Escolar Documentos
Profissional Documentos
Cultura Documentos
Tank farms
Pumping stations
Metering stations
Valve manifolds
Pigging stations
SCADA systems
SUB STATIONS
TRANSFORMERS
SWITCH GEAR
ELECTRIC MOTORS
MOV ACTUATORS
EMERGENCY GENERATORS
By this demand factor we can know the capacity of transformer and the conductor
size, and all equipment associated with distribution of electrical power to utilization equipment.
2.1.3 Diversity Factor:
Diversity factor is defined as the ratio of the sum of the individual maximum
demands of various subsystems within a system to the maximum demand of the system.
2.1.4 Load Factor:
Load factor is defined as the ratio of the average load over a designated period of
time to the peak load occurring in that period.
A low load factor indicates short-time demand peaks which can result in heavy
charges to the Using Agency. Low load factor will be corrected by shedding loads or by peakshaving generation during periods of peak demand.
2.2 Voltage Requirement:
The voltage requirement is based on the type of distribution. That means
primary distribution and secondary distribution.
The voltage requirement is also based the type of equipment we are using.
3. SUBSTATIONS
Substations mainly consist of:
Power transformers
Underground cables
Buses
Protective relays
Grounding
4. TRANSFORMERS
4.1 BASIC PRINCIPLE:
The transformer is based on two principles:
A changing magnetic field within a coil of wire induces a voltage across the ends of the
coil (electromagnetic induction).
Disconnect the transformer from both the HV systems and the LV systems.
Unlock and remove the padlock, if fitted. Release the tapping switch mechanism by lifting
the operating handle.
Turn the handle to the desired position to increase LV volts - turn to a higher tap position
number, which will decrease the HV, turns in circuit and proportionally increase the output
voltage.
4.3 MAINTENANCE:
4.3.1 ONLINE MAINTENANCE:
Frequency of routine maintenance is quarterly for distribution transformers and daily
for grid transformers.
Check load current: If more than rated, reduce non priority loads
Check voltage: control the appropriate voltage H.V voltage and L.V voltage variations. If
online tap changer (O.L.T.C) is provided change the tap positions as required.
Check oil level in Transformer and O.L.T.C: check the oil level in respective conservators.
Ensure that they are not beyond rated temperature. If not top up with dry transformer oil.
Check transformer for oil leaks.
Check breather on transformer and O.L.T.C: check color of silica gel. It should be blue. If
it is pink replace it by spare charge.
Check sound level: Certified sound levels determined in accordance with NEMA, shall not
exceed the following:
9 KVA
40 dB
10 - 50 KVA
45 dB
51 - 150 KVA
50 dB
55 dB
60 dB
TABLE-01
Visual inspection of transformers for oil leakage, oil level, and silica gel conditions should
be done.
Open H.T terminal box and check for loose connections, heating and oil leakage from
bushings.
Examine Bucholzs relay, OTI (oil temperature indicator) and WTI (winding temperature
indicator) relays operation and check for accuracy.
New oil
Old oil
1 Electrical strength
40kv
25kv/40kv
2 Moisture, Mechanical
impurities
None
25/35 ppm
3 Flash Point
1400C
Max. 50 C lower
0
4 Viscosity at 27 C
27 cst
27 cst
TABLE-02
After one year any changes in the oil properties above said, the oil should be changed. The old
mineral oil should be reconditioned.
SYMPTOM
High Temperature.
CAUSE
CORRECTIVE
MAINTENANCE
Over voltage.
Over current.
Insufficient cooling.
Fractured metal or
porcelain parts of the
bushings.
Contaminated by varnishes.
Carbonized oil due
switching.
Winding or core failure.
DRY_TYPE
TRASNFORMERS:
High temperatures
Moisture
Environmental changes.
insulation breakdown. Due to these, some part of the cable (specifically, underground) get
heated up and burst.
5.3 LOCATING CABLE FAULT:
There are two basic methods of locating an underground cable fault.
5.3.1 Sectionalizing:
In this procedure, we divide the cable into smaller sections and examine the insulation
resistance or continuity.
5.3.2 Thumping:
When we supply a high voltage to a faulted cable, the resulting high-current arc
makes a noise loud enough for us to hear above ground. While this method eliminates the
sectionalizing method's cutting and splicing, it has its own drawback. Thumping requires a
current on the order of tens of thousands of amps at voltages as high as 25kV to make an
underground noise loud enough for you to hear above ground.
The heating from this high current often causes some degradation of the cable insulation.
