Escolar Documentos
Profissional Documentos
Cultura Documentos
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
5 ProjectDescription
This chapter provides a detailed description of the various
elements of the Technical Ammonium Nitrate Production
Facility (TANPF) Project to assist in evaluating the associated
potential environmental impacts. The TANPF Project
descriptionisbasedonBurrupNitratesPtyLtd(BNPL)sproject
concept study. The Engineering, Procurement and Construction
(EPC) Contractor has not yet been determined, and as such,
certaindetailsofengineering,designandconstructionareyetto
be finalised. Despite this, the design is sufficiently developed to
allow for the assessment of potential environmental impacts
associatedwiththeTANPFProject.
5.1 ProjectOverview
BNPL is proposing to construct a TANPF with a production
capacity of (circa) 350,000 TPA or 915 MTPD of technical
ammonium nitrate (TAN). TAN will be delivered principally to
mining customers in the Pilbara, to help make up the basic
component of ANFO (ammonium nitratefuel oil) used for
explosives.
TheSiteisapproximately79Hainsizeandislocatedadjacentto
the existing Burrup Fertilisers Pty Ltd (BFPL) ammonia plant,
with site access from Village Road, Burrup Peninsula. The
choice of location for the proposed TANPF enables significant
sharing of services and utilities between BFPL and BNPL. This
willreduceenvironmentalimpactsbyallowingasmallerproject
footprint (eg. independent ammonia storage, transport and
supply) and permitting the incorporation of technical and
designefficiencies.ThemainfeedstockfortheproposedTANPF
is liquid ammonia, which will be transferred via pipeline from
theBFPLplant.
TheproposedTANPFwillrequireabout35Haofthe79HaSite.
The TANPF will contain three major process units, each
producingaseparateproductinthemanufacturingprocess:
a Nitric Acid (NA) plant to convert ammonia and
atmosphericairintoNA;
an Ammonium Nitrate (AN) Solution plant to convert
ammoniaandNAintoANsolution;and
a TAN plant to convert AN solution into TAN prills (final
product).
The key characteristics of the TANPF Project are outlined in
Table5.1. The boundary locations of the Site are presented in
Table5.2andTable5.3.
Table5.1 KeyCharacteristicsoftheTANPF
Criteria KeyCharacteristicsoftheTANPF
ProjectPurpose ToproduceTANfromammoniausingadvanced
productiontechnologyforsaletomostlylocal
markets
ProjectLife 20+years
ConstructionPeriod Approximately30months
ProjectValue ApproximatelyUS$600million
TANPFCapacity 350,000TPA
AreaofProjectLease 79Ha(SiteD)
AreaofDisturbance 35Ha
PlantFacilities MainProcessUnits
NitricAcid(NA)Plant
AmmoniumNitrate(AN)SolutionPlant
TechnicalAmmoniumNitrate(TAN)Prilling
Plant
Storage,LoadingandTransportFacilities
LiquidAmmoniapipelinebetweenBFPLand
BNPLplants
BaggedTANstoragebuilding
BulkTANstoragebuilding
TANBaggingfacility
Truckbulkloadingsystem
Nitricacidbufferstorage
Ammoniumnitratesolutionstorage
OtherFacilities
SeaWaterCoolingTower
ClosedLoopWaterCoolingSystem
Wastewaterhandlingfacility
ElectricalPowerdistributionsystem
Instrumentandplantairsystem
Controlroom
Steamgrid
Administration,maintenanceandwarehouse
unit
Firesystem
PlantOperations TheTANPFisdesignedtooperate24/7,withan
averageplantavailabilityof90%(328.5daysper
year)excludinganydowntimeduetomarket
reasonsorotherreasonsnotrelatedto
operation.
ShutdownTime Anannualturnaroundofaboutoneweekis
foreseen.Additionaldowntimemaybecausedby
acombinationofplannedstops(e.g.cleaning)
andunplannedstops(eg.process,cycloneetc.)
ProductStorage BaggedTANstoragebuildingwithacapacityof
1,800MT
BulkTANstoragebuildingwithacapacityof
12,000MT
Nitricacidbufferstorage,twotankswithatotal
capacityof3,000m
3
locatedinabundedarea
withacidresistantsurface
Ammoniumnitratesolutionstorage(8092%),1
tankwithacapacityof500MT
PotableWater 2m
3
/hrfromWaterCorporation
Seawater 456m
3
/hrfromWaterCorporation
20
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
Criteria KeyCharacteristicsoftheTANPF
PowerRequirement 8.5MWwillberequired.Ofthis,about5MWwill
beimportedfromBFPL.
Theremainingpowerwillbegeneratedbyexcess
steamfromtheoperationofthenitricacidplant
(about3.5MW).
EmergencyPower Incaseofapoweroutageemergencypowerwill
beprovidedbydieselgenerators
EnergyInput 5MWfromBFPL
DischargePipeline ConnectingtotheWaterCorporationfacility
AmmoniaPipeline 710mfromBFPLAmmoniaplant(storagetanks)
totheTANPF(withinBNPLandBFPLleases)
Catalysts Platinum(Pt)/Rhodium(Rh)gauzesforthe
ammoniacombustion
RecoverysystemforthePt/Rhgauzes
N
2
Ocatalyst
NO
x
catalyst
ExpectedMaximumEmissions
underNormalOperations:
DailyLoad
(kg/day)
PertonneTAN
(kg/MTTAN)
AnnualLoad
(kg/year)
NO
x
370 0.40 28,318
N
2
O 466 0.51 161,563
CO
2
(produced) 1,279 1.40 515,670
CO 131 0.15 41,987
SO
2
trace trace
VOC(CH
4
) 51 0.06 17,697
NH
3
208 0.22 68,339
ANDust(Particulatematter) 130 0.14 42,705
Wastewater 11,661kg/hProcessCondensate(non
contaminated)toseawaterblowdown.
