Escolar Documentos
Profissional Documentos
Cultura Documentos
BY
R.PRASANNA VENKATESH (213067)
PRATAP.B.PATIL (213068)
M. VENKATESH (213107)
CONTENTS
1.
INTRODUCTION..............................................................................................................................4
1.1.
1.2.
1.3.
3.
3.2.
BARRIERS .......................................................................................................................................24
4.1.
4.2.
ECONOMIC AS PECTS..............................................................................................................25
4.3.
4.4.
CONCLUS ION...............................................................................................................................108
NICM AR
PROJECT REPORT
AIM: To study about the high rise structures and different barriers for the construction of high
rise building in India.
OBJECTIVE:To overcome the barriers and to find a suitable solution for the construction of high rise
building with reference to Indian context.
What is a barrier?
Barrier in dictionary means a fencing that creates an obstacle. In this thesis the term
barrier means the difficulties the construction industry faces during the actual execution
as well as the planning of the high rise buildings.
1. To study the barriers and Impact of the following aspects on High rise construction
1.1
1.2
Technical or Technology
1.3
Economical
1.4
Cost
1.5
Social
1.6
Environmental and
NICM AR
PROJECT REPORT
1. INTRODUCTION
From the beginning in the middle of
the last century and right up to the present day,
high-rise buildings have always been a dominant
landmark in the townscape, visible from far and
wide, like the towers of Antiquity and the Middle
Ages. At the same time, this sky-scraping
construction method has always been an ideal
means of displaying power and influence in the
community. In the light of this goal, reasonable
economic considerations often recede into the
background during the erection and subsequent
use of these high-rise buildings. A prestige objects
for the builder, these edifices not only have an
effect on their immediate neighbours, but also
influence many areas of urban life in very
different ways. These aspects will also be taken up
in this thesis.
In the ear ly years, the builders urge to r ise to dizzying heights was lim ited
by unsolved technical problems. In recent years, however, a real competition has
developed among the builders of skyscrapers to be world champion at least for a few
months before being outdone by a rival with an even higher building. Even seemingly
Utopian projects now stand a good chance of becoming reality.
This rapid development has only become possible because the technical
conditions and methods used in constructing high-rise buildings have improved
decisively and in some cases changed fundamentally in the last few years. Up until the
end of the last century, high-rise buildings were still made of solid br ick masonry, which
ultimately required foundation walls up to 1.8 m thick. When steel frames adapted from
steel bridge construction were introduced, with their increased strength and lower weight,
builders and architects were able to soar to greater heights. With this steel skeleton, the
net weight of the structure was considerably lower than that of a solid masonry building;
it thus not only cut the costs of construction, but also gave wings to the architects
imagination. By the turn of the century, they were designing buildings that also looked
light and delicate as even at that time the skeleton structure permitted a large proportion
of windows on the outer facade. Since then, the construction of high-rise buildings has
continued to change with the requirements imposed by air-conditioning and particular ly
office communications.
NICM AR
PROJECT REPORT
The high-rise office buildings of the nineties have little in common with
their predecessors. Instead of compact walls and ceilings, we now have a high-tech
structure made up of largely prefabricated elements which are welded and bonded
together on site. The building comprises a skeleton of steel or reinforced concrete which
is rounded off by suspended ceilings and false floors creating the space required for
installations. The originally load-bear ing outer wall has been replaced by a prefabricated
facade. However, this complex method of construction promotes the spread of fire and
fumes, and therefore, in conjunction with the considerable concentration of values
involved, represents an extremely sensitive risk both during construction and throughout
the service life of the building. The major fires which broke out in a number of high-rise
office buildings shortly before their completion in the early nineties show how correct the
appraisal of the fire risk in high-rise buildings is the losses incurred through these fires
are several times higher than the amounts of indemnity known to date.
This is consequently one of the main reasons why high rise buildings
constitute a new dimension of risk for the insurance industry, one which has made it
necessary to draw up new concepts for underwriting, loss assessment and PML
determination throughout every phase of construction and subsequent use. We are fully
aware of the fact that many of the aspects considered with regard to the construction, use
and insurance of high-rise buildings naturally apply in the case of lower buildings too.
Nevertheless, we do not wish to lim it ourselves to aspects which only apply
specifically to high rise buildings. After a brief overview, we will therefore consider in
detail all the risks and problems associated with high-r ise buildings and the techniques
that are applied in order to illuminate possible solutions from the point of view of both
construction technology. Moreover, the more broadly based general information available
will make it easier not only to assess the risk of high-rise building projects but also to
arrive at a price for such projects.
PROJECT REPORT
491 feet (23 m to 150 m) high are considered high-rises. Buildings taller than 492 feet
(150 m) are classified as skyscrapers. The average height of a level is around 13 feet (4
m) high, thus a 79 foot (24 m) tall building would comprise 6 floors. Most building
engineers, inspectors, architects and similar professions define a high-rise as a building
that is at least 75 feet (23 m).
Davis Langdon (2002) states that it is not possible to define high r ise using
absolute measures. They believe that tall buildings are therefore best understood in
relative terms as buildings whose planning, design, construction and occupation is
influenced by height in ways that are not normally associated with more typical, local
developments.
High-rise buildings became possible with the invention of the elevator ( lift)
and cheaper, more abundant building materials. Normally, the high r ise structures
functions as high-rise apartment building or high-rise offices.
For the sake of this study, the terms tall building and high-rise shall be used
for structures with approximately eight or more stories while towers are tall buildings
with a slender shape.
PROJECT REPORT
floors were in greater demand than the lower floors. Following completion of the
Equitable building, it was the done thing to reside on one of the top floors.
Burnham and Roofs Monadnock building, which was completed in Chicago
in 1891, must also be mentioned as one of the last witnesses of a whole generation of
solid masonry high-rise buildings. Sixteen floors of robust brick masonry rise skywards
in stern, clear lines: an astonishing s ight to eyes accustomed to the frills and fancies of
the late 19th century. Standing on an oblong base measuring 59 m _ 20 m, the building is
reminiscent of a thin slice and not only recalls the industrial brick buildings of the late
19th century, but also anticipates the formal simplification of the later 1920s.
The buildings rose higher and higher with the spread of pioneer ing
construction methods such as the steel skeleton or reliable deep foundation methods
as well as the invention and development of the elevator. The highly spectacular skylines
of North American cities, particularly Chicago and New York, originated in the ear ly
years of the 20th century. Glancing over Manhattans stony profile, the silhouettes
dotting the first 12 km of the 22-km-long is land bear vociferous testimony to this
dynamic development:
The World Trade Center, currently the tallest building in New York, 417 m high,
The legendary Empire State Building, built in 1931, 381 m,
The United Nations building erected in 1953, 215
m,
The Chrysler Building dated 1930, 320 m,
The former Pan Am Building completed in 1963,
246 m,
The Rockefeller Center (19311940), a complex
of 19 buildings,
The Citicorp Center built in 1978, 279 m, and
The AT&T Building opened in 1984, a
pioneering building by the post-modern architect
Philip Johnson, with an overall height of 197 m.
It is only recently that attention has also
turned to interesting high-rise buildings outside North
Amer ica: Norman Fosters Hong Kong and Shanghai
Bank, Ieoh Ming Peis Bank of China in Hong Kong
and the twin tops of the Petronas Towers in Kuala
Lumpur, currently the tallest building in the world at
452 m. High-rise buildings in Germany are a modern
development and are concentrated particularly in
Frankfurt am Main: today, Frankfurt is the only German
NICM AR
PROJECT REPORT
city with a skyline dominated by skyscrapers. One of the tallest buildings in the city is the
Messeturm built in 1991 with a height of 259 m, which is not much more than half the
height of the Sears Tower in Chicago, currently the tallest office and business tower in
North America with a total height of 443 m. It was the rapid growth in population that
originally promoted the construction of high-rise buildings.
New York once again provides a striking example: land became scarce well
over a hundred years ago as more and more European immigrants streamed into the city.
From roughly half a million in 1850, the citys population grew to 1.4 million by 1899.
More and more skyscrapers rose higher and higher on the solid ground in Manhattan, as
buildings could only be erected with great difficulty on the boggy land to the right and
left of the Hudson River and East River. In this way, New York demonstrated what was
meant by urban densification despite the considerable doubts originally voiced by
experts in conjunction with this development.
The first area development code to come into force in New York was the socalled zoning law of 1916, according to which the height of a building must not exceed
two and- a-half times the width of the road running alongside the building. The building
mass was further limited by the requirement that the floor space index must not exceed
twelve times the area of the site. Among other things, the zoning law stipulated that only
the first twelve floors of a building were allowed to occupy the full area of the site and
that all subsequent floors must then recede in zoned terraces a requirement of major
aesthetic signif icance, for this terraced form still dom inates the silhouette of Amer ican
skyscrapers today.
All doubts as to the profitability of high-r ise buildings were set aside with
completion of the Empire State Building, the Chrysler Building and other skyscrapers in
the 1930s, for they would never have been built if they could not have turned a prof it.
Although rentals proceeded slowly at first when the Empire State Building was
completed in the heart of the recession in the 1930s and it was therefore known as the
Empty State Building for many years, it subsequently generated satisfactory revenues
once all the premises had been let. Cities in Europe and Asia grew horizontally and it was
only when production and services acquired greater economic signif icance throughout the
world and the pr ice of land rose higher and higher in economic centers after the Second
World War that they also began to grow vertically.
Modern Hong Kong is a striking case in point: it encompasses an area of
1,037 km2 (Victoria, Kowloon and the New Territories), of which only one-quarter has
been developed, but with maximum density and impressive efficiency. Almost all the
new buildings, office towers and particularly residential towers in the New Territories
have more than thirty floors.
NICM AR
PROJECT REPORT
NICM AR
PROJECT REPORT
1.3.1.
The annual exponential growth rate of urban population during 1950s was
3.5 per cent. This was the highest the country had seen until that time and led to the
emergence of theories of over urbanization. Subsequently, this high growth rate has
been attributed to independence and partition of the country as also non-rigorous
identification of towns and cities in the 1951 Census. Formalization of the criteria for
identifying urban centres in the 1961 Census resulted in a dramatic decline in urban
growth figures in the following decade. The 1970s, however, following the same
methodology of urban population enumeration, saw a very high urban growth of 3.8 per
cent, fuelling speculation that India was on the verge of an urban explosion. Speculations
notwithstanding, the growth rate came down to 3.1 per cent in the 1980s. It has gone
down further to 2.7 per cent in the 1990s, which is the lowest in the post-independence
period. As a consequence, the percentage of population in urban areas has gone up
sluggishly from 17.3 in 1951 to 23.3 in 1981 and then to 27.78 in 2001. But, in terms of
population size, Indias urban population is vast. Moreover, population in large cities has
grown rapidly and this has led to serious infrastructural deficiencies in urban India.
1.3.2.
URBANIZATION PATTERN
NICM AR
PROJECT REPORT
10
over the decades in the last century. The massive increase in the percentage share of
urban population in class I cities from 26.0 in 1901 to 68.7 in 2001 has often been
attributed to faster growth of large cities, without taking into consideration the increase in
the number of these cities.
Undoubtedly, the faster demographic growth is an important factor
responsible for making the urban structure top-heavy. One can note that the class I cities
have experienced a distinctly higher growth rate than lower order towns except those in
class VI. Indeed, the latter do not fall in line with the general pattern of urban growth in
other size categories as they are governed by factors exogenous to the regional economy.
In the context of demographic dominance of urban scene by class I cities, it is important
to note that there were only 24 classes I cities in 1901 that have gone up to 393 in 2001.
While a number of lower order towns have graduated to class I category, the process of
rural settlements acquiring urban characteristics has been weak.
The pattern of growth has remained similar over time although there is a
general deceleration in urban growth in all size categories in the past two decades. Class I
cities have maintained an edge over class II, III, IV and class V towns in terms of the
growth rate (of common towns). The gap, however, seems to have widened during 1991
01. Class I cities in the country experienc ing higher population growth as compared to
other categories (except VI) is due to both aer ial expansion as well as in-migration. A
large number of satellite towns have emerged in the vicinity of these cities.
NICM AR
PROJECT REPORT
11
Many of these are becoming a part of the city agglomeration over time. There
are also outgrowths that have been treated as parts of the agglomeration by the Census.
Further, there has been expansion in the municipal boundar ies of the class I cities,
resulting in higher urban growth figures. The growth pattern of metro citiescities
having population of a million or morecorroborate further the thesis of concentrated
urban development. The demographic growth in metro cities has been higher than that of
common towns or even the class I cities in recent decades (Figure 2.5). The growth
would have been even higher but for the location of large industrial units outside the
municipal limits, thanks to the pressures exerted by the environment lobby. This is
facilitated by easy availability of land, access to unorganized labour market, besides
lesser awareness and less stringent implementation of environmental regulations in the
rural settlements at the urban per iphery. The poor are able to build shelters in these
degenerated peripher ies and f ind jobs in the industries located therein or commute to
the central city for work (Kundu 1989 and Kundu et al. 2002). The entrepreneurs,
engineers, executives, etc., associated with modern industries and business, however,
reside within the central city and travel to the periphery through rapid transport corridors.
