Você está na página 1de 15

APPENDIX I

Protected Species Management Plan

16454/EN033/04
Volume 4: Construction Environmental Management
Plan

Page 31

Ramboll
Report No. 16454-EN033-rev 05

A477 ST CLEARS TO RED ROSES IMPROVEMENT


CONSTRUCTION ENVIRONMENTAL MANAGEMENT PLAN
APPENDIX I
PROTECTED SPECIES MANAGEMENT PLAN

1.

INTRODUCTION

This plan forms one of a series of discipline plans which, collectively, form the Construction
Environmental Management Plan (CEMP) for the A477 St Clears to Red Roses Improvement.
(Project)
These plans shall be implemented throughout the construction phase of the works for the
Project. They form part of the site management procedures as defined in the Project Quality
Plan.
This plan provides procedures for the management of protected species within the permanent or
temporary works areas during construction. This plan does not cover invasive species as
separate plans cover these elements. A separate plan is also provided for unexpected protected
or rare species.
2.

POTENTIAL IMPACTS

The Environmental Statement (ES) and Statement to Inform Appropriate Assessment (SIAA) for
the Project included a detailed assessment of existing third party information on the ecology of
the area. It also contained significant surveys for specific protected and rare species over a multiyear period. These surveys continued in 2011 and 2012.
As part of the ES and the SIAA the potential impact on protected species was identified. This
included:
Loss of two Badger main setts and closure of a number of outlier setts. Severance of
badger foraging areas.
Loss of two bat roost trees and severance to foraging areas (NB following publication of
the ES one of the two bat roost trees was removed by a third party);
Loss of reptile habitat;
Effects on otter; and
Potential effects on nesting Goshawk.
Surveys in advance of site clearance have identified the presence of dormouse on the site.
Mitigation is being provided for badgers (for which a licence application to close setts will be
made), dormouse and bats (European Protected Species Licenses have been applied for to
permit impacts on dormouse and the remaining bat roost). A method statement has been
prepared to cover reptile capture and relocation. Method statements have been provided to
minimise impacts on otter and goshawk.
The location of all protected species have been shown on the Site Clearance drawings (16454-H200-01 to 015)) which show (for instance) the location of badger setts and bat roosts within the
Permanent and temporary works areas. In addition, the Existing Vegetation Design (16454-H3000-01 to 015) shows some of these features.

3.

PROCEDURES

The appendices to this plan found in Appendix P contain the following:


1. A copy of the Badger license (to be appended when received);
2. A Badger Method statement;
3. A copy of the dormouse license (to be appended when received);
4. A dormouse Method statement;
5. A copy of the Bat License (to be appended when received);
6. The bat method statement;
7. The otter method statement;
8. The Goshawk method statement; and
9. The reptile method statement.
The main procedures for the avoidance of impacts on, and protection of protected species are
contained within each of the method statements. Each method statement shall be enacted on site
as, and when, required. Most notably this will be during site clearance, erection of boundary
fencing, erection of the temporary crossing of the Afon Hydfron, construction of the embankment
across the Afon Taf and Afon Hydfron floodplains and construction of the new flood alleviation
culvert. The roles and responsibilities for the implementation of the protected species method
statements are given below.
As part of the main landscape and ecological design, the ES identified a range of ecological
mitigation to be implemented to reduce impacts on the site ecology, and to enhance the
ecological value of the final design. This included:
Creation of landscape and ecological mitigation areas in isolated plots of land adjacent to
the main alignment;
Creation of new habitat alongside the main alignment;
Movement of existing lichen and bryophyte habitat;
Translocation of 1200m of important hedgerows;
Construction of two artificial badger setts
Construction of two artificial otter holts;
Erection of bat and bird boxes (including in/on new structures);
Erection of deadwood;
Erection of artificial refugia and log piles.
The Environmental Co-Ordinator shall ensure that mitigation identified in the Commitments
register (from the ES and SIAA) is included in the detailed design and implemented/constructed
on site. As part of the detailed design, the Project ecologist shall identify the ecological objectives
for the landscape planting scheme and will document these, along with a timeline showing when
these objectives are likely to be achieved.
The Environmental Clerk of Works and the Environmental Co-Ordinator shall ensure that
temporary mitigation is included in the detailed design and implemented and maintained on site
during construction.
As a summary Appendix I1provides programming information in relation to protected species
present in the project footprint or vicinity.

4.