Contaminatedwater(fromcleaningequipment
etc)willbesentdirectlytothecontaminated
surfacewaterpond.
Thenoncontaminatedwaterwillbesentto
WaterCorporationviaapipeline(approximately
3,100ML/year).
Thecontaminatedwaterisevaporatedina
designatedpondwhichisaclosedsystem(eg.no
discharge).Accumulationofunspecifiedvolumes
ofsludgefromthecontaminatedsurfacewater
pondwillbecollectedfordisposalasrequired
(estimatedonceeverytwoyears).
SolidWaste Offspeccoatingremovalbarrels(expected120
kg/daymax)
Workforcenumbers(direct) Construction:Average400,peak650
Operation:60(fulltime)
5.2 ProjectLocation
TheTANPFProjectwillbelocatedatSiteD(theSite)withinthe
BIE,approximately13kmnorthwestofKarratha(Figure1.1and
Figure4.2).GeographiccoordinatesoftheproposedSiteandthe
proposed area of disturbance are provided in Table5.2 and
Table5.3respectively.
Table5.2 SiteDBoundaryCoordinates
Latitude Longitude
degrees minutes seconds degrees minutes seconds
20 37 17.815 116 47 8.044
20 37 20.638 116 47 36.463
20 37 57.086 116 47 23.843
20 38 2.246 116 47 7.988
Northings Eastings
477660.256mE 7719713.884mN
478479.474mE 7719628.771mN
478116.860mE 7718500.870mN
477660.230mE 7718348.890mN
Table5.3 TANPFBoundaryCoordinates(Areaof
Disturbance)
Latitude Longitude
degrees minutes seconds degrees minutes seconds
20 37 17.815 116 47 8.044
20 37 20.638 116 47 36.463
20 37 32.2206 116 47 32.445
20 37 35.0904 116 47 17.0586
20.626406 37 35.061 116 47 8.0478
Northings Eastings
477660.256mE 7719713.884mN
478479.474mE 7719628.771mN
478366.280mE 7719271.240mN
477924.010mE 7719182.250mN
477660.090mE 7719183.670mN
5.2.1 LandOwnershipandTenures
Lots within BIE are available for lease to strategic heavy
industry through the WA Department of State Development
(DSD), which allocate sites through a lease arrangement from
LandCorp(WA'slandandpropertydevelopmentagency).
TheSitehasbeenallocatedtoBNPL,subjecttotheapprovalofa
riskreporttobesubmittedtotheWADepartmentofMinesand
Petroleum(DMP)inthecomingmonths.
5.2.2 Zoning
The Site is zoned Strategic Industrial under the Roebourne
ShireTownPlanningScheme(TPS)No.8.Asoutlinedwithinthe
TPS the purpose of the Strategic Industry zone is to
accommodate such industries as the TANPF. In considering
applications for planning approval in the strategic industry
zone, the Shire of Roebourne Council shall ensure that the
industry(ShireofRoebourne,2008):
a) Optimises the effectiveness of the zone as a strategic
industrialareaand.createsasymbiosiswithotherindustries
orincludesresourceprocessingindustry;
b) issignificanttotheregionaland/orstateeconomies;or
c) Provides goods and services which directly support or
complementindustriesdescribedina)andb)above;and
d) Minimisesoroffsetsimpactsonlocalinfrastructure,economic
andcommunitydevelopment.
21
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
5.2.3 LandRequired
Approximately 35Ha of land within the project lease will be
disturbed as part of the TANPF Project (see Figure4.2). There
will be no additional temporary land requirements for the
construction phase, as construction laydown areas will be used
throughout the operational phase. This land is required to
accommodate:
Processingplants(NA,ANSolutionandTANproduction)
Utilitiesarea
Storages for bagged TAN, bulk TAN, AN solution, nitric acid
andchemicalstore(generalprocesschemicals)
Truckbulkloadingsystem/Baggingunit
Offspectreatmentunit
Otherfacilities,including:
SeaWaterCoolingTower
ClosedLoopWaterCoolingSystem
Clean surface water pond (discharge to Water
Corporation)
Contaminatedsurfacewaterpond(evaporationpond)
Desalinated/firewaterstorage
Controlroom/Office/Administration
Miscellaneous(internalroads,etc.)
Laydownareasandaccessroads.
Table5.4 EarthworksandAssociatedCutandFill
TypeofEarthworks VolumeofCut/Fill(approximate)
Growthremoval 350,000m
2
Striptopsoil&stockpile 19,500m
3
Cutsoil 61,900m
3
Loadsoil/haul/place 92,500m
3
Importedengineeredfill isnotforeseen
5.2.4 AdjacentLandUses
Adjacent land uses for the TANPF Project are shown in
Figure5.1 and include industrial facilities present to the south
and west of the Site while the proposed Burrup Peninsula
Conservation Reserve occurs to the north and south of the Site,
withHearsonCovetotheeast.
