Você está na página 1de 59

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

ELECRICAL EQUIPMENT MAINTENANCE IN PIPELINES


1. INTRODUCTION:
The most economical way of transporting petroleum products from one place to
another is through the pipelines. The pipeline offers low operating cost and high reliability of
transportation of fluids.
Generally pipeline consists of the following major systems:

Tank farms

Pumping stations

Metering stations

Valve manifolds

Pigging stations

SCADA systems

Corrosion control systems

Figure-1: Product pipe line system

1 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

The major electrical equipments that are used in pipelines are:

POWER SUPPLY AND DISTRIBUTION

SUB STATIONS

TRANSFORMERS

SWITCH GEAR

ELECTRIC MOTORS

MOV ACTUATORS

CATHODIC PROTECTION SYSTEMS

EMERGENCY GENERATORS

2. POWER SUPPLY AND DISTRIBUTION


The power supply and distribution depend on the electrical power requirements (or
maximum demand load) for the installation.
2.1 LOAD ESTIMATION:
Load estimation requires analysis of load characteristics and will take into account
the demand factor relationship between connected loads and the actual demand imposed on the
system. For load estimation the following factors are used.
2.1.1 Preliminary loads:
The minimum loads which are connected to power system.
2.1.2 Demand Factor:
It is defined as ratio of maximum demand (largest demand during a specified time) to
the total connected load.
2 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

By this demand factor we can know the capacity of transformer and the conductor
size, and all equipment associated with distribution of electrical power to utilization equipment.
2.1.3 Diversity Factor:
Diversity factor is defined as the ratio of the sum of the individual maximum
demands of various subsystems within a system to the maximum demand of the system.
2.1.4 Load Factor:
Load factor is defined as the ratio of the average load over a designated period of
time to the peak load occurring in that period.
A low load factor indicates short-time demand peaks which can result in heavy
charges to the Using Agency. Low load factor will be corrected by shedding loads or by peakshaving generation during periods of peak demand.
2.2 Voltage Requirement:
The voltage requirement is based on the type of distribution. That means
primary distribution and secondary distribution.

Primary distribution means distribution from main substations to local substations.

Secondary distribution means local substations to domestic users.

The voltage requirement is also based the type of equipment we are using.

3. SUBSTATIONS
Substations mainly consist of:

Power transformers

Underground cables

Air circuit breakers or Oil circuit breakers

Buses

3 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Protective relays

Current transformers and Voltage transformers

LT/HT control panels

Lightening or Surge arrestor

Grounding

Figure-2: An 11 KV substation (single line diagram)

4. TRANSFORMERS
4.1 BASIC PRINCIPLE:
The transformer is based on two principles:

An electric current can produce a magnetic field (electromagnetism)

A changing magnetic field within a coil of wire induces a voltage across the ends of the
coil (electromagnetic induction).

4 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Figure -3: An ideal step-down Transformer

4.2 SWITCHING ON AND OPERATION:


4.2.1 HV Energisation:
When the installation has been fully checked, the HV side can first be switched-on and
following this, the LV side. It is recommended that the transformer is left energized for a few
hours before switching-on the LV side and applying load. During this time the transformer should
be closely supervised paying attention to both coolant oil level and temperature. Verify the voltage
between the low voltage phases and phase to neutral if used.
4.2.2 Re-adjusting the tap switch:
The tap switch enables sections of the HV winding to be in or out of the turns ratio
thus affecting the secondary low voltage side. When the voltage measured at the low voltage side
deviates from the required value this usually indicates that the incoming HV voltage is too high or
too low. Normally the supply voltage is held within limits of plus or minus 6%. The tapping switch
can compensate for variations of plus or minus 5% in 2.5% steps. If adjustment is desired then the
following procedure should be followed.
5 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Disconnect the transformer from both the HV systems and the LV systems.

Unlock and remove the padlock, if fitted. Release the tapping switch mechanism by lifting
the operating handle.

Turn the handle to the desired position to increase LV volts - turn to a higher tap position
number, which will decrease the HV, turns in circuit and proportionally increase the output
voltage.

4.3 MAINTENANCE:
4.3.1 ONLINE MAINTENANCE:
Frequency of routine maintenance is quarterly for distribution transformers and daily
for grid transformers.

Check load current: If more than rated, reduce non priority loads

Check voltage: control the appropriate voltage H.V voltage and L.V voltage variations. If
online tap changer (O.L.T.C) is provided change the tap positions as required.

Check OTI&WTI readings:

Check the temperature does not increase beyond rated temperature.

Check oil level in Transformer and O.L.T.C: check the oil level in respective conservators.
Ensure that they are not beyond rated temperature. If not top up with dry transformer oil.
Check transformer for oil leaks.

Check breather on transformer and O.L.T.C: check color of silica gel. It should be blue. If
it is pink replace it by spare charge.

Check sound level: Certified sound levels determined in accordance with NEMA, shall not
exceed the following:

6 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Sound Level Rating


Transformer Rating
0 -

9 KVA

40 dB

10 - 50 KVA

45 dB

51 - 150 KVA

50 dB

151 - 300 KVA

55 dB

301 - 500 KVA

60 dB
TABLE-01

4.3.2 ANNUAL SHUTDOWN MAINTENANCE:

Visual inspection of transformers for oil leakage, oil level, and silica gel conditions should
be done.

Clean the transformer body and paint it if necessary.

Check the oil level and top-up in necessary.

Remove the silica gel and reactivate if necessary.

Open H.T terminal box and check for loose connections, heating and oil leakage from
bushings.

Open L.T terminal box and check for the same.

Check the body and neutral earthing joints.

Check the tap changer for pitting and overheating etc;

Examine Bucholzs relay, OTI (oil temperature indicator) and WTI (winding temperature
indicator) relays operation and check for accuracy.