ROLES AND RESPONSIBILITIES

The following staff have roles and responsibilities for works under this plan:
Activity
Implementation
of
Protected
Species
Management
Plan
and attendant Method
Statements
Landscape
and
Ecology Design
Installation
and
maintenance
of
temporary ecological
mitigation such as bat
fencing/wires
Erection of artificial
setts, refugia, logpiles,
holts, deadwood, bat
boxes and bird boxes.
Translocation
of
hedgerow
Lichen and Bryophyte
habitat
Site
clearanceimplementation
of
method statements
Weekly checks of
protected
species
fencing
during
construction
Maintenance
of
ecological/audit
records
Preparation
of
ecological reports
Auditing of planting
undertaken
Post
Construction
monitoring

Primary Role
Env
Manager
/
Ecological
subconsultant

Review Role
Environmental
ordinator

Environmental
ordinator
Project ecologist
Env Manager

Design Manager

co-

co-

Authorisation Role
Site Manager

Project Manager

Environmental
ordinator

co-

Site Manager

Clerk

Environmental
ordinator

co-

Site Manager

Environmental Clerk
of works
Env Manager
Project Ecologist

Environmental
ordinator

co-

Site Manager

Environmental
of works

Environmental
ordinator

Environmental
of works
Env Manager

Clerk

Site Supervisor

Site Manager
co-

Site Manager

Site
Construction
supervisors

Environment Clerk of
Works

Site Manager

Environmental
of works

Environmental
ordinator

co-

Site Manager

Environmental
ordinator
Environmental
ordinator
Environmental
ordinator

co-

Site Manager

co-

Site Manager

co-

Site Manager

Clerk

Project ecologist
Environmental Clerk
of works
Project ecologist

5.

MONITORING SURVEY AND ACTIONS

5.1

Coverage

The Plan covers all areas of temporary and permanent works. The Plan covers known protected
species (bats, dormouse, badger, goshawk, otter and reptiles) at known locations. Should these

species be identified elsewhere within the permanent or temporary works during construction, the
Environmental Clerk of Works will instigate the unexpected species plan and undertake an initial
review. Thereafter, the method statements attached to this plan and the EMP drawings will be
updated and a suitable action plan prepared by the Environment Clerk of Works with advice from
the Project Ecologist.
Should protected species not identified in this plan, and for which no method statement is
currently available, is detected, the Unexpected Protected or Rare Species Management Plan
shall be implemented (Appendix O).
Should protected or rare species be seen in the immediate area of the works, but off site, this
information should be passed to the Environmental Clerk of works who will define any actions
thought to be required. In most instances this will only comprise recording of the information (the
boundary protected species fences should minimise access to the site by protected and rare
species.
5.2

Identification of Protected and Rare Species

All Employees shall be given tool box talks. The talks will revolve around a series of simple to
remember actions:
1. If any employee on site identifies a plant or animal they believe to be protected or rare,
and they are not marked on the environmental management plans, they are to report this
to the Environment Clerk of works immediately;
2. The site supervisor should be informed and he will stop works in the area the species is
located;
3. Under no circumstances should suspected protected or rare species be picked up,
moved or disturbed by site employees, even where they appear to be injured or in
trouble.
4. The Environmental Clerk of Works will visit the location of the find as soon as possible
and inform site staff of the appropriate measures required.

5.3

Initial Site Visit and Review

Please refer to the Unexpected Protected or Rare Species Plan (Appendix O).
5.4

Action Plans

Please refer to the Unexpected Protected or Rare Species Plan.


5.5

Monitoring and Verification

A programme of monitoring of mitigation measures for Protected species shall be undertaken


throughout the construction period. This shall comprise:
Check

Frequency

Ecological mitigation
during site clearance

Daily
during
clearance

Responsibility
site

Environmental
of Works

Clerk

Verification
Completion
Environmental
Ordinator

of
Co-

Translocation
of
hedgerows
Translocation of rootbowls and lichen and
bryophyte habitat from
Ancient woodland
Ecological mitigationprotected
species
fence checks
Construction
of
ecological mitigation
Restoration of Afon
Hydfron at crossing
points
Investigate reports of
protected species
Audit
installed
landscape planting
6.