Table5.5 ListofFacilitiesAdjacenttotheProposedTANPF
Facility/SensitiveReceptors ApproximateDistancefromTANPF(m)
NorthWestShelfVenture 3,200m
WoodsideLNGPlutoDevelopment 2,200m
DampierPortAuthority 4,000m
KingBaySupplyBase 3,000m
SchlumbergerSupplyBase 2,100m
BFPL Adjacent,ammoniatanks~600m
HearsonCove(visitors) 9001,300m
DeepGorge 1,300m
NearestRockArtSite Approximately400m
NearestRockArtSitewithinNational
HeritageBoundary
Approximately400m
CurrentlytheBFPLandtheWaterCorporationmultiuser(both
part of the same plot) facilities exist within King Bay/Hearson
Cove Industrial Precinct, with the potential inclusion of Dyno
NobelandWoodsideEnergyyettobeconfirmed.
NobuildingsorinfrastructurecurrentlyexistswithintheSite.
5.3 ProjectSchedule
The TANPF is scheduled to begin operations by last quarter
2013. This schedule is based around the following key
milestonesinTable5.6.
Table5.6 ProjectDevelopmentSchedule
ProjectPhase ScheduleTiming
SubmissionofEnvironmentalScopingDocument(ESD)toOEPA July2009
EPASUandDEWHAreviewESD JulySeptember2009
BNPLsubmitsrevisedESD September2009
OEPAapprovesfinalESD October2009
SubmissionofPERtoEPASU(andDEWHA) October2009
EPASUcommentsonPER OctoberDecember2009
BNPLrevisesPERdocument December2009
ApprovalofPERreleaseforpublicreview December2009
PublicreviewperiodofPER(8weeks) JanuaryFebruary2010
BNPLpreparessubmissionsummaryandresponse MarchApril2010
EPASUreviewsresponsetosubmissions AprilMay2010
OEPAreportandrecommendationspublished MayJuly2010
AppealperiodonOEPAsreportandrecommendations July2010
StateMinisterdecision August2010
CommonwealthMinisterdecision August2010
Construction Lastquarter2010
Commissioning June2013
Operation Lastquarter2013
Environmental Resources Management Australia Pty Ltd
6th Floor, 172 St Georges Tce, Perth, WA, 6000
Telephone +61 9 321 5200
Figure 5.1
Adjacent Land Uses to the
Proposed TANPF
Client:
Project:
Drawing No:
Date:
Drawn by:
Source:
Scale:
Burrup Nitrates Pty Ltd
PER
0086269p_GIS04_PER
21/12/2009
DD
Base information LANDGATE
1:40 000
Suffix No:
Drawing size:
Reviewed by:
R1
A4
BC
[
N
B U R R U P
P E N I N S U L A
King Bay
Withnell Bay
Cowie
Cove
Nickol Bay
Proposed
Development
Site
0 380 760 1,140m
Legend
Site D Boundary
National Heritage Listed Place (Site ID 105727)
H
E
A
R
S
O
N C
O
V
E
R
D
V
ILLA
G
E
RD
B
U
R
R
U
P
R
D
North West
Shelf Venture
Pluto
Operations
Dampier
Port Authority
Schlumberger
Supply Base
Pluto
Supply Base
Hearson Cove
BFPL
Ammonia
Plant
Beach & Picnic Area
Deep
Gorge
23
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
5.4 CharacteristicsandPropertiesofthe
TANPFsMainRawMaterialsand
Product
5.4.1 NitricAcid
Nitric acid is a colourless, yellow, or red, fuming liquid with an
acrid odour. The acid is often used in an aqueous solution.
Fuming nitric acid is concentrated nitric acid that contains
dissolvednitrogendioxide.
Table5.7 PropertiesofNitricAcid
NitricAcid(HNO
3
)
ChemicalAbstractsService(CAS)Number 7697372
RegistryofToxicEffectsofChemical
Substances(RTECS)Number
QU5775000
ImmediatelyDangeroustoLifeorHealth
(IDLH)
25ppm
ExposureLimits NationalInstituteforOccupational
SafetyandHealth(NIOSH)
RecommendedExposureLimit(REL):
Timeweightedaverage(TWA)2ppm
(5mg/m
3
)
OccupationSafetyandHealth
Administration(OSHA)permissible
exposurelimits(PEL):TWA2ppm
(5mg/m
3
)
NationalPollutionInventory(NPI)Ranking 43of90
Molarmass 63.012g/mol
PhysicalDescription Colourless,yellow,orred,fumingliquid
withanacridodour
FreezingPoint At60%conc.:22
o
C
BoilingPoint At60%conc.:120
o
C
SpecificGravity At60%conc.andat25
o
C:1,360kg/m
3
Solubilityinwater completelymiscible
Flashpoint NoncombustibleLiquid,butincreases
theflammabilityofcombustible
materials
DangerousSubstancesDirective Oxidant,Corrosive
5.4.2 Ammonia
Anhydrous ammonia is a colourless nonflammable liquefied
gas.Itsvapourislighterthanair[(vapourdensityof0.6)air=1]
and has the same pungent odour as household ammonia.
Although ammonia vapour is lighter than air, vapours from an
accidentalleakarelikelytohugthegroundappearingasawhite
cloud. Chemically ammonia is 82% nitrogen (N) and 18%
hydrogen(H).
