Você está na página 1de 7

What went wrong?

Unsuccessful information
technology projects

Brenda Whittaker
Senior Consultant, KPMG Consulting, Toronto, Canada

Keywords . Poor estimates or weak definitions of


Computer software, Introduction requirements at the project planning stage
Information technology,
Project control, Information technology (IT) project manage- also contribute to project failure.
Project management, ment is a crucial issue for organizations . Projects can run into trouble due to the
Software development today. The failure rate of IT projects is vendors' inability to meet commitments.
astounding. A 1995 study in the USA found . Of the failed projects, 60 per cent were
Abstract
Information technology (IT) pro- that 31 per cent of software projects will be planned to take less than one year to
ject management is a crucial issue canceled before completion, and more than complete.
for organizations today. A 1995
half the projects will cost an average of 189 This report outlines the reasons behind the
study in the USA found that 31 per
cent of software projects will be per cent of their original estimates. With the failure of information technology projects,
canceled before completion, and $250 billion spent each year in the USA on IT thus providing the first steps towards mini-
more than half the projects will application development, we see that the cost
cost an average of 189 per cent of
mizing the risk of future failures. Learn the
the original estimates. This article of failures and overruns is staggering lessons of past mistakes, and improve project
examines the results of a survey (Standish Group, 1995). management techniques so that the stagger-
questionnaire that was sent to What were the causes of project failure? ing costs of IT project failures do not affect
Canada's 1,450 leading public and
How best to manage software projects to your organization.
private institutions to find the
causes of IT project failure. It avoid excessive costs? In April 1997, a survey
found that the three most common questionnaire focusing on IT project man-
reasons for project failure are poor
project planning, a weak business
agement issues was sent to Canada's leading Research method
case, and a lack of top manage- 1,450 public and private sector organizations.
In April 1997, the Program Management
ment involvement and support. It KPMG's 1997 Survey of Unsuccessful Infor-
then outlines the reasons behind
practice of KPMG sent a questionnaire con-
mation Technology Projects revealed that the
these failures, thus providing the cerning unsuccessful information technology
three most common reasons for project fail-
first steps towards minimizing the projects to chief executives of 1,450 public
risk of future failures. ure are:
and private sector organizations across
1 Poor project planning. Specifically, inade-
Canada. The aim of the survey was to collect
quate risk management and a weak pro-
information on the reasons behind the failure
ject plan. Risk management becomes more
of such projects. Failure was defined as
important as the organization gets bigger,
meaning:
so larger organizations need to pay more . the project budget was overrun by 30 per
attention to this area. cent or more; and/or
2 A weak business case. The need for the . the project schedule was overrun by 30 per
system should be justified in ways that cent or more; and/or
relate directly to the organization's busi- . the project was canceled or deferred due to
ness needs. its inability to demonstrate or deliver the
3 Lack of top management involvement and planned benefits[1].
support. This often dooms the project to
failure before it starts. Securing buy-in Projects canceled or deferred due to un-
# Brenda Whittaker. from the top, often by a strong business planned changes in business priorities were
case backed up with a realistic project not covered.
Respondents were asked to rank factors
plan, is an essential step.
contributing to project failure, from the
Some of the other main findings are: following areas:
Information Management &
Computer Security . Projects fail more often because of sche- . Project accountabilities.
7/1 [1999] 23±29 dule overruns than budget overruns. . Establishing project expectations.
MCB University Press . Many projects fail because they use new . Risk management.
[ISSN 0968-5227]
or unproven technology. . Project management ± planning.
[ 23 ]
Brenda Whittaker . Project management ± execution. Project size
What went wrong? . The project team. A high number of failed projects were
Unsuccessful information
technology projects
. Technology architecture. ``small'' projects; that is, they were scheduled
. Corporate culture. to take 12 months or less to complete. Of
Information Management &
Computer Security
. Other factors. failed projects, 60 per cent fell into this
7/1 [1999] 23±29 category. Looking at this 60 per cent, nearly
all respondents (92 per cent) with small
Respondent analysis projects reported that these projects went
The response rate for this survey was 14 per over schedule. Of those with large projects
cent. Of these responses, 176 arrived in time (projected schedules of over 12 months) a
to be analyzed for this report; of these, 61 per lower percentage (86 per cent) found meeting
cent reported details on a failed IT project these schedules a problem (see Figure 4).
(see Figure 1).
Common reasons for project failure
For the purposes of this survey, a small
Common reasons for project failure were:
organization was defined as having up to 250 . Poor project planning (specifically, risks
employees, a medium one as having 251 to
were not addressed or the project plan was
1,000 employees, and a large organization as
weak).
having more than 1,000 employees. . The business case tor the project was
Responses came from a wide cross-section
weak in several areas or missing several
of Canadian business (see Figure 2 and Table
components.
I). . A lack of management involvement and
support.