There are some relatively new methods of locating cable faults that use rather
sophisticated technology.
5.3.3 Time Domain Reflectometry (TDR):
The TDR sends a low-energy signal through the cable, causing no insulation
degradation. A theoretically perfect cable returns the signal in a known time and in a known
profile. Impedance variations in a "real-world" cable alter both the time and profile, which
the TDR screen or printout graphically represents. This graph (called a "trace") gives the user
approximate distances to "landmarks" such as opens, splices, Y-taps, transformers, and water
ingression.
One weakness of TDR is that it does not pinpoint faults. TDR is accurate to
within about 1% of testing range.
Arc reflection
The arc reflection method uses a TDR with a filter and thumper. The filter limits both
the surge current and voltage that can reach the cable under test, thus allowing
minimal stress to the cable. Arc reflection provides an approximate distance to the
fault (when there is an ionizing, clean arc produced at the fault and the TDR in use is
powerful enough to sense and display a reflected pulse).
The surge pulse reflection method uses a current coupler and a storage oscilloscope
with a thumper. The advantage of this method is its superior ability to ionize difficult
and distant faults. Its disadvantages are that its high output surge can damage the
cable, and interpreting the trace requires more skill than with the other methods.
The voltage pulse reflection method uses a voltage coupler and an analyzer with a
dielectric test set or proof tester. This method provides a way to find faults that occur
at voltages above the maximum thumper voltage of 25kV.
One test to detect an open neutral requires shorting a known good conductor to a
suspect neutral, then measuring the resistance with an ohmmeter. If the reading is 10
ohms or higher, we can suspect an open neutral. Remember, other objects can
complete the circuit.
Cast metal conducting tubes to make the electrical cable connection with snap-off
bolt heads to ensure that perfect compression torque is applied.
A container of liquid silicone, which is poured into the polyester mould, completely
encasing the cable joint.
Figure-4: Cutaway view of straight water resistance medium voltage underground joint
The above figure shows us how the polyurethane jointing process is going. The
third from right connector is having its white, inner shell mould filled with liquid silicone.
Note the temporarily placed funnel, mounted in the white inner shell, towards the foreground,
which ensures the correct level of the silicone fill and zero air entrapment, and the support
frame holding the container, as the filling is carried out. The liquid silicone container has two
outlets, and the flow rate into the white, inner shell, is controlled by the gentle release of the
seal on the second, (red) cap. As soon as the silicon pour is completed, the entry holes into
this white mould are sealed. The whole process is cold, ideal for hazardous zoned areas.
5.4.2 HEAT SHRINKABLE CABLE JOINT:
Heat shrink splices are available as a series of heat shrinkable tubes. Some may
be preassembled by the manufacturer to reduce the number that must be handled in the field.
The tubes must be slipped over the cable prior to connecting the conductors. After
positioning each tube over the connected cables, heat is applied to shrink the tube snugly over
the underlying surface and soften any mastic material used in the assembly. Stress relief is
15 submitted by Anirban Das
generally provided by stress control tubes that are also shrunk into place so that ends of the
stress control tube overlap both cable insulation shields. The joint is finished in the normal
manner.
During the heat shrink installation process, the stored recovery force of the tube
is released in addition to the recovery force of the heat shrinkable outer layer. A pre-designed
screen and thick layer of insulation is installed in one simple process. This allows extremely
tight electrical interfaces due to the shrink force generated. The elastomeric (tube) insulation
characteristic combined with the rigid outer heat shrinkable screen layer enables the joint to
follow the thermally induced dimensional changes of the cable insulation.
5.5 MAINTENANCE:
SCHEDULE
Annually
5 yearly
EQUIPMENT
TASK
Cable Terminations
Cable loading
Earthing
Earthing
TABLE-04
For the circuit breaker it is necessary to beak the circuit immediately when the fault
occurs and isolates the fault position from healthy position.
To ensure the equipment remains safe and reliable, regular examination is essential.
6.3 MAINTENANCE:
Essential areas requirements for inspection and testing:
6.3.1 INSULATION:
Insulation systems must be closely inspected for sings of over heating, cracking and
other defects.
6.3.2 CONTACTS:
Inspect the contacts for signs of excessive wear and over heating. Free movement of
the contactors also examined.
6.3.3 TERMINALS:
All terminals must be checked for firmness and signs of over heat.
6.3.4 CABLES:
Power and control cables must be examined with the connecting equipment.