RECORDING

6.1

Reporting

During site clearance

Environmental Clerk
of Works
Project ecologist

Environmental
Ordinator
Environmental
Ordinator

Co-

Weekly

Environmental
of Works

Clerk

Environmental
Ordinator

Co-

Throughout
construction
Upon completion of
works

Environmental
of Works
Environmental
of Works

Clerk

Environmental
Ordinator
Environmental
Ordinator

Co-

As required

Environmental
of Works
Environmental
of Works

Clerk

During site clearance

Upon completion of
works

Clerk

Clerk

Environmental
Ordinator
Environmental
Ordinator

Co-

Co-

CoCo-

All ecological reports shall be reviewed and signed off by the Project ecologist and Environmental
co-ordinator. All ecological reports shall be reviewed and agreed with the Project Manager and
the Welsh Governments Project Manager (or his appointee) prior to issue to third parties.
As areas of ecological mitigation are completed and released for construction works, the form in
appendix I will be used to record the sign off.

New Otter Holt to be built in


woodland
Reptile Area suitable habitat for
reptiles present

200

Several
areas
knotweed

1100-1350

of

Japanese

be

1100-1200
(north)

to

Artificial badger
constructed.

1100-1200
(north)

980-1180

800-1100

sett

Picking Gate.
Invasive species
present (Japanese knotweed).
Existing Bat crossing 2, screens
required to direct bat flight paths.
Reptile Area suitable habitat for
reptiles present
Retained grassland enhanced for
reptiles

800-1100

500

Sensitive
working
practices
required around retained, off site
trees with potential for roosting
bats.
Hedgerow to be cleared under
dormouse precautionary method

250-440

200-240

Features from the woodland are to


be retained for use in new
woodland planting plot

Wet
Woodland
and adjacent
hedges (including H8). Woodland
contains evidence of Dormouse
and will be cleared according to
the Dormouse Method Statement,
under license.

Description

200-300.

Location
Chainage
200-430

Y (for herbi
-cide use)

Y (for herbicide use)


Y

N,
but
reliant
on
site
clearance
N

Seasonal
constraint
Y

Needs
to
be
constructed as soon
as possible
Invasive
Weed
method statement

Invasive
Weed
method statement
Screens to be in place
April onwards
Reptile
Method
Statement.
Refer
to
Ecology
Design

Dormouse
precautionary method

Refer
to
Ecology
Design / specifications
Reptile
Method
Statement.
Ground
clearance should be
carried out by mid
March when reptiles
become active
Careful working
as
defined in the bat
licence

Consents
or
methods that apply
No
works
until
dormouse licence is
obtained. Work under
dormouse licence in
two phases (*tree
clearance under ecological supervision)
Refer
to
Ecology
Design

A477 SCRR Ecological Programme for Site Clearance and Associated Works
J

Retain
logs

Tree
clearance*

Retain
topsoil
and
stumps

Ground
clearance

ECOW

Ecologist

Ecologist

Ecologist

ECOW

Dormouse
licensed
ecologist
ECOW

ECOW

Ecologist

Ecologist

Ecologist/
ECOW

ECOW

Responsibility
Dormouse
licensed
ecologist

Badger sett exclusion zone where


groundworks only as directed by
the
Ecologist
applies
until
mitigation is complete (under
licence as necessary)
Screens required to direct bat
flight paths.
Woodland around stream/sunken
lane
contains
evidence
of
Dormouse and will be cleared
according
to
the
Dormouse
Method Statement, under license.

Series of badger setts exclusion


zone where groundworks only as
directed by the Ecologist applies
until mitigation is complete (under
licence as necessary)
Up to three trees with potential for
bats to be present, to be felled
under Bat Precautionary Method.
Reptile Area suitable habitat for
reptiles present
Hedgerow to be cleared under
dormouse precautionary method

Hedgerow to be cleared under


dormouse precautionary method

1240
(ch.
435
Picking
Gate)

14001550

2140-2220

1950

1900

1500

1380-1620

1350-1950

Hedgerows to be translocated to
be
cleared
under
dormouse
precautionary method

Hedgerows to be cleared under


dormouse precautionary method

Description

1200,
1350-1400

Location
Chainage
1180-1360

Y sett
closure
required at
1400

Seasonal
constraint
Y

Dormouse
precautionary method

Felling as defined in
Bat licence for trees
affected
Reptile
Method
Statement.
Dormouse
precautionary method

Screens to be in place
April onwards
No
works
until
dormouse licence is
obtained. Work under
dormouse licence in
two phases (*tree
clearance under ecological supervision)
Badger
Method
Statement / Licence
sett closure in period
July to November

Dormouse
precautionary
method/
hedgerow
translocation method
Badger
Method
Statement / Licence
sett closure in period
July to November

Consents
or
methods that apply
Dormouse
precautionary method

Tree
clearance*

Ground
clearance

Sett closure under


licence and following
badgers adoption of
artificial sett at 11001200 (north)

Dormouse
licensed
ecologist
Dormouse
licensed
ecologist

Bat
licensed
ecologist
Ecologist

Badger
licensed
ecologist

ECOW

Dormouse
licensed
ecologist

ECOW

Badger
licensed
ecologist

Responsibility
Dormouse
licensed
ecologist
Dormouse
licensed
ecologist

Two sheds need to be checked for


presence of bats and barn owl
prior to demolition. Existing Bat
Crossing 5.
Hedgerows to be cleared under
dormouse precautionary method

3500

Artificial badger
constructed.