Findings The most common reason for project failure


was poor project planning ± in two distinct
Failure types areas.
Project failure was defined in three ways: First, risks were not addressed as part of
overrunning its budget by 30 per cent or the project planning process. Respondents
more; overrunning its schedule by 30 per cent ranked various risks as being particularly
or more; or failing to demonstrate the significant, with slippage from the schedule
planned benefits. Of these, failure by over- coming first (see Table II).
running schedule was by far the most Some comments from respondents:
common. A total of 87 per cent of failed . ``The original time line was unrealistic,
projects exceeded their initial schedule esti- and not revised once completion of en-
mates by 30 per cent or more. This compares hancements was identified.''
to 56 per cent of failed projects that exceeded . ``I attribute the failure of this project
their estimated budget by the same amount, primarily to the management of the scope
and 45 per cent of failed projects which failed of the project. Changes in scope that were
to produce the expected benefits (see Figure introduced were not properly evaluated
3). prior to inclusion in the project.''

Figure 1
Survey response statistics

Surveys Analyzed
176

Private Sector Public Sector


100 76

Small* Medium* Large* Small* Medium* Large*


23 30 42 6 32 35

*Where information was given

[ 24 ]
Brenda Whittaker Figure 2
What went wrong? Industry response by organization size
Unsuccessful information
technology projects
Information Management &
Computer Security Industry
7/1 [1999] 23±29
Manufacturing

