What is network?
Define event float in CPM.
What is meant by network construction?
What is meant by critical path?
Define planning?
6. Define scheduling?
7. Define control?
8. List out the rules for network construction?
9. What are the general guidelines for network crashing?
10. Define resource allocation technique?
11. Define players?
12. Define strategy?
13. Define pure strategy?
14. Define mixed strategy?
15. Define maximin principle?
16. Define minimax principle?
17. What is saddle point?
18. What is mean by value of the game?
19. What is mean by two-person zero-sum game?
20. What is the crashing of project network?