Existing Bat Crossing 6 temporary


screens
required
during
construction to direct bat flight
paths

3800-3900

3900

3750-4300

be

Badger sett exclusion zone where


groundworks only as directed by
the Ecologist applies until closure
carried out or licenced mitigation
is complete

3280
3290

to

Screens required to direct bat


flight paths.
Hedgerow to be translocated to
be
cleared
under
dormouse
precautionary method

3030-4000

sett

Enhancement of grassland

2200

3030

Reptiles present.

Description

Location
Chainage
2140

Seasonal
constraint
Y

Needs
to
be
constructed as soon
as possible
Screens to be in place
April onwards

Bat
licence
precautionary method
applies (check and
watching brief)
Dormouse
precautionary method

Consents
or
methods that apply
Reptile
Method
Statement.
Ground
clearance should be
carried out by mid
March when reptiles
become active
Landscape
specification

enhancement
technique
to
be
confirmed but may
involve use of turf
from 2140
Screens to be in place
April onwards
Dormouse
precautionary
method/
hedgerow
translocation method
Badger
Method
Statement if unused*
- March / Licence
sett closure in period
July to November

Sett closure under


licence if monitoring
shows setts in use

ECOW

Bat
licensed
ecologist/
ecologist
Dormouse
licensed
ecologist
Ecologist

Badger
licensed
ecologist

Dormouse
licensed
ecologist

ECOW

Landscape
architect/
ecologist

Responsibility
Ecologist

Japanese knotweed in various


locations.
Screens required to direct bat
flight paths.
Existing Bat Crossing 7 temporary
screens
required
during
construction to direct bat flight
paths
Bat roost tree to be felled under
licence, additional trees with bat
potential to be felled under Bat
Precautionary Method.
Pond AM2 potential presence of
fish, consent from EAW would be
required to remove fish

4500-4600

5100

4820

4600

4560-4670

Grassland to be enhanced

Japanese knotweed present and


control is necessary.
400m buffer zone to potential
Goshawk nesting woodland. Work
to be underway in these locations
by mid February 2012 and 2013.
Japanese knotweed present and
control is necessary.
Reptile Area suitable habitat for
reptiles present
Three outbuildings to be checked
for
bat
evidence
prior
to
demolition

Badger Sett exclusion zone where


groundworks only as directed by
the Ecologist applies until licenced
mitigation is complete.

Description

4500

4480

4350

4290

4000-6100

4000

Location
Chainage
4000

Y (for herbi
-cide use)
Y

Y (for herbi
-cide use)
Y

Seasonal
constraint

Bat licence method


and
precautionary
methods apply (check
and watching brief)
Pond to be drained
down to a level which
allows
visual
inspection
to
determine if fish are
present and whether
EAW consents are
required

Invasive
Weed
method statement
Screens to be in place
April onwards
Screens to be in place
April onwards

Invasive
Weed
Method Statement
Goshawk
Method
Statement
and
monitoring
by
ecologist
Invasive
Weed
method statement
Reptile
Method
Statement.
Bat
licence
precautionary method
applies (check and
watching brief)
Landscape
specification

Consents
or
methods that apply
Badger
Method
Statement / Licence
sett closure in period
July to November

Herbicide
Mid-February to July

Sett closure under


licence and following
badgers adoption of
artificial sett at 38003900
Excavate
(under
badger licence)

ECOW

Bat
licensed
ecologist

ECOW

ECOW

Landscape
architect/
ecologist
ECOW

Bat
licensed
ecologist

Ecologist

ECOW

ECOW/
Ecologist

ECOW

Responsibility
Badger
licensed
ecologist

Sensitive
working
practices
required around retained, off site
trees with potential for roosting
bats under bat licence.
Japanese knotweed present in
woodland.
Badger sett in adjacent woodland,
exclusion
zone
where
groundworks only as directed by
the Ecologist applies until licenced
mitigation is complete.
Screens required to direct bat
flight paths.
Existing Bat Crossing 9 temporary
screens
required
during
construction to direct bat flight
paths
Hedgerow to be cleared under
dormouse precautionary method

5270-5310

Hedgerow to be translocated to
be
cleared
under
dormouse
precautionary method

Badger sett exclusion zone where


groundworks only as directed by
the Ecologist applies until licenced
mitigation is complete.