Table5.8 PropertiesofAmmonia
Ammonia(NH
3
)
CASNumber 7664417
RTECSNumber BO0875000
IDLH 300ppm
ExposureLimits NIOSHREL:TWA25ppm(18mg/m
3
)
OSHAPEL:TWA50ppm(35mg/m
3
)
NationalPollutionInventory(NPI)Ranking 45of90
Molarmass 17.031g/mol
PhysicalDescription Colourlessgaswithstrongpungent
odour.Itiseasilyliquefiedunder
pressure
FreezingPoint 77
o
C
BoilingPoint 33
o
C
Solubilityinwater 1176g/100mL(0C)
702g/100mL(20C)
88g/100mL(100C)
Flashpoint NoncombustibleasaGas
DangerousSubstancesDirective Toxic,Corrosive,Dangerousforthe
environment(ifreleaseduncontrolled)
5.4.3 TechnicalAmmoniumNitrate
Thechemicalcompoundammoniumnitrate(NH4NO3)isasaltof
ammonia and nitric acid. Ammonium nitrate (AN) is a
colourless, crystalline substance and has a melting point of
169Canddecomposesabove210C.Itishighlysolubleinwater
and soluble in alcohol and liquid ammonia. AN is not in itself
combustible but, as it is an oxidising agent it can assist other
materialstoburn,evenifairisexcluded.
Figure5.2 PhotoofTANPrills
Scale (mm)
0 4 8
Scale (mm)
0 4 8
Scale (mm)
0 4 8
24
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
TAN will be the main product from the TANPF Project. TAN
prills will be produced with specifications similar to that in
Table5.9.TheTANprillswillbeusedinthelocalmarketforuse
inANFO(ammoniumnitratefueloil)explosives.
Table5.9 SpecificationsofTANPrills(typical)
TechnicalAmmoniumNitratePrills(TAN)
CASNumber 6484522
RTECSNumber BR9050000
Molarmass 80.043g/mol
PhysicalDescription WhiteSolid
PH 5
MeltingPoint 169C
BoilingPoint approx.210Cdecomposed
Solubilityinwater 118g/100ml(0C)
150g/100ml(20C)
297g/100ml(40C)
410g/100ml(60C)
576g/100ml(80C)
1024g/100ml(100C)
Shock/FrictionSensitivity Verylow
NitrogenContent 34.5%w
BulkDensity 0.700.83kg/L
FreeMoisture 0.030.16%w
OilAbsorption 8%14%w
TheeffectsofheatingofANaredescribedabove.
Arunawayreactionisachievedwhentheheatgeneratedbythe
reactionexceedstheheatlossbyasignificantlyhighmargin.For
pure AN, these circumstances are difficult to achieve given its
low decomposition rate and endothermic effect when
unconfined.
PureANisnotshockorfrictionsensitiveandcannotbeinduced
todetonateundernormalstorageconditions;detonation,which
are characterised by a supersonic pressure wave moving
through the material, can occur only if the dimensions of the
material are greater than some particular value known as The
critical charge diameter. For solid AN this diameter is more
than1manddecreaseswithdecreasingbulkdensityofthesolid
AN. The corresponding diameter for decomposing molten AN is
about10cm.
UncontaminatedandunconfinedANisverydifficulttodetonate.
Neitherflame,norsparknorfrictioncancauseadetonation.
TheconsensusofopiniononANhazardsisthat,intheeventofa
largefireatanANstore,apoolofliquidammoniumnitratewill
be formed at the side of the stack that is nearest to the fire. If
thispoolisstruckbyahighspeedmissile(eg.somethingfalling
orpartofadrumthathasexploded)thenalocalexplosionmay
occursendingashockwaveintothemainANstackthathasnot
meltedandthatcouldleadtodeflagration.
25
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
Stacks of AN in the open are assumed to be incapable of
exploding because the probability of an explosion trigger such
asagirderfallingintoamoltenpoolisverylow.
5.5 DesignConsiderations
5.5.1 HESDesignStandards
The Health Environment and Safety (HES) premises for the
TANPF Project provide a minimum set of standards to ensure
that identified risks to people, assets, environment and
reputation have been addressed in the project design. The
designmitigationstogetherwiththemanagementmeasureswill
ensuretheyareacceptabletoAsLowAsReasonablyPracticable
(ALARP)levels.
NitricAcidPlant
The NA plant will use the dual pressure process, which ensures
optimal conditions in the combustion as well as in the
absorption stages to accommodate stringent environmental
pollution control requirements. In addition, the NA plant will
applyBATforfurtherabatementofN2OandNOx.
ThecatalyticprocessforN2Oreductionrequirestheuseofsome
natural gas, with the maximum consumption to be 50Nm
3
/h.
This use of gas will result in CO2 formation, with a maximum
emission of 0.064t/h. Some slippage of methane will occur
which will correspond to a maximum value of 0.045t/h CO2e.
These additional emissions from the use of a N2O reduction
catalyst are required as they result in a far greater CO2e
reduction (approximately 90% reduction) than operations
withoutaN2Oreductioncatalyst.
26
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
TechnicalAmmoniumNitratePrillingPlant
The TAN prilling plant will also use BAT to minimise
atmosphericemissions.TheprilltoweroftheTANprillingplant
will be designed with a recycle air closed loop air recycling
system to minimise the total amount of air rejected to the
atmosphere (less than 1/3 compared to open loop prilling).
This gives one single emission point expected to be well below
European Fertilizer Manufacturers Association (EFMA) Best
Available Techniques 2000 levels. In addition, all exhaust from
the prill tower will be cleaned in two stages using efficient
abatementsystems.
5.5.3 SafetyandSecurity
As well as environmental aspects, safety and security
considerations have significantly influenced the design of the
TANPF. Yara has developed Technical and Operational
Standards (TOPS) that will be implemented in the design and
engineeringaswellasfortheoperationandmaintenanceofthe
TANPF.
