Escolar Documentos
Profissional Documentos
Cultura Documentos
Department of Electrical Engineering, Faculty of Engineering, University of Malaya, 50603 Kuala Lumpur, Malaysia
UM Power Energy Dedicated Advanced Centre (UMPEDAC), Level 4, Wisma R&D UM, University of Malaya, 59990 Kuala Lumpur, Malaysia
c
Faculty of Electrical Engineering, University of Technology MARA (UiTM), 40450 Shah Alam, Selangor, Malaysia
b
a r t i c l e
i n f o
Article history:
Received 26 September 2011
Received in revised form 22 December 2011
Accepted 13 March 2012
Available online 8 May 2012
Keywords:
Distributed generation
Under-Frequency Load Shedding
Load prioritization
Rate of change of frequency
Islanding
a b s t r a c t
Under-Frequency Load Shedding (UFLS) is a common technique to maintain power system stability by
removing the overload in some part of the system. The existing UFLS schemes operate successfully in
the interconnected grid system. A particular approach of UFLS scheme is required for an islanded system
which is known to be not as strong as the grid. This paper presents a new approach of UFLS scheme for
the implementation in an islanded distribution system. The scheme is based on a combination of adaptive
and intelligent techniques. The disturbance magnitude for response based and event based is treated differently: (1) event based is based on the power imbalance and (2) response based is based on the swing
equation which relies on the frequency and rate of change of frequency measurement. Dynamic simulation on an intentional islanding operation is performed on an existing Malaysian network interconnected
with a mini hydro generation. The objective is to investigate the effectiveness of the proposed scheme.
The simulation results demonstrate that the proposed scheme is capable of improving the frequency
response of the islanded system. A signicant nding is that the scheme can successfully reduce the effect
of power deciency following the grid connected to islanding operation transition.
2012 Elsevier Ltd. All rights reserved.
1. Introduction
In the recent years, intentional islanding of a distribution network connected with distributed generation (DG) has becomes a
topic of interests to improve security and reliability of a distribution network. Implementing an intentional islanding operation of
DG will establish continuity of supply whereby the DG must be
able to take over the role of the grid by independently feeding
the whole island [1]. Although the operation is currently prohibited (as stated in IEEE STD 929-2000 [2] and IEEE STD 1547-2003
[3]) due to the severe consequences islanding can bring, this operation is inspired with the high penetration level of DG expected in
the near future and it could offer benets. Accordingly, IEEE 1547
group has produced a draft series of guides referred as P1547.4
Draft Guide for Design, Operation, and Integration of Distributed
Resource Island System with Electric Power System [4] which will
serve yet as a guide for practicing an intentional islanding operation in an electric power system.
128
Main Grid
Islanded
Distribution Network
Load Shed
Controller
Module
Distributed
Generation
Frequency
Calculator
Module
G1
G2
Start
f 1 & f2
f1 : frequency of generator1
f2 : frequency of generator2
f: system frequency
129
Generator number 1 is
disconnected from the
system ?
Yes
f = f2
No
Generator number 2 is
disconnected from the
system ?
Yes
f = f1
No
f = System frequency
No
Yes
End
Fig. 2. Algorithm of the frequency calculator module.
where DP is the imbalance power; PGrid is the grid power generation; PDG is the DG power generation and PLoad is the total load
consumption.
130
Start
Frequency from
FCM
& ROCOF
No
Is distribution network
islanded ?
Yes
Frequency from
FCM
&
ROCOF
Response based
Event based
Define the UFLS method
Yes
Disturbance magnitude
+DG generation at this moment >
DG rated value
No
No
Frequency<= f set
Yes
End
Fig. 3. Flowchart of the proposed load shedding controller module.
amount of power imbalance is estimated by using the swing equation which is expressed in
2 H dfc
Pm Pe
fn
dt
131
Connect
to Grid
1047
Load 5
Vital Load
Incoming Grid
Substation Breaker
1079
1056
1058
1046
Load 7
1075
Load 12
1057
1039
1018
Load 6
Load 9
1019
1154
1010
1013
Load 13
Load 1
Vital Load
Load 8
1020
1050
1012
Load 3
Load 4
1004
1141
1064
1151
1029
NOP
Load 11
1000
Synchronous
Generator1
Load 2
Load 10
Vital Load
Load 14
Load 15
Synchronous
Generator2
Table 1
Excitation parameters.