7 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

4.3.3 CAPITAL OVERHAUL:


Capital over haul shall include overhaul inspection, lifting of core and coils, cleaning
of transformer tank. Frequency of overhaul will be normally in between 7 to 8 years.
TRANSFORMER OIL: Properties
S.No Description

New oil

Old oil

1 Electrical strength

40kv

25kv/40kv

2 Moisture, Mechanical
impurities

None

25/35 ppm

3 Flash Point

1400C

Max. 50 C lower

0
4 Viscosity at 27 C

27 cst

27 cst

TABLE-02

After one year any changes in the oil properties above said, the oil should be changed. The old
mineral oil should be reconditioned.

8 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

The following table depicts the transformer trouble shooting

SYMPTOM

High Temperature.

CAUSE

CORRECTIVE
MAINTENANCE

Over voltage.

Change the circuit voltage or


transformer connections to avoid
over excitation.

Over current.

If possible reduce the load.


Heating can often be reduced by
improving power factor of load.
Check parallel circuits for
circulating currents which may be
caused by improper ratios of their
impedances.

High ambient temperatures.

Either improve ventilation or


relocate transformer in lower
ambient temperature.

Insufficient cooling.

Make sure cooling is adequate.

Fractured metal or
porcelain parts of the
bushings.

Unusual strains place on Cables and bus bars attached to


terminal connections.
the transformers should be
adequately supported. In the case
of
heavy
leads,
flexible
connections should be provided to
remove strain on the terminal and
bushing porcelain.

Badly discolored oil.

Contaminated by varnishes.
Carbonized oil due
switching.
Winding or core failure.

Retain oil if di-electric strength is


satisfactory.
to Filter/ reclaim/ replace oil.
Repair transformer.

DRY_TYPE
TRASNFORMERS:
High temperatures

Insufficient air flow

Moisture

Check that in take is not


obstructed. If unit is fan cooled
check fan speed.

Transformer in moisture Transformers dry out to be done.


atmosphere or accidental
wetting
TABLE-03
9 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

5. ELECTRICAL POWER CABLES


5.1 INTRODUCTION:
A power cable is an assembly of two or more electrical conductors, usually held
together with an overall sheath. The assembly is used for transmission of electrical power.
Power cables may be installed as permanent wiring buried in the ground, run overhead, or
exposed. Flexible power cables are used for portable devices, mobile tools and machinery.

For constructional details of power cables see ANNEXURE- A

For cable selection criterion see ANNEXURE-B

For cable laying details see ANNEXURE-C

For testing of cables see ANNEXURE-D

For NETA insulation standards see ANNEXURE-E

5.2 CABLE FAULTS:


The problems occurs in the cables due to

Environmental changes.

Changes in the thermal resistivity of the soil.

Defects in the earthing and bonding.

Excavation by other utilities.


The most frequent faults are short circuit faults and earth leakage faults and

insulation breakdown. Due to these, some part of the cable (specifically, underground) get
heated up and burst.
5.3 LOCATING CABLE FAULT:
There are two basic methods of locating an underground cable fault.

10 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

5.3.1 Sectionalizing:
In this procedure, we divide the cable into smaller sections and examine the insulation
resistance or continuity.
5.3.2 Thumping:
When we supply a high voltage to a faulted cable, the resulting high-current arc
makes a noise loud enough for us to hear above ground. While this method eliminates the
sectionalizing method's cutting and splicing, it has its own drawback. Thumping requires a
current on the order of tens of thousands of amps at voltages as high as 25kV to make an
underground noise loud enough for you to hear above ground.
The heating from this high current often causes some degradation of the cable insulation.
There are some relatively new methods of locating cable faults that use rather
sophisticated technology.
5.3.3 Time Domain Reflectometry (TDR):
The TDR sends a low-energy signal through the cable, causing no insulation
degradation. A theoretically perfect cable returns the signal in a known time and in a known
profile. Impedance variations in a "real-world" cable alter both the time and profile, which
the TDR screen or printout graphically represents. This graph (called a "trace") gives the user
approximate distances to "landmarks" such as opens, splices, Y-taps, transformers, and water
ingression.
One weakness of TDR is that it does not pinpoint faults. TDR is accurate to
within about 1% of testing range.

11 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Another weakness of TDR is that reflectometers cannot see faults-to-ground with


resistances much greater than 200 ohms. So, in the case of a "bleeding fault" rather than a
short or near-short, TDR is blind.
5.3.4 High-voltage radar method:
There are three basic methods for high-voltage radar, they are

Arc reflection

Surge pulse reflection

Voltage pulse reflection

The arc reflection method uses a TDR with a filter and thumper. The filter limits both
the surge current and voltage that can reach the cable under test, thus allowing
minimal stress to the cable. Arc reflection provides an approximate distance to the
fault (when there is an ionizing, clean arc produced at the fault and the TDR in use is
powerful enough to sense and display a reflected pulse).

The surge pulse reflection method uses a current coupler and a storage oscilloscope
with a thumper. The advantage of this method is its superior ability to ionize difficult
and distant faults. Its disadvantages are that its high output surge can damage the
cable, and interpreting the trace requires more skill than with the other methods.

The voltage pulse reflection method uses a voltage coupler and an analyzer with a
dielectric test set or proof tester. This method provides a way to find faults that occur
at voltages above the maximum thumper voltage of 25kV.

One test to detect an open neutral requires shorting a known good conductor to a
suspect neutral, then measuring the resistance with an ohmmeter. If the reading is 10
ohms or higher, we can suspect an open neutral. Remember, other objects can
complete the circuit.

12 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

5.4 REPAIRING OF CABLES:


The repairing is nothing but locating the cable fault and cut the cable and re-joint
the cables. There are two methods presently used in jointing of the cable, they are
Polyurethane Cable Jointing.
Heat shrinkable Cable Jointing.
5.4.1 POLYURETHANE CABLE JOINT:
Underground cable joints in electricity distribution networks must remain
moisture free to prevent arc failure of any joint. Because the joints are created on-site, the
quality of the jointing technique is critical.
The quality of the joint is such that it does not add any resistant to the circuit. The
materials and technique so designed to give adequate mechanical and electrical protection to
the joints under all service conditions.
Polyurethane kit consists of

Adequate number of mechanical conductors.

