Escolar Documentos
Profissional Documentos
Cultura Documentos
1.0 Introduction
The category 3 contingencies in NERCs Transmission System Planning Performance
Requirements are multiple contingencies and defined as loss of one component, followed by
system adjustments, and loss of another component. The contingencies are well known as N-1-1
contingencies. At PSS
E only. If PSS
=
S i
i P
Pi
PI
2
)
max
(
Where S is the set of all overloaded monitored elements, Pi is the power flow on monitored element
i, Pmaxi is the rating of monitored element i.
Siemens Energy, Inc.
N-1-1 Contingency Analysis User Guide Power Technologies International
3/25/2009 15
The analysis result report first lists N-1 contingency analysis results obtained from Contingency
Analysis function with corrective action enabled as shown Figure 7b. Contingency cases are
classified into converged cases, converged cases with thermal limit violations, clean cases,
contingency cases which a set of corrective actions is specified, contingency cases which a set of
corrective actions is specified and which are clean after the corrective actions are applied. For each
class, the number of contingency in the class and contingency labels are listed. The set of
corrective actions from the worst case is selected to apply to the base case and an N-1 contingency
analysis is re-performed on the corrected base case. The worst case is the case that has thermal
limit violations and for which a set of corrective actions can be found to remove the violations.
It may take several iterations to correct the base case so it satisfies contingency case performance
criteria. At each iteration the applied corrective actions are tabulated in groups of generation re-
dispatch, phase shifter angle adjustment, and load curtailment. Each controls initial, change and
new values are listed, in MW for generation re-dispatch, in degree for phase shifter angle
adjustment, in MW for load curtail. An N-1 contingency analysis is then re-performed on the
corrected base case and the summary report of the N-1 contingency analysis lists the numbers of
converged contingency cases and clean cases, as well as contingency case labels in each group.
For example, in the Figure 7c the contingency case N1OVRLOD 2 has the largest PI and can be
cleaned by corrective action analysis, and is then picked as the worst case. AC corrective action
analysis is carried out on the contingency case and corrective actions specified for the case
N1OVRLOD 2 are used to adjust the base case and N-1 contingency analysis is re-conduction
with the modified base case. The results show all 14 contingency cases do not result in thermal
limit violations; therefore the base case satisfies base case and contingency case performance
criteria.
N-1-1 Contingency Analysis Report
For each N-1 contingency case, the N-1-1 contingency analysis results are organized in the same
format as defined in the N-1 contingency analysis report. Note that the base case is now the N-1
base case and an N-1 contingency analysis is performed with the pre-defined contingency list of
secondary contingencies. Similar to N-1 contingency analysis report, an N-1-1 contingency analysis
report is divided into two parts: N-1 base case and N-1-1 contingency analysis reports.
If an N-1 base case satisfies base case performance criteria, a message is presented to indicate
that the base case is clean. Otherwise the base report lists for each overloaded monitored element:
the rating, MVA flow, Current flow and percent loading; followed by corrective actions as shown in
Figure 8.
Siemens Energy, Inc.
N-1-1 Contingency Analysis User Guide Power Technologies International
16 3/25/2009
Figure 8. N-1 Base Case Report
Following is an N-1-1 contingency analysis report. If an N-1 base case does not satisfy contingency
case performance criteria, the iterative process is started to correct the base case and verify that
the corrected N-1 base case satisfies contingency case performance criteria.
Summary Report
The Figure 9 shows a sample of summary report. The summary report tabulates the N-1-1
contingency analysis results. The first column lists the primary contingencies; the second column
lists secondary contingency cases of each primary contingency. The rest of the columns list results
at each iteration; each of them is headed by the iteration number. To meet N-1-1 criteria, results
shown at the last iteration must be all YC.
Siemens Energy, Inc.
N-1-1 Contingency Analysis User Guide Power Technologies International
3/25/2009 17
Figure 9. Summary Report
Siemens Energy, Inc.
N-1-1 Contingency Analysis User Guide Power Technologies International
18 3/25/2009
6.0 Application Notes
Each primary and secondary contingency must have a unique contingency label. Function
check_conlbls can be used to pre-process contingency labels to make sure they are
unique.
A primary contingency (N-1 contingency) can not be used as an N-1 base case if the
contingency involves generation dispatch specified by contingency specification command
DISPATCH.
The N-1-1 contingency analysis function only evaluates user specified contingency cases, in
other words the contingencies that are defined in N-1 and N-1-1 Contingency Description
Data File. Contingency ranking feature is disabled for N-1-1 contingency analysis.
N-1-1 contingency analysis is essentially based on AC power flow solutions. N-1
contingency analysis must be performance at least once for the N-0 base case and each N-
1 base case. The number of power flows solved could be huge if the lists of primary and
secondary contingency are long.
Under normal condition, a system should satisfy base case and contingency case
performance criteria. Although N-1-1 contingency analysis function has the capability to
correct a base case in case the base case fails to the criteria, the N-1-1 contingency
analysis will be greatly accelerated when run with a clean base case.
_____________________________
Copyright 1990-2009 Siemens Energy, Inc., Siemens Power Technologies International (Siemens PTI)
Information in this manual and any software described herein is confidential and subject to change without notice and does not
represent a commitment on the part of Siemens PTI. The software described in this manual is furnished under a license
agreement or nondisclosure agreement and may be used or copied only in accordance with the terms of the agreement. No
part of this manual may be reproduced or transmitted in any form or by any means, electronic or mechanical, including
photocopying, for any purpose other than the purchasers personal use, without the express written permission of Siemens
PTI.
PSS
E high-performance transmission planning software is a registered trademark of Siemens PTI in the United States and
other countries.
The Python programming language is a trademark of the Python Software Foundation.
Other names may be trademarks of their respective owners.