the underlying is equal to the strike price
of the option.
II. The time value is the difference between the market quoted premium and the intrinsic value.
a. I only
b. II only
c. Both I and II
d. Neither I or II
Correct answer: b
Reading reference: Energy Modelling: Advances in the Management of Uncertainty, Kaminski (Hampton):
Chapter 2, p. 52.
Explanation: Answer b is correct: Statement I is false, all else equal, time value will be greatest when the
underlying is trading at the strike price; Statement II is true, by definition the time value of an option is equal
to the difference between the market quoted premium and the intrinsic value.
43. Which of the following tests can be used to demonstrate that model errors are unbiased and normally distributed?
I. QQ plot
II. R-squared
III. Autocorrelation test
a. I and II
b. I and III
c. II and III
d. I, II and III
Correct answer: b
Reading reference: Energy Risk, Pilipovic; Chapter 4, p. 81-84.
Explanation: QQ plot and the autocorrelation test are used for testing that errors are normally distributed
and that there is no bias from error to error. R-squared measure, on the other hand, measures how well the
model fits the data. Hence, it tells us nothing about the distribution of the errors, but gives us general infor-
mation about model performance. Hence, the correct answer is b.
44 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
44. Which of the following statements about the storage of natural gas is/are correct?
I. Gas is stored to provide base load storage to meet seasonal demands.
II. Gas is stored to provide peak storage to smooth out the demand curve.
a. I only
b. II only
c. Both I and II
d. Neither I or II
Correct answer: c
Reading reference: Fundamentals of Natural Gas Processing, Kidnay and Parish: Chapter 12, p. 254.
Explanation: Answer b is correct; by definition both statements are factual.
45. Countries have varying policies regarding hydropower, with some countries making it a national policy to rely
on hydropower. From the options below, choose the one that correctly lists the four countries from highest-
to-lowest in terms of the ratio of hydropower-generated electricity to total national electricity generation:
a. Sweden, Norway, Brazil, Canada
b. Canada, Norway, Brazil, Sweden
c. Brazil, Canada, Sweden, Norway
d. Norway, Brazil, Canada, Sweden
Correct answer: d
Reading reference: Energy for the 21st Century: A Comprehensive Guide to Conventional and Alternative
Sources, Nersesian: Chapter 8, p. 299.
Explanation:The correct ranking from highest to lowest is d: Norway, Brazil, Canada, and Sweden. In
Norway reliance of hydropower is a national policy, nearly all the electricity in Norway is generated from
hydroelectric plants.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 45
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
46. Patel is managing a portfolio with 100 long puts on March peak forward power contracts. If the delta of the
put contracts is -0.4, what position in March peak forward power contracts does Patel need to create for the
combined portfolio to be delta neutral?
a. Short 40 March Peak Forward contracts
b. Long 40 March Peak Forward contracts
c. Short 60 March Peak Forward contracts
d. Long 60 March Peak Forward contracts
Correct answer: b
Reading reference: Energy Derivatives: Pricing and Risk Management, Clewlow and Strickland: Chapter 9.2, p. 164-7.
Explanation: Answer b is correct. A Long Put is really a short position in the underlying, in this case March
Peak Power. In order to make the delta of the complete portfolio neutral or equal to zero, the position in
March Peak Forward power contracts needs to be long an enough to offset the -0.4*100 = -40 of the March
Peak Forward. Consequently, one needs to be long 40 March Peak Forward power contracts.
47. A producer holding a commodity is said to be _____ and could hedge by going _____ a forward contract.
a. Long, long
b. Long, short
c. Short, short
d. Short, long
Correct answer: b
Reading reference: Managing Energy Risk, Burger, Chapter 2.
Explanation: By definition, someone holding a commodity is said to be long and could hedge by going short
a forward contract.
48. A natural gas-fired power plant uses 15,200 MMBtu of gas to generate 2,000 MWh of electricity. What is the
heat rate for this power plant?
a. 0.131 MMBtu/MWh
b. 7.6 MMBtu/MWh
c. 30.4 MMBtu/MWh
d. 7,600 MMBtu/MWh
Correct answer: b
Reading reference: Energy Trading & Investing, Edwards; Chapter 2.2, p. 109.
Explanation: The heat rate is determined by dividing the quantity of fuel used by the quantity of power
produced, in this example 15,200 MMBtu divided by 2,000 MWh = 7.6 MMBtu/MWh.
46 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
49. A 3-month natural gas option with a strike of USD 6.00 on an August contract is trading at a Black-implied
volatility of 45%. Another call option with the same contract specifications, with a strike of USD 6.50, is trading
at a Black-implied volatility of 50%, producing a volatility smile. Which of the following conclusions can be
made given the market information above?
a. The volatility smile tells us that the market is feeling good about the economy and prices are expected to
go higher.
b. The different volatilities for the two call options tell us that the lognormal Black model cannot capture
the true underlying price behavior with a single volatility measure.
c. A call option with the same contract specifications as the two options in the problem but with a strike of
USD 7.00 must therefore be trading at a Black-implied volatility of 55%.
d. The two options should have exactly the same volatility, and therefore this is a case of market arbitrage:
the USD 6.00 option is under-priced relative to the USD 6.50 option.