Health

Education

Government Services

Retail

Communications

Financial Services

Distribution Services

Other Industry

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%
Percentage of Respondents

Key
Up to 250 Employees
251 to 1000 Employees
Over 1000 Employees
Uncategorized

Table I Figure 3
Industry response by sector Type of project failure

Industry sector Percentage of respondents


100%
Manufacturing 24
90%
Health 23
Percentage of Failed Projects

80%
Education 12
Government services 9 70%
Retail 8 60%
Communications 6 50%
Financial services 5 40%
Distribution services 4 30%
Other industry 9 20%
Total 100 10%
0%
Overran Overran Did not
Schedule Budget Demonstrate
. ``Cutbacks across the organization led to Planned
more competition for scarce IT resources, Benefits
and the IT personnel were too `stretched'
to do more than simply firelight.''
. ``Activities in the plan were reported as
. ``The turnover of key individuals asso- being done, when in fact they were not.''
. ``We had insufficient information systems
ciated with the project was a major
staffing to stabilize the initial phase
problem.''
quickly.''
Second, the plan was weak. The four most
A weak business case was the second most
common deficiencies in project plans are common reason for project failure. The busi-
shown in Table III. ness case was most likely to be weak in, or
Some comments from respondents included: missing, the components shown in Table IV.
. ``Learning the new development tools took Some comments from respondents in-
much longer than planned.'' cluded:
[ 25 ]
Brenda Whittaker Figure 4 . ``The complexity of the dcliverables was
What went wrong? Overrun vs planned schedule not understood by the key users.''
Unsuccessful information
technology projects
. ``A major change in the funding climate
took place without reassessing the impor-
Information Management &
Computer Security
100% tance of the project.''
7/1 [1999] 23±29 90%
Percentage of Failed Projects
Finally, a lack of management involvement
80%
and support was cited as the third most
70%
common reason for project failure.
60% Some comments from respondents in-
50% cluded:
40% . ``The business sponsor and main contact
30% was not committed to the success of the
20% project since he had a vested interest in
10% the `old' systems.''
. ``The executive management ideals did
0%
0 to 12 Greater not remain consistent with the estab-
Months than 12 lished policies and procedures which they
Months
endorsed up front.''
Planned Schedule . ``The president and CEO was the sponsor
Key but did not want the detail.''
Did not overrun . ``Senior management support and lack of
Overran by 30 to 49% follow through with middle management
Overran by 50 to 100% was a problem, as was the entrepreneurial
Overran by more than 100% attitude of the business areas cultivated
by senior management ± the project was a
corporate head office project.''
Table II
The four most important risks not addressed as part of the project planning Other important reasons for project failure
process It is clear through the comments received
from respondents that other important rea-
Percentage of sons contributed to project failure. The
respondents patterns which they build are persuasive.
who identified Many projects had problems with new or
risk as a unproven technology. Some 14 per cent of
Ranking Factor problem respondents who reported failed projects
1 Slippage from the schedule 73 found that new technology, often in beta
2 Change in scope of technology, 51 version or otherwise not fully tested, had
functionality or business case contributed to the failures.
3 Cost overruns associated with one or more 45 Some comments from respondents in-
project components cluded:
4 Change in any key individuals such as the 38 . ``The vendor's `beta' software was not
business sponsor, project manager or ready. Enormous amounts of time were
vendor manager spent testing software that was not ready
for use.''
. ``New unproven software was a problem:
the purchased application was not fully
Table III developed (too many bugs). The product
The four most common deficiencies in project plans was relatively new (almost beta); there-
fore no track record was established.''
Percentage of . ``The vendor's product was not ready for
respondents
market.''
who identified
project plan Many projects ran into trouble because the
Ranking Factor as a problem vendors did not meet commitments. Some 15
per cent of failed projects reported a problem
1 Incorrectly estimated activity durations 63
with the vendor's ability to deliver a product
2 Incorrect assumptions regarding resource 52
to meet objectives and timelines, and some-
availability
3 Inadequate assignment of activity 51 times even to deliver any product at all.
accountabilities Some comments from respondents in-
4 Missing or incomplete review and approval 47 cluded:
activities
. ``The vendor could not deliver a finished
product.''
[ 26 ]
Brenda Whittaker . ``It is somewhat doubtful that the supplier definition of requirements or specifications
What went wrong? could have delivered the system, due to or an underestimation of the resources
Unsuccessful information
technology projects his over-committed and over-extended required for the project.
position on other major projects with Some comments from respondents in-
Information Management &
Computer Security third parties.'' cluded:
7/1 [1999] 23±29 . ``The application vendor underestimated
. ``The specifications were incomplete until
the scope, and didn't have enough skilled late in the project.''
resources.''
. ``The project significantly exceeded the
. ``Vendor inability to meet objectives and cost estimates made at the outset. If actual
fill commitments was a factor.'' costs had been known at the outset, an
alternative solution would have been
Poor estimates or definitions of requirements pursued.''
at the project planning stage contributed to . ``Unrealistic time estimates: underesti-
project failure. Of the respondents who mated the availability of staff time to the
reported failed projects, 10 per cent relayed project.''
through open comments that they ran into
Risk management became more important as
problems at least partially due to a poor
the size of the organization increased. Re-
spondents were asked to rank the signifi-
Table IV cance of the factors contributing to project
The most likely factors that cause a weak business case failure. Based on this, the survey results
Percentage of showed that, in general, the larger the
respondents organization, the greater the importance
who identified attributed to risk management as a factor in
project plan project failure. Only organizations of be-
Ranking Factor as a problem tween 1,001 and 5,000 employees disturbed
this trend (see Figure 5).
1 Business and operational changes needed 48
to deliver the benefits Serious budget and schedule overruns
2 Clearly understood deliverables 46 A serious budget or schedule overrun was
3 Quantified costs and benefits 44
defined to be 50 per cent or more over the
4 Overall scope of project 37
original estimate. The survey identified pat-
(tied) Business and technology risks
terns in the projects that suffered this fate.