Table 3
Hydraulic turbine parameters.
Parameter
Value
Parameter
Value
Parameter
Value
Parameter
Value
TC
TB
KA
TA
VAMAX
VAMIN
VRMAX
SE (VE1)
VE1
0
0
400
0.02
14.5
14.5
6.03
0.1
4.18
KF
TF
TE
KE
KC
KD
VRMIN
SE (VE2)
VE2
0.03
1
0.8
1
0.2
0.38
5.43
0.03
3.14
TW
fP
D
1.2
0.02
0.5
0.7
1.0
1.0
Table 2
Governor parameters.
Parameter
Value
Parameter
Value
KP
KI
KD
TA
RP
Max gate position
2
0.35
0.9
0.05
0.04
1.0
TC
TD
Max gate opening
Max gate closing
Dead band value
Min gate position
0.2
0.2
0.16
0.16
0
0
DP
2
PN
i1 H i
fn
dfc
dt
132
the disturbance magnitude is required to be shed to prevent further drops in the frequency. In this case, the LSCM will estimate
the amount of load needed to be shed by using the swing equation.
Table 5
Case studies.
Case studies Descriptions
Case
Case
Case
Case
I
II
III
IV
P P0
Q Q0
V
V0
a
V
V0
1 K PF df
b
1 K QF df
The exponent a and b are equal to the slope of dP/dV and dQ/dV at
V = V0, respectively. The range of a is typically between 0.5 to 1.8
and the exponent b is between 1.5 and 6.
Also, KPF ranges from 0 to 3, and KQF is between 2 and 0 [34]. In
this study, the exponent value for a and b is set to 1.0 and 2.0
respectively. Meanwhile, KPF and KQF are set to 1.0 and 1.0 respectively. Thus, by choosing these values, the load is a voltage and frequency dependent type.
3.3. Case studies
In order to test the proposed scheme, an intentional islanding is
performed to the test system. Prior to islanding, a total power of
3.06 MW is dispatched by the generators. Since it is grid connected,
the excess or deciency of power in the distribution system is
accommodated by the grid system. Islanding detection of islanding
operation is simulated with the opening of incoming grid substation breaker at time t = 10 seconds (s).
Table 4
Load ranking table.
Load ranked
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
Total
Bus number
1013
1141
1012
1050
10471079
1057
1058
10101039
1018
1004
1020
1046
1154
1064
1029
1019
1151
1056
Peak load
Base load
Load category
P (MW)
Q (MVAR)
P (MW)
Q (MVAR)
0.0684
0.0796
0.0796
0.1095
0.1794
0.189
0.198
0.234
0.1742
0.2122
0.2767
0.2551
0.2097
0.1398
0.3469
0.1601
0.1608
0.5139
0.0423
0.0495
0.0495
0.0576
0.0792
0.1152
0.1229
0.1101
0.108
0.1314
0.1716
0.1579
0.1274
0.0867
0.2147
0.0991
0.0996
0.3281
0.0491
0.0581
0.0464
0.0568
0.1175
0.0558
0.1089
0.1607
0.1005
0.0705
0.1621
0.2548
0.1215
0.1389
0.2042
0.0967
0.0964
0.446
0.0253
0.0297
0.0297
0.0346
0.0739
0.0346
0.0738
0.0999
0.0648
0.0491
0.1029
0.1579
0.0765
0.0867
0.129
0.145
0.0598
0.2641
3.5869
2.1508
2.3449
1.5373
Non-vital
Non-vital
Non-vital
Non-vital
Non-vital
Non-vital
Non-vital
Non-vital
Semi-vital
Semi-vital
Semi-vital
Semi-vital
Semi-vital
Semi-vital
Semi-vital
Vital
Vital
Vital
133
134
Fig. 10. System voltages of some buses in peak load for case II.
Base load
Peak load
1.23
1.80
0.824
1.828
135
due to imbalance power resulting from the islanding. The DGs have
to change their operation by reducing the dispatched power to
match with the loads in the islanded system (i.e. 2.46 MW). In this
case, load shedding is not required and thus the LSCM is not
initiated.