Correct answer: b
Reading reference: Energy Risk, Pilipovic: Chapter 8, p. 232.
Explanation: Answer b is correct. Black-implied volatilities for options with the same contract specifications
but different strikes are necessary to capture the true underlying price behavior and therefore traded option
prices. Black option pricing model assumes log-normal price behavior for the underlying forward prices,
which generally does not capture the full spectrum of behavior of energy prices given a single volatility
measure. Therefore, the correct answer is b.
50. Consider global proven recoverable coal reserves. Which of the following correctly lists the countries in order
of largest to smallest recoverable coal reserves?
a. United States, China, Russia, Australia, India
b. Russia, United States, India, China, Australia
c. United States, Russia, China, India, Australia
d. China, United States, Australia, Russia, India
Correct answer: c
Reading reference: Producing Liquid Fuels from Coal: Prospects and Policy Issues Bartis, Chapter 2, p. 5.
Explanation: Answer b is correct. As compared to oil and gas resources, coal reserves are often character-
ized as widely dispersed. On one hand this is an accurate characterization, because major portions of the
global reserve base are spread among the continents. On the other hand, the eight nations listed in Table 1.1
hold 88 percent of reported prove recoverable reserves. Leading the list is the United States, with proven
recoverable coal reserves of about 270 billion tons.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 47
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
51. Carsten needs to refine petroleum into high octane gasoline. Which process will he use?
a. Horizontal refining
b. Catalytic cracking
c. Distillation process
d. Vertical hydrolytic emersion
Correct answer: b
Reading reference: Petroleum Refining: Technology and Economics, 5th Edition, Gary: Chapter 1,p. 4.
Explanation: Answer b is correct in that it is the technique to create higher octane gasoline. Answers a and c
relate to an early method of refining, one that does not produce higher octane gasoline. Answer d is incor-
rect because it is a made up term.
52. Which of the following processes refers to the refining of crude oil into separate fractions or cuts?
a. Distillation
b. Treatment
c. Blending
d. Conversion
Correct answer: a
Reading reference: Refining: Technology and Economics, 5th Edition, Gary et al, Chapter 1, p. 2.
Explanation: Answer a is correct; refining begins with distillation by boiling crude, separating the resulting
vapor and cooling it into separate fractions or cuts, creating a range of distilled petroleum products
(gasoline, kerosene, naphtha, etc.) in the process.
53. A call swaption is exercised covering 6 months for 100,000 barrels of crude per month. The premium is
USD 1.00 per barrel and the strike price is USD 65 per barrel. During the ensuing six months the average
price is USD 70 per barrel. What is the net cash flow from the swaption?
a. USD 400,000
b. USD 500,000
c. USD 2,400,000
d. USD 3,000,000
Correct answer: c
Reading reference: Managing Energy Price Risk, Kaminski (Hampton): Chapter 2, p. 78.
Explanation: Answer c is correct as per the formula on page 78: USD 2,400,000 = 600,000 x (70-65-1).
48 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
54. A call option has a premium of USD 5 and a strike price of USD 28. What is the time value of the call option if
the current price of the underlying is USD 31?
a. USD 5
b. USD 3
c. USD 2
d. USD 0
Correct answer: c
Reading reference: Energy Markets: Price Risk Management and Trading, James: Chapter 6, p. 137-8.
Explanation: Answer a is incorrect, this is the premium. b is incorrect, this is the intrinsic value. c is correct. It is
the premium less the intrinsic value: intrinsic value = USD 31 - USD 28 = 3, so USD 5 - USD 3 = USD 2, therefore
time value = USD 2. d is incorrect. Only when the premium and intrinsic value are equal is the time value 0.
55. Eloise, ERP, is the risk manager for a large natural gas company. The company uses a VaR model with a 95%
confidence level to measure risk exposure and compliance. If Eloise is concerned with the impact of extreme
events, she should:
a. Continue VaR testing at the 95% confidence level.
b. Move the VaR confidence level up to 97%.
c. Move the VaR confidence level down to 90%.
d. Implement stress testing to assess the impact of extreme events.
Correct answer: d
Reading reference: Energy and Emissions Markets: Collision or Convergence? James and Fusaro: Chapter 11, p. 194.
Explanation: Answer d is correct, VAR measures only possible realities given a set of inputs, it does not
account for unexpected or extreme events.
56. Which of the following Greeks measures the sensitivity of an options price to changes in the underlying
instruments implied volatility?
a. Delta
b. Gamma
c. Theta
d. Vega
Correct answer: d
Reading reference: Energy Markets: Price Risk Management and Trading, James: Chapter 6, p. 141-3.