This segmented structure of city growth, variants of which are emerging across
regions has brought the migrants to the rural peripheries in many large cities. While
demographic growth rates in the state capitals and Delhi have been at par with the 3.84
per cent growth in the million plus category of cities during 198191, the growth rates of
the former have declined substantially in the 1990s to 2.79 per cent only. It would be
important to enquire whether this is because of the strategy of structural adjustment,
NICM AR
PROJECT REPORT
12
expenditure control, fall in the infrastructure investments by the central and state
governments etc., which could have adversely, affect the growth of the capital cities.
PROJECT REPORT
13
NICM AR
PROJECT REPORT
14
PROJECT REPORT
15
All these factors together with increased liquidity in the real estate sector through
the international real estate funds and private equity funds will result in radically
transforming the real estate landscape over the next 3-5 years. India's investment scenario
is already undergoing a sea change and has been seen to be making roads in rural India
with telecom, rural retailing, agricultural supply chain and logistics facilities, microcredit, etc. All these factors foretell that the real estate growth will soon spread out of the
established boundaries.
However, to support this growth and to make it more expansive, a lot needs to be
done. Foremost is the thrust on infrastructure. According to a World Bank estimate, India
needs to invest an additional 3-4% of its GDP on infrastructure to sustain its current
levels of growth and to spread the benefits of growth more widely. Some positive steps
have already been taken in this direction. Huge investments in infrastructure to the tune
of $350 billion have been envisaged over the next five years. Connectivity may get a
boost with the completion of ~13,000 kms of roads under the Golden Quadrilateral,
North-South-East-West (NSEW) corridor and with 4-laning of all the major national
highways. This will further facilitate the economic development of smaller towns and
cities in the country.
Major real estate destinations of the country and some other emerging towns can be
classified into three broad categories depending upon the stage of real estate development
that each one of them is undergoing.
NICM AR
PROJECT REPORT
16
The sheer magnitude of the projects forces all planners to adopt a scale totally out
of proportion to all natural dimensions and particular ly to the people concerned
NICM AR
PROJECT REPORT
17
when planning their buildings. In the past, urban development plans were easily
drawn up on a scale of 1:100 or at most 1:200, a scale which could still be directly
related to the s ize of a human being. With todays high rise buildings, however, a
scale of at least 1:1000 is required simply in order to depict the building on paper.
This is illustrated by the example of the Sears Tower in Chicago: completed in
1974, the Tower measures 443 m in height. Drawn to a scale of 1:2000, a human
being is represented by a minute dot measuring barely 0.9 mm.
In the past, it was the master builder and architect who defined the construction
and consequently the appearance of a building; today, on the other hand, technical
developments determine what can and cannot be done; the appropriate and
basically essential symbiosis between engineer ing designer and artist has been
abandoned. This critical discourse on the architectural, urban development and
economic background is not basically to cast doubt on high-rise buildings as such,
but it does illum inate some of the facets that are central to considering the risk
potential inherent in high-r ise buildings. This almost inevitably raises the question
why high-rise buildings should have to be built in todays dimensions.
One reason is indisputably the need for a landmark. In other words, to express
economic and corporate power and domination in impressive visual terms. Nothing
has changed in this respect since the very first high-rise buildings were erected.
The steadily r ising pr ice of land in pr ime locations and an increasingly scarce
supply have made it essential to make optimum use of the air space. Prices in
excess of DM 50,000 per square metre are not uncommon for land in conurbations
and economic centres. Despite their height, however, high-rise buildings still
occupy areas of truly gigantic proportions: the ratio of height-to-base width of the
cubes in the 417-m-high World Trade Center.
However, high-rise buildings do little to prevent land being
sealed on a large scale. The suburbs of modern Amer ican cities are a prime example: as
far as the eye can see, the landscape is covered with single-family homes, swimming
pools and artif icially designed gardens simply to provide sufficient private residential
land for all the people working in a high-rise building occupying only a few thousand
square metres. Many of the techniques and materials which are also used for normal
buildings today would never have been invented and would never have become
established if high-rise construction had not presented a challenge in terms of technical
feasibility. Rationalized, automated sequences are beneficial to high-r ise buildings; at no
time in the past were such huge buildings erected in such a short space of time. Short
construction periods also mean shorter financing per iods and consequently profits which
NICM AR
PROJECT REPORT
18
partly compensate for the additional costs incurred in the construction and finishing of
the building.
3. Financing Models
Today, the first question when it comes to design is still how much does it
cost? High Rise as a sample of high tech is assumed to cost a fortune. Many towers
especially in Europe and Asia have been designed with cutting edge technologies and
pioneering des igns. The first cost on those high rise structures could be substantially
higher than conventional budgets, such as Commerzbank in Frankfurt, Germany designed
by Norman foster and the SOM design of Pearl River Tower in Guangzhou China. The
Guangzhou project cost over eight times the Chinese national average for high rise
projects of its type, that is, 8,181.8 RMB/ m! compared to 1,000 RMB/ m!
(95.05USD/SF).
Emerging Business Models
Real estate itself is a regulated activity and is subject to a number of FDI restrictions.
These restrictions essentially result in a market where foreign investors with no Indian
joint venture partner must invest a s ignif icant amount and undertake substantial
development schemes with a lim ited ability to repatriate the funds in the short term.
There is therefore a lim ited ability for a foreign company to make a tentative entry into
the market as a sole investor. This position has resulted in a number of business models
being used to facilitate investment.
Four main market entry strategies have been adopted by foreign real estate players in
India:
Large scale direct entry: With an independent approach for undertaking property
development schemes
Establishm ent of an umbrella property development joint venture with a local
player in order to carry out numerous future projects
Multiple joint venture approach where a number of ventures are entered into with
local partners each negotiated on a scheme by scheme basis and often with the
local player placing land into the venture as equity
Investment into the Indian property m arket through the creation of a capital
fund which in turn facilitates local developers.
Irrespective of the method of entering the market there are a large number of potential
market opportunities. Large and well publicised property development activity has taken
place in the principal areas of Delhi, Mumbai, Chennai and Bengaluru. In terms of
specific sectors of investment, housing remains the single largest new construction
activity whilst commercial office schemes, particularly for the IT sector have generated
signif icant opportunities. Organised retail although remains a relatively small sector by
NICM AR
PROJECT REPORT
19
the standards of most major economies, is growing rapidly and many industry observers
have further identified the hospitality sector as an area set for future expansion.
Investment Models
Real estate, being a capital intens ive sector, offers crossborder investors with several
investment opportunities. Post the sector opening up for FDI inflows have been typically
through multinational developers or financial institutions/ venture capitalists. Pure play
financial investors are placing their money through strategic investments in projects/
companies. The investment through financial investors comes primarily in the form of
opportunity funds, private equity and venture capital. Some of the prominent investment
models are as follows:
NICM AR
PROJECT REPORT
20
NICM AR
PROJECT REPORT
21
3.1. Cost-Benefit
A real estate market shift doesnt happen unless its profitable, and this shift
is no exception. A recent study completed by Lawrence Berkeley National Laboratory,
the most definitive cost-benefit analysis of buildings ever conducted, concluded that the
financial benefits of design are between $50 and $70 per square foot, more than 10 times
the additional cost associated with building. The large positive impact on employee
productivity and health gains suggests that green building has a cost-effective impact
beyond just the utility bill savings.
Buildings are generating a signif icant Return on Investment (ROI).
According to the McGraw-Hill 2006 Smart Market Report, High rise generates 3.5%
higher occupancy rates, 3% higher rent rates, an average increase of 7.5% in building
values, and it improves ROI by 6.6% on average. High r ise buildings are fetching
signif icant sales premiums. In Chicago, the John Buck Company spent US$270 million
constructing the LEED-Gold 51-story 111 South Wacker Drive tower in the citys Loop
market. Completed in late 2005 when the Loop market was struggling with an 18%
vacancy rate for Class A office space, the building leased up quickly to prestigious
tenants. In January 2006, 111 South Wacker Drive was sold to a German 25 investment
fund for US$386 million, a $116 million profit, or a total sale price of $401 per square
foot. Additionally, the buildings initial construction costs represent only 20-30 percent
of the buildings entire costs over its 30 to 40 year life (2030 Challenge, 2006), emphasis
should be placed on the life cycle costs of a public building rather than on solely its
initial capital costs.
3.2.1.
LEASING
NICM AR
PROJECT REPORT
22
3.2.2.
BOT
BOT stands for build, operate and transfer (there are other variations but
these will not be discussed in further detail here). In the case of this financing model, the
owner of the land places his land at the disposal of a contractor who then erects a
building on it, such as an office tower. The owner of the land can exert a certain influence
on the planning and intended use, but does not share in the construction costs.
The contractor must organize the projects financing himself, be it with own
funds or with the aid of loans (build). In return, the owner of the land waives all or
some of the income from occupancy of the building for a certain period of time, usually
25 years. During this time, the builder must obtain rents that are calculated to cover his
debt service and draw a profit from the invested capital (operate). The builders risk
with regard to rents and debt interest is often considerable. At the end of the agreed
occupancy period, both the land and the office tower become the property of the
landowner (transfer). There are differences between these financing models: although
the BOT model grants the landowner the right to ownership, he is for a long time
excluded from occupancy of the property. With the leasing model, the high capital
investment required is transferred to the lessor and the financing costs are replaced by
monthly payments akin to rent by the lessee.
3.2.3.
DEVELOPER
PROJECT REPORT
23
stage only exists on paper. Construction work begins when tenants or lessees have been
found. La Defense in the Paris Basin is a typical example of such a development. This
suburb was created on the drawing board in the 1950s. A dilapidated district was
demolished and completely redesigned. The traffic systems, such as Metro, urban
railway, motorway and access roads were moved below ground level and covered by a
concrete slab 1.2 km long. Mostly office towers were erected on this slab with open
squares and green areas in between. The ensemble is rounded off by the Grande Arche de
la Defense designed by the Danish architect Johann Otto von Spreckelsen and completed
in 1989. The Grande Arche is a huge cube which is open on two sides with 37 off ice
floors and a height of 110 m equal to its ground lengths.
All the capital invested on the site came from private sources and was
controlled by a public-law community of interests. In times of sluggish investment
activity, however, it is not uncommon to find that only certain parts of the master plan are
actually realized. Or iginally planned as a homogeneous townscape, the result is then
nothing more than an unrelated fragment and areas that should have been f illed with life
appear to be deserted and uninhabited instead. In the mid-nineties Londons Docklands
provided a dramatic example of such a development: the transformation of the West India
Docks built between 1802 and 1806 resulted in what was for a while the highest
mountain of debt in the world with the high-rise obelisk on Canary Wharf. After having
consumed roughly US$ 3bn, the half-finished project was temporarily abandoned before
finally being completed and let following a variety of financial transactions.
4. BARRIERS
4.1. Infrastructural Aspects
The different fates of La Defense and Canary Wharf are not (only) due to the
extremely different planning per iods of 30 years (La Defense) and 8 years (Canary
Wharf), but above all to the manner in which the necessary infrastructure for the two
projects was tackled. In the case of La Defense, the entire necessary infrastructure was
completed before the construction work actually started: underground railway lines and
roads, service systems were all planned and built beforehand. As a result, a fully
functional and above all adequately dimensioned infrastructure was consequently
available when the buildings were taken into service. This made La Defense attractive to
investors and tenants alike; the new district soon pulsated with life as an economically
sound basis for the entire project.
A jungle of political, economic and investment difficulties must be
overcome for such prospective planning because the owner of the high-rise complex
NICM AR
PROJECT REPORT
24
bears no direct responsibility for the large major ity of these far-reaching infrastructural
measures. The projects progress is consequently controlled by the municipal authorities,
as well as by supply and operating companies and not by the owner of the complex. The
situation of Canary Wharf in Londons Docklands is exactly the opposite and proves that
the La Defense type of planning is the economically more appropriate approach, despite
the associated delay in starting construction work and the longer prelim inary f inancing
required.
A second City of London was to be
created in the heart of the Docklands within the
shortest possible space of time, with thousands of
square metres of tailor-made office space, hotels,
shops and apartments for high-income tenants. A
rail-bound fully automatic cabin railway known as
the Docklands Light Railway was to ensure the
necessary access. However, this transport system
fell far short of meeting the requirements, as its
capacity was far too low and it lacked the essential
connection to the London Underground. The road
connections for private traffic and public buses were
similarly inadequate. This made the Docklands
unattractive to both commercial and private tenants.
An Underground link was finally built after
extensive planning and at the enormous cost of
roughly US$ 1.7bn; the road connections were
likewise improved at the cost of almost US$ 1bn. Only then did the precarious economic
situation of Canary Wharf improve. As these examples show, almost every high-rise
construction project is doomed to at least economic failure if the infrastructure is not
considered, planned and actually installed down to the very last detail.