4.1.2. Peak load scenario
Following islanding, the system frequency begins to decline in
response to the islanded system that has an excess of loads. It
should be noted that both generators have a provision of spinning
reserved (i.e. 0.6 MW), thus it is adopted to supply power to the
loads in the island. The LSCM will only be initiated when the total
loads in the island surpass a value of 3.6 MW. In this case, the total
load is 3.797 MW. Consequently, the LSCM automatically initiates
its event based strategy to prevent further decline in frequency.
The power imbalance is determined. Accordingly, the load at bus
1013, 1141 and 1012 are intelligently shed based on the look-up
table as in Table 4. The load shedding is accomplished in one step.
The frequency response with and without load shedding is as
shown in Fig. 6. It can be seen that without load shedding, the
frequency fails to restore. With the load shedding scheme, system
frequency drops to 47.76 Hz and then gradually recovers to
its nominal value. Note that even though the loads have been shed
after some delay, the frequency keeps on dropping until 47.76 Hz.
This is due to the slow response of the hydro generator following
the sudden changes in the output power resulting from the load
shedding. The smooth response without any overshoot will justify
Fig. 11. System frequency of the peak load when the load ranked 12 is not considered to be shed.
136
Fig. 13. Frequency of the system in based load for case III.
that the loads are optimally shed. Fig. 7 shows the change of active
power dispatched before and after load shedding. It can be observed that following islanding, the power generations of DGs are
increased.
4.2. Case II
In this case, loss of one generator is simulated at simulation
time, t = 75 s following system islanded in case I. Frequency responses for base and peak load scenarios are shown in Figs. 8
and 9 respectively.
Since the loads in the islanded system are supplied by the two
small hydro DG, loss of one DG will give a great impact to the island.
As a result of losing half of the island generation (1.8 MW in peak
load case), the voltages across the system and the system frequency
has dropped. System voltages of some buses are shown in Fig. 10. In
response to the event and to stabilize the islanded system, the LSCM
would immediately trip signicant numbers of load feeders. The
LSCM categorizes the event under event-based strategy.
Optimum load shedding value is as presented in Table 6. The total loads shedding for both scenarios are observed. For base load
scenario, following the event, the LSCM disconnect load ranked 1
until 10. This is based on the determined disturbance magnitude
where the lowest ranked load is rstly shed followed by the next
lower ranked. As shown in Fig. 8, system frequency drop to
47.74 Hz and then slowly restores to its nominal value.
For peak load, the LSCM intelligently disconnects load starts
from ranked 4 until 12. Note that load ranked 1 and 3 have been previously disconnected in case I. As previously described in the algorithm, the load shedding is performed after some delay. As
depicted in Fig. 9, the delay corresponds to the instant the system
frequency starts to rapidly increase to 50.71 Hz from the initial response of sudden loss of generation. The rise of frequency explains
that more loads than required have been shed. To investigate this issue, load ranked 12 is omitted from being shed. The response is as
illustrated in Fig. 11. It can be seen that the frequency does not recover to its nominal value. This proves that even though the load
shedding has caused the overshoot of the system frequency, the
LSCM has actually shed the optimum numbers of feeder loads and
eventually has brought the frequency to its nominal value.
4.3. Case III
In this case, an overload scenario in the islanded system for
peak and base load is simulated. To create the overloads, a new
load feeder rated 0.54 MW is suddenly connected to the bus number 1058 at simulation time, t = 75 s. Figs. 12 and 13 present the
system frequency response for overloads scenario in peak and base
load system respectively.
Prior overload, the total loads in the islanded system was
2.46 MW and 3.58 MW for base and peak load respectively.
Following overload, the total loads increased to 3 MW and
4.12 MW. The ROCOF measurement detects |ROCOF| is greater than
ROCOFmax which then triggers the LSCM to initiate its response
based strategy. As highlighted in Fig. 3, there are two considerations for the response based strategy. The rst consideration is
initiated if the total load (including the additional load) is more
than the maximum power output of the generators (3.60 MW)
while the second consideration is initiated if the total load is less
than the generator maximum power output but more than the current generation. Thus, in this case, the LSCM evaluates the peak and
base load scenario under the rst and second consideration
respectively.