PTFE (Polytetrafluoroethylene) tube set to provide primary electrical insulation and


correct cable positioning.

Cast metal conducting tubes to make the electrical cable connection with snap-off
bolt heads to ensure that perfect compression torque is applied.

Armour bonding system in case of armoured cables (Earth continuity).

A pair of white Glassfibre-Reinforced-Polyester (GRP) mating shell moulds which


completely enclose and seal the joint, forming the inner shell.

A container of liquid silicone, which is poured into the polyester mould, completely
encasing the cable joint.

13 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Figure-4: Cutaway view of straight water resistance medium voltage underground joint

Figure-5: Cable jointing Kit

Figure-6: Conductor joints in the cable

14 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Figure-7: POLYURETHANE JOINTING PROCESS

The above figure shows us how the polyurethane jointing process is going. The
third from right connector is having its white, inner shell mould filled with liquid silicone.
Note the temporarily placed funnel, mounted in the white inner shell, towards the foreground,
which ensures the correct level of the silicone fill and zero air entrapment, and the support
frame holding the container, as the filling is carried out. The liquid silicone container has two
outlets, and the flow rate into the white, inner shell, is controlled by the gentle release of the
seal on the second, (red) cap. As soon as the silicon pour is completed, the entry holes into
this white mould are sealed. The whole process is cold, ideal for hazardous zoned areas.
5.4.2 HEAT SHRINKABLE CABLE JOINT:
Heat shrink splices are available as a series of heat shrinkable tubes. Some may
be preassembled by the manufacturer to reduce the number that must be handled in the field.
The tubes must be slipped over the cable prior to connecting the conductors. After
positioning each tube over the connected cables, heat is applied to shrink the tube snugly over
the underlying surface and soften any mastic material used in the assembly. Stress relief is
15 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

generally provided by stress control tubes that are also shrunk into place so that ends of the
stress control tube overlap both cable insulation shields. The joint is finished in the normal
manner.

Figure-8: Heat shrinkable cable jointing Kit

During the heat shrink installation process, the stored recovery force of the tube
is released in addition to the recovery force of the heat shrinkable outer layer. A pre-designed
screen and thick layer of insulation is installed in one simple process. This allows extremely
tight electrical interfaces due to the shrink force generated. The elastomeric (tube) insulation
characteristic combined with the rigid outer heat shrinkable screen layer enables the joint to
follow the thermally induced dimensional changes of the cable insulation.

16 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

5.5 MAINTENANCE:
SCHEDULE
Annually

5 yearly

EQUIPMENT

TASK

Cable Terminations

Check connections for security


(Except switchgear connections)

Cable above ground

Check for outer sheath damage


Check attachment to pole
Where fitted, ensure protective
pipe is secure.

Cable loading

Where fitted, check and record


Demand indicator readings
(MV cable loadings are normally
established by load flow studies).

Earthing

Check all earth connections for


security.

Earthing

Test all earth connections at MV


and LV substations and compare
to standards.

TABLE-04

6. SWITCH GEARS AND PROTECTIVE RELAYS


6.1 INTRODUCTION:
Switch gears are available in many forms, from single simple isolator to
sophisticated vacuum breakers.
The term switchgear, used in association with the electric power system, or grid,
refers to the combination of electrical disconnects, fuses and/or circuit breakers used to isolate
electrical equipment. Switchgear is used both to de-energize equipment to allow work to be done
and to clear faults downstream.

17 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

6.2 TYPES OF CIRCUIT BREAKERS:


The circuit breakers are classified on the basis of insulating medium present in it.
They are

Air circuit breaker

Vacuum circuit breaker

SF6 circuit breaker

Oil circuit breaker

18 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Figure-9: A 25 kv Single phase Air Circuit Breaker

For the circuit breaker it is necessary to beak the circuit immediately when the fault
occurs and isolates the fault position from healthy position.
To ensure the equipment remains safe and reliable, regular examination is essential.
6.3 MAINTENANCE:
Essential areas requirements for inspection and testing:
6.3.1 INSULATION:
Insulation systems must be closely inspected for sings of over heating, cracking and
other defects.
6.3.2 CONTACTS:
Inspect the contacts for signs of excessive wear and over heating. Free movement of
the contactors also examined.
6.3.3 TERMINALS:
All terminals must be checked for firmness and signs of over heat.
6.3.4 CABLES:
Power and control cables must be examined with the connecting equipment.
6.3.5 BUS BARS:
Bus bars shall subject to periodic inspection.
6.4 MAINTENANCE OF POWER AIR CIRCUIRT BREAKER:
Power air circuit breaker should be maintained annually.
To perform maintenance, withdraw the circuit breaker from its enclosure and do the following:
19 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Inspect alignment of movable and stationary contacts. Make adjustments as


recommended in manufacturers manual.

Wipe bushings, barriers, and insulating parts. Remove the dust, smoke, and any foreign
deposits. Replace the damaged parts.

Check control devices and replace if needed.

Check breaker control wiring and ensure that the connections will be tight.

Operating breaker in fully opened and closed position after service. Check for any
binding before going to put in the circuit.

6.5 MAINTENANCE OF CONTACTOR:


The duty of the contactor is very often in a day. Such duty reflected in mechanical wear and tear
and also electrical contact wear. The maintenance process:

Cleaning

Dressing or renewal of main and auxiliary contacts.

Checking contact alignment.

Trip mechanism inspection.

Check tightness and conditions of all connections.

Arc chute inspection.

Lubrication.

20 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

6.6 MAINTENANCE OF ISOLATOR:


The maintenance of isolator mainly consists of:

Cleaning, checking contact conditions and tightness of connections and confirming the
tightness and continuity of the fuses, if fitted.

6.7 PROTECTIVE RELAY MAINTENANCE:


The maintenance of protective relays should include general inspection of physical condition of
all parts at regular intervals. Maintenance as follows:

Relays are provided with dust proof covers and before a cover is removed, the cases
should be carefully dusted.