PROJECT REPORT
25
overlooked that even the municipal authorities and the service companies are also
affected by the failure of a high-rise building and that its effects can be felt nationwide
or even worldwide in the worst case. This scenario not only applies to such total failure
as a major f ire or collapse of the building. Despite (or precisely because of) its size, a
high-rise building is an incredibly sensitive and vulnerable system. Even a brief power
failure can result in operational and economic chaos. The same applies to outside
disturbances in the form of strikes by public transport corporations or a malfunction in
the underground or urban railway system.
PROJECT REPORT
26
PROJECT REPORT
27
some adjacent areas remain permanently in the shade. Illuminated facades and large glass
fronts are a death trap for many birds. The people outs ide the high-rise buildings also
often have the feeling that they are being observed or threatened by the possibility of
falling objects. That fear is surely not entirely unfounded, for there have been cases in
which parts of buildings, such as glass panes, have been torn out of their anchorage by
strong winds and injured or even killed people on the street below. Our love-hate
relationship with high-rise buildings is finally also revealed in such recent box-office hits
from Hollywood as Deep Impact, Godzilla or Independence Day. It seems that
their directors simply cannot avoid the temptation of reducing one of New Yorks most
beautiful buildings the Chrysler Building to a smoulder ing heap of rubble with the
help of floods, monsters or meteorites. As a result, these skyscrapers more or less become
the real stars of the film on account of their magic attraction and immediate
recognizability.
NICM AR
PROJECT REPORT
28
BUILDING CO NSTRUCTION
USING
SUMMARY
High-rise buildings are commonly built in densely populated countries or urban
areas. A balanced floor construction cycle is critical for construction of the frame
structures. The objectives in scheduling the floor cycle are to ensure smooth flows of
resources and to optimise the use of formwork and other materials. The floor area is
usually divided into zones to allow the labour force and formwork materials moving
between zones. The preparation of the floor construction cycle would therefore be a
resources allocation exercise. However, the process is complex and difficult when it is
done manually. Floats are created deliberately in the schedule to ensure the balance in
resources and to provide buffers. Simulation that can demonstrate the real world
operations is an effective tool in handling this scheduling problem. This case study
examines the constraints in planning the f loor cycle and the effects of working period on
the overall schedule. Network based simulation model is used to investigate the
problems. It is noted that variations in working per iods have significant impacts on the
time schedule. A saving of 37.2% in time could be achieved when the working period is
extended by 20%. The findings indicate that simulation can be used to assist planners to
improve their decisions and decide the strategies in scheduling and reviewing the floor
construction schedule.
INTRODUCTIO N
High-rise buildings are still the essential form of building structure constructed
extensively in urban areas, in particular, in the hearth of the commercial zones of
metropolitan cities. On the other hand scarcity of land supply encourages the construction
of high-rise buildings.
In scheduling the f loor construction cycle, a simple approach is to adopt a constant
duration for the construction of the typical floors. However, this always induces a false
NICM AR
PROJECT REPORT
29
impression to s ite personnel that the construction processes are simple and could be
achieved easily. For the construction of high-rise buildings, site planning including
activity scheduling and site production layout has to be reviewed and re-plan from time to
time in practice as site conditions and resources are dynamic and uncertain. Although
Genetic Algor ithms and other AI techniques have been used by researchers in optimising
complex problems, practitioners are sceptical in applying these techniques with which
they are not fam iliar. This paper evaluates the scheduling of typical f loor construction
using network based simulation techniques, a more practical and easily apprehensible
approach, to improve decision making in site planning in response to the changing site
conditions.
TYPICAL FLOOR CO NS TRUCTION CYCLE
In the construction of a high-rise building, one of the planning objectives is to
ensure the early completion of the structural frames to generate floor areas for the
execution of finishing works, building services installation and internal f itting out. The
completion of the structural frames is therefore critical in the overall programme. For a
building of 42-storeys high, it may consist of 40 typical floors resting on two podium
floors. It is not surprised to have construction programme aiming at a 2-day or 4-day
cycle for the typical f loors. It would be a time-cost trade off problem in determ ining the
duration for a project in project-wise considerations or in selecting construction methods
for major construction activities. Planning engineers have to balance the resources inputs
and the duration for activities in order to ensure a smooth flow of work sequences in
meeting the project duration.
In minim izing the construction costs for constructing a reinforced concrete frame,
the formwork cost is one of the key concerns. It is well recognized that formwork is a
temporary work for forming moulds for wet concrete. The cost of formwork is highly
related to the number of re-use or re-cycling. It is a general assumption that a set of
formwork can be re-used for at least six to eight times and 100 times for timber and steel
form respectively. Steel formwork systems are prevailing in high-rise building
construction because of their durability, good concrete finish and environmental
sustainability.
However they are expensive unless the formwork system is designed to yield a high
number of reuse. Taking the above example, a set of formwork for 40 typical floors is
still uneconomical. Consequently, it has to subdivide the floor area into zones in order to
generate a high number of reuse. The subdivision of a floor into two or four zones will be
a feasible solution. It is obvious that dividing the floor into four zones would yield a high
number of re-use that is 160 times. The following example shows the arrangements of a
6-day floor cycle for a typical residential building block.
NICM AR
PROJECT REPORT
30
PROJECT REPORT
31
for a building block owing to both economic reasons and space availability. Therefore,
the crane can only serve one activity at one time and it is important to optim ise the usage
of a tower crane which is one of the critical resources in high-rise construction.
A Start and Stop node is assigned in the network for controlling the numbers of
simulation. During the simulation process, activity boxes are attached with a coloured
spinning icons showing their status. Resources shared by activities can be represented by
graphics moving between the activities boxes.
NICM AR
PROJECT REPORT
32
NICM AR
PROJECT REPORT
33
In order to generate realistic results, the duration assigned for the simulation has
taken into account the effects on hoisting times due to variations in hoisting height. For
example, the hoisting and fixing of eight precast faades takes about 51 minutes at the
lower floors and 75 minutes at the upper. Planners can adjust the duration if they identify
signif icant differences between the original input and the actual s ite conditions.
Alternatively, planners can carry out simple work study techniques on site to collect data
for predicting the hoisting time.
Apart from modifying the duration to suit the dynam ic site conditions, planning
engineers can review the effects of working hours for a working day to a f loor cycle.
Exam ining the standard floor cycle shown in Figure 1, it is evident that there are idling
times in the schedule. The idling tim es are created for levelling the resources. However,
manual resource levelling is complex and difficult and optimum solution cannot be easily
found. The numbers of working hours for a working day can be input as a constraint in
the simulation. In Hong Kong, most of the residential areas are densely populated and the
government has imposed stringent noise control ordinance to restrict the working hours
for using noisy construction plant and equipment. The normal working period to which
there is no restriction is between 7:00am and 7:00pm. On the other hand, the normal
working hours for the building industry lie between 8:00am and 6:00pm. Any time
beyond the normal working hours, the trade workers need to be paid with an overtime
allowance of 50% of their basic wages. It is vital to minimize the labour costs while
meeting the programme of the project. In this study, four working period scenarios have
been reviewed by using the simulation model. The summary of the simulation results is
shown in Table 2.
In the four scenarios, the first working period follows the industry normal working
hour and constant activity duration was used. The remaining scenarios have been tested
with stochastic activity duration. The simulation results confirm that the first scenario is
working approximately on a 6-day cycle. However, it is noted that there are signif icant
saving in time when the durations of activities are varied. In the second scenario, there is
NICM AR
PROJECT REPORT
34
a saving of 25.8% even the activities are scheduled within the normal working per iod.
However, when the working period is extended by one hour in the third scenario, further
decrease in time is minimal. In the last scenario, the working period is extended by two
hours; a further saving of 11.4% (a total saving of 37.2%) is yielded. It means that the
increase of the working hours by 20% is not effective since the labour costs will be
increased by 40%. This is a typical time-cost trade off problem when time is approaching
to the crash time solution.
SELECTIO N OF APPROPRIATE WORKING SCHEDULE
The simulations described above provide alternatives for planners to make
decisions on initial scheduling and subsequent updating. The simulation results enable
planners to locate the upper limit of the floor cycle, ie approaching to the crash time
solution. However, it is a general rule in planning that the normal time should be used in
the planning stage unless the project duration would have already been overrun. An
aggressive project manager may consider applying the second scenario in order to shorten
the frame construction by 62 days (ie. 40 x [ 6.0 4.45]) without spending overtime
payments. If the project is undergone delay, a more drastic decision will be to extend the
working period by two hours as if in the fourth scenario. Therefore, when deciding the
appropriate floor cycle duration, planners have to review the factors and the merits prior
to determine the strategies.
This case study examines the application of simulation techniques in evaluating
and scheduling the floor construction cycle of a high-rise building. The typical floor
construction cycle is always the main concern of planning engineers. The early
completion of the floor slabs releases working areas for the subsequent activities.
The initial planning and the subsequent re-scheduling are therefore important for
the successful management of a high-rise building project. The traditional schedule for a
typical floor aims at balancing the resources, in particular the formwork system, to assure
a steady movement of resources while maintaining the progress. Simulations for the floor
cycle using stochastic duration and different working period had been conducted in this
study. The simulation results generated show that the duration for the floor cycle could be
shortened by 25% to 37%. The shortening is achieved by reducing the idling time of the
resources. In deciding the duration of the floor cycle, planning engineers have to consider
the project budget because additional overtime costs for labour would be incurred. The
simulation results could provide useful information for planners to decide upon their
strategies in scheduling a typical floor construction cycle at different stages of the project.
NICM AR
PROJECT REPORT
35
NICM AR
PROJECT REPORT
36
NICM AR
PROJECT REPORT
37
NICM AR
PROJECT REPORT
38
7.1
7.2
7.3
The open space to be left between two blocks shall be equivalent to the open
space mentioned in Column.
7.4
It is permitted to transfer upto two metres of setback from one side to the
other side, which needs to be uniform at any given point, subject to
maintaining of minimum setback of 7 m on all sides.
7.5
8
8.1
8.2
8.3
Such type of high rise building may be allowed with the following open space
requirements:
9.1
At ground level : Minimum 9 metres alround open space for the first five
floors
9.2
At upper floors: increase of 1 metre alround open space or more, for every 5
upper floors or 15 m height or part thereof, over and above the ground level
open space of minimum 9 metres.
NICM AR
PROJECT REPORT
39
10
Provision of greenery:
10.1
In every high r ise building s ite, an organized open space which shall be
utilized as greenery, tot lot or soft landscaping, etc. shall be provided over
and above the mandatory open spaces to be left in and around the building.
This space shall be at least 10% of total site area and shall be a minimum
width of 3mts. This may be in one or more pockets and shall be open to sky.
10.2
In addition to the above, a minimum 2 metres wide green planting strip in
the periphery on all sides within the setbacks are required to be developed
and maintained with greenery and trees in all high rise building sites.
10.3
Rain water harvesting structures shall be provided in the prescribed manner
within the setbacks.
NICM AR
PROJECT REPORT
40
Such buildings shall be planned, designed and constructed to ensure fire and safety
requirements are met and maintained and shall comply in accordance with the Fire
Protection Requirements of National Building Code of India.
The facilities for providing fire protection and fire f ighting facilities in such
buildings shall be in compliance with the stipulations laid down and clearance
issued by the Fire Department from time to time. NOC from the Fire Department
shall be obtained from time to time regarding the f ire safety requirements and
facilities installed. The designs and installations regarding fire protection and
safety measures including exit requirements and smoke containment and smoke
management measures shall be undertaken through a fire engineer / fire consultant.
Compliance of the parking requirements shall be as given in these rules. The
parking facilities and vehicles driveways etc. shall be maintained to the satisfaction
of the sanctioning Authority.
Such buildings shall be provided with solar water heating system in the building
and solar lighting in the site for outdoor lighting, etc. and give a bank guarantee to
this effect to the sanctioning authority for compliance of the same.
All High-Rise buildings with covered area above 300 sq m shall be designed and
constructed to provide facilities to the physically handicapped persons as
prescribed in the National Building Code of India,2005.
In all buildings irrespective of above height provisions, the requirements of parts of
the building like size and area requirements of habitable rooms, kitchen, bathrooms
and Water closets, other areas, corridor and staircase widths, service ducts, etc.
shall conform to the provisions of the National Building Code of India,2005.
All environmental aspects like provision of Rain water harvesting structures,
greenery, solar heating and lighting systems and provisions of the Andhra Pradesh
Water, Land and Trees Act 2002 shall be complied in such of the sites and
Schemes where these are applicable.
Notwithstanding anything contained in these Rules or any other orders, the minimum
clear setback on the sides and rear sides of any high-rise building under any
circumstances and in cases where a concession or incentive is availed in terms of
setbacks shall not be less than 7 meters, and such minimum setback area shall be clear
without any obstructions including balcony projections, to facilitate movement of fire
fighting vehicles and for effective fire fighting operations.
NICM AR
PROJECT REPORT
41
NICM AR
PROJECT REPORT
42
In case of high r ise buildings parking space may be provided in the set back after
leaving a m inimum setback of 6 Mtrs alround the building to enable movement of
Fire Tender.