Yaras TOPS have been developed following over 40 years of
operational experience of TAN plants to provide safe and
reliable design and operation of equipment, individual process
units and plants. The standards are divided into different
categories:
1) StandardsapplicabletoallYara/BNPLoperations
2) Maintenance
3) Nitricacid
4) Ammoniumnitrate
5) Industrial/CO2
6) Transport,loading/unloading
27
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
configuration with 3 layers and about 300 tons or less in each
stack and with a distance of 7 9m between the stacks. Floor
markingwillensurethatsafestackingzonesaremaintained.
Figure5.3 OptimalTANBagStackingConfigurations
PlantOperation
The process safety and all relevant procedures of the TANPF
Project will be set out in a document that describes the
minimumrequirementstobeimplemented.
SafeplantoperationisakeyfocusofBNPLandensuringproper
maintenance is a key to safe operation. Important elements in
achieving optimum safety, performance and reliability of
operatingequipmentaresystematicmaintenanceandcondition
monitoring. Details on how this is done will be described in the
TOPS for maintenance, which will be implemented for the
TANPF. Other important elements are modifications/
management of change, work permits and associated risk
assessment/job safety analysis. All modifications of process
systemsandprocessequipmentwillhavetobeapprovedbased
onasystematicreviewofHESissues.
28
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
TheTANPFwillalsobeauditedonaregularbasisusinginternal
and/orexternalauditorstoensurecompliancewiththevarious
TOPS as well as regulations, codes, standards and WA and/or
CommonwealthMinisterialconditions.
5.5.4 UnplannedEvents
An Emergency Response Plan covering all credible HES
emergency scenarios (including tropical cyclone response)
during all phases of the project and the escalation potential of
any emergency situation will be developed for the TANPF
ProjectandisdiscussedfurtherinSection8.11.4.
Thecleansurfacewaterpondwillhaveanareaof40mby25m,
andadepthof1.5m.Thecontaminatedsurfacewaterpondwill
haveanareaof70mby70m,andadepthof1.5mbothponds
will be bunded. Preliminary plans of the drainage design are
showninAnnexF.
TheTANPFdesignlevelincorporatesthepotentialforfuturesea
level rise for the 20 year plus operational phase. The TANPF
maybefurtherraiseddependingontheoutcomeofgeotechnical
worktobeundertakenpriortoconstruction.
5.6 TANProcessDescriptionand
AssociatedInfrastructure
5.6.1 Introduction
TheTANPFwillbepositionedinthenorthwestcorneroftheSite
(Figure4.2). The plant layout is shown in Figure5.4 and
Figure5.5.
Figure5.4 3DModelofPlant
30
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
The TANPF will comprise of the following main project
elements:
MainProcessUnits,including:
NitricAcid(NA)Plant;
AmmoniumNitrate(AN)SolutionPlant;
TechnicalAmmoniumNitrate(TAN)PrillingPlant;
Storage,LoadingandTransportFacilities;
OtherFacilitiesandBuildings;and
SupportingInfrastructureandCommunications.
Figure5.6belowrepresentsasimplifiedvisualillustrationofthe
TAN production process. This is followed by an overview of
eachmainprocessingunitwithintheTANPF.
Figure5.6 TANProductionProcess
5.6.2 NitricAcidPlant
The NA plant will be based on the dual pressure process and
will:
Haveacapacityof760MTPDNA(as100wt%);
Requireammoniaandoxygen(air)asrawmaterials;
Generateabout3.5MWofpowerfromexcessprocesssteam
whichwillbeusedtodrivecompressorsintheNAplant;
Bedesignedtooperatebetween70and100%load;and
ProduceNA(approximately60%concentration)thatwillbe
senttotheANsolutionplant.
Inthedownstreampipingandequipment,NOisoxidisedtoNO2
generating additional heat that is used in the heat recovery
network.
The tail gas will then enter the abatement reactor (N2O/NOx
reductionunit).ThisreductionunitutilisesBAT,andthetailgas
vented to the atmosphere from the TANPF will comply with
statutoryrequirementsandenvironmentalguidelines.
After the abatement reactor the tail gas will enter the tail gas
turbine where it is expanded to recover 70% of the power
demandforthecompressortrain.
31
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
Table5.10 NAPlantSummaryDevelopment
NitricAcidPlant
Inputs/quantities
orvolumes
Outputs/Products Outputs/Wastes&Emissions
Ammonia:
8,977kg/h
Air:
160,359kg/hor
51,629m
3
/hr
Water
(saline,potable):
Noconsumption
directlyinprocess
Power:
3.5MWinternal
generation(Steam
fromNAPlant)
0.38MWinternal
consumption
ProduceNA(approx.
60%concentration)
52,778kg/hor39.8
m
3
/hrasan
intermediateproduct
thatwillbesentto
theANsolutionplant
1) AirEmissions
N
2
O
- Normaloperation100ppm
or19.4kg/hr
- Max
1
2,000ppmor180kg/hr
NO
x
- Normaloperation75ppmor
15kg/hrcalculatedasNO
2
- Max
1
700ppmor100kg/hr
calculatedasNO
2
CO
2
- Normaloperation250ppm
or49.5kg/hr
- Max
1
400ppmor79.42kg/hr
CO
- Normaloperation<40ppm
or<4.45kg/hr
- Max
1
40ppmor4.45kg/hr
CH
4
- Normaloperation30ppmor
2.1kg/hr
- Max
1
100ppmor7.1kg/hr
NH
3
- Normaloperation1ppmor
0.08kg/hr
- Max
1
5ppmor0.4kg/hr
H
2
S
- Normaloperation,traces
only
- Max
1
,tracesonly
2) LiquidEmissions
Oilresidueandsludgefromthe
heatexchangersandstorage
tanks,minimalquantities
3) Catalysts
ThePt/Rhcatalystgauzesand
thecatchmentsystemwillbe
completelychangedand
recycledapproximatelytwo
timesayear.