Relay interior should be free from dust, iron particles etc.

Dust and dirt should be carefully wiped off by a soft squirrel hair brush. Mechanical
blowers or blowing by mouth is not recommended.

The internal wiring, ICs, printed circuits should be examined for corrosion. Excessive
heat may damage the insulation.

Relay flags/targets should operate freely without friction and also reset freely.

Perform complete tripping and operational tests to verify all control and protective
functions and alarms and tripping mechanism.

21 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

TROUBLE SHOOTING:
SYMPTOM

Over heating

CAUSE

CORRECTIVE
MAINTENANCE

Improper alignment and Contacts should be aligned and


adjustment of contactor.
adjusted properly. Contacts to be
repaired or replaced properly.
Burnt and pitted due to
lack of attention after
many heavy operations,
or
too
frequent
operations.

Burnt and pitted contacts should


be dressed up if possible or
replace with new parts. Dressing
up to be done carefully.

Breaker kept closed (or Contacts to be wiped out for


open) for a too long cleaning and if possible silver-toperiod.
silver contacts to be arranged.
Transmission of heat to
the
breaker
from
overheated or inadequate
cables or connection bars.

Breaker is not closing.

If heat is due to excess current,


fault should be corrected. If
cable size is in adequate, cable
should be replaced.

Failure of latching device. Examine surface of the latch, if


worn or corroded, check latch,
wipe, and adjust according to
instruction book.
Damaged trip coil

Replace it.

Damaged
or
dirty Dress or replace damaged
contacts
of
tripping contacts. Clean the dirty
circuit
contacts.
Faulty connections in trip
circuit (loose or broken)
Insufficient
voltage Replace faulty wires. All
caused by too much drop connections are to be tightened.
in leads.
Replace with oversize wires.
Improve contact at connections.
Poor voltage regulation
Check up voltage, if less correct
it.
Loose connections

22 submitted by Anirban Das

Tighten the connections.

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Frequent damage of Inadequate


current Capacity of contactors as well as
moving and fixing carrying capacity
breakers should be examined.
contacts

Improper replacement of Capacity of original switch gear


switch
gear
during should be matched with new one.
maintenance.
Misalignment of controls Contacts to be dressed up. Spring
or inadequate pressure etc. to be checked for proper
between moving and pressure.
fixed contacts

Bushing problems

Accumulation of dirt or Clean external surface.


other deposits
Flash over due to foreign Frequency of cleaning to be
deposits like salt, cement increased. Carbon tetra chloride
dust etc.
or liquid ammonia or any other
suitable agent may be used to
clean porcelain.
TABLE-05

7. ELECTRIC MOTOR
7.1 INTRODUCTION:
Motors covert electrical energy into mechanical energy. Mainly motors are classified
into two types:

D.C motors

A.C motors
D.C. motors are mainly used in traction works and cranes where constant speed

characteristics are necessary. These are not used in domestic and industrial purposes because the
cost of the D.C motor is high and also the supply of D.C power also costly one.

23 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

So the best alternative is using A.C motors. In general most of industries are using 3phase motors. Hence we here consider 3-phase motors only.
The motors are classified into two types:

Induction motors

Synchronous motors
Let us briefly discuss about induction motors because many industries using

induction motors only.


7.2 CONSTRUCTION:
Motor mainly consists of two basic parts know as

Stator

Rotor

Figure-10: cut way view of squirrel cage induction motor

24 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Figure-11: Rotor of the squirrel cage induction motor

The stator winding and rotor windings are insulated. The primary purpose of
insulation is to withstand turn-to-turn, phase to-phase and phase-to-ground voltage such that to
direct the stator phase currents through the desired paths of stator windings.
The insulations are classified as:

Class A: 105C

Class B: 130C

Class F: 155C

Class G: 180C
For motors having high temperature rise class F insulation is uses.

7.3 MAINTENANCE OF MOTOR:


Motors are designed to give many years of reliable service with less attention. A
definite schedule of preventive/inspection/predictive maintenance should be established to avoid
breakdown. The schedule depends on the operating conditions and experience with the similar
equipment.

25 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

7.3.1 PREDECTIVE MAINTENACE:


The main goal of the predictive maintenance is to predict and fix the faults by using
following techniques before they occur.
The techniques are:
Vibration analysis:
This technique involves measuring machinery vibration to identify ongoing
conditions through vibrometer. This tells us the bearing damages.
Motor circuit analysis:
This technology monitors the conditions of complete motor circuit parameters like phase
resistance, inductance and capacitance.
7.3.2 PREVENTIVE MAINTENANCE:
7.3.2.1 A schedule for LT&HT motors (Half yearly):

Counter check that equipment is isolated positively.

Check the terminal box for loose connection in the cable termination.

Perform regreasing.

Remove front and rear grease cups if regreasing system is not healthy.

Check the condition of the grease. Top up grease if condition is not o.k.

Put back grease cups.

Connect the terminal box.

Check the earthing and return the clearance.

Perform the visual inspection of the stator module, cable terminals.

7.3.2.2 B schedule for LT&HT motors (Predictive):

26 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Counter check that equipment is isolated positively by means of LT/HT tester.

Get the motor decoupled.

Open the terminal cover and remove the cable connections.

Open the foundation bolts and take out the motor from foundation and send to electrical
workshop for schedule.

Inspect the motor for visible damages and rotor freeness.

Open the fan cover and remove the fan from the shaft.

Remove the grease cups on both sides. Inspect the condition of grease.

Take out both rear and front end shields.

Check the bearing housing for correct measurement of the bearing with sufficient
tolerances.

Remove both front and rear bearing from the shaft.

Clean all the grease using suitable solvent. Then wash the bearing with diesel and dry air.

Remove the rotor from stator.

Inspect rotor thoroughly for the loose bars and cage/shorting rings.

Inspect the bearing seat. If it is worn out and loose metalize the bearing.