Explanation: Answer d is correct, Vega measures the sensitivity of an option to a change in implied volatility.
2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material 49
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
57. Akiko, an ERP, is pricing a daily transportation deal between Henry Hub and Houston Ship Channel using the
mean-reverting Ornstein-Uhlenbeck process to model gas prices. In order to calculate the at-the-money
(ATM) implied volatilities for Henry Hub and Houston Ship Channel Akiko will need to do which of the following?
a. Calculate the correct volatilities since the implied volatilities from a Black-Scholes calculation are not the
same volatilities used in the Ornstein-Uhlenbeck process.
b. Scale the implied volatilities by 365250 since it is a daily deal.
c. Roughly estimate implied volatilities. Nothing else needs to be done.
d. Scale the implied volatilities by 250365 since it is a daily deal.
Correct answer: a
Reading reference: Energy Derivatives: Pricing and Risk Management, Clewlow and Strickland: Chapter 3.2.2, p. 41.
Explanation: Answer a is correct. Volatility has to be estimated in the context of the stochastic process
assumption. The volatility for an Ornstein-Uhlenbeck process has different units to that which is used in the
Black-Scholes model. The volatility for the Ornstein-Uhlenbeck process has units of dollars. The volatilities in
Black-Scholes and Ornstein-Uhlenbeck are not interchangeable.
58. The Cost of Alternative Transportation method of establishing pipeline shipping rates involves comparison
against the costs of alternative forms of product transportation such as ship, barge, rail, and truck. Assuming
the cost of shipping 1,000 bbl of crude from Tucson, AZ to St. Louis, MO via truck is USD 25/bbl, and by rail
is USD 21/bbl, what would be the appropriate charge for transporting 1,000 bbl of crude by pipeline?
a. USD 23.00 USD 25.00/bbl
b. USD 19.50 USD 21.00/bbl
c. USD 24.50 USD 25.50/bbl
d. USD 21.00 USD 22.50/bbl
Correct answer: b
Reading reference: Oil and Gas Pipelines: In Nontechnical Language, Miesner and Leffler: Chapter 10, p. 221.
Explanation: The cost of alternative transportation method involves understanding the rates charged by the
competing forms of transportationship, barge, rail, truck. The pipeline charge will be set equal to or slightly
below those rates. Calculating rates using this method can be very favorable for the pipeline owner, especially
for long-distance transportation.
This Page Left Blank
59. Hydroelectric projects are not being pursued in many developed nations despite the fact they are an
emissions-free source of power. What is the primary reason most developed countries are not building
hydroelectric plants?
a. National environmental regulations make the construction of new hydro projects extremely difficult
b. Without a global cap-and-trade emissions scheme, it is less-expensive to build fossil fuel-powered
generation plants
c. Government incentives favor renewable projects like wind and solar over hydroelectric plants
d. Most developed nations have already largely exploited their hydroelectric potential
Correct answer: d
Reading reference: Renewable Energy in Nontechnical Language, Chambers; Chapter 6, pages 150-152.
Explanation: While all are factors, d is the major reason. With the exception of Canada, most developed
nations have already constructed hydroelectric plants at suitable sites within their national borders. Much
of the future growth in hydropower will come from developing nations like China, Indonesia and Brazil.
60. Which of the following statements regarding oil sands production are true?
I. Extracting oil sands on a large scale has significant environmental impacts.
II. Mining and in-situ operations in oil sands use a significant amount of water.
III. Large tailing ponds are created in the production of oil sands and their management is one of the main
challenges for the industry.
a. Statement I
b. Statement III
c. Statements I and III
d. All are correct
Correct answer: d
Reading reference: Toman: Chapter 4, p. 19-20.
Explanation: d is correct. All statements are factual.
50 2011 Global Association of Risk Professionals. All rights reserved. It is illegal to reproduce this material
in any format without prior written approval of GARP, Global Association of Risk Professionals, Inc.
Energy Risk Professional Examination (ERP) Practice Exam 1
Creating a culture of
risk awareness.
TM
Global Association of
Risk Professionals
111 Town Square Place
Suite 1215
Jersey City, New Jersey 07310
USA
+ 1 201.719.7210
Regus Ofce Number 527
68 King William Street
London EC4N 7DZ
UK
+ 44 (0) 20 7959 2260
www.garp.org
2011 Global Association of Risk Professionals. All rights reserved. 10-11
About GARP | The Global Association of Risk Professionals (GARP) is a not-for-profit global membership organization dedicated to
preparing professionals and organizations to make better informed risk decisions. Membership represents over 150,000 risk manage-
ment practitioners and researchers from banks, investment management firms, government agencies, academic institutions, and
corporations from more than 195 countries. GARP administers the Financial Risk Manager (FRM) and the Energy Risk Professional
(ERP) exams; certifications recognized by risk professionals worldwide. GARP also helps advance the role of risk management via
comprehensive professional education and training for professionals of all levels. www.garp.org.

Você também pode gostar