5560-5690

5770

5560

5550

5530-6500

5300

5220

Hedgerow to be translocated to
be
cleared
under
dormouse
precautionary method

Existing Bat Crossing 8 temporary


screens
required
during
construction to direct bat flight
paths
Hedgerow / woodland to be
cleared
under
dormouse
precautionary method
Bat boxes to be installed on
retained trees.

Description

5280

5120

5100-5300

Location
Chainage
5100

Y (for herbi
-cide use)
Y

Seasonal
constraint
Y

method

Dormouse
precautionary
method/
hedgerow
translocation method
Badger
Method
Statement / Licence
sett closure in period
July to November

Dormouse
precautionary method

Screens to be in place
May onwards
Screens to be in place
April onwards

Invasive
Weed
method statement
Badger
Method
Statement / Licence
sett closure in period
July to November

Dormouse
precautionary
method/
hedgerow
translocation method
Careful working
as
defined in the bat
licence

Bat licence
applies

Dormouse
precautionary method

Consents
or
methods that apply
Screens to be in place
April onwards

Sett closure
licence

Sett closure
licence

under

under

Badger
licensed
ecologist

Dormouse
licensed
ecologist
Dormouse
licensed
ecologist

ECOW

ECOW

Badger
licensed
ecologist

ECOW

ECOW

Dormouse
licensed
ecologist
Bat
licensed
ecologist
Dormouse
licensed
ecologist

Responsibility
ECOW

Invasive
weed
present
(VYA
section of Invasive Weed Method
statement to be followed).
Features of the woodland are to
be retained for use in new
woodland planting plots at 65406670.

Tavernspite Road - Badger sett


exclusion zone where vegetation
removal and groundworks only as
directed by the Ecologist applies
until
licensed
mitigation
is
complete.

6500-6600

6520

6500-6600

6500-6600

Woodland contains evidence of


Dormouse and will be cleared
according
to
the
Dormouse
Method Statement, under license
and
with
reference
to
the
constraints posed by the badger
sett present.
Trees with bat potential to be
felled under Bat Precautionary
Method when dormouse licence is
obtained and according to badger
method statement / licence.

Tree with bat potential to be felled


under Bat Precautionary Method if
affected by works.
Vegetation south of Tavernspite
Road
to
be
cleared
under
dormouse precautionary method
Old
Pale
Ancient
Woodland.
Badger setts; exclusion zone
where vegetation removal and
groundworks only as directed by
the Ecologist applies until licensed
mitigation is complete.

Description

6500-6600

6500-6600

6320-6550

Location
Chainage
5890

N,
but
reliant
on
site
clearance

Y (for herbi
-cide use)

Y (and see
6520,
6530)
Y

Seasonal
constraint
Y

to

Ecology

Badger
Method
Statement / Licence
sett
closure
most
likely in period July to
November

Refer
Design

No
works
until
dormouse licence is
obtained.
Badger
Method Statement /
Licence sett closure
in period July to
November
No
works
until
dormouse licence is
obtained. Work under
dormouse licence in
two phases (*tree
clearance under ecological supervision)
No
works
until
dormouse licence is
obtained. Bat licence
precautionary method
applies (check and
watching brief)
Invasive
Weed
Method Statement

Consents
or
methods that apply
Felling as defined in
Bat licence for trees
affected
Dormouse
precautionary method

Retain
logs/
trunks

Tree
clearance*

Closure
of
disused
holes if
possible

under

Retain
stumps
rocks
and
soil
Sett closure under
licence NB may be
possible earlier in the
year, to be confirmed
following monitoring

Ground
clearance

Sett closure
licence

Badger
licensed
ecologist

ECOW

ECOW

Bat
licensed
ecologist

ECOW

Dormouse
licensed
ecologist

Responsibility
Bat
licensed
ecologist
Dormouse
licensed
ecologist
Badger
licensed
ecologist

7230

7230

7100

7100

7000

Existing
Bat
Crossing
14.
temporary screens required during
construction May to September to
direct bat flight paths
Pilgrims
Way
has
Japanese
knotweed present.