Check the rotor trueness. If the shaft is bent send it for reshafting.

Replace the studs and nuts of the grease cups if worn out.

Inspect the stator winding for loose coils, loose connections, heating effect, deterioration
of insulation etc.

Clean the stator winding with clean dry cloth and blower.

Heat the winding in heating chamber up to 100C for 8 hours.

Again clean the winding.

Heat the stator for 6 hours.

27 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Apply protective coat of varnish.

Heat the windings (80C) till the varnish is dried.

Clean the stator and make ready for the assembly.

Clean the rotor also and insert the rotor in position.

Put the bearings on the shaft.

Assemble the motor with end shields in position.

Put back the fan on shaft.

Put back coupling on the shaft.

Run the motor and monitor the performance for four hours.

TROUBLE SHOOTING:

SYMPTOM

Motor will not start

CAUSE

CORRECTIVE
MAINTENANCE

Overload control trip

Wait for overload to cool. Try


starting again. If motor still
doesnt start, check all the
causes shown below.

Power not connected to motor

Connect power to motor.

Faulty (open) fuses

Test fuses and circuit breakers.

Low voltage

Check motor name plate values


with power supply. Check
voltage at motor terminals with
motor under load to be sure wire
size is adequate.

Wrong control connections

Check connection with control


wiring diagram.

Loose terminal lead connections Tight connections.


Open circuit in stator or rotor Check for open circuits.
winding
Short circuit in stator winding

28 submitted by Anirban Das

Check for shorted coil.

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Motor noisy

Motor vibrates

Bearings stiff

Free bearings or replace.

Over load

Reduce the load.

Motor running in single phase

Stop motor and then try to start


motor, it will not start in single
phase.

Electrical load unbalance

Check current balance.

Vibration due to unbalance or Balance or align the machine.


misalignment
Mechanical system resonance

Remove motor from load. If


motor is still noisy, rebalance
the rotor.

Air gap is non uniform

Centre the rotor and if necessary


replace the bearings.

Noisy ball bearings

Check the lubrication. Replace


bearings if noise is excessive.

Loose punching or loose rotor Tighten all holding bolts.


on shaft
Objects caught between fan and Disassemble motor and clean it.
end shields
Motor loose on foundation

Tighten holding-down bolts.

Coupling loose

Check coupling joint, check


alignment. Tighten coupling.

Overload

Measure the motor load with


ammeter and reduce the load.

Electrical load unbalance

Check for voltage un balance or


single phasing.

At higher than normal Restricted ventilation


Clean
air
passages
and
temperature
or
windings.
smoking
Incorrect voltage and frequency. Check motor name plate values
with power supply.
Stator winding shorted

Rotor
29 submitted by Anirban Das

winding

with

Use
insulation
procedures.

testing

loose Tighten if possible or replace

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

connections

with another rotor.

Motor used for rapid reversing Replace with motor designed for
service
reversing service.
Bent shaft

Straighten the bent shaft at


service shop.

Insufficient oil

Add oil if oil is very low.

Foreign materials in oil or poor Drain, oil flush, and re lubricate


grade of oil
using industrial lubricant.
Bearings hot

Sleeve bearings

Oil rings rotating slowly or not Oil too heavy, drain and replace.
rotating at all
Replace bearings. Resurface
Defective bearings or rough shaft.
shaft

TABLE-06

8. MOV ACTUATORS
8.1 DESCRIPTION:
Electrically operated motor operated valves are widely used in power plant/process
units and play a critical role. A typical actuator consists of

3-phase induction motor

Control gear

Travel limit switches and torque switches

Local controls

30 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Electronics circuit consists of power supply unit, remote operating unit, and logic cords.

Figure-12: Sectional View of Motor operated valve

31 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Figure-13: Motor Operated Valve

8.2 MAINTENANCE:
Schedule:
Based on the plant run length and application, a routine maintenance program is to
be developed. The maintenance period will be 1 year.

Check for evidence of oil leakage and rectify

Check the condition of gear case oil and replace if necessary.

Check the security of actuator mounting bolts.

Check cable connections to the actuator.

Check motor winding insulation resistance and check winding resistance is balance.

Check engagement of the clutch.

Energize the actuator and check direction of rotation.

Check electrical operation to limits.

In intelligent units check the healthiness from the diagnostic codes as per the vendors
manual.

32 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

TROUBLE SHOOTING:

SYMPTOM
MOV not operating

CORRECTIVE MAINTENANCE

Check healthiness of 3 phase supply.


Check mechanism for freeness.

MOV not operating


although 3 phase
supply is healthy

Check control gear/contactor.


Check PCBs.
Check control circuit.
Check limit switch.

MOV not operating


for intelligent type
MOV

Check internal battery.


Check PCBs.

TABLE-07

9. CATHODIC PROTECTION
9.1 INTRODUCTION:
Cathodic protection is an electrochemical method used to prevent or control
corrosion of buried or submerged metallic structures.
After a CP system is installed and adjusted to provide adequate protection, currents
and potentials should remain relatively stable; changes in currents or potentials indicate a
problem.

33 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

9.2 CATHODIC PROTECTION METHODS:


Sacrificial (Galvanic) Cathodic protection.
Impressed current Cathodic protection.

Out of these two methods impressed current protection is the most economical one
for the long pipelines. The disadvantages of the Galvanic protection is small driving voltage is
available, and small current available in higher resistivity electrolytes. Here we discuss briefly
about impressed current CP protection.
In an impressed current system, the protective current is supplied by a rectifier (or
other DC power source) to the structure.

Figure-14: Impressed Current Cathodic Protection System

Impressed current Cathodic protection systems use alternating current or solar


powered rectifiers as a power source.
Rectifiers used for Cathodic protection commonly use an

Adjustable step down transformer,

Rectifier stacks,

34 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

A shunt to measure output current,

Meters to indicate output current and voltage.

The function of the rectifier is to convert alternating current into controlled direct current.

