Escolar Documentos
Profissional Documentos
Cultura Documentos
Start
10:00 AM
End
10:45 AM
Purpose
2014 Construction Meeting #17
Distribution/Attendance:
City of Ithaca
Downtown Ithaca Alliance
Sasaki Associates
Labella Associates
Vacri Construction / ACP
Power & Construction Group
Verizon
NYSEG Gas
DDS
NYSEG Electric
Next Time
10:00 AM
Prepared By
Jessica Buckley
Location
Commons Project Office 215 East State St Ithaca, NY
(Present at meeting unless noted: A absent)
Michael Kuo, Jessica Buckley, Nicole Mason
Tammy Baker
Susannah Ross, Eamonn Hutton (A), Kimberly Michaels TWM
Dan Walker, James Matzat (A)
Ralph Avery, Andy Breznay, Matt Thomas (A), Roberto DeVincentis (A),
Bob Bellavigna ACP
Lou Zupan, Bill Planert, Brian Planert (A)
James Edwards (A), Dave Comer (A)
Doug Stafford (A), Jack Barker, Dawn Stillwell, John Mattiace (A)
Jeff Bubb (A), Flint Brann (A), Andy Gana (A)
Jack Czapranski (A), Dennis Kuhn (A)
Item / Description
1. RFIs, SUBMITTALS
1.1. Vacri (Contract #3A):
1.1.1.Granite Shop #87 - EX6 Roughing
Coordination AC+P and P&CG
1.1.2.Roadway Curb sample photos to
be sent to Sasaki
Notes
Mark up returned on granite shop
drawing; PCG to resend EX6 granite detail
to Vacri; Conduit to be daylighted and
installed below 12 slab & 6 of sub base;
PCG to have electrical inspector to
approve; Vacri to send a submittal sheet
on curb sample to Sasaki
PCG to follow up with accessory details for
the catenary pole submittal; All light
fixtures are to be included in one
submittal; EX2 pole submittal to be sent
by PCG next week; PCG to submit on stage
floor boxes today
Page 1 of 2