6.3.5 BUS BARS:
Bus bars shall subject to periodic inspection.
6.4 MAINTENANCE OF POWER AIR CIRCUIRT BREAKER:
Power air circuit breaker should be maintained annually.
To perform maintenance, withdraw the circuit breaker from its enclosure and do the following:
19 submitted by Anirban Das
Wipe bushings, barriers, and insulating parts. Remove the dust, smoke, and any foreign
deposits. Replace the damaged parts.
Check breaker control wiring and ensure that the connections will be tight.
Operating breaker in fully opened and closed position after service. Check for any
binding before going to put in the circuit.
Cleaning
Lubrication.
Cleaning, checking contact conditions and tightness of connections and confirming the
tightness and continuity of the fuses, if fitted.
Relays are provided with dust proof covers and before a cover is removed, the cases
should be carefully dusted.
Dust and dirt should be carefully wiped off by a soft squirrel hair brush. Mechanical
blowers or blowing by mouth is not recommended.
The internal wiring, ICs, printed circuits should be examined for corrosion. Excessive
heat may damage the insulation.
Relay flags/targets should operate freely without friction and also reset freely.
Perform complete tripping and operational tests to verify all control and protective
functions and alarms and tripping mechanism.
TROUBLE SHOOTING:
SYMPTOM
Over heating
CAUSE
CORRECTIVE
MAINTENANCE
Replace it.
Damaged
or
dirty Dress or replace damaged
contacts
of
tripping contacts. Clean the dirty
circuit
contacts.
Faulty connections in trip
circuit (loose or broken)
Insufficient
voltage Replace faulty wires. All
caused by too much drop connections are to be tightened.
in leads.
Replace with oversize wires.
Improve contact at connections.
Poor voltage regulation
Check up voltage, if less correct
it.
Loose connections
Bushing problems
7. ELECTRIC MOTOR
7.1 INTRODUCTION:
Motors covert electrical energy into mechanical energy. Mainly motors are classified
into two types:
D.C motors
A.C motors
D.C. motors are mainly used in traction works and cranes where constant speed
characteristics are necessary. These are not used in domestic and industrial purposes because the
cost of the D.C motor is high and also the supply of D.C power also costly one.
So the best alternative is using A.C motors. In general most of industries are using 3phase motors. Hence we here consider 3-phase motors only.
The motors are classified into two types:
Induction motors
Synchronous motors
Let us briefly discuss about induction motors because many industries using
Stator
Rotor
The stator winding and rotor windings are insulated. The primary purpose of
insulation is to withstand turn-to-turn, phase to-phase and phase-to-ground voltage such that to
direct the stator phase currents through the desired paths of stator windings.
The insulations are classified as:
Class A: 105C
Class B: 130C
Class F: 155C
Class G: 180C
For motors having high temperature rise class F insulation is uses.
Check the terminal box for loose connection in the cable termination.
Perform regreasing.
Remove front and rear grease cups if regreasing system is not healthy.
Check the condition of the grease. Top up grease if condition is not o.k.
Open the foundation bolts and take out the motor from foundation and send to electrical
workshop for schedule.
Open the fan cover and remove the fan from the shaft.
Remove the grease cups on both sides. Inspect the condition of grease.
Check the bearing housing for correct measurement of the bearing with sufficient
tolerances.
Clean all the grease using suitable solvent. Then wash the bearing with diesel and dry air.
Inspect rotor thoroughly for the loose bars and cage/shorting rings.
Inspect the bearing seat. If it is worn out and loose metalize the bearing.
Check the rotor trueness. If the shaft is bent send it for reshafting.
Replace the studs and nuts of the grease cups if worn out.
Inspect the stator winding for loose coils, loose connections, heating effect, deterioration
of insulation etc.
Clean the stator winding with clean dry cloth and blower.
Run the motor and monitor the performance for four hours.
TROUBLE SHOOTING:
SYMPTOM
CAUSE
CORRECTIVE
MAINTENANCE
Low voltage
Motor noisy
Motor vibrates
Bearings stiff
Over load
Coupling loose
Overload
Rotor
29 submitted by Anirban Das
winding
with
Use
insulation
procedures.
testing
connections
Motor used for rapid reversing Replace with motor designed for
service
reversing service.
Bent shaft
Insufficient oil
Sleeve bearings
Oil rings rotating slowly or not Oil too heavy, drain and replace.
rotating at all
Replace bearings. Resurface
Defective bearings or rough shaft.
shaft
TABLE-06
8. MOV ACTUATORS
8.1 DESCRIPTION:
Electrically operated motor operated valves are widely used in power plant/process
units and play a critical role. A typical actuator consists of
Control gear
Local controls
Electronics circuit consists of power supply unit, remote operating unit, and logic cords.