Alternate means of parking such as terrace parking, multi stage parking, parking
silos may be permitted, subject to production of NOCs from the Authorities (in
case of high rise buildings). In such cases, a clear height of 3.6 Meters in the
basement floor has to be provided, and the space to be earmarked per unit of Car
parking may be determined by the authority.
Parking in the upper floors can be allowed only if ramps are provided after leaving
the minimum setback line to reach such floors.
Ventilation shaft
For lighting and ventilating the space in water closets and bath rooms, when no
opening is provided towards any open spaces, they shall open on to the ventilating shaft,
the size of which shall not be less than as indicated below:
Exit requirements for high rise buildings, public and industrial buildings
Every building m eant for human occupancy shall be provided with exits sufficient
to permit safe escape of occupants, in case of fire or other emergency.
In every building for multi fam ily dwellings and all places of assembly, exits shall
comply with the minimum requirements of these bye-laws.
All exits shall be free of obstructions.
No building shall be altered so as to reduce the number, and size of exits to less
than that required.
Exits shall be c lear ly visible Routes to reach the exits shall be clearly m arked and
signs posted so as to guide the persons using each floor.
Wherever necessary, adequate and continuous illumination shall be provided for
exits.
NICM AR
PROJECT REPORT
43
Number of exits
The location, width and number of exits shall be in accordance with the travel
distance, capacity of exits and the population of building based on occupant load;
There shall not be less than 2 exits serving every floor for buildings of 15 mtrs
height and above and at least one of them shall be an internal stairway.
NICM AR
PROJECT REPORT
44
SAFETY IN HIGHRIS E
5.4 FIRE PROTECTIO N AND OPERATIONAL SECURITY
Many of the construction regulations
concern fire protection. There can be many
thousands of people in a high rise building at any
one time. If a fire breaks out, they must all be able
to leave the building in the shortest possible space
of time and without risk of injury. This is why
regulations concerning the number and execution
of escape routes and fire escapes, fire
compartments and the choice of materials must be
observed
Operational security encompasses
regulations governing the safety of elevators and
escalators, the execution of stairs, railings and
parapets or the installation of emergency lighting. Some regulations also include CO2
alarm systems for underground parking lots; indeed, there are even regulations governing
the non-slip nature of floor coverings in traffic areas, sanitary rooms and kitchens.
PROJECT REPORT
45
specified by the regulations in order to ensure that the building will withstand windstorms
or earthquakes up to certain load lim its. At the same time, this will serve to rule out the
risk of bodily injury due to falling parts of the building, especially parts of the facade.
5.4.1.3 SOCIAL ASPECTS
SURRO UNDI NGS
AND
PRO TECTION
OF
THE
NICM AR
PROJECT REPORT
46
PROJECT REPORT
47
drive for var ious operations listed above using s imple squirrel cage motors. This
transforms the standardized three phase supply network into a net with variable voltage
and frequency. This means the motor can continuously absorb every revolution, working
to full capacity even in the part load operational range. The crane can be positioned
smoothly and accurately. Hoisting speeds are increased and with that turnover capacity.
The motor does not require high starting current which to certain extent reduces the
consumption of energy.
A recent milestone is the operational add-on module of radio transmission of
machine data. This makes constant on line monitoring and evaluation of the crane data
possible and allows for fast diagnosis and trouble shooting in the case of breakdowns.
Flat top tower cranes
The first trolley jib crane with a compact top was introduced in the Nineties. This
is an advantage when several cranes are swivelling on-site at the same time and when
height restriction applies, for example airports. While there are advantages of lesser space
requirements, problem includes the necessity for erection of full jib in one operation and
consequent requirement of space and higher capacity crane required for erection.
Tower crane Brief Description
Tower crane is the only type of crane specially des igned for buildings and other
high rise structures. They can distribute material for whole plan area of a tall structure.
Tower cranes can be fitted with a derricking jib or horizontal jib with traversing trolley.
A derricking jib is necessary if required to be raised to clear obstructions. A horizontal jib
is easier to operate, is faster and has lower power consumption.
Tower cranes can be rail mounted but require properly laid level track; the travel is also
electrically operated. Other options include f ixed base tower crane or climbing tower
cranes when attached in the height to the frame work of the building. In such cases the
designer of the building should permit attachment with resultant loads, at appropriate
points. With winches of higher capacity, the maximum height of the attached crane can
be increased.
Site conditions regulate the height of the unattached crane depending upon
exposure to high winds etc. The fixed base may involve substantial area and depth of
concrete. Cabins are usually on top of the mast and jib slews either with the mast or
around the mast. Control is usually by the operator; remote control is also possible. The
cranes are usually electrically operated.
Climbing Cranes
The mast climbs with the building being erected. The maximum height to which
these can be used is dependent only on site condition where wind pressures can seriously
affect the load and the type of load handled. A world record has been created during the
NICM AR
PROJECT REPORT
48
construction of the tallest building in the World (Bur j Dubai); climbing tower cranes have
been used for building height of more than 600m. the design of the building is an
important element in the economics and efficient use of climbing cranes. Such cranes can
be located in lift shafts and service wells. The permanent structure must be sufficiently
strong for the crane reaction. The control of the climbing crane is usually remote.
Choosing the correct type of crane
Tower cranes feature a high maneuverability, a large space below the crane and
high arrangement of the boom which can pass over the erected structures.
The type and number of cranes to be used will depend on the plan, size and shape
and the height of the building and the access spaces around it. Where the tower crane is
located outside a high r ise structure, it has to be often tied to the structure at intervals to
stabilize the mast. The structure assists in taking up the reaction at a certain points, in
which case the structure has to be designed for the stresses generated by the anchors.
Mobile tower cranes are subdivided with respect to their running gear into rail mounted,
truck, wheeled, and crawler cranes. Most widely are rail mounted cranes, they are simple
in service and ensure a high safety.
Cranes employed in construction have a lifting capacity of 3 to 25 tonnes and a
maximum swingning radius is 90m. separate motors are used for hoisting, travelling,
luffing, traversing etc. Stationery Cranes are mounted on a foundation and they serve the
construction site from one point. Climbing tower cranes are usually common in the
construction of multi storied and high rise buildings.
Where access around the site is restricted, a tower cranes might be used internally
by leaving out the floor panels or making use of the lift shaft or stair well. Thus it is
possible to poperate from a more central point in the structure and makes most use of its
reach. Alternatively, a c limbing crane may be more economical. A disadvantage when
the lift shaft is used is that the lift installation is delayed pending removal of the crane.
However, it is possible to construct the lift lining and assemble from the bottom up,
following the passage of the crane.
Avoid Scaffolding
For maximum speed and economy, where the cranes are installed, the use of
scaffolding should be avoided as far as possible and external elevational work shall be
kept to a minimum. In such a case pre glazed windows and designed c ladding panels or
proprietary curtain walling which can be fixed from inside, can be used. Many cantilever
units, stairs or intricately shaped concrete items are best pre-cast.
Tower cranes and plan shape of building
Internal or fixed external tower cranes are suitable for square and Y or star
shaped plan buildings. For long and narrow buildings, a rail mounted travelling crane
NICM AR
PROJECT REPORT
49
may be used. For cluster of low raised buildings, a tyre mounted self erecting tower crane
is most appropriate. Such cranes are light in weight, with a generator mounted on base
frame. The erection as well as holding up is computer controlled and takes less than one
hour. Such self erecting tower cranes are available with mast height up to 25m and jib
length of about 30m.
Erection and commissioning a tower crane
A specialist group with knowledge of erection and commissioning the tower crane
should be employed in order to optimize the operation. The fountains, where required,
should be cast in advance after obtaining the drawings from the manufacturer. Using a
crew with optimized training, the erection and commissioning of a typical tower crane
should be completed within three days. In the absence of trained crew and management,
it may take up to one or two weeks to erect and commission the centre. A mobile crane is
required to assist in erection of a various components of the tower crane. For tower
cranes of large capacities, a 100t. capacity mobile has been used.
Rail track
Proper performance of the crane is dictated by the state of the rail track. The gauge
and specification for the rails are normally provided by the tower crane manufacturer.
Concrete sleepers are normally used. The maintenance of the rail track during the service
of the tower crane similar to that of a rail line passing high speed trains.
Control and Safety Devices
To ensure safe operation and better use of cranes, they are fitted with safety and control
devices and instruments.
Anemometres
Pressure due to high winds may force the crane to derail or collapse. Wind pressure
is determinted with anemometers where a crane operator ca n read the wind velocity.
Cranes are safe to operate in wind velocities up to 40 Km per hour. PLC devices assist in
automatically shutting down the crane when the wind velocity is exceeded.
Lim it switches are used in cranes to limit the hoisting height. Safety to restrict the cane
travel. Swinging radius indicator is secured on the jib. The scale can be graduated to
indicate not only the jib radius, but also the safe loads that can be handled at the given
radius.
Components of a typical tower crane
The various components are indicated in the fig.1. The major components are : the
mast, the jib, the trolleys, hoisting, s lewing, luff ing and lowering mechanisms. The mast
is in sections, convenient to handle during erection and dismantling (usually 3 to 6
NICM AR
PROJECT REPORT
50
metres). Sections are connected by pin or bolted joints. Special torque wrenches are
required in the case of bolted joints and are usually supplied along with the crane.
Erection and Dismantling of tower crane
These are specialized activities and are required expert guidance. In particular, the
method of dismantling the tower crane from the top of the high r ise structure requires
careful planning and tools. This is usually planned by the supplier of the crane who also
provides the necessary fixtures for dismantling purposes. The intermittent anchoring
systems by guy ropes for very tall structures are also carefully designed by manufactures.
The designer of the permanent structure should interact with the manufacturer and ensure
that the permanent structure is not taxed beyond its designed stress limits. Sometimes it
may be necessary to locally strengthen the structure around the anchorages by additional
reinforcement, higher grade of concrete etc. so that the construction speed is not
compromised.
Safety in Erection, Commissioning, Use and Dismantling Tower Cranes
The first requirement is to have qualif ied, trained and exper ienced operator. Indian
project sites do not give adequate attention to this aspect, resulting in inefficient
operations, avoidable accidents, work-down time, causalities etc. the operator should
have adequate language skills for reading the operation manuals and following them.
Minimum qualif ication should be at least ITI certificate. It is paradoxical that in real life
situation, the contractor spends a few crores on purchase of tower crane and selects an
th
unqualif ied operator, who had not even passed 8 standard!
Some of the ITI certificate holders may also not be proficient in English; it is
desirable that the operations manuals are printed in the local language in addition to
English. If this service is not provided by the equipment manufactures (normally they
should provide), the end user should get the translation done in one or two prominent
languages and provide the copies to the operators.
The tower crane operators must have read the operations instructions in particular,
the chapters concerning safety. The personnel must wear safety clothing/ protective
equipment during maintenance/ repair work. They should not wear loose and long hair,
loose clothing, jewellery etc.
Repairs and adjustments must be made only by qualif ied and trained m echanics.
No modifications shall be allowed to be made without the consent of the manufacturer.
The rail track should invariably on concrete foundations and not on timer sleepers. The
rail track foundation details should be obtained from the manufacturer. While not in use
the boqie should be locked to the rail and the jibs should be free to rotate. The hook
should be raised and locked to the jib trolley. The tower crane should not be operated
during high winds with speed exceeding 40 Km. per hour. The crane should not be
travelled with load. The jib should not be slewed by more than 360 Degrees.
NICM AR
PROJECT REPORT
51
While traversing, the lim it switches should restrict movement of trolleys to within
the operating range of the jib with automatic slow down at both ends of jibs. Lim it
switches should control the hook movement so that the hook dose not hit the ground or
the jib. S imilar ly lim it should be used for slewing a maximum of 360 Degrees with
automatic slow down at the end of the movements.
Var ious electronic lim it switches are provided as standard fittings to the tower crane:
Hoist limit switch
Slewing lim iter
Trolley lim it switch
Travelling limit switch
Load limiters
Moment cut out
High speed and maximum safe working load cut outs
Var ious
audio warning and indicator lights are provided in the operators cabin
On Power indicates crane is energized
On indicates crane in service
Load and dynamic moment indicates load and dynamic moment achieved
Fault Hoist indicates malfunctioning of the hoist winch
Fault slewing indicates malfunctioning of slewing
Fault trolley indicates malfunctioning of the trolley winch
Hoist limit Switch avoids possible driving errors. It allows to stop the hoisting
motion as soon as the pulley block comes near the jib trolley. When lowering, it
forbids the rope to unwind completely and wind up onto the drum in the reverse
direction.
Trolley Lim it Switch avoid possible driving error by stopping the trolley motion
before reaching the stops at the jib foot and jib nose.
Track
Use slightly worn rail for good bearing surface. Rails should be absolutely parallel
and well bedded down on a solid base. Tracks should be earthed. It should be perfectly
straight, unless otherwise designed. Use same type of rail throughout.