For peak load scenario, the amount of load to be shed is determined with regards to the estimated disturbance magnitude (refer
to Table 7). It is observed that load ranked 4 until 6 are shed. The
fast operation of LSCM is depicted in the frequency response of
Fig. 12. It proves that the LSCM has optimally shed the load.
For the base load scenario, a different consideration is required.
The generators still have unused capacity. Thus, priority is given to
the generator secondary controller to activate its spinning reserve
to maintain the system frequency stability. The LSCM will only
perform load shedding if the estimated value of disturbance magnitude exceeds the unused capacity of generators. Subsequently, if
the frequency keeps dropping until 48 Hz, then a certain amount of
load needs to be shed. The certain amount of load is determined by
using the swing equation. At this point, the frequency might further decline and reach the under-frequency threshold limit
(47.5 Hz), thus a precaution is required. As can be seen in Fig. 13,
the frequency has passed through 48 Hz which then activates the
LSCM to quickly shed some load. Considering the spinning reserve,
only load ranked 1 and 2 with a total amount of 0.107 MW (as
recorded in Table 7) is chosen to be shed. As a result, the frequency
Table 7
Optimal load shedding by LSCM.
Load case
Overload (MW)
Base load
Peak load
0.54
0.54
0.107
0.478
137
Fig. 14. Active power generation of the system for based load.
Fig. 15. Frequency response and load shedding for case IV.
Fig. 16. Frequency response and load shedding for case IV.
for both DGs. It is obvious that following the overload, the generator still has unused capacity to dispatch more power.
138
4.4. Case IV
In this case, an overload scenario in the islanded system, similar
to case III is simulated. In contrast to case III, the overload is simulated at different bus feeder e. bus 1029. The response of LSCM to
the changes of overload location is investigated. It is observed that
the LSCM has assessed this case similar to case III. As a result, the
system frequency response as shown in Figs. 15 and 16 correspond
to that in case III.
From the simulation results (cases III and IV), it is very obvious
that the proposed load shedding scheme can shed the optimum
load according to the disturbance magnitude regardless of the
location of the disturbance. It also demonstrates the feasibility of
the scheme to improve the system stability when the islanded system is subjected to a large disturbance.
5. Conclusion
In this paper, a new approach of UFLS scheme to solve the stability and under-frequency issue for an islanded system in a distribution network is presented. The approach has adopted the
adaptive and intelligent schemes. Two strategies based on, the
response based and event based have been proposed. The disturbance magnitude for the event based is determined, based on the
power imbalance whilst for the response based; it is estimated
using the swing equation based on the frequency and ROCOF measurement. The effectiveness and robustness of the scheme have
been investigated based on two scenarios. The rst scenario is
immediately after a distribution system is islanded. The second
scenario is when it is subjected to different disturbances and loading conditions in the islanded system. It is observed that the developed scheme manages to immediately perform the load shedding
in one step and intelligently distinguish between the event and response based condition. Simulation results show that optimal
amounts of load can be shed according to the well-determined load
prioritization. Thus in this scheme, less important loads are the
rst to be shed. Of signicance is that the scheme has proved to
be an essential tool for a successful islanding operation. The power
quality of the island can be sustained thus allowing the island to
persist.
Acknowledgments
This work was supported by the Malaysian Government and
University of Malaya, Kuala Lumpur under HIR/MOHE research
Grant (Grant Code: D000004-16001).
References
[1] Aghamohammadi MR, Shahmohammadi A. Intentional islanding using a new
algorithm based on ant search mechanism. Int J Electr Power Energy Syst 2011.
[2] IEEE Recommended Practice for Utility Interface of Photovoltaic (PV) Systems.
IEEE Std 929-2000; 2000. p. i.
[3] IEEE Standard for Interconnecting Distributed Resources with Electric Power
Systems. IEEE Std 1547-2003; 2003. p. 116.
[4] Basso TS, DeBlasio R. IEEE 1547 series of standards: interconnection issues.
IEEE Trans Power Electron 2004;19:115962.
[5] Fu X, Wang X. Determination of load shedding to provide voltage stability. Int J
Electr Power Energy Syst 2011.
[6] Terzija VV, Koglin HJ. Adaptive underfrequency load shedding integrated with
a frequency estimation numerical algorithm. IEE Proc Gener Transm Distrib
2002;149:7138.