Figure 5
Risk management as a factor contributing to project failure

5.0

4.5

4.0
Ranking of Importance of Factor

3.5

3.0

2.5

2.0

1.5

1.0

0.5

0.0
Up to 250 251 to 500 501 to 10000 1001 to 5000 Over 5000
Employees Employees Employees Employees Employees

Organization Size (by number of employees)


Key
Average Answer

[ 27 ]
Brenda Whittaker Larger organizations are more in danger of between schedule and budget overrun. How-
What went wrong? suffering from serious budget overruns (50 ever, this correlation is much stronger in cases
Unsuccessful information
technology projects per cent or more over the original target). with budget overruns, than in cases with
Information Management & One-third of responding organizations with schedule overruns. A serious (greater than 50
Computer Security over 5,000 employees reported serious budget per cent) budget overrun meant a serious
7/1 [1999] 23±29
overuns, compared with only 20 per cent in (greater than 50 percent) schedule overrun as
organizations of 1,001 to 5,000 employees (see well in 91 per cent of cases. But the reverse is
Figure 6). not usually true; most of those projects with
Even with a serious schedule overrun, serious schedule overruns did not have a
project managers can hope to keep the budget serious budget overrun as well (see Figures 7
from serious overrun. There is a correlation and 8).

Figure 6
Serious budget and schedule overrun by organization size

50% Key
Overran budget > 50%
45% Overran schedule > 50%

40%

35%
Percentage of Projects

30%

25%

20%

15%

10%

5%

0%
Organization Size (by number of employees)

Figure 7 Figure 8
Projects overrunning budget by 50 per cent or Projects overrunning schedule by 50 per cent or
more more

Did not also


Did not also overrun budget
overrun schedule by 50% or more
by 50% or more 55%
9%

Also overran schedule Also overran budget


by 50% or more by 50% or more
91% 45%

[ 28 ]
Brenda Whittaker Figure 9
What went wrong? Types of project overrunning budget and schedule
Unsuccessful information
technology projects
Information Management &
Computer Security
7/1 [1999] 23±29 Type of Application

Custom-developed Application 69%

Purchased Application Installation 52%

New Data Management System 48%

New Operating System 38%

New Communication System 34%

Other Components 10%


% of Projects

Table V and schedule, 69 per cent of the projects


Factors that contributed to serious budget and schedule overruns involved custom-developed applications (see
Figure 9).
Ranking for Project management (execution) was rated
total sample Ranking Area of project management as the most important area contributing to
1 1 Project management ± execution project failure in cases with both serious
4 2 The project team budget and schedule overruns (see Table V).
2 3 Risk management Where projects were seriously overrun, the
5 4 Project accountabilities skills of the project manager and the mon-
itoring of progress against plan were high-
Table VI lighted as major factors. Risk management
Project manager failings that can contribute to serious budget overrun remains the highest ranked factor contribut-
ing to project failure, but the lack of required
Ranking for skills or expertise on the part of the project
total sample Ranking Factor
manager and inadequate monitoring against
1 1 Risks were not addressed in several areas progress and initiation of corrective action
9 2 The project manager did not have the were ranked second and third (see Table VI).
required skills or expertise
5 3 Project progress was not monitored and Note
corrective action was not initiated 1 A serious budget or schedule overrun was
7 4 The experience, authority and stature of defined as one that exceeds the original
the project manager were inconsistent with target by 50 per cent or more.
the nature, scope and risks of the project
Reference
Custom-developed applications were asso- Standish Group (1995), Chaos (Application Project
ciated with serious budget and schedule Failure and Success), The Standish Group
overruns. Of those respondents who went 50 International, January. URL http://
per cent and over on their original budget www.standishgroup.com/chaos.html

[ 29 ]

Você também pode gostar