8.2 MAINTENANCE:
Schedule:
Based on the plant run length and application, a routine maintenance program is to
be developed. The maintenance period will be 1 year.
Check motor winding insulation resistance and check winding resistance is balance.
In intelligent units check the healthiness from the diagnostic codes as per the vendors
manual.
TROUBLE SHOOTING:
SYMPTOM
MOV not operating
CORRECTIVE MAINTENANCE
TABLE-07
9. CATHODIC PROTECTION
9.1 INTRODUCTION:
Cathodic protection is an electrochemical method used to prevent or control
corrosion of buried or submerged metallic structures.
After a CP system is installed and adjusted to provide adequate protection, currents
and potentials should remain relatively stable; changes in currents or potentials indicate a
problem.
Out of these two methods impressed current protection is the most economical one
for the long pipelines. The disadvantages of the Galvanic protection is small driving voltage is
available, and small current available in higher resistivity electrolytes. Here we discuss briefly
about impressed current CP protection.
In an impressed current system, the protective current is supplied by a rectifier (or
other DC power source) to the structure.
Rectifier stacks,
The function of the rectifier is to convert alternating current into controlled direct current.
Silicon diodes
Thyristors
Switch mode
Maintenance Schedule:
Thirty days after cathodic protection system is installed and properly adjusted.
Procedure:
Visually check all rectifier components, shunt box components, safety switches.
Tighten all accessible connections and check temperature of all the components.
For rectifiers with more than one circuit, measure the output voltage and current for each
circuit using a dependable hand-held meter, and calibrate the rectifier meters, if present.
Calculate the cathodic protection system circuit resistance of each circuit by dividing the
rectifier DC voltage output of each circuit by the rectifier DC ampere output for that
circuit.
9.5.2 IMPRESSED CURRENT CHECK:
Maintenance schedule:
Sixty days after rectifier inspection, more frequent checks may be required by local
conditions.
Procedure:
Measure output D.C voltage and current from the rectifier.
Ensure the DC ampere output of the rectifier meets the current (ampere) requirement of
the system.
36 submitted by Anirban Das
Calculate the cathodic protection system circuit resistance of each circuit by dividing the
rectifier DC voltage output of each circuit by the rectifier DC ampere output for that
circuit.
Calculate the D.C out put voltage of the rectifier and check that it is rated or not.
TROUBLE SHOOTING:
.
TABLE-08
Air compressors
Centrifuges
UPS system
The armature winding is fed through three slip rings (collectors) and a set of brushes
sliding on them.
The core is slotted (normally open slots), and the coils making the winding are placed
in the slots.
Apparent power
MVA
Real power
MW
Mega watts
Reactive power
MVARs
Power factor
Stator current
Field voltage
Vf
Direct voltage
Field current
If
Frequency
Hz
Speed
pf
A dimensionless quantity
Vt
Alternating voltage
Ia
Hertz
rpm
Load test to minimum 30% its rated load for minimum 2 hours. Record all the gauge
readings.
Replace oil filter. Cut filter and inspect for foreign material.
Cooling system
Replace thermostats.
The ground cables should be inspected to ensure they are tight and in generally good condition.
Signs of damage would be corrosion, overheating, fraying, or cracking.
11. SAFETY WHILE DOING ELECTRICAL MAINTENANCE
While doing maintenance works every one should follow the safety procedures.
A routine task can easily become a hazard if the required procedure is not followed or if
attention to detail is not applied.
Do not assume that the hazards in your work area are always at your eye/foot level. Be
aware of ALL your surroundings.
A complete review of all systems should be conducted prior to any maintenance work.
Wear Common Protective or Safety Equipment such as Safety Shoes, Glasses, Gloves,
Hearing Protection, Hard Hats, or Life Jackets.
When working on cables that are close to energized cables, particularly if they are
running in parallel, precautions shall be taken to minimize the risk of injury to personnel.
Similar precautions are required when working within 100 meters of a Zone.
Jointing of high voltage cables shall only be carried out by personnel trained and
accredited for a particular joint type.