Fit rail stops at least 1m before end
A travel lim it switch
A spring stop (buffer)
A fixed stop, welded to the rail
NICM AR
PROJECT REPORT
52
Counterweight (Ballast)
Base: Reinforcement concrete blocks. The reinforcement and hooks for hoisting
and hanging the blocks should be designed for safety. Paint the weights on the side of
blocks.
Erection- Safety
Do not work with overload
Use slings in good condition
Erect in the order indicated
Fit the counter jib & jib parallel to the track
Fit rail clamp & wedges on rails
Exam ine pins. Some are made to manual.
Telescoping operations according to manual.
During rais ing, DO NOT- slew the jib, move the trolley or carry out any
hoisting/ lowering
Telescoping only if wind speed < 40 Km/Hr.
Safety during Operation
Check loads to be lifted/ working heights, permissible wind speeds, loads with
more than 1 sq.m. /ton, surface area exposed to wind. When several cranes are working
close together the distance between two cranes must be at least 2m longer than the lowest
jib likely to meet the mast of the other machine. Alternatively anti collision devices must
be used.
FORMWORK FOR HIGHRISE CONS TRUCTIO N
SLIP FORMS
Slip forming was introduced into Australia around 1952, mostly for silo
construction. It has been in use overseas much longer. A slip form is made so that it can
move slowly whilst being continually kept full of concrete. The form is not deep and it
moves so that concrete is not in the form for long. The concrete is left behind by the form
when it is just strong enough to support itself.
Typically, the concrete stays in a vertical s lip form for 1.5 - 6 hours. In horizontal
slip forming, as in forming the kerb of a roadside, the concrete can be exposed sooner.
Because the form is continually filled it produces jointless concrete. That's useful for
construction of containers, such as water tanks, silos, cooling towers and reactor shields
where breaks in the concrete must be avoided. It is also used in the construction of tall
structures such as lift wells, where the surface needs few spaces or protrusions.
It has been used for many years in the construction of tall buildings which have flat
walls and the same dimensions all the way up It is also very good for circular structures
NICM AR
PROJECT REPORT
53
which have changing dimensions, such as cooling towers because the size of the form can
be changed as it moves. The height of a vertical slip form can range from about 1 m to 2
m with the most common size being 1.2 m tall. The surrounding supporting structure and
work platforms add to the size of the structure. A schematic diagram of a vertical slip
form is shown below.
Slip forming is suitable for round the clock pouring and so structures can be built quite
quickly. Typically, slip forms rise at about 30 cm per hour, allowing a tall structure to be
built in days. Horizontal slip forms, such as in those used for forming of water or road
surfaces, move along more quickly. Hundreds of metres, even kilometres per day and can
be achieved.
NICM AR
PROJECT REPORT
54
NICM AR
PROJECT REPORT
55
The height of the form will depend on the temperature, the type of concrete used and its
hardening rate. In cold climates, a taller form is used which allows the concrete to be in
the form longer, allowing it to harden. Slip forms can be made from proprietary panels if
the job is a standard one where such panels can be used. It can also be designed to
become bigger or smaller as it rises producing a bigger or smaller structure.
CALCULATI NG MATERIAL QUANTI TIES
The most important calculation in the design of slip forms is the length of time the
concrete needs to be in the formwork. When you know that, the rate of rise can be
adjusted to suit.
The time (T) that the concrete spends in the slip form is calculated from the formula:
T = [D - (F + t + t' + L)] / R
NICM AR
PROJECT REPORT
56
NICM AR
PROJECT REPORT
57
CONSTRUCTION TECHNIQUES:
Core Wall Survey Control System for High Rise Buildings.
In recent years there has been considerable interest in the construction of super
high-rise buildings. From the prior art, various procedures and devices for surveys during
and after the phase of erection of a high-rise building are known. High-rise buildings are
subject to strong external tilt effects caused, for instance, by wind pressures, unilateral
thermal effects by exposure to sunlight, and unilateral loads. Such effects are a particular
challenge in the phase of construction of a high-rise building, inasmuch as the high-rise
building under construction is also subject to tilt effects, and will at least temporarily lose
its as a rule exactly vertical alignment. Yet construction should progress in such a
way that the building is aligned as planned, and particularly so in the vertical, when
returning into an un-tilted basic state.
It is essential that a straight element be constructed that theoretically, even when
moving around its design centre point due to varying loads, would have an exactly
vertical alignment when all bias ing conditions are neutralised. Because of differential raft
settlement, differential concrete shortening, and construction tolerances, this ideal
situation will rarely be achieved.
For this reason a regular matching of the reference system is required for surveys during
the construction phase of a high-rise building once this has attained a certain height or a
certain ratio of height to cross section.
Up to now, surveying on high-rise buildings is done by geodetic electro-optical
total stations yielding non-contact optical measurements of the points to be surveyed,
these instruments periodically being referenced to fixed external reference points with
known coordinates. The precision of the entire surveying procedure depends on the
reference points serving as fixed points for the total station; therefore, points are selected
for which absolute constancy of the position is guaranteed. Pr imarily points close to
ground are suitable that are not subject to influences producing shifts. However,
increasing construction heights, possibly aggravated by densely built-up surroundings,
give rise to difficulties in the use of ground-level fixed points, inasmuch as the distance
between the total station installed on the uppermost construction level of the high-rise
building and the reference points becomes excessive for exact referencing of the total
station while the relative distances between the fixed points become too small,
particular ly so in heavily developed zones.
Beyond a certain threshold height, it becomes altogether impossible to use groundlevel reference points. Particularly in the Far East, demand increases for high-rise
buildings having heights beyond this threshold and a ratio of height to cross section that
gives rise to strong tilt and sway of the building. The strong movements of the structure
create a number of problems for the correct design of controls. It will be essential at any
NICM AR
PROJECT REPORT
58
particular instant in time to exactly know how much the building is off from its design
position, and at the same time to know the precise position of the total station. The
situation is further complicated by vibrations in the building due to the construction work
and by movements of the building making it very difficult, if not impossible, to keep
instruments levelled.
This presentation describes a procedure developed by Leica Geosystems using
GPS observations combined with a precision inclination sensor to provide reliable
coordinated points at the top of the worldwide highest-rise building under construction in
Dubai.
INTRODUCTIO N
Overview
The Burj Dubai tower in Dubai, UAE, will rise to a height of over 800m when
complete in 2008. In addition to being very tall it is also quite slender and it is anticipated
that there will be movement of the building at upper levels due to wind loads, crane
loads, construction sequence and other factors. The self climbing formwork system for
the building is complex, due to the shape of the structure and requires a large number of
control points. It has been necessary to develop a survey system that can efficiently
provide the large number of control points and can be used when the building is moving.
An analysis of predicted movements has been completed and a system installed which
delivers accurate positioning for construction set out at the top level of the formwork.
Lim ited results are available to date but monitoring indicates that the required accuracy is
being achieved.
Building Movements
The various components resulting in the displacement and motion of the structure can be
divided in to three groups.
Long Period Movements
These components may cause movement in the tower in a period of from one week
to 6 months.
Uneven Raft Settlement: As the load on the raft foundation increases it will
continue to settle and if the settlement is uneven this will cause a corresponding tilt
in the tower structure.
Raft Deformation: Due to the greater load at the centre of the tower the raft
foundation will deform as construction progresses and this deformation may affect
the verticality of the structure.
NICM AR
PROJECT REPORT
59
NICM AR
PROJECT REPORT
60
on the tower will cause it to move from the theoretical vertical axis and the natural
building resonance will cause it to oscillate about this offset position. The survey
system had to be designed to tolerate this movement and allow construction to
proceed in a continuation of the alignment of the previous levels.
Form work System
The formwork for each concrete pour is comprised of a series of individual forms
which all require control. This has resulted in 240 control points for the formwork system
for each level. It was not practical or safe to use the traditional method of plumbing up
through floor penetrations and at the beginning of the project it was decided to use
resection as the primary procedure for survey control.
Initial Surveys
At contract commencement six permanent bench marks were established around
the site and precisely surveyed. These marks consisted of a concrete encased steel I
beam extending down to about 15m below ground level. A cap was cast at the top to
provide a solid work platform. These marks were used for all the initial set out surveys
and as a base for the monitoring work.
Lower Levels
Due to the large number of control points required for the formwork it was
necessary to develop a method so that the control was only measured once. The only
solid part of the building is the concrete and the technique sets marks in the top surface of
the newly cast concrete.
A total station instrument is also set up on the concrete and position established by
resection to the external bench marks. The marks set in the top surface are measured by
radiation from this resected control position and the precise coordinates for each mark
calculated. When the formwork is raised to the next level the marks are offset onto the
main working deck of the formwork which is tied in to the concrete at that position. The
back of the shutters can then be positioned from these marks. From ground to about Level
20 resection was possible from the external control marks which were distant about 100
to 150 m from the base of the tower. Observation redundancy was possible and very high
quality results were achieved. Verticality observations confirmed that the tower was not
moving and raft foundation measurements indicated there was no differential settlement
to cause the tower to tilt. Hence it was a straight forward surveying task to set out control
for the formwork using this method.
Upper Levels
As the building r ises it will come under the influence of various forces as described
in 1.2 above and will start to move by varying amounts and sometimes in random
NICM AR
PROJECT REPORT
61
directions. Above Level 20 it became increasingly difficult to sight the external control
on site due to obstruction from the upper decks of the formwork system. In Dubai the
nearest tall, stable, buildings were over 500m distant from the site and could not be used
because of potential vis ibility problems and poor geometry.
At this stage it became necessary to implement a new method of resection and a
measurement system that could tolerate building movement. It was also necessary to
install a means of measuring the building movement to ultimately identify any long term,
permanent movement of the tower in a particular direction which might need to be
counteracted.
CORE WALL SURVEY SYSTEM
The movement of the structure creates several problems for precise survey; at a
particular instant in time, theoretically, you need to know exactly how much the design
centre line of the building is offset from the vertical axis and at that same instant you
need to know the precise coordinates of the instrument. However a mean position taken
over a short period for both elements can provide a suitable solution.
Instrument Position Determination
GPS operating in static mode are being used to
establish survey control at the upper levels. The
system comprises a minimum of 3 GPS antenna/
receivers mounted on tall f ixed poles at the top
level of the formwork.
A tiltable circular prism is placed below
each antenna and a Total Station instrument
(TPS) is set up on the concrete visible to all GPS
stations. The GPS plus TPS comprises a
measurement system. In static GPS mode,
satellite signal data is received and recorded for a
period of up to 1 hour. During this same period of
time, the TPS instrument is used to measure a
series of angles and distances to the prisms
mounted below the GPS antennas. The TPS then
measures to the reference marks placed on fresh
concrete which are the reference points for
control of the formwork as described in 1.4.1.
After completion of observations, data is returned
to the office for processing. Computation of GPS
NICM AR
PROJECT REPORT
62
antenna positions is carried out, processed against data from a Continuous ly Operating
GPS Reference Station Leica GPS GRX1200 Pro with AT504 chokering antenna and
Leica GPS Spider software, using Leica Geo Office software (LGO).
Computation of TPS position is then carried out actually as a least squares
resection. Finally transformation is performed of the 3 no WGS84 antenna coordinates
and resected TPS coordinates into the local coordinate system and from this a
determination of coordinates of all measured reference marks is made. These steps yield
coordinates of survey instrumentation and reference marks in the site project coordinates.
A total station, or more generally any theodolite, can be considered as a dual axis system
supporting the line of sight of a transit/telescope. For reducing the effect of the
mechanical misalignments on the observations, classical operational procedures have
been applied since the first use of such instruments.
Today, a total station can take these axis misalignm ents into account using an
inbuilt dual axis compensator and special f irmware to correct the resulting error in the
measurements. However, the operational range of the compensators is restricted,
typically to about six m inutes of arc. The operator aligns the main axis coarsely by
keeping the bubble of the station inside the graduation. In case of a compensator out of
range signal, the station must be realigned manually.
This procedure known by experienced operators as simply inappropr iate when
operating a total station in this case when we expect dynamic behaviour and overal as we
the building main axis will not be aligned with the direction of local gravity To remove
that restriction it will be necessary to consider this instrument as a local 3D axis system.
The coordinates computed by using the observations (directions and distance) are
internally consistent but must be transformed into the reference frame defined by the set
of GPS antennas. In our case as we use a single total station, the problem is simply a 3D
transformation also known as similar ity transformation or Helmert transformation.
NICM AR
PROJECT REPORT
63
Continuous, real-time measurements of structure tilt can be logged for each instrument
floor, and data output as X and Y components of building alignment from the vertical.
Amplitude peaks of smoothed data represent structure oscillations.
NICM AR
PROJECT REPORT
64
The mean displacement of the regression line represents total mean displacement
of the structure. A block of data corresponding to the GPS observation data will be used
for this purpose. Differentiation of the tiltmeter data at different heights will allow
correction for nonlinear structure tilt.