[7] Ding X, Girgis AA. Optimal load shedding strategy in power systems with
distributed generation. In: Power engineering society winter meeting, vol. 2,
2001. IEEE, 2001. p. 78893.
[8] Terzija VV. Adaptive underfrequency load shedding based on the magnitude of
the disturbance estimation. IEEE Trans Power Syst 2006;21:12606.
[9] Shokooh F et al. Intelligent load shedding. IEEE Ind Appl Mag 2011;17:4453.
[10] Shokooh F, et al. An intelligent load shedding (ILS) system application in a
large industrial facility. In: Industry applications conference, 2005. Fourteenth
IAS annual meeting. conference record of the 2005, vol. 1; 2005. p. 41725.
[11] Pasand MS, Seyedi H. New centralized adaptive under frequency load shedding
algorithms. Large Eng Syst Conf Power Eng 2007:448.
[12] Seyedi H, Sanaye-Pasand M. New centralised adaptive load-shedding
algorithms to mitigate power system blackouts. IET Gener Transm Distrib
2008;3:99114.
[13] Girgis AA, Mathure S. Application of active power sensitivity to frequency and
voltage variations on load shedding. Electr Power Syst Res 2010;80:30610.
[14] Prasetijo D et al. A new load shedding scheme for limiting underfrequency.
IEEE Trans Power Syst 1994;9:13718.
[15] Rudez U, Mihalic R. Analysis of underfrequency load shedding using a
frequency gradient. IEEE Trans Power Deliv 2011:1.
[16] Anderson PM, Mirheydar M. An adaptive method for setting underfrequency
load shedding relays. IEEE Trans Power Syst 1992;7:64755.
[17] Jung J et al. Adaptation in load shedding under vulnerable operating
conditions. IEEE Trans Power Syst 2002;17:1199205.
[18] Andersson D et al. Intelligent load shedding to counteract power system
instability. IEEE/PES Transm Distrib Conf Exposit: Latin America
2004;2004:5704.
[19] Hazarika D, Sinha AK. Method for optimal load shedding in case of generation
deciency in a power system. Int J Electr Power Energy Syst 1998;20:41120.
[20] Wang P, Billinton R. Optimum load-shedding technique to reduce the total
customer interruption cost in a distribution system. IEE Proc Gener Transm
Distrib 2000;147:516.
[21] Luan WP et al. Genetic algorithm for supply restoration and optimal load
shedding in power system distribution networks. IEE Proc Gener Transm
Distrib 2002;149:14551.
[22] Faranda R et al. Load shedding: a new proposal. IEEE Trans Power Syst
2007;22:208693.
[23] Rudez U, Mihalic R. A novel approach to underfrequency load shedding. Electr
Power Syst Res 2011;81:63643.
[24] Wangdee W, Billinton R. Utilization of time varying event-based customer
interruption cost load shedding schemes. Int J Electr Power Energy Syst
27:67481.
[25] Tomsic T et al. Revision of the underfrequency load-shedding scheme of the
Slovenian power system. Electr Power Syst Res 2007;77:494500.
[26] Thompson JG, Fox B. Adaptive load shedding for isolated power systems. IEE
Proc Gener Transm Distrib 1994;141:4916.
[27] Concordia C et al. Load shedding on an isolated system. IEEE Trans Power Syst
1995;10:146772.
[28] Huang C-C, Huang S-J. A time-based load shedding protection for isolated
power systems. Electr Power Syst Res 1999;52:1619.
[29] Mahat P et al. Underfrequency load shedding for an islanded distribution
system with distributed generators. IEEE Trans Power Deliv 2010;25:9118.
[30] Aponte EE, Nelson JK. Time optimal load shedding for distributed power
systems. IEEE Trans Power Syst 2006;21:26977.
[31] Ford JJ et al. Adaptive load shedding and regional protection. Int J Electr Power
Energy Syst 2009;31:6118.
[32] Rudez U, Mihalic R. Monitoring the rst frequency derivative to improve
adaptive underfrequency load-shedding schemes. IEEE Trans Power Syst
2011:1.
[33] Giroletti M et al. A hybrid frequency/power based method for industrial load
shedding. Int J Electr Power Energy Syst 2011.
[34] Kundur P et al. Power system stability and control. New York: McGraw-Hill;
1994.