TheNO
x
andN
2
Ocatalysthas
alifetimeofapproximately10
yearsandwillbereturnedto
themanufacturer
1.Maxvaluesareassociatedwithupsetconditionsandincludestartupandshutdown,
whichdonotgenerallylastmorethan4hours.
5.6.3 AmmoniumNitrateSolutionPlant
The AN solution plant will apply the vacuum neutralisation
technologyandwill:
Haveacapacityof965MTPDAN(as100wt%)tomatchthe
NAplantcapacity;
Requireammoniaandnitricacidasrawmaterials;and
Produce AN solution that is either sent to the TAN prilling
plantorstored.
Table5.11 ANSolutionPlantSummaryDevelopment
AmmoniumNitrateSolutionPlant
Inputs/quantitiesor
volumes
Outputs/Products Outputs/Wastes&Emissions
Ammonia:
8,630kg/h
NitricAcid:
52,756kg/has60%
concentration
Water(saline,
potable):
nowater
consumption
Power:
(BFPLorinternal)
105KW
ProduceANsolution:
43,300kg/hmaxand
40,300kg/hnominal
as93%willbeused
forTANproduction.
1) AirEmissions
None
2) LiquidEmissions
Cleancondensate(15ppmN
frombothammoniaandAN)
isusedinthescrubberandas
makeupwater
Blowdown,containing
suitablecontamination
concentrationstobeexported
totheWaterCorporation
(about12m
3
/h).
1.Maxvaluesareassociatedwithupsetconditionsandincludestartupandshutdown,
whichdonotgenerallylastmorethan4hours.
2.Nitricacidemissionsofoffvapourscanbeproducedfromtheneutralisationreactor
intheTANplant.However,alloffvapoursproducedwillbecondensedbackintothe
system,ie.itisaclosedsystem,thereforetherewillbenoemissions.
5.6.4 TechnicalAmmoniumNitratePrillingPlant
The TAN prilling plant will be designed based on the Yara
process for final evaporation and prilling/drying/cooling, and
will:
haveacapacityof915MTPDprilledTAN(as100wt%);
requireANsolutionasrawmaterials;and,
produce TAN prills that are either bagged or stored in bulk
andthensentviatrucktocustomers.
32
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
AmmoniumNitrateSolutionConcentration
The AN solution from the neutraliser is sent to a falling film
evaporatorthatoperatesundervacuum.Evaporationultimately
resultsinaproductconcentrationupto96.5wt%AN.
AdditivePreparation
To produce the higher density grade AN, an additive known as
permalene is required. This permalene solution (25%) is
prepared from the raw materials boric acid, ammonium sulfate
and diammonium phosphate. On the other hand, lower density
AN is produced by theintroductionof an organic additive. Note
that for safety reasons, this organic additive is introduced just
beforetheprillnozzle.Theadditivesareeitherproducedonsite
oraredeliveredasreadymadechemicals.
Prilling
TheANsolutionispumpedtothetopoftheprillingtower.Here,
the solution flows by gravity to the prilling nozzles where they
form droplets that crystallise as they fall from the top of the
tower. The cooling air required for crystallisation of the AN is
recycled to limit atmospheric emissions, while cool and hot air
generatedisreusedviaaseriesofunitoperations.
Drying
Prills exiting the prill tower are directed to the drying section
for reducing the moisture content from 3 4wt% to 0.05
0.2wt%, depending on grade. This is achieved via either co
current or counter current dryers. This unit operation removes
mostofthewaterpresentandresultsinaporousproduct.
CoolingandConditioning
Dried prills are screened before being fed to the fluidised bed
cooler. Oversizes and fines are removed and recycled while the
onspec prills are cooled to the optimal storage temperature.
Thefluidisedbedcoolerisatwostagecoolerwithintermediate
air recycle. The air usage in this section is also integrated to
othersectionsofthefacility,whichisagoodmeansofachieving
higher economic and environmental viability. The cooled
product is finally sent to a coating drum where anti caking
agentsaresprayedon.
Table5.12 TANPrillingPlantSummary
TechnicalAmmoniumNitratePrillingPlant
Inputs/quantities
orvolumes
Outputs/Products Outputs/Wastes&Emissions
ANsolution:
40,300kg/has93%
concentration
NitricAcid:
290kg/has60%
conc.
ProducePrilledTAN
38190kg/h
1) AirEmissions
ANDustparticles
- Normaloperation2.8kg/hr
- Max
1
5.4kg/hr
NH
3
- Normaloperation2.3kg/hr
- Max
1
8.7kg/hr
TechnicalAmmoniumNitratePrillingPlant
Inputs/quantities
orvolumes
Outputs/Products Outputs/Wastes&Emissions
PrillCoating:
38.5kg/h
InternalAdditive:
26.5kg/h(2types
organicorinorganic)
Water(saline,
potable)
2m
3
/hrdesalinated
water
Power
BFPLorinternal)
3.04MW
Continuousemissionswillbe
cleanedinseveralstages
culminatinginacommon
scrubberthatventstothe
atmospheretomeetstatutory
requirements.Duringnormal
operationtheammonium
nitrateandammonia
emissiontoatmospherewill
be2.3and2.8kg/h,
respectively.
2) LiquidEmissions
Occasionalfloorwashings,
drains,dripsrainwateretc
(about4m
3
/day).