Core Wall Survey System
The GPS Reference Station, the GPS receivers and antennas with circular prism,
the Total Station are combined with the precise clinometers network as shown below
composed the 4 measuring sub-elements of the complete data fusion system.
PRECISION
An examination of the likely errors in the
CWSS indicates that it will be possible to
continue to set out the formwork along the
vertical alignment of the structure to a precision
of 15mm. It should also be possible to identify
any long term movement of the tower that has a
value of >20mm in any given direction.
ANALYSIS
Monitor ing
surveys
will
provide
information on raft foundation settlement and
deformation and this can be used to accurately
determine the offset of the tower at a particular
level due to the inf luence of these factors.
Similarly surveys to measure the differential
shrinkage and creep in the core walls and
columns can be used to derive this possible
component of tower movement.
A dynamic model of the building has been
developed and from this it has been possible to
derive values at any given level for the effects of
construction sequence, building design and solar
effects. For the period of the control survey if the
tower cranes are shut down then the only
remaining unknown component of building
movement is that due to wind.
Weather stations are to be established at
three locations on the tower and these will stream
NICM AR
PROJECT REPORT
65
continuous data on temperature, wind speed and direction. This can be correlated with the
tilt meter data to determine a relationship. It is anticipated that this analys is will reveal
any long term movements in a given direction and if necessary corrective action can be
taken. The Nivel200 Network segment of this system can be used for tower monitor ing,
both during construction and after completion of the structure. If this is integrated with
other monitoring information it will provide a complete system of structure monitoring.
A combination of GPS survey techniques, Automatic Total Station, clinometers
readings and mathematical modelling will provide a means to drive the construction of
the worlds tallest building as a straight structural elem ent and provided a wealth of data
on building movement. Its only the start of a long journey up to the final completion of
the Bur j Dubai tower and the authors know that they will have to complement the
existing data fusion system with other elements the time being.
NICM AR
PROJECT REPORT
66
High cement content is costly, generates high heat of hydration and leads to more
cracking and shrinkage. Hence, high grade cement (G43,G53) are effectively used to
produce high grade concrete.
For the same cement content as that of G33, we can produce high strength concrete
which can be used to produce sleek and elegant structures. Alternately, by using lower
cement quantity we can produce concrete of same strength. Since there is not much
difference in the cost of G33 and G43/G53 cements, savings in cement is the direct
saving in cost of construction.
Comparative studies carried out on concrete using G33 and higher grades of
cement show that the use of high strength cement results if following savings.
I. In the cost of cement
20-30%
II. In the cost of steel
5-10%
III. In the cost of shuttering
5%
High grade cements produce more durable(less permeable) concrete. High ear ly
strength enables the shuttering to be removed earlier and thus speeds up construction.
2. Reinforcement
In RCC, reinforcement accounts for 30-40% of the total cost of construction per
m3 of concrete. Use of high grade steel substantially reduces this cost. For eg. In case
of doubly reinforced beam, use of Fe500 results in reinforcement savings of 44-47%
over mild steel (Fe250) and 14-15% over Fe415 in terms of weight and 35-37% over
mild steel and 6-8% over Fe415 in terms of cost.
3. Advantages of using high grade materials
I. Sleeker and elegant structures, giving more f lexibility in generating the
design concept.
II. Earlier hardening and high ear ly strength speeds up the construction process.
Scaffolding can be removed in just 7-10 days instead of the usual 15-21 days
hence centring cost is considerably reduced.
III. Use of high grade cement to produce high grade concrete reduces the section
and consumption of steel .
IV. Buildings can be designed with smaller sections to meet the same function
and to take the same load. This result in mater ial saving and increase in the
useful carpet area.
V. As result of lesser cement consumption in concrete, G53 grade gives low
heat of hydration, giving crack free mortar and concrete.
VI. Saves cement consumption.
Sr. Item
Cement
Cement %
%
no.
G43
G53
Saving
Saving
NICM AR
PROJECT REPORT
67
in
Material
in Cost
28.5
13.8
26.0
10.8
13.8
10.8
1:1.5:3
1:5:10
1:2.5:4.
5
1:2.5:4.
5
1:2:4
18.75
15.8
1:4
1:6
25
22
1:6
1:6
1:4
1:4
of cement
1:8
1:8
1:6
1:6
33
21
30
25
20
18.5
27
22
Concrete
1
Foundation
2
Footing
1:4:8
1:2:4
1:2:4
Columns/slabs/be
ams
4
Water tanks
Mortar
1
Flooring
/Tilework
2
Br ickwork
3
Internal Plaster
4
External P laster
5
Ceiling Plaster
Table (1) : Savings for various types
NICM AR
PROJECT REPORT
68
products lead to appreciable economy in consumption of cement and steel due to their
lightweight and high strength to weight ratio. Aerated concrete products are ideally suited
for walling blocks.
Flyash lightweight aggregate is suitable for use in produation of structural light weight
concrete and precast lightweight concrete buildings units.
1. Calc ium silicate bricks
Production of calcium silicate br icks requires 30% less energy as compared to
traditional bricks. They reduce the cost of construction by around 40%. Less mortar is
required as compared to conventional clay br icks. Lesser wall thickness are obtained
giving more carpet area.
2. Cellular concrete blocks
They are lighter than clay bricks by around 40-45% and possess technical
advantages such as better strength to weight ratio, low thermal conductivity, better sound
insulation and resistance to fire and water seepage.
There are appreciable savings in wall thickness and foundation cost. Plaster can be
completely avoided. From considerations of transportation, within a radius of 40km from
the plant site, cellular concrete blocks are cheaper by 10-15% are compared to traditional
bricks.
Their density is almost one-fourth of concrete and one-third of bricks, leading to
reduced dead load and savings in cement and steel. They are easy to handle, transport and
hoist, therefore are suitable in low bearing soils and in seismic zones.
3. Clay flyash aggregate concrete
These are lighter and easy to transport. Clay flyash bricks have low thermal
conductivity therefore have better insulation properties.
4. Sintered flyash aggregate concrete
This lead to a lower bulk density of concrete, resulting in a reduction of dead
weight of buildings by 30-40%. There is a corresponding reduction of 20-22% in the cost
of steel as well as the cost of steel as well as the cost of foundation.
This concrete has better thermal and acoustical properties. It is more resistant to fire and
earthquake hazards. It gives more living space for the same plinth. Precast units can be
speed up the construction process.
Polymer Concrete
Polymer addictives such as powdered emulsions and water soluble polymers
produce a concrete of higher tensile and flexural strength. It has much higher ductility
and elasticity. Polymer concrete is highly res istant to chemical attack, abrasion and
NICM AR
PROJECT REPORT
69
cavitation. Polymer concrete has good bond strength, low permeability and its hardens
rapidly. Polymer impregnated concrete is used for precast wall panels. It enhances
durability of concrete and increases its strength by as much as five times.
Ferrocement
Precast units ferrocement produce light and thin structures, resulting in
considerable savings in formwork and costs. Ferrocement encased RCC columns were
cast and tested for direct compression ta the Government college of Engineering Pune.
These columns carried same load as RCC columns and saved the cost of formwork. The
ferrocement casing acted as inbuilt formwork.
A ground plus one structure has been constructed using only ferrocement precast chajjas,
doors, walling units, staircase are widely used in Pune for various constructions.
Insulating Material
Fibreboards and gypsum plaster boards are light and fire resistant. These are
available in various dimensions. In particular they are used for false ceilings, lightweight
partitions and insulation walls. Phenotherm and decofoam are fire resistant insulation
forms. They have exceptionally low thermal conductivity and low water absorption.
Wonder wood
This precast concrete with wood like grains is used for frames for doors and
windows. It is highly economical compared to wood, steel aluminium, FRP or any other
comparable material used for frames. These high strength and load bearing members
elim inate the need for casting lintel.
Precast Units
Precast units elim inate costly shuttering. Furthermore, since the units are made
under factory conditions, there is greater quality control. Hence, uniform units of high
quality and strength can be obtained.
Precast units require less labour and can be erected faster. Therefore, construction
can be speeded up. Shrinkage cracks are elim inated, which avoids the corrosion of
reinforcement and makes the structure more durable. Precast unit construction is
statically determinate. Therefore standardised sections are used.
Hollow blocks are light, economical and easy to handle. They have better appearance,
better insulating properties and require lesser maintenance. The can be made in various
sizes and shapes.
Siporex Blocks
NICM AR
PROJECT REPORT
70
Siporex blocks are as strong as RCC, but weight is only th of RCC. The save 3040% in cement and 35-50% in steel, leading to economical des ign. The yare 10 tim es
more insulating than concrete and 4 to 6 times than masonry. Thus, they are economical
for air conditioned units. They require less maintenance.
The compressive strength can be as much as 40kg/cm2 in dense form. Its reinforcement
is specially treated against corrosion and for better bond. The dead load weight on
foundations can be reduced by 50-75%. They are suitable for structures on low bearing
soils and in earthquake prone areas. The strength to weight ratio is 21 for siporex as
compared to 15 RCC.
Erection can be speeded up with siporex and they are convenient for additions and
extensions to structures. Prefabricated slabs are used for floors roofs and walling for
which they are 25 to 30% cheaper than conventional RCC. Use of siporex systems saves
up to 10% energy.
Plastics
Plastics used for doors, windows profiles, water distribution pipe, toilet fittings and
fixtures, drain ways, water storage tanks and indoor panelling. They are resistant to
corrosions, light in weight, strong and easy to handle and install.
They are dimensionally stable, possess high strength to weight ratio and are excellent
sound and thermal insulators. Plastics save on cement and steel and are economical to
use.
EXTERIOR INS ULATION AND FINISH SYS TEMS (EIFS)
THE ISSUES
Exterior insulation and finish systems (EIFS) are light weight exterior cladding systems
consisting of insulation board mechanically and / or adhesively attached to a wind loadbearing substrate, and covered with an integrally reinforced base coat and a protective
surface finish. EIFS are based on the concept that optimal wall performance is achieved
when all of the temperature and moisture sensitive components are placed on the interior
side of the insulation.
To protect the insulation from the environment while providing an architecturally
pleas ing finish, the insulation must be coated with a thin finish layer. This layer needs to
be reinforced to resist cracking from temperature, wind and structural movement. The use
of a source drained1 barrier approach to moisture management is considered the
minimum for best practice for EIFS and is an essential component of any EIFS assembly.
Moisture barrier protection of the substrate, drainage and ventilation strategies may also
be required depending on particular project and climatic conditions.
Advantages of EIFS include:
NICM AR
PROJECT REPORT
71
location of the insulation protects the primary structure from temperature extremes
and moisture-related damage,
exterior insulation, particular ly in steel framed buildings, can result in energy
savings, and reduced cost of HVAC equipment,
complex surface features are possible in a wide range of finish colours and
textures,
smaller dead loads and reduced structural costs,
thinner walls will increase usable area and reduce building footprint,
an EIFS can be pre-manufactured in tranferrable panels.
Disadvantages include:
sensitivity to def iciencies in workmanship, particular ly at joints penetrations and
sealants,
susceptibility to mechanical damage.
Consideration should also be given to three key elements of EIFS:
Rain Penetration at Joints
Interstitial Condensation
Cracking of the Lamina
DESI GN CONSIDERATIO NS
The most serious and widespread problems associated with EIFS relate to moisture
damage, often to the substrate system or sheathing since EIFS themselves are made up of
essentially moisture tolerant materials.
Rain Penetration at Joints
Face sealed joints are not recommended; use 2-stage seals in joints that provide for
water drainage at the source.
A drained subsill under windows is essential in most applications.
The EIFS finish should stop at least 8 above grade & a special system is required
below grade. Manufactuers should be consulted for the appropriate details.
Interstitial Condensation
Where possible, additional insulation should not be placed in the stud space. This
will maintain the interior side surface temperature of the substrate sheathing above
the dew point of the interior air. If insulation is required in the stud space a
dynamic analysis for the prediction of condensation should be carried out prior to
finalizing the design.
NICM AR
PROJECT REPORT
72
Rainscreen walls are assemblies that provide a cavity behind the exterior cladding.
The principal function of the cladding is to deflect intruding rainwater without damage to
moisture sensitive materials within the wall assembly. However, water that is present on
the outer face of the cladding, may enter the cavity as a result of a number of forces,
including momentum, surface tension, gravity and air pressure differences. The cavity
acts as a capillary break to prevent water reaching the remainder of the wall assembly.
The cavity also acts as a drainage space to shed moisture to the exterior by means of
flashings and vents provided at the bottom of each cavity compartment.
Pressure equalized rainscreen (PER) wall assemblies attempt to reduce water
penetration of the wall assembly as a result of pressure differences. Wind forces create in
higher air pressures on the exterior of the wall than within the building or the wall
assembly. Air movement in response to this pressure difference can transport moisture
present on the exterior of the cladding into the wall.
PER wall systems and assemblies require that they be designed so that the pressure
difference across the exterior cladding is nearly zero at all times. This reduces the driving
force associated with pressure differences, and prevents moisture from moving through
the wall assembly. The air barrier, in conjunction with a vented and compartmented
cavity, acts to reduce or elim inate air pressure differences across the cladding.