ANNEXURE-A:
CONSTRUCTION:
Cables consist of three major components: conductors, insulation, and protective jacket. The
makeup of individual cables varies according to application. The construction and material
are determined by three main factors:
MAJOR SIZES
(Sq mm)
33kv underground
XLPE
400,300
22kv underground
PILC
300
11kv underground
PILC
240,120,70
LT cables underground
XLPE
240,120,50
HT cable components:
Conductors:
H4 grade Aluminum conductor of electrolytic grade stranded of circular cross section
complying with IS-8130/1984.
Size
Min. Number of
Wire (mm)
1000
89
3.93
400
59
3.04
300
36
3.4
150
36
2.4
mm
Conductor Screening:
Either non-metallic semi-conducting tape or a layer of extruded semi-conducting compound
or a combination of two.
Insulation:
XLPE extruded insulation
Insulation Screening:
Extruded Semi-conducting screening with water swellable tapes and metallic screening.
Inner Sheath:
Pressure extruded inner sheathing of Black PVC.
Armour:
The Armour shall be of galvanized steel round wires with fault level of 1500 MVA at 33kV
& 500 MVA at 11 kV. Duration of fault level is one (1) second.
Outer Sheath:
XLPE INSULATION
SECTOR SHAPED
ALLUMINUM CONDUCTOR
2 core 25 sq. mm
4 core 25 sq. mm
4 core 50 sq. mm
EXTRUDED PVC
OUTER SHEATH
FLAT G.S.STRIP
EXTRUDED PVC
INNER SHEATH
Insulation:
XLPE extruded insulation
Inner Sheath:
An extruded inner sheathing of Black PVC conforming to the requirement of type
ST-2.
Armour:
The dimension of galvanized steel Strips shall be as specified and shall conform to IS:
7098/Pt-1
Outer Sheath:
An extruded outer sheathing of Yellow PVC.
ANNEXURE-B:
Cable Selection Criterion:
Cable Types- XLPE, PILC & PVC.
XLPE cables are most popular because of its better electrical and thermal properties like
higher continuous operating temperature, Short Circuit temperature, Break Down strength
etc.
Main Consideration:
For 11 kV,22 kV and 33 kV cables, the cable size is determined by continuous current
rating and short circuit rating.
For 1.1 kV cable, the selection of size is determined by continuous current rating, the
maximum permissible voltage drop and short circuit rating.
In addition to above, following are some factors for deciding the type and size of
cable.
ANNEXURE- C:
METHODS OF CABLE LAYING:
Drawing in Ducts
Horizontal drilling
The cables are laid directly in the ground with a depth of 1 meter. Cables are also pulled in
ducts. The pulling tension is important and depends on the method of pulling.
Maximum allowable pulling tension:
The maximum allowable tension on cable conductors that should be used during
pulls must be based on experience as well as good engineering. Factors that have an impact
on the value include type of metal, temper, and factors of safety.
METAL
TEMPER
POUNDS
CIRCULAR MILL
Copper
Soft
0.008
Aluminum
Hard
0.008
Aluminum
Hard
0.006-0.008
Aluminum
Hard
0.003-0.004
Aluminum
Soft
0.002-0.004
T= tension in pounds
W= weight of one foot of cable in pounds
PER
cable installation;
All subsequent changes in the cable drawings are entered after the job. All drawings are
maintained in digital format.
Cables shall be marked with one tag indicating direction or exit from underground
facilities
This tag shall indicate the general direction of the cable(s) to the next facility where
the cable is located.
All tags will be labeled with the next point of connection (i.e. transformer 1 to
transformer
A red plastic warning tape shall be spread above the underground electrical cable
within the right-of-way at a depth of 0.6 m from the ground surface.
ANNEXURE-D:
TESTING OF CABLES:
The testing methods are
ANNEXURE-E:
Insulation Resistance Test Values Electrical Apparatus and Systems
Nominal Rating
of Equipment in Volts
250
Recommended Minimum
Insulation Resistance in
Megohms
25
600
1,000
100
1,000
1,000
100
2,500
1,000
500
5,000
2,500
1,000
8,000
2,500
2,000
15,000
2,500
5,000
25,000
5,000
20,000
15,000
100,000
S.No
Tool name
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
List of Standards:
IEEE Standard 389-1996 is the IEEE Recommended Practice for Testing Electronics
Transformers and Inductors.
IEEE Standard 1415-2006 IEEE Guide for Induction Machinery Maintenance Testing
and Failure Analysis.
NEMA
(National
Electrical
Manufacturing
Association)
TR1-1993(R2000)
Transformers.
IEEE P-400 Guide for Field Testing and Evaluation of Shielded Power Cables