August, 2014
DOCUMENT NUMBER:
[SOK-NG01011666-SOKG1-XXXXX-XXXXX]
Proprietary Information: This document contains proprietary information and may not be partly or wholly reproduced
without prior written permission from Shell Petroleum Development Company
The Process Manager for this procedure is the Major Projects General Manager, the Process Owner is the Major
Projects Project Services Manager
Revision
R01
Date
Description
Originator
FELIX
ANYANELE
Checker
ARVIN DO
REGO
Approver
IKENNA ONYEKONWU
REF IND.
NAME
SIGN
DATE
Revision Philosophy
All revisions for review will be issued at R01, with subsequent R02, R03, etc as required.
All revisions approved for issue or design will be issued at A01, with subsequent A02, A03, etc as required.
Documents approved for Construction will be issued at C01, C02, and C03 respectively.
Documents or drawings revised as As built will be issued as Z01, Z02 Z03 etc.
Narrative sections revised from previous approved issues are to be noted in the table below and/or highlighted in the RH
margin (using the appropriate revision status) thus: | A02
Previous revision highlighting to be removed at subsequent issues.
Drawings/diagrams revised from previous approved issues are highlighted by 'clouding' the affected areas and by the use
of a triangle containing the revision status.
Revision History
REVISION NO.
R01
DATE OF
ISSUE
SOK-NGO1011666-SOKG1XXXXX-XXXXX
TABLE OF CONTENT
S. NO.
1.
2.
3.
4.
5.
6.
7.
8.
DESCRIPTION
INTRODUCTION
SCOPE
REFERENCES
RESPONSIBILITIES
MANPOWER, MACHINERY AND EQUIPMENT
HSE REQUISITES
PRE-REQUISITES
PROCEDURE
PAGE
4
4
4
5
6
6
7
8
1. INTRODUCTION
This method statement outlines the requirements, responsibilities and effective guidance for the
installation of Aftercooler Compressor, E-2180 for the SOKU NAG COMPRESSION FACILITY
INSTALLATION PROJECT.
Whilst there are inherent dangers associated with this work, consequently, this method statement is
developed to ensure that all activities to be carried out are in compliance with applicable COMPANY
SOK-NGO1011666-SOKG1XXXXX-XXXXX
2. SCOPE OF WORK
The scope establishes the requirements and responsibilities for the installation of the
Aftercooler, E-2180 in accordance with the contract. The CONTRACTOR shall be responsible
for the loading, unloading, safe handling, installation of the Compressor Aftercooler, E-2180 and
connection of the associated insulated pipe work including electrical and instrumentation
ancillaries required. Lifting and installation of the Compressor Aftercooler, E-2180 shall be in
stages and by approved cranes with the appropriate safe working loads (SWL). The new
Compressor Aftercooler, E-2180 shall be installed on the existing supports. The lifting and
installation of the Compressor Aftercooler, E-2180 shall be in accordance with relevant
COMPANY DEPs, Standard Construction Specification Section 19 (Mechanical Equipment)
Approved for Construction drawings.
3. REFERENCES:
Project Quality Plan
SOK-NG01011666-SOKG1-QA5798-00001
Non-Conformity Procedure
SOK-NG01011666-SOKG1-QA5880-00001
SOK-NG01011666-SOKG1-VA6036-00001
SOK-NG01011666-SOKG1-VA6180-00002
Material Preservation
Lifting, Erection and Installation Plan
SOK-NG01011666-SOKG1-BA5736-00002
AFC DRAWINGS
Project Quality Assurance
DEP 82.00.10.10-Gen
DEP 70.10.70.11
DEP 61.10.08.11
Mechanical Equipment
Human Factors Engineering Application
DEP 30.00.60.14-Gen
During Construction
Manufacturers Erection Manual
4. RESPONSIBILITIES
SOK-NGO1011666-SOKG1XXXXX-XXXXX
PROJECT MANAGER
The CONTRACTOR Project Manager shall primarily be responsible for the coordination and
execution
CONSTRUCTION MANAGER
The Construction Manager shall coordinate all construction activities whilst stand in as the
interim Project Manager during the absence of CONTRACTORs Project Manager.
He shall be present at construction sites at all times when construction is in progress and shall
be responsible for the installation of the Compressor Aftercooler, E-2180.
MECHANICAL SUPERINTENDENT
The CONTRACTORs Mechanical Superintendent shall coordinate and oversee the installation
of the Aftercooler, E-2180 and its ancillaries.
RIGGING SUPERVISOR
The Rigging Supervisor shall be responsible for the coordination, and monitoring the lifting and
moving of the Aftercooler, E-2180 and its components during the installation activity.
QA/QC MANAGER
The CONTRACTORs QA/QC Manager shall be responsible for quality assurance/quality
control actions associated to the installation of the Aftercooler, E-2180.