The control of airflow is inherent in the PER wall systems and assemblies. If the
airflow through and within the fabric of the wall is not controlled, the air pressure
difference across the rainscreen (or outer section of the wall) cannot be equalized.
NICM AR
PROJECT REPORT
73
PROJECT REPORT
74
The wall system must contain a continuous and durable air barrier that controls
airflow through the wall. The air barrier system must be made of structural elements, or
be supported by structural elements capable of resisting wind loads. The air barrier
system should be rigid to minim ize material fatigue, especially at the points of attachment
to the structure.
Sealed Compartments
Air pressures induced by winds vary over the width and height of the building.
Steep gradients can develop towards the corners and the roof line while pressures can be
fairly uniform near the centre of the walls. These pressure differentials can induce lateral
airflow within the cavity unless interrupted at suitable intervals by sealed compartments.
The frequency of these cavity compartments should be such that the air pressure within
any compartment can be nearly instantaneously equalized with the exterior pressure.
The size of the compartments should vary over the face of the wall, with larger
compartments located at the centre where pressures gradients are lower, and relatively
smaller compartments located at higher pressure gradients locations near the building
edges. Cavities must be closed at the corners because wind flowing around the building
produces high pressure differences at these locations. Specific design guidelines include:
the cavity depth should be at least 25mm,
the cavity should contain sealed compartments at each corner and at 1.2m intervals
for 6m from the corners and the top,
sealed compartments located at the centre of the wall in both directions at every
3m to 6m.
Venting
Sufficient venting is required in the pressure equalized rainscreen to ensure that
cavity air pressure is quickly equalized to the outside pressure. The location and size of
vents must allow air to flow into and out of the cavity, thereby achieving pressure
equalization across the rainscreen. The effective area and location of the vents should be
based on the envelope air leakage and the cavity volume.
NICM AR
PROJECT REPORT
75
Asymmetrical Venting
Appropriate sizing and location of vents
can provide an additional means of improving
rain penetration resistance. The asymmetrical
venting concept is based on concentrating vents
in places where the wind pressure on the face of
compartment is greatest. This has the effect of
raising cavity pressure so that most of the
compartment experiences an outward pressure.
The raised cavity pressure forces water out of
leakage paths rather than in. Asymmetrical
venting is achieved by concentrating the required
vent area on the side of the compartment closest
to the centre of the faade.
Quality Contol
The quality control and commissioning process has been discussed previously in
the Air Barriers section. A similar process should be applied to other envelope systems
including pressure equalized rainscreens.
The commissioning of a rainscreen wall will verify building performance
objectives before completion of construction. This is accomplished through performance
NICM AR
PROJECT REPORT
76
engineering and f ield or laboratory testing. To assist with performance engineer ing,
CMHC has developed a computer program (RAIN) that simulates the pressure
equalization (P.E.) performance of any design.
The quality control process for pressure equalized rainscreen walls should include:
determining that facade areas and windows to be designed as pressure equalized
rainscreens,
locating vertical and hor izontal compartments and determining the number of
rainscreen cavities,
developing basic design of wall or window system to include an air barrier
system,
compartment seals, and cladding system with vents/drains,
determining physical attributes to each rainscreen cavity i.e. volume, vent area,
leakage area, and stiffness of cladding and air barrier systems,
simulating the performance of each rainscreen cavity using CMHCs RAIN
Rainscreen 2.1 and iterate the design until performance attributes are attained (90%
pressure equalization),
constructing a mock-up to test the P.E. performance of a design at preconstruction,
assessing the complete design of envelope and prepar ing construction
documentation,
preparing a tender package requiring on-site mock-up test to verify field
performance and workmanship quality,
complete testing of rainscreen wall and window system, correct problems as
required, and report results,
ensuring rainscreen P.E. performance complies with design objectives and
certifying that workmanship as complies with drawing and specifications,
providing design information necessary for proper maintenance of walls
systems
RETROFI T OPPORTUNI TY
PERs should be used in all high-rise retrofit or recladding projects. In addition to
providing an appropr iate level of water management performance, rainscreen assemblies
also include an effective air barrier and offer an opportunity to add additional insulation
to the exterior of the building. Changing from face-sealed walls to raiscreen assemblies
may result in additional wall thickness. Careful detailing will be required at interfaces
with components such as windows and other penetrations. In many older buildings
replacing windows at the same time as recladding will allow for correct detailing of
NICM AR
PROJECT REPORT
77
interfaces with walls and will also improve overall envelope thermal performance. Highrise envelope retrofit projects will often involve scaffolding of the building exter ior. The
cost of providing access in this manner is expensive; upgrading all envelope assemblies
and components at one time may result in lower life-cycle costs.
5.5
PROJECT REPORT
78
despite the reduction in scale. For this reason, these studies can only be carried out by
highly specialized test institutes.
NICM AR
PROJECT REPORT
79
NICM AR
PROJECT REPORT
80
phase, but also during the subsequent construction phase, errors may possibly not be
discovered until the work has reached a fairly advanced stage.
This leads to time-consuming and costly changes and corrections, usually at
the expense of the professional indemnity insurance prescribed for architects in many
countries. The most commonly occurring design errors can be subdivided into two
groups: failure to observe building and planning codes on the one hand, and errors in the
choice of materials and wrong or inadequate construction details on the other.
PROJECT REPORT
81
identified, that party can face considerable penalties for any shortcomings ascertained. It
is irrelevant in this context whether this party was actually aware of these shortcomings
or merely must have been aware of them. For this reason, all insurers and particular ly
fire insurers are well advised to ascertain whether all of the safety requirements have
been met before they conclude a policy for buildings entailing high risk potential.
NICM AR
PROJECT REPORT
82
4.5
CULTURAL R ESPONSE
The skyscrapers are built for only two reasons: to make money, responding
to existing demand, or to advertise and flaunt the money one already has Said Philip
Nobel11. Nowadays we can rarely tell the location of a high rise structure due to their
similar style. Some architects even feel proud that their work can be located anywhere in
the world. Obviously, tall building is not a typology to fix in with its context. It prefers to
soar above, and dominate its surroundings. But that does not mean it cannot become a
positive element in the urban composition. It can and should relate to its surroundings
and respond to the history cultural context. Antony Wood in his New Paradigms in High
NICM AR
PROJECT REPORT
83
Rise Design (2004) introduced several approaches to design help cities in their quest for
an appropriate high rise expression.
4.6
ENVIRONMENTAL ASPECTS
NICM AR
PROJECT REPORT
84
A city centre site is often a brownfield site and therefore regarded as more
sustainable than using a greenf ield site. One of the main dr ivers for tall buildings is 66 to
minimize the use of land. If a city centre developer wants to minimize the impact on land
use, the only way to expand is upwards. Therefore, high-rise buildings are likely to be the
preferred option in dense urban areas. (Alison Crompton Ant Wilson 2003) The sites of
most new built high rises were occupied by some low rises.
Normally, there are two ways to clear the site, recycle or reuse. It is possible
to recycle the materials of the old buildings to a less important new built facility and
reuse them, like a public bathroom or a landscape building. For example, in One and Two
Potomac Yard, Arlington, VA, all affected material, mainly cinder ballast generated by
coal-burning locomotives and then used for railroad subgrades, was removed from the
site and used to build roads in a Richmond, Virginia, landf ill. Some high rises may
choose the sites where former high rises were built on. And using the existing footing
could cause a major saving of the construction like 4 Times Square in New York City and
111 South Wacker in Chicago.
Standard:
Reduce the environmental impact from the location of a building on a site.
Reuse the existing building
Reduce the pollution while construction
Recycle the landfill
SITE PLANNI NG
THE ISSUES
A building has a permanent environmental impact on its site, both in terms of
changes to the surrounding ecosystem, and its relationship to the local community. Initial
site planning is key to the overall environmental performance of the building. It has
ramifications on all other aspects of design. Through careful attention during ear ly stages
of design, the building designer can anticipate negative ecological impacts, improve the
quality of the development, and enhance the sustainability of the neighbourhood.
The basic considerations include:
Preservation and Protection of Natural Features
Building Location and Footprint
Building Orientation
DESI GN CONSIDERATIO NS
Preservation and Protection of Natural Features
NICM AR
PROJECT REPORT
85
The site plan should be prem ised upon preserving, protecting, and enhancing such
natural features as site contours, stream channels, hydrological flows, existing vegetation,
scenic views, and wildlife habitats. These features all play integral roles in the proper
functioning of the ecosystem as a whole, and can contribute signif icantly to proper
building functioning. Restrictions on development of environmentally sensitive or
important productive lands are crucial. Agr icultural, forest renewal and hazardous lands,
or lands that might result in extensive environmental damage, should have lim ited
development. For example, steep slopes and hillsides, flood plains, and wetlands are all
examples of areas where development should be restricted and / or regulated.
Building Location and Footprint
The construction of high-rise buildings can affect the local microclimate,
modifying wind and sun patterns in the area, and shading other buildings and ecosystems.
The building should be s ited to create des irable summer and winter microclimates at the
pedestrian level. The location of a building on a site can result in positive or negative
environmental impacts. Consideration should be given to the impact of the building on
views, how much of the site will be disturbed both during construction and operation, soil
capabilities, linkages to transportation networks, existing buildings on site, changes to the
microclimate caused by altering the contours of the land, and so on.
In order to minim ise site disturbance for construction, buildings and access roads
can be aligned to follow the length of existing contours. The buildings impact upon local
solar access is an important consideration. Buildings should be located to minim ise the
loss of solar access to surrounding buildings and publicly accessible, open space areas.
This is an important consideration for colder climates in particular.
Ideally, high-density development should have good access to services and
amenities, maxim ising the potential for pedestrian travel and m inim ising the need for the
automobile. Easy access to public transit, stores, health services, schools, and recreational
facilities all provide for a more sustainable approach to development. Opportunities for
mixed uses at the lower levels of the building can reduce infrastructure costs and provide
for a livelier community aspect in the building. Examples of mixed uses include daycare
space for children and the elder ly, as well as the more typical small-scale retail,
professional and commercial facilities.
Design of site features such as outdoor sitting areas, playgrounds and allotment gardens
provide an opportunity for building residents to enjoy the outdoors and socialise around a
common interest.
There are many other opportunities to enhance the relationship of the building to
the neighbourhood. These include orienting the building to pedestrian traffic, massing
NICM AR
PROJECT REPORT
86
and siting the building to relate to the scale of surrounding structures, providing an
entrance design that is pedestrian friendly, and minim ising the use of large quantities of
pavement.
Building Orientation
A buildings orientation has enormous impacts
on the ability to optimize all opportunities for
environmentally-responsive design strategies. For
example, natural daylighting, heating, and ventilation
strategies are all linked to the buildings proper
orientation. A sites latitude determines the suns
azimuth at any given time of day and year. Simple
calculations will determ ine the path of the sun and a
buildings orientation should be determined to take
advantage of this information. The effectiveness of
passive and active solar systems will be enhanced with
appropriate building orientation and maximum access
to sunlight (SSE to SSW 5% to 15%).
Consideration should be given to the minim isation of solar shadows. The
calculation of site shading can avoid the creation of on-site solar voids and cold-air
drainage dams that collect pools of cold air. The shading of adjacent buildings and lots
should also be avoided. This is particular ly important in temperate and cold clim ates. The
building should be orientated to consider existing airf low patterns and their cooling effect
in both summer and winter. Consideration should also be given to the buildings effect
upon local wind patterns and snow accumulation, avoiding adverse effects upon adjacent
buildings or public open spaces.
A building should also be oriented so as to maxim ize the safety, ease of access and
protection from the elements of its entranceway. The use of overhead structures near
entranceways, for example, can provide pedestrian protection from cold downdrafts.
RETROFI T OPPORTUNI TI ES
While there are few changes that can be made to a buildings location or
orientation through retrofits, there do exist some opportunities for improving the
environmental performance of a building through site alterations.
At the site level, the most readily available and least costly opportunities are
through modifications to the surrounding m icroclimate. In many cases, such retrofits can
improve the energy performance of the building at the same time as improving the
relationship of the building to its natural context. For example, alter ing paving materials
NICM AR
PROJECT REPORT
87
NICM AR
PROJECT REPORT
88
DESI GN CONSIDERATIO NS
Source / Quality of Materials
Many mater ials come from sources which are considered non-renewable or which
involve more severe negative environmental impacts than others. Tropical hardwoods are
considered a scarce resource, not just because they represent an endangered species, but
also because the acquisition process causes dire ramifications on biodiversity. The
selection of materials should involve consideration of the source in order to ensure that a
non-renewable material is not being used. For wood products, third-party forest
certification is the best way to guarantee the suitability of the source.
The source of materials also refers to whether materials are virgin or whether they
are salvaged. Using salvaged mater ials and mater ials with recycled content reduces the
extraction of raw resources. Assemblies that allow easy extraction of the material for
recycling when the building is eventually replaced also result in reduced environmental
impact.
