Escolar Documentos
Profissional Documentos
Cultura Documentos
DESIGNED BY NESPAK
REPORT PREPARED BY
023Asad Waheed Khan
TABLE OF CONTENT
1- Introduction
2- Project Brief
3- Project Mission
4- Work Breakdown structure
5- Construction Details
6- Scope of Work
7- Budget
8- Risk
1- Introduction:
Kalma Chowk Flyover is a flyover and a road bridge passing over the main square of
Lahore. It is passing through the Kalma Chowk. This flyover was made due to the heavy
traffic on the Ferozepur Road. The project was started by the Punjab government on
March 5, 2011 and completed in a record period, in 135 days.
Recently, due to the Metrobus (Lahore), a popular mode of transportation in Lahore,
further improvements at this junction needed to be made. The Punjab Government,
considering public difficulties, decided to construct an underpass from Gulberg to
Garden Town along with four, signal-free U-turns to facilitate traffic movement. By
constructing the underpass and signal-free U-turns, more than 150,000 vehicles will
benefit. The project was initiated on 11 December 2012 with a mobilization period of ten
days. The actual date of commencement was 21 December 2012. In spite of very
severe climatic conditions and several landslides due to rainfall, the project was
completed in eighty days. Currently, it is the longest underpass in Pakistan with a full
height of 5.1 meters (17 feet); it is strong enough to support heavy as well as light
vehicles. (1)
2- PROJECT BRIEF:
The flyover will have two
carriageways (three lanes
each) having 10 m space
between them for the Bus
Rapid Transit System. The
length of bridge including
ramps will be 572 m.
NESPAK is providing design
and construction supervision
services for the project. The
target date for completion of
project was August 14, 2011.
(2)
This project consisted of a
construction of an underpass
with two bores, one for each
carriageway, with variable
lengths of ramps. In addition,
two single span bridges have
been constructed one on each side of the underpass. These bridges allow traffic to
take a U-turn. The construction of the underpass will not only give relief to traffic but
also allow smooth running of the Metro bus (Lahore), with minimum possible delays at
the crossing. Before undertaking the development of the underpass, a model study of
the traffic diversion plan was conducted to help in arriving at a plan capable of meeting
every eventuality. A large number of information and warning signboards, as well as
traffic police, were placed to guide the road users. (1)
3- Project Mission:
This project consisted of a
construction of an
underpass with two bores,
one for each carriageway,
with variable lengths of
ramps. In addition, two
single span bridges have
been constructed one on
each side of the
underpass. These bridges
allow traffic to take a U-
turn. The construction of the underpass will not only give relief to traffic but also allow
smooth running of the Metro bus (Lahore), with minimum possible delays at the
crossing. Before undertaking the development of the underpass, a model study of the
traffic diversion plan was conducted to help in arriving at a plan capable of meeting
every eventuality. A large number of information and warning signboards, as well as
traffic police, were placed to guide the road users.
5- Construction Details:
Type
Description
Name
Executing agency
LDA TEPA
Consultant
Contractor
3.0 km
95 metres (main)
Barrel length
30 + 45 metres U-turns
Height of underpass
Number of lanes
4+3
Barrel width
Green planter
5.2-meters
Commencement date
11 December 2012
(1)
6- Scope of Work
The scope of
work consisted
of construction
of two bores with
variable width
along the Barket
Market Liberty
Market Road.
The underpass
has ramps of
varying length
and height of the
retaining walls.
The two bores
are
separated by two retaining walls in the underpass in such a way that four retaining walls
are inside each bore. The carriageways on the Liberty side are separated by a green
belt while the carriageways on Barket Market side are separated by a retaining wall.
The length of the ramps on the Barket Market side varies. In addition, two single span
bridges have been provided on each ramp to facilitate making a U-turn. The Barket
Market side U-turn is a double U-turn. The bridges are on spread footing with precast
pre-stressed concrete girders. The underpass structure is over piles, and piles have
also been used as a retaining structure. Service roads and slip roads have been
provided at grade. A sump pump has been constructed on the Liberty-side ramp before
the start of the bore to prevent rain water from falling over the entire area of the
underpass. Arrangements were made for its disposal. (1)
The total number of bridge piers on both the flyovers is 22 with 104 bridge piles (each
pier has 4 to 5 piles). The officials said that when they received the design of a pier they
started work and as the work was about to finish, NESPAK handed them another
drawing of the same pier. (5)
Lahore Bachao Tehreek convener and architect Imrana Tiwana said the project was
started by the Punjab government in haste.
It was started without fulfilling the mandatory requirement of having an environment
impact assessment (EIA) aimed at considering alternatives and impacts and whether or
not to do the project at all.
There has been a big conflict of interest in the project. Nespak was appointed design
engineering firm and it was also entrusted with undertaking the EIA. The Nespak fee
for the project is 1.83 per cent of the total cost of the project. Can Nespak prepare an
impartial report when it is chief engineer of the project? said Ms Tiwana who is an
urban designer and environmental planner. She said work on the project was being
carried out round the clock, even on holidays. It was an ad hoc decision, with no
connection to the existing plans, which are not considered anyway and do not exist in
totality.
The government has decided to go ahead with the rapid rail system after the recent visit
of the chief minister to China. Kalma Chowk is the route of the green line of the rapid rail
system. If the rapid rail system is to be built, this project will have to be demolished
within a year. Furthermore, the Kalma Chowk project does not refer to the Lahore Urban
Transport Plan being prepared by Japanese International Cooperation Agency (JICA)
and the Punjab government, she said.(7)
REFERENCE:
1- http://en.wikipedia.org/wiki/Kalma_Underpass,_Lahore
2- Nespak news report
3- http://www.urbanpk.com/forums/index.php/topic/3145-lahore-kalma-chowkflyover-underpass/page-2
4- http://www.dawn.com/news/789819/kalma-chowk-underpasses-open-today
5- http://tribune.com.pk/story/176703/kalma-chowk-design-flaws-plague-flyoverproject/
6- http://tribune.com.pk/story/176703/kalma-chowk-design-flaws-plague-flyoverproject/
7- http://www.urbanpk.com/forums/index.php/topic/3145-lahore-kalma-chowkflyover-underpass/page-2