Figure-15: Impressed current Cathodic protection system Rectifier

9.3 RECTIFIERS USED IN CATHODIC PROTECTION:

Silicon diodes

Thyristors

Switch mode

9.4 ANODE MATERIAL:


The anodes of an impressed current system provide the means for the protective
current to enter the electrolyte. Since the anodes form the corroding part of the system, the best
material is one that has a low rate of weight loss per ampere-year. The most commonly used
materials for impressed current anodes are graphite and high-silicon cast iron.
9.5 MAINTENANCE:
9.5.1 RECTIFIER OPERATIONAL INSPECTION:

35 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

The purpose of the rectifier operational inspection is to determine the serviceability


of all components required to impress current to the anodes of the impressed current system.

Maintenance Schedule:

Thirty days after cathodic protection system is installed and properly adjusted.

One to two years after that.

Procedure:
Visually check all rectifier components, shunt box components, safety switches.
Tighten all accessible connections and check temperature of all the components.
For rectifiers with more than one circuit, measure the output voltage and current for each
circuit using a dependable hand-held meter, and calibrate the rectifier meters, if present.
Calculate the cathodic protection system circuit resistance of each circuit by dividing the

rectifier DC voltage output of each circuit by the rectifier DC ampere output for that
circuit.
9.5.2 IMPRESSED CURRENT CHECK:
Maintenance schedule:
Sixty days after rectifier inspection, more frequent checks may be required by local
conditions.
Procedure:
Measure output D.C voltage and current from the rectifier.
Ensure the DC ampere output of the rectifier meets the current (ampere) requirement of
the system.
36 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Calculate the cathodic protection system circuit resistance of each circuit by dividing the
rectifier DC voltage output of each circuit by the rectifier DC ampere output for that
circuit.
Calculate the D.C out put voltage of the rectifier and check that it is rated or not.

TROUBLE SHOOTING:

Figure-16: Wiring diagram of a Rectifier

37 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

.
TABLE-08

10. EMERGENCY GENERATOR


10.1 INTRODUCTION:
Generator is the alternate energy source for emergency power needs in the pumping
station. There are many names for generator such as A.C generator and alternator. Alternator is
the commonly used name.
A typical pump station consists of diesel engine driven alternator to cater to
emergency power requirements like,
38 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Radiator motors of mainline engines

Air compressors

Centrifuges

UPS system

Lighting in the pump shed and control room etc.

10.2 GENERATOR CONSTRUCTION:

The stationary field

The rotating dc magnetic field.

The armature, normally containing a three-phase winding, is mounted on the shaft.

The armature winding is fed through three slip rings (collectors) and a set of brushes
sliding on them.

The rectifier-bridge is fed from a shaft-mounted alternator, which is itself excited by


the pilot exciter.

The core is slotted (normally open slots), and the coils making the winding are placed
in the slots.

39 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Figure-17: The figure shows Silent type Generator

10.3 MACHINE RATINGS:


A generator is usually described by giving it a rating. This rating is given at the generators
capability point of maximum continuous power output. The terms generally used to provide
the rating are as follows:

Apparent power

MVA

Mega volt amperes

Real power

MW

Mega watts

Reactive power

MVARs

Mega volt amps reactance

Power factor

Stator terminal- Voltage

Stator current

Field voltage

Vf

Direct voltage

Field current

If

Direct current amperes

Frequency

Hz

Speed

40 submitted by Anirban Das

pf

A dimensionless quantity

Vt

Alternating voltage
Ia

Alternating current amperes

Hertz
rpm

Revolutions per minute

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Figure-21: Name plate details of A Generator

10.4 GENERATOR MAINTENANCE:


10.4.1 Weekly Maintenance: Before starting engine

Check oil level (add oil as needed).

Check coolant level.

Walk around inspection.

Check air cleaner indication (change filter as needed).

Fuel system- check for leaks.

Inspect belts, adjust or repair as needed.

Check generator for moisture, dust, &debris and clean it.

10.4.2 Weekly Maintenance: With engine running

Check for proper oil pressure.

Check for proper jacket water temperature.

41 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Check for proper fuel pressure.

Check frequency and voltage.

Record engine run hours.

10.4.3 Weekly Maintenance: After stopping engine

Automatic switches- check switches in proper position for automatic start.

Check fuel level; refill the tank if below 3/4 full.

10.4.4 Yearly Maintenance: Before starting the engine

Perform all weekly before starting engine maintenance first.

Add coolant conditioner as needed.

Drain water and sediment from fuel tank.

Change fuel filter.

Inspect and clean or replace air filter element if needed.

Check and adjust all linkages.

Test all engine protective devices.

Check generator winding with mega ohm meter.

Check generator bearing. Lubricate as required.

10.4.5 Yearly Maintenance: With engine running

Perform all weekly with running engine maintenance first.

Inspect engine mounts. Check for proper torque.

Load test to minimum 30% its rated load for minimum 2 hours. Record all the gauge
readings.

Jacket water temperature will be higher compared to weekly no-load tests.

42 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

10.4.6 Yearly Maintenance: After stopping engine

Perform all weekly after stopping engine maintenance first.

Obtain oil sample for analysis of chemical and physical test.

Change engine oil.

Replace oil filter. Cut filter and inspect for foreign material.

10.4.7 Three years maintenance: Before starting engine

Perform all weekly & yearly before starting engine first.

Cooling system

Drain, clean and flush.

Replace thermostats.

Refill with coolant solution and conditioner.

Inspect radiator cap and replace if needed.

Replace all hoses and belts.

Inspect turbo charger for proper operation.

Perform engine adjustment & tune up.

10.4.8 Three years maintenance: With engine running

Perform all weekly & yearly before starting engine first.

Check engine mounts. Check for proper torque.

Check exhaust system for leaks. Repair as needed.

10.4.9 Three years maintenance: After stopping engine

Perform all weekly & yearly after stopping engine first.

Obtain oil samples for analysis.