Atmosphericmoisture
condensationfromplantair
conditioning,about1.9m
3
/h
1. Max values are associated with upset conditions and include startup and shut
down,whichdonotgenerallylastmorethan4hours
5.6.5 Storage,LoadingandTransportFacilities
BulkTANStorageBuildingandTruckBulkLoadingSystem
The bulk TAN storage will have a capacity of 12,000 MT. The
storage/layout of the product piles are based on
recommendations from the world renowned Dutch research
institute TNO to ensure safe conditions (see Section5.5.3 for
further details). As a consequence the storage will have several
bulk piles with a distance of about 1 m to avoid sympathetic
detonation. Due to the ambient temperature of the Pilbara
region, the bulk storage will have a special roof construction to
maintain temperatures within acceptable levels. Air
dehumidification or conditioning is likely to be further
consideredtoimprovethestorageifdeemednecessary.
The final TAN product leaving the TAN prilling plant will be
conveyed to the bulk storage or directly to the truck loading
area(includingweightbridge).Thetruckloadingcanalsobefed
from the bulk storage using a front end loader and conveying
system.
33
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
ThebaggingfacilitywillhaveacapacitytobagTANinto1,000
1,250kg bags. Product that is to be bagged will also be
reclaimed from the bulk storage and conveyed to the bagging
plant.Forkliftswillbeusedtotransportbaggedproductstothe
bagged TAN storage building. Bagged products will be
transportedtocustomersusingtrucksasdiscussedabove.
NitricAcidBufferStorage
Two tanks with a total capacity of 3,000m
3
will be located in a
bundedareawithanacidresistantsurface.
AmmoniumNitrateSolutionStorage
ExcessANsolutionwillbestoredatconcentrationsof8092%
withina500MTtankthatwillbelocatedinabundedarea.
34
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
Biocide To be mainly stored in a 1 m
3
container at the
NA plant from where a 300L day tank will be fed. There
will be continuous consumption during operation of
about 0.5L/h. Depending on delivery more containers
maybestoredinthechemicalstore.
Scale inhibitor To be mainlystored in a 1m
3
container
at the NA plant from where a 300L day tank will be fed.
There will be continuous consumption during operation
of about 0.75L/h. Depending on delivery more
containersmaybestoredinthechemicalstore.
DieselStorage
An onsite above ground diesel fuel store of a capacity of
approximately 12m
3
will be installed to provide refuelling for
the payloaders and possible feed to the emergency diesel
generatordaytank.Thistankwillbelocatedinanappropriately
bundedarea.
PotablewaterobtainedfromtheWaterCorporationwillbeused
forsafetyshowers,utilitiesanddomesticpurposes.
ClosedLoopFreshWaterCoolingSystem
The cooling requirements of the process elements within the
TANPF will partially be provided by a closed loop fresh water
cooling system. Process heat exchangers requiring cooling
waterwillnormallybefedfromthissystem,with6,545m
3
/hof
fresh water to be within the loop system with the exception of
thesteamcondenserintheNAplant.Thehotfreshwaterwillbe
cooled with seawater from the cooling towers. The steam
condenser of the NA plant shall be fed directly from the
seawaterloopsystem.
35
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
WaterPonds
A clean surface water pond and a contaminated surface water
pond will be utilised at the facility to managethe various liquid
streams.
NaturaldrainageontheSitewillbedivertedtoensurethatflows
continue into the salt flats. BNPL will consult with DEC over
drainage design to ensure that there is a minimal impact on
naturalflows.
Wastewaterandrainwaterwillbecollectedonsite,andwillbe
segregated to drain to either the clean or contaminated surface
water pond (as discussed above). Water quality will be
controlled and monitored using conductivity and pH
measurements, and water will be routed to the appropriate
pond.Waterfromthecleansurfacewaterpondwhichdoesnot
exceedtheWaterCorporationsagreedMinisteriallimitswillbe
senttotheWaterCorporation.
The TANPF shall comprise a network of bunded areas and
trenches so that any potentially contaminated water is kept
completely isolated from rainwater. All storage tanks and all
main plant units will be bunded. Bunded areas within the
complex shall in most cases include a collecting pit from which
wastewaterissenttothecontaminatedsurfacewaterpond.
36
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
Once operating, the synthesis of nitric acid gives off significant
waste heat that will be transferred to a steam system. Some of
this steam will be used in the process units of the TANPF (for
example air heaters), with the remaining excess heat to be sent
throughtoahighefficiencyturbinetogenerateelectricalpower
through the use of steam. This allows for a significant decrease
in the energy required to operate the TANPF and thereby
significantly reduces the air emissions and greenhouse gases
produced.
37
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
Permanent housing for operational workforce will be built or
acquired in the Karratha region (for about 60 Karratha based
personsintotal).
Sewage
Sanitary waste will be collected by authorised personnel using
trucks and transported to an offsite treatment plant. The
amount of sanitary waste is estimated to be a maximum
0.2m
3
/person/day. During the construction an average of 400
persons will be on site with a peak of 650 persons. When the
TANPF is in normal operation a total of 60 persons will be
employed (including shift personnel). Sanitary waste storage,
collection and disposal will be organised sufficiently for the
number of personnel onsite in accordance with all relevant
legislativerequirements,includingthoseoftheWADepartment
ofHealth(DoH).
Lighting
The provision and use of artificial lighting are required for
safety and operational reasons as the TANPF will operate on a
24 hour, seven days a week basis. Artificial sources of light will
be used during the construction and operations phases of the
TANPFasfollows:
Lightingtoenable24houradayactivitiesattheTANPF.
