Você está na página 1de 3

ID Task

Mode
Task Name Duration Start Finish
1 Anderson Point Park
Embankment Repair
46 days Wed 10/1/14 Wed 12/3/14
2 Submitalls 17 days Thu 10/2/14 Fri 10/24/14
3 Project Schedule 1 day Thu 10/9/14 Thu 10/9/14
4 Schedule of Values 1 day Fri 10/10/14 Fri 10/10/14
5 Emergency Contact List 1 day Fri 10/10/14 Fri 10/10/14
6 Damages Claim Form 1 day Fri 10/10/14 Fri 10/10/14
7 TESC 1 day Fri 10/10/14 Fri 10/10/14
8 SPCCP 1 day Fri 10/10/14 Fri 10/10/14
9 Material submittals 17 days Thu 10/2/14 Fri 10/24/14
10 Pre-Construction Meeting 1 day Wed 10/1/14 Wed 10/1/14
11 On site meeting 1 day Wed 10/1/14 Wed 10/1/14
12 Notice to Proceed 1 day Mon 10/27/14 Mon 10/27/14
13 Notice to Proceed 1 day Mon 10/27/14 Mon 10/27/14
14 Mobilize 2 days Tue 10/28/14 Wed 10/29/14
T T S M W F S T T S M W F S T T S M W F S T T S M W F S T T S M W F
Sep 28, '14 Oct 5, '14 Oct 12, '14 Oct 19, '14 Oct 26, '14 Nov 2, '14 Nov 9, '14 Nov 16, '14 Nov 23, '14 Nov 30, '14
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 1
Project: Anderson Point Project
Date: Wed 10/22/14
ID Task
Mode
Task Name Duration Start Finish
15 Move in Equipment and
Materials
2 days Tue 10/28/14 Wed 10/29/14
16 Remove white gate 2 days Tue 10/28/14 Wed 10/29/14
17 Tree trimming in access 2 days Tue 10/28/14 Wed 10/29/14
18 TESC Measures 2 days Tue 10/28/14 Wed 10/29/14
19 Safety Fencing Install 2 days Tue 10/28/14 Wed 10/29/14
20 Install silt fence 2 days Tue 10/28/14 Wed 10/29/14
21 Survey 1 day? Fri 10/24/14 Fri 10/24/14
22 Survey and stake clearing
limits
1 day Fri 10/24/14 Fri 10/24/14
23 Construction staking 1 day Fri 10/24/14 Fri 10/24/14
24 Clearing and Grubbing 2 days Wed 10/29/14 Thu 10/30/14
25 Clear and grub
construction area
2 days Wed 10/29/14 Thu 10/30/14
26 Drainage 10 days Thu 10/30/14 Wed 11/12/14
27 Install temporary
drainage
1 day Thu 10/30/14 Thu 10/30/14
28 Intall permanent
drainage system
3 days Mon 11/10/14 Wed 11/12/14
T T S M W F S T T S M W F S T T S M W F S T T S M W F S T T S M W F
Sep 28, '14 Oct 5, '14 Oct 12, '14 Oct 19, '14 Oct 26, '14 Nov 2, '14 Nov 9, '14 Nov 16, '14 Nov 23, '14 Nov 30, '14
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 2
Project: Anderson Point Project
Date: Wed 10/22/14
ID Task
Mode
Task Name Duration Start Finish
29 Wall Construction 20 days Thu 10/30/14 Wed 11/26/14
30 Excavate for wall 3 days Thu 10/30/14 Mon 11/3/14
31 Stockpile reuasable
material from wall
excavation on site
3 days Thu 10/30/14 Mon 11/3/14
32 Construct Wall 18 days Mon 11/3/14 Wed 11/26/14
33 Substantial Completion 6 days Wed 11/26/14 Wed 12/3/14
34 Substantial Completion 1 day Wed 11/26/14 Wed 11/26/14
35 Demobilization 3 days Mon 12/1/14 Wed 12/3/14
36 Clean up 3 days Mon 12/1/14 Wed 12/3/14
37 Demobilization of
equipment
3 days Mon 12/1/14 Wed 12/3/14
T T S M W F S T T S M W F S T T S M W F S T T S M W F S T T S M W F
Sep 28, '14 Oct 5, '14 Oct 12, '14 Oct 19, '14 Oct 26, '14 Nov 2, '14 Nov 9, '14 Nov 16, '14 Nov 23, '14 Nov 30, '14
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Page 3
Project: Anderson Point Project
Date: Wed 10/22/14

Você também pode gostar