43 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

10.4.10 Grounding Cables:


Schedule: Monthly:
All generator frames and casings are grounded to the power plant grounding system.
This is usually done at one location only to allow control over the ground current flow, and to
ensure that there are no circulating currents in the generator frame structure that will cause arcing
between components inside the machine.

Figure-19: Grounding of a Generator

The ground cables should be inspected to ensure they are tight and in generally good condition.
Signs of damage would be corrosion, overheating, fraying, or cracking.
11. SAFETY WHILE DOING ELECTRICAL MAINTENANCE
While doing maintenance works every one should follow the safety procedures.

A routine task can easily become a hazard if the required procedure is not followed or if
attention to detail is not applied.

Do not assume that the hazards in your work area are always at your eye/foot level. Be
aware of ALL your surroundings.

44 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

A complete review of all systems should be conducted prior to any maintenance work.

All electrical equipment connected to line voltage must be bonded to ground

Necessary electrical repairs should be made by a qualified electrician.

ALWAYS de-energize electrical power source before making any adjustments

Discharge capacitors (if present) to prevent electrical shock.

Beware of moving parts.

Remove and replace any safety guards.

Figure-20: Protective Equipment

Wear Common Protective or Safety Equipment such as Safety Shoes, Glasses, Gloves,
Hearing Protection, Hard Hats, or Life Jackets.

When working on cables that are close to energized cables, particularly if they are
running in parallel, precautions shall be taken to minimize the risk of injury to personnel.

Similar precautions are required when working within 100 meters of a Zone.

Jointing of high voltage cables shall only be carried out by personnel trained and
accredited for a particular joint type.

45 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Jointing of high voltage cables is not permitted if it is raining.

Make sure that system is properly earthed.

Tag out the devices.

ANNEXURE-A:

46 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

CONSTRUCTION:
Cables consist of three major components: conductors, insulation, and protective jacket. The
makeup of individual cables varies according to application. The construction and material
are determined by three main factors:

Working voltage, determining the thickness of the insulation

Current-carrying capacity, determining the cross-sectional size

Environmental conditions such as temperature, water, chemical or sunlight exposure,


and mechanical impact, determining the form and composition of the outer cable
jacket.

Fig:Cut way view of the cable


TYPES OF CABLES USED FOR DISTRIBUTION NETWORK
MAJOR TYPES

MAJOR SIZES
(Sq mm)

33kv underground

XLPE

400,300

22kv underground

PILC

300

11kv underground

PILC

240,120,70

LT cables underground

XLPE

240,120,50

47 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

XLPE- CROSS LINKED POLY ETHYLENE CONDUCTOR


PILC- PAPRE INSULATED LEAD SHEATHED CONDUCTOR
HT CABLES:

FIG: CROSS SECTIONAL DRAWING FOR 33KV 3CX400 sq.mm-A2XWY CABLE

HT cable components:
Conductors:
H4 grade Aluminum conductor of electrolytic grade stranded of circular cross section
complying with IS-8130/1984.

48 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Size

Min. Number of

Min. Diameter of each strand/

strands/wires per conductor

Wire (mm)

1000

89

3.93

400

59

3.04

300

36

3.4

150

36

2.4

mm

Conductor Screening:
Either non-metallic semi-conducting tape or a layer of extruded semi-conducting compound
or a combination of two.
Insulation:
XLPE extruded insulation
Insulation Screening:
Extruded Semi-conducting screening with water swellable tapes and metallic screening.
Inner Sheath:
Pressure extruded inner sheathing of Black PVC.
Armour:
The Armour shall be of galvanized steel round wires with fault level of 1500 MVA at 33kV
& 500 MVA at 11 kV. Duration of fault level is one (1) second.
Outer Sheath:

49 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

An extruded outer sheathing of Blue PVC.


LT CABLES:
D:\\ OLDHDD\MISC\cross sectional view of 3.5 c x 240 sqmm cable

CROSS SECTIONAL DRAWING FOR


3.5 C X 240 sqmm (A2 X FY) L.T. CABLE

XLPE INSULATION
SECTOR SHAPED
ALLUMINUM CONDUCTOR

LT cables Standardized Ratings are:

2 core 25 sq. mm

4 core 25 sq. mm

4 core 50 sq. mm

3.5 core 120 /240 sq. mm

3.5 core 150 / 300 sq. mm

50 submitted by Anirban Das

EXTRUDED PVC
OUTER SHEATH
FLAT G.S.STRIP
EXTRUDED PVC
INNER SHEATH

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Insulation:
XLPE extruded insulation
Inner Sheath:
An extruded inner sheathing of Black PVC conforming to the requirement of type
ST-2.
Armour:
The dimension of galvanized steel Strips shall be as specified and shall conform to IS:
7098/Pt-1
Outer Sheath:
An extruded outer sheathing of Yellow PVC.

51 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

ANNEXURE-B:
Cable Selection Criterion:
Cable Types- XLPE, PILC & PVC.
XLPE cables are most popular because of its better electrical and thermal properties like
higher continuous operating temperature, Short Circuit temperature, Break Down strength
etc.
Main Consideration:

For 11 kV,22 kV and 33 kV cables, the cable size is determined by continuous current
rating and short circuit rating.

For 1.1 kV cable, the selection of size is determined by continuous current rating, the
maximum permissible voltage drop and short circuit rating.

In addition to above, following are some factors for deciding the type and size of
cable.

1. Earth fault current carrying capacity.


2. Voltage drop (For low voltage system)
3. Power loss

ANNEXURE- C:
METHODS OF CABLE LAYING:

Laying direct in ground

Drawing in Ducts

Horizontal drilling

52 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

The cables are laid directly in the ground with a depth of 1 meter. Cables are also pulled in
ducts. The pulling tension is important and depends on the method of pulling.
Maximum allowable pulling tension:
The maximum allowable tension on cable conductors that should be used during
pulls must be based on experience as well as good engineering. Factors that have an impact
on the value include type of metal, temper, and factors of safety.