Lighting within the construction site, should nighttime
worksberequired.
38
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
PlantInstallation
The proposed activities associated with plant installation for
TANPFwillinclude:
Transport of construction materials on and offsite (via
KarrathaDampierRd,BurrupRdandVillageRd)including
cranes;
Operationofcranes;
Grindingandwelding;
Insulationandpainting;
Nondestructivetesting(incorporatingxraytestsofwelds);
Joiningcoolingwaterlines(resins,glassfibre);and
LandingofprefabricatedComponents.
39
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
All units may require cleaning prior to actual testing. All waste
developed from cleaning process will be collected and disposed
offappropriatelyinaccordancewithrelevantlegislationandthe
wastemanagementplanwithintheCEMP.
5.7.4 Emissions,DischargesandWasteduring
Commissioning
AtmosphericEmissions
Duringblowingoutofthenitricacidplant(cleaningwithair)air
with small amounts of dust and sand will be emitted to
atmosphere.
Althoughsomesectionsmayrequirecleaningwithsolventsthat
can evaporate, it is not foreseen that significant amounts of
solventsshallbeused.
SolidWaste
During commissioning a number of systems may be operated
outsidenormaloperatingconditionsthatmayresultintheneed
to replace consumable parts of the systems more frequently
than during nominal operation. For example the oil unit of the
turbo set in the NA plant will be cleaned by circulating oil
through the oil filter. The cartridges of the oil filter will be
changed when these filters are spent. The spent cartridges are
non hazardous wastes and will be disposed of appropriately in
accordancewithrelevantlegislationandthewastemanagement
planwithintheCEMP.
LiquidWaste
SomeflowlineswithintheTANPFwillbecleanedwithwateror
water with chemicals. For example, the process gas cooler
system of the NA plant will be boiled out with water and some
chemicals.
Thewaterusedforleaktestingand/orpressuretestingwillalso
besenttoeitherthecontaminatedorcleansurfacewaterponds.
Any contaminated materials will be sent offsite to licensed
contractorsfortreatmentanddisposalasrequired.
Itwillhaveanannualuptimeof90%minustheprovisionofany
downtime due to market reasons or other reasons that are not
related to plant operations. An interstage NA storage tank will
allow the NA plant and the AN solution and TAN plants to
operateindependentlyforupto two days. This is deemed to be
adequate in terms of time, for plant maintenance (e.g. catalyst
change in NA plant, necessary cleaning in the TAN plant etc.).
WhentheNAplantisshutdown,thenecessarysteamandpower
tomaintaintheAN/TANproductionwillbeprovidedbyBFPL.
40
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
Upset conditions may result from some perturbation to the
systemthatpreventstheTANPFfromstabilisinginnominaland
steady conditions. Upset conditions may require special
attention and additional personnel (such as laboratory
personnel)sothatsteadyoperationcanbereachedagain.
FortheANplantcontinuousemissionswillbeemittedfromone
single stack into which a common scrubber will exhaust all air
used from the plant. The use of BAT shall be reflected in the
exhaust air quality (<30mg/Nm
3
particulate and <50mg/Nm
3
ammoniaasperEFMABestAvailableTechniques2000).
SolidWaste
Anyspillsoforganicadditivesorcoatingagentfromtheoffspec
treatmentunitthatisexpectedtocontainsignificantamountsof
TAN shall be recovered and treated as special waste. The waste
management plan (to be completed prior to operation and
included in the OEMP) shall describe procedures for
managementofhazardouswasteindetail.
Therewillalsobesolidsaltsresultingfromtheoperationofthe
contaminatedsurfacewater pond.Thesesaltsshallbecollected
anddisposedasperlegislativerequirements.
41
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
LiquidWaste
TheonlyliquidwastesourcesresultingfromtheTANPFprocess
duringnormaloperationare:
Oilresidueandsludgefromtheheatexchangersandstorage
tankswillberecoveredandtreatedasspecialwaste.
Seawaterblowdownof350m
3
/hshallbeexportedbackto
the Water Corporation in compliance with the Water
Corporations approved Ministerial conditions for release of
watertoKingBay.
Water collected in the clean surface water pond shall be
controlled for pollution and once water is deemed of
acceptable quality, it shall be transferred to the Water
Corporationforfurthertreatment.
Spent oil from machinery shall normally be sent out to be
treatedasnonhazardouswaste.
Blow down and draining of equipment and miscellaneous
washings that may contain nitrogen will be sent to the
contaminatedsurfacewaterpond.
Liquid waste from the laboratory may contain special
chemicals that shall be treated as special waste (hazardous
or nonhazardous depending on the exact nature of the
chemicals).
Sanitary wastewaters shall be collected by truck for
treatment,asdetailedinSection5.6.9.
5.7.7 Decommissioning
Decommissioning activities will involve the recovery of catalyst
(platinum) from the heat exchangers and vessels in the NA
plant. The decommissioning phase will last approximately four
to six months with an average manning level of 20 personnel.
Upon decommissioning, the TANPF is not considered likely to
have any significant hazardous wastes or contaminated lands.
All left over wastes and contaminated material will be cleaned
and removed in accordance with relevant legislation and a
Decommissioning Environmental Management Plan (DEMP) to
bedevelopedpriortodecommissioning.
42
B U R R U P N I T R A T E S P T Y L T D
TechnicalAmmoniumNitrateProductionFacility
PublicEnvironmentalReviewJanuary2010
Thispageintentionallyblank