Badger sett exclusion zone where


vegetation
removal
and
groundworks only as directed by
the Ecologist applies until licensed
mitigation is complete.
Afon Taf and Afon Hydfron
Floodplain Himalayan balsam
New Otter holt proposed in
embankment
Afon Hydfron. Upstream of SAC
and Himalayan Balsam along
banks.
Banks to be reprofiled.
Existing bat crossing 13.
Afon Hydfron otter habitat

6730

6700-7700

Hedgerow to be cleared under


dormouse precautionary method

Tavernspite Road - Tree with bat


potential to be felled under Bat
Precautionary Method if affected
by works.
Existing
Bat
Crossing
11
temporary screens required during
construction May to September to
direct bat flight paths
Existing
Bat
Crossing
12
temporary screens required during
construction May to September to
direct bat flight paths
Hedgerow to be translocated to
be
cleared
under
dormouse
precautionary method

Description

6720-6790

6620-6900

6600

6550

Location
Chainage
6530

Y (for herbicide use)

Y (for herbicide use)


N

Y (and see
6730)

Invasive
Weed
Method Statement if
affected

pre-construction
check for otter.
Screens to be in place
April onwards

Badger
Method
Statement / Licence
sett
closure
most
likely in period July to
November
Invasive
Weed
Method Statement
Refer
to
Ecology
Design
Invasive
Weed
Method Statement,

Dormouse
precautionary
method/
hedgerow
translocation method
Dormouse
precautionary method

Screens to be in place
April onwards

Screens to be in place
April onwards

Consents
or
methods that apply
Felling as defined in
Bat licence if affected

Seasonal
constraint
Y

Sett closure under


licence NB may be
possible earlier in the
year, to be confirmed
following monitoring

Prior to piling/reprofiling banks/installation of bailey


bridge

ECOW

ECOW

Ecologist

ECOW

Ecologist

ECOW

Dormouse
licensed
ecologist
Badger
licensed
ecologist

Dormouse
licensed
ecologist

ECOW

ECOW

Responsibility
Bat
licensed
ecologist

8700-8750

8600-8700

7800

7600-7670

7490,
7650
(north),
7650
(south),
8200,
8470
7430-7500

7360-7800

Sensitive
working
practices
required around retained, off site
trees with potential for roosting
bats.
Three trees with bat potential to
be felled under Bat Precautionary
Method
Reptile Area suitable habitat for
reptiles present
Flood meadows to be used for
otter habitat
Himalayan balsam present both
banks of the Afon Taf

Tree with bat potential to be felled


under Bat Precautionary Method if
affected
Screens required to direct bat
flight paths.
Hedgerows to be translocated to
be
cleared
under
dormouse
precautionary method

7320

7240-7350

Vegetation in wet woodland to be


cleared
under
dormouse
precautionary method
Reptiles present

Hedgerows (x2) to be translocated


to be cleared under dormouse
precautionary method

Description

7220-7350

Location
Chainage
7230

Y (for herbicide use)

Seasonal
constraint
Y

as
bat

Invasive
Weed
Method Statement

Felling as defined in
Bat licence for trees
affected
Reptile
Method
Statement.
N/A

Careful working
defined in the
licence

Reptile
Method
Statement.
Ground
clearance should be
carried out by mid
March when reptiles
become active
Felling as defined in
Bat licence for trees
affected
Screens to be in place
April onwards
Dormouse
precautionary
method/
hedgerow
translocation method

Consents
or
methods that apply
Dormouse
precautionary
method/
hedgerow
translocation method
Dormouse
precautionary method

Install fencing around these two areas as soon as


possible

ECOW

ECOW

Bat
licensed
ecologist
Ecologist

ECOW

Dormouse
licensed
ecologist

Bat
licensed
ecologist
ECOW

Dormouse
licensed
ecologist
Ecologist

Responsibility
Dormouse
licensed
ecologist

A477 ST CLEARS TO RED ROSES IMPROVEMENT


Construction Environmental Management Plan
Archaeological and Ecological Sign Off
Location (Chainage, from-to).

Ecology/Archaeology Sign Off

Description of Works

Summary of any Mitigation Undertaken and


Overview of Results

Map of signed off area attached (delete one)


Yes / No
Confirm no outstanding issues (delete one)
Yes / No
Sign off agreed with relevant regulatory
authority (delete one)
Yes / No
SRB Ramboll Signature (below)
Ramboll:
SRB:

Signed off as clear for construction by relevant regulatory authority (please define)
Name
Role / Organisation
Date

Você também pode gostar