Design stages
Concept/Schematic
Item of works
1. Collect client brief
Out put
Concept/schematic design report and consist of :
Design criteria
Brief systems description
Preliminary calculation
Design stages
Design development
Item of works
8. Identify major services routes and propose riser location
Out put
Sketch pipe shaft location
5. Confirm main routes and sizes for all services and coordinate with other Drawing floor plan layout for all main pipes
disciplines as required
Siteplan drawing showing location of incoming
services
6. Develop schematic diagram system
Design stages
Item of works
Inform to electrical engineer the position of indoor hydrant box, alarm
valve and branch control valve
Out put
1. Confirm (with architect) fixture locations in all areas and hydrant position
2. Prepare complete layout drawings showing all branch pipe lines to all fixtures Complete drawing floor plan layout
and equipments.
Complete schematics for all systems showing
sizes and other technical datas
3. Size all branch pipes
4. Complete all technical data equipments
5. Prepare detail drawing and section for plant room, tank and sump pit