QA/QC INSPECTOR
The CONTRACTORs QA/QC inspectors shall be responsible for the monitoring of all QC
activities whilst ensuring work being executed is in conformance with the project specifications.
SOK-NGO1011666-SOKG1XXXXX-XXXXX
S. NO.
DESCRIPTION
1.
2.
Surveyor Mate
3.
QA/QC Inspector
4.
HSE Officer
5.
6.
Rigging supervisor
7.
Mechanical Technicians
8.
E&I Technicians
9.
Crane operators
DESCRIPTION
1.
2.
3.
Crane
4.
5.
Spreader bar
6. HSE REQUIREMENTS:
Prior to commencing the works a detailed Job Hazard Analysis (JHA) shall be carried out. After all
known, suspected or potential hazards and risks have been identified, the work force shall be
informed of the hazard and control measures that must be put in place to eliminate or control the
hazard and potential risk.
All personnel involved in the survey activity shall receive safety training induction
SOK-NGO1011666-SOKG1XXXXX-XXXXX
All personnel to be engaged in this work shall be properly mobilized and inducted. This is to enable
them to appreciate the risk hazards involved in the operations.
All workers shall be medically fit to work.
The health, safety and environment of all personnel shall be safeguarded to avoid injuries and
illness.
There shall be a qualified first aider, fully equipped with first aid drugs required in the first aid
administration.
Dedicated site HSE officers shall man all work sites.
Warning signs and barriers shall be positioned around all work areas.
All personnel shall wear the appropriate PPE reference Job Specific JHA. All the work force shall
comply with the Contractors Health, Safety and Environment requirements as per the HSE plan.
Only authorized personnel shall be allowed into the work area. All necessary measures as per
Clients requirements or manufacturers recommendations shall be adhered to.
PTW and the JHA shall be signed off.
All personnel shall be swimming certified and only those required to use helicopter shall be HUET
certified.
Supervisor and safety officer to ensure lifting plan for the lift activity is prepared and understood.
7. PRE-REQUISITES:
All information related to the existing bench-mark shall be collected from the COMPANY and
transferred to the existing work site.
SOK-NGO1011666-SOKG1XXXXX-XXXXX
8. WORK PROCEDURE
S. NO.
8.1
8.2
8.3
8.4
TASK STEPS
STEP DESCRIPTION
Equipment
Calibration and
Certification
company.
Securing of work
area
Work area
work area
existing steel
structure and
foundation
Carry out
8.6
Integrity of
8.5
REMARKS
alignment check
on existing steel
structure
CONTRACTOR &
COMPANY personnel,
correct PPE and adequate
supervision.
To be verified by
competent
CONTRACTOR
personnel.
Approved lifting plan shall
equipment
8.7
setting-out
The weight of the equipment is XX tons based on
data from VENDOR manual, a crane with a SWL
SOK-NGO1011666-SOKG1XXXXX-XXXXX
S. NO.
TASK STEPS
STEP DESCRIPTION
of XX tons shall be used for this operation as per
REMARKS
INSTALLATION SEQUENCE
Assemble and fit into place the plenum, air cooler
8.9.1
Assembling of air
cooler
Use of competent
personnel, correct PPE,
equipment, tools and
adequate supervision.
positioning of
tube bundle
Use of competent
on the equipment.
adequate supervision.
Use of competent
installation
adequate supervision.
S. NO.
TASK STEPS
STEP DESCRIPTION
REMARKS
8.9.4
8.9.5
Isolation of
process inlet/
outlet points
Use of competent
personnel, correct PPE,
equipment, tools and
adequate supervision.
Use of competent
Electrical &
Instrument
adequate supervision.
Installation
Connect all earth bosses according to VENDORs
specification.
8.9.6
Structural
Installation
8.9.7
Verification
Use of competent
personnel, correct PPE,
equipment, tools and
adequate supervision.
Use of competent
adequate supervision.
applicable;
Alignment of belt pulleys;
Rigidity of fan and belt guards;
Proper tension of belt drives;
Guards protecting personnel from hot
surfaces;
Proper alignment of process piping
headers to ensure no excessive nozzle
loading;
Full priming of grease lines between
grease nipple and bearing house;
SOK-NGO1011666-SOKG1XXXXX-XXXXX
S. NO.
TASK STEPS
STEP DESCRIPTION
REMARKS
CLEANLINESS
Use of competent
8.10.1
House-keeping
area.
8.11
DOCUMENTATION
Documentation(s) relating to the installation work
8.11.1
Documentation
Use of competent
Completion
CONTRACTOR representatives.
personnel
ATTACHMENTS:
SOK-NGO1011666-SOKG1XXXXX-XXXXX