METAL

TEMPER

POUNDS
CIRCULAR MILL

Copper

Soft

0.008

Aluminum

Hard

0.008

Aluminum

Hard

0.006-0.008

Aluminum

Hard

0.003-0.004

Aluminum

Soft

0.002-0.004

Ref: AEIC CG5-(2nd Edition)-2005

Pulling tension calculation:


The basic equation to calculate the pulling tension is
T= W*L*f
Where

T= tension in pounds
W= weight of one foot of cable in pounds

53 submitted by Anirban Das

PER

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

L= length of pull in feet


f = co-efficient of friction for the duct material and outer layer of the cable.
Horizontal drilling is employed where excavation of roads for cable laying is not possible. In
this method the road is drilled horizontally and cables are laid through Hume pipes which are
inserted into the drilled holes.
CABLE INSTALLATION PLAN:
On completion of laying, termination and jointing of cables, a computerized
drawing is prepared, which contains the following details of the installation.
Type of cables, cross-section area, rated voltage, details of construction, cable number and
drum number;
a. Year and month of laying;
b. Actual length between joint-to-joint or ends;
c. Location of cables and joints in relation to certain fixed reference points, for e.g.Buildings, hydrant etc;
d. Name of the jointer who carried the jointing work;
e. Date of making joint and Result of original electrical measurements and testing on

cable installation;
All subsequent changes in the cable drawings are entered after the job. All drawings are
maintained in digital format.

CABLE MARKING AND LOCATION:


54 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

Cables shall be marked with one tag indicating direction or exit from underground
facilities

This tag shall indicate the general direction of the cable(s) to the next facility where
the cable is located.

All tags will be labeled with the next point of connection (i.e. transformer 1 to
transformer

A red plastic warning tape shall be spread above the underground electrical cable
within the right-of-way at a depth of 0.6 m from the ground surface.

ANNEXURE-D:
TESTING OF CABLES:
The testing methods are

Direct voltage testing

Low voltage D.C testing

High voltage D.C testing

Power frequency testing

Low voltage testing:


This test is used to determine the insulation resistance of the cable. In this test Cable phases
not under test should have their conductors grounded. Ends, both at test location and remote,
should be protected from accidental contact by personnel, energized equipment and grounds.
Apply the prescribed test voltage for specified period of time. It may be advantageous to
conduct the test with more than one voltage level and record readings of more than one time
period.
55 submitted by Anirban Das

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

High voltage testing:


This test is used to determine the leakage current in the cable. Apply the prescribed test
voltage for the specified period of time. Total apparent leakage output current is recorded as a
function of time at a prescribed voltage level.
Power frequency testing:
As the name implies, these test methods are based on using alternating current at the
operating frequency of the system as the test source. This test is used to determine the Partial
Discharge. Partial discharge measurement is an important method of assessing the quality of
the insulation of power cable systems, particularly for extruded insulation materials.
PD testing is an evolving technology for periodic diagnostic testing of XLPEinsulated cables. Partial discharges occur at voids in insulation and at the interface layers
between cable and accessory insulation. These discharges emit broadband radiation in the
range of 50 kHz to 500 MHzs PD testing is a nondestructive testing method, generally
accepted as one of the most effective techniques for locating defects in XLPE cables.

ANNEXURE-E:
Insulation Resistance Test Values Electrical Apparatus and Systems

Nominal Rating
of Equipment in Volts
250

56 submitted by Anirban Das

Minimum Test Voltage, DC


500

Recommended Minimum
Insulation Resistance in
Megohms
25

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

600

1,000

100

1,000

1,000

100

2,500

1,000

500

5,000

2,500

1,000

8,000

2,500

2,000

15,000

2,500

5,000

25,000

5,000

20,000

34,500 and above

15,000

100,000

REF: INTERNATIONAL ELECTRICAL TESTING ASSOCIATION (NETA)

ANNEXURE-F: ELECTRICAL TOOL KIT FOR MAINTENANCE WORKS

S.No

57 submitted by Anirban Das

Tool name

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28

58 submitted by Anirban Das

D-24 Reversible Screwdriver, 3/set


D-74-L Screwdriver w/Checker
D-81 Reversible Stubby Screwdriver
D-331-150 Screwdriver
D-332-150 Phillips Screwdriver
N-9-150 Diagonal Cutting Pliers
N-838 Snips
P-15-150 Long Nose Pliers w/Cutter
P-56-175 Pliers w/Side Cutter
P-86-125 Tweezers
P-211Z-150 Slip Joint Pliers
P-245 Slip Joint Pliers
P-704 Crimping Tool, w/Stripper
P-95 Wire Stripper
W-210-200 Adjustable Wrench
W-210-300 Adjustable Wrench
W-521 Open End Wrench Set
Z-341 Measure Tape
Hammer
Quick-point Knife (Large)
Sealing Tape
Vinyl Tape
Plastic mallet
Penlight (with Batteries)
Brush
Hex Wrench Set
Multi meter
B-56-B Tool Box

ELECTRICAL EQUIPMENT MAINTENANCE IN PIPELINES

List of Standards:

IEEE Standard 43-2000 is the .Recommended Practice for Testing Insulation


Resistance of Rotating Machinery.

IEEE Standard 389-1996 is the IEEE Recommended Practice for Testing Electronics
Transformers and Inductors.

IEEE Standard 1415-2006 IEEE Guide for Induction Machinery Maintenance Testing
and Failure Analysis.

NACE SP0169:2007 - Control of External Corrosion on Underground or


Submerged Metallic Piping Systems.

NACE TM 0497 - Measurement Techniques Related to Criteria for Cathodic


Protection on Underground or Submerged Metallic Piping Systems.

NEMA

(National

Electrical

Manufacturing

Association)

TR1-1993(R2000)

Transformers.

IS: 2705 for current transformer compilation.

IS: 3156 for voltage transformer compilation.

AEIC (Association of Edison illuminating Companies) G7-90 testing practices of


underground cables.

IEEE P-400 Guide for Field Testing and Evaluation of Shielded Power Cables

59 submitted by Anirban Das

Você também pode gostar