NICM AR
PROJECT REPORT
89
It is also necessary to consider the quality of the materials. Lower quality, less
durable materials will require frequent replacementmeaning that more resources will
be used without adding any value to the building. While lower quality materials may cost
less at the buildings inception, both the economic and environmental cost will be much
higher over the lifetime of the building. Durable materials with a long service life
typically are those that are low-maintenance and that result in lower operation costs. Hard
flooring, for example, has several times the service life of vinyl flooring or carpets, and
reduces both waste and cleaning requirements.
Em bodied Energy
Embodied energy is the term used to describe the energy input invested in a
material during extraction, manufacturing, transportation, and installation. Through
choice of materials, the designer can greatly influence the embodied energy invested in
the building as well as the energy required to operate the facility. The goal is not to
minimize embodied energy per se, but to consider its significant contribution to total lifecycle energy associated with the building. As a case in point, processing of recycled
alum inium requires only 5% of the energy necessary to produce aluminium from bauxite.
Because only 7% to 10% of the embodied energy in buildings is the result of the on-site
construction process, it is crucial to expand embodied energy calculations to include the
entire life-cycle of the building and its attendant material requirements. For example, if
the construction of a new building involves the demolition of an existing on-site building,
the initial embodied energy calculations should include mater ials removed through
demolition.
Reducing the embodied energy of a building can be achieved through:
Increasing the useful life of buildings and their components,
Reducing the energy intensity of building materials (such as fly-ash substitution in
concrete),
Reducing the amount of material in a building,
Reducing construction waste,
Using advanced framing techniques,
Increasing the amount of recycled material in a building,
Using more durable materials,
Using local rather than imported products.
Quantities of Materials
Very large quantities of materials are used to construct and maintain buildings. The
failure to optimize designs results in an excessive amount of mater ials being used.
Opportunities exist to elim inate oversized and decorative materials and still achieve
NICM AR
PROJECT REPORT
90
appropriate aesthetic appeal. Finishes with short life spans, such as carpeting, account for
a large percentage of lifecycle costs.
Waste also results from non-standard dimensions in the design. Off-cuts from studs
and wall panels are examples. By using the common dimens ions of materials such waste
can be reduced. Use of engineered wood products, such as stair stringers, can also help to
minimize material quantities.
PROJECT REPORT
91
materials, paints and sealants, and so on. Examples of materials that are healthy include
low-VOC paints and adhesives, low emission carpets (often made of natural fibres) and
hard non-porous materials (see Indoor Air Quality in this document).
Impact on Natural Ecosystems
Many industries today are adopting a life-cycle product stewardship model as a
way of incorporating environmental concerns into all stages of the products life. For
building des ign, this means comparing the environmental impact of materials resulting
from: extraction and processing, manufacturing, transportation and packaging,
installation, operation, maintenance and replacement, and eventual disposal or recycling
potential. Certif ication programs, such as for wood from sustainably managed forests,
represent a key strategy for ensuring limited impact on natural ecosystems.
Materials Selection Guidelines
At the design concept stage, it is helpful to develop comprehensive design
guidelines that include selection of green materials. The following guidelines are
examples of practices that can be included and that could improve the design and
materials specification process.
RETROFI T OPPORTUNI TI ES
While there are few changes that can be made to a buildings location or
orientation through retrofits, there do exist some opportunities for improving the
environmental performance of a building through site alterations. At the site level, the
most readily available and least costly opportunities are through modif ications to the
surrounding microclimate. In many cases, such retrofits can improve the energy
performance of the building at the same time as improving the relationship of the
building to its natural context.
For example, altering paving materials (from asphalt to pervious pavers) can lead
to reductions in surrounding micro-climate temperatures that in turn reduce the cooling
loads on the building while also addressing stormwater run-off issues. Another example
is to add landscaping interventions that enhance the natural features of the site while also
improving the buildings energy performance. These can include such things as adding
deciduous plants on the south and west sides of a building to allow for summer cooling
and winter solar access.
Exam ples of Green Building
Materials
NICM AR
PROJECT REPORT
92
Foundations
ABS drain tile with recycled content
Pier foundation systems
Concrete with fly-ash content
Walls
Insulation with high recycled content
CFC and HCFC-free insulations
Cellulose insulation
Drywall with high recycled content
Steel / alum inium/ vinyl with recycled content
Roofing
Recycled rubber roof deck
CFC and HCFC-free rigid insulations
Green Roofs`
Interior Finishes
Zero- and Low-VOC paints
Zero- and Low-VOC caulks and adhesives
Bio-based natural materials (cork, linoleum, wool, sisal, etc.)
Landscaping
Rubber flooring from recycled tires
Chipped wood waste for flower beds
Crushed concrete as aggregate for road sub-base
Materials Selection
Specify recycled products and attendant strategies.
Specify reuse of salvaged building materials.
Design with panel, pre-cut and engineered construction products.
Specify durable exterior and interior finishes.
Specify wood from sustainable-managed sources.
Use low-emissions finishes and interior materials.
SOLID WASTE
THE ISSUES
NICM AR
PROJECT REPORT
93
PROJECT REPORT
94
in the construction of an average house. Both the economic and environmental costs of
disposing of this waste are enormous. However, construction waste can be cut by as
much as 85%, and disposal costs significantly reduced by implem enting plans which are
based on the 4 Rs of waste management.
Building Operation
The solid waste that is generated during the operation of res idential buildings is
typically comprised of consumer products and organic waste from food preparation and
landscaping. About half of the solid waste stream from residences consists of packaging
materials; approximately 30% of organic materials, and the remaining 20% is made up of
other paper products, textiles and small amounts of old appliances and household
hazardous products. Through recycling and composting strategies, up to 80% of this
waste stream could be reduced.
If appropriate dedicated facilities for composting and for recycling storage /
handling / pickup are integrated into a buildings design, residents will have the
opportunity to achieve such reductions.
Building Demolition
The waste caused by demolition represents one of the largest contributors to the
waste stream. The economic costs associated with disposing of this waste are also
signif icant. It is estimated that approximately five to eight percent of the total job costs
are allocated to disposal. By managing demolition responsibly, however, signif icant
quantities of demolition waste can be diverted from disposal. Case studies have shown
that up to 90% of waste generated in demolition can be diverted cost-effectively. Through
dismantling rather than demolishing a building, for example, such savings can be
achieved from both cost and environmental perspectives.
NICM AR
PROJECT REPORT
95
RETROFI T OPPORTUNI TI ES
The focus of retrofit opportunities in terms of solid waste is on ensuring the most
appropriate facilities for collecting, storing and handling waste for recycling and
composting. Although the best opportunities for providing dedicated waste management
spaces exist during initial design and construction, the conversion of interior and exterior
NICM AR
PROJECT REPORT
96
HVAC Systems
The principal water use associated with HVAC components in a high-rise building
relates to evaporative losses from cooling towers. It should be possible to reduce
evaporative losses to less than 5% through better design. Opportunities to reuse water for
make-up purposes should be explored, rather than using potable supplies.
Exterior Water Use
Outdoor water consumption is a major concern to water authorities. Peak monthly
demand for water occurs during late summer when municipal reservoirs are at their
lowest levels. Most municipalities that impose watering restrictions do so during summer
months when outdoor water use substantially increases overall consumption. There are
NICM AR
PROJECT REPORT
97
many conservation practices that can reduce outdoor water consumption. Some of the
most common approaches are discussed later in this section, in Landscape Practices.
On-Site Water Treatment
Centralised wastewater treatment is the status quo for most municipalities. These
sewage collection and treatment networks represent extensive infrastructure with large
energy requirements. Canadian municipalities use substantial amounts of energy in the
operation of water and wastewater treatment facilities. The total amount of energy used is
approximately equal to the energy required to operate all munic ipally-owned buildings
and facilities.
Of the total energy required for these operations, wastewater treatment plants
account for approximately half, or 2200 GWh per year. Municipalities use water
conservation policies to reduce peak water demand, defer the upgrading of facilities and
to ensure adequate supplies of water. These also have the additional benefit of reducing
energy consumption at water and wastewater plants.
One strategy to reduce water consumption is to use on-site infrastructure to treat
wastewater and reuse it for non-consumptive purposes. On-site treatment systems offer
an alternative to the conventional centralised approach. Essentially the on-site systems
provide a modularised and low cost system for treatment in close proximity to the
buildings. The on-site systems can be built incrementally, which reduces the need for
large capital expenditures. Moreover, since key components of the infrastructure may be
located within each private development, municipal expenditures can be further reduced.
On-site operations provide primary and secondary treatment that produces water
that is colourless, odourless and suitable for many re-uses within the vicinity. Also, the
treatment facility can be designed for multipurpose use, giving added value to nearby
residents. For example, a secondary function of a solar aquatic liquid waste treatment
system is a greenhouse.
Exterior Water Use
For the typical high-rise lot, rain sensor equipment may cost approximately $150.
Savings from water conservation would be 12-15% or $125 per season (at $1.00/m3).
Simple payback would be 1.5 years.
LANDSCAPE PRACTICES
THE ISSUES
NICM AR
PROJECT REPORT
98
DESI GN CONSIDERATIO NS
Water-Efficient Landscape Practices Reducing watering requirements by at least
50% is achievable when specifying a water-efficient landscape. There are many water
conservation practices that can achieve such reductions.
NICM AR
PROJECT REPORT
99
Water-efficient Irrigation
Drip irrigation is more water- efficient than sprinkler irrigation. Sprinklers can lose
approximately 25% to 50% of water content to wind and runoff . Drip irrigation reduces
NICM AR
PROJECT REPORT
100
evaporation through the application of water directly into the soil. It also limits irrigation
to planted surfaces only, avoiding the unnecessary watering of sidewalks and pavement.
Drip irrigation can save 50% to 75% compared to a sprinkler system. Also, rain sensors
prevent overwatering. Small and inexpensive rain sensors can be installed to prevent
automatic watering systems from activating dur ing or after rainfall. Installation costs can
be recouped within two years through water costs savings.
Lawns
Lawns typically require 25 mm (1 in.) of water per week. This can add up to
750,000 litres annually for a typical high-rise building. In general, groundcovers require
less water because they have a larger root zone from which to draw soil water. High-use
areas may be impractical for groundcovers, however. In such cases, droughttolerant
turfgrasses are available and should be used (see Appendix 3: Turfgrasses for Canadian
Lawns in Household Guide to Water Efficiency, CMHC 2000). Also, only fertilize lawns
once in the spring. Over-fertilized lawns grow beyond their limits and require increased
watering.
Mulching
Besides controlling weeds, mulches retain soil moisture levels and prevent soils
from overheating and drying-out by reducing evaporation. Mulches will also increase the
wetted surface area of soil under the mulch. Over time, organic mulches will also
breakdown and improve the structure of soils, improving water infiltration. Proper
mulching practices will reduce the quantity of water required for irrigation; it can reduce
evaporation and run-off by 75% to 90% over unmulched areas5. A mulching depth of 10
cm will result in optimum moisture retention. Storm water management represents a
signif icant cost to municipalities, via infrastructure required to transport and treat run-off.
It also represents a cost to the environment through non-point source pollution.
This is the transfer of pollutants from roadways and parking lots directly to water
bodies via run-off. The landscape architect as well as the civil engineer is able to offset
these costs by using appropriate best management practices for storm water management.
Many on-site devices are available for slowing and filtering storm water. Other strategies
include minimizing the amount of run-off from a site as well as re-using it.
PROJECT REPORT
101
inputs than conventional lawns. Woodland-type gardens performed the best, however.
The low maintenance lawn consists of hardy, drought-tolerant, slow-growing grass and
broad-leafed species, such as clover, that do not require frequent mowing. The woodland
shade garden is composed of native trees, shrubs and groundcovers. Xeriscapes and
Meadows were also found to require minim al energy inputs. Xeriscapes consist of plants
suited to local rainfall conditions and require almost no watering. Meadows feature native
grasses and wildflowers. Graphs at the left illustrate these comparisons.
Summer
Use plants and landscape structures to reduce summer heat gain by:
Shading the building from direct solar radiation,
Diverting or channelling air movement away from or towards the building,
Creating cooler temperatures near buildings through evaporation and transpiration.
The Heat Island Effect
The heat island effect is the phenomena of higher temperatures occurring in
urbanised areas relative to their suburban and rural surroundings. On warm summer days,
the air in a city can be up to 5C hotter than its surrounding areas. One reason for this is
less vegetation in urban areas to intercept solar radiation, and cool the air with the
transpiration process. Transpiration is the process of water loss to the atmosphere through
living-plant surfaces.
At the m icroclimate level, vegetation can directly reduce surface temperatures
through shading and the interception of solar radiation. Trees can reduce the temperature
in their immediate vicinity by up to 5C from shading alone. One m ature beech for
example, will shade 170m2 of surface area . Air temperatures above vegetated areas can
be up 8 to 14C lower than over asphalt or concrete areas of equal size. As a result, urban
vegetation can alter the surface energy balance within a localised area and result in lower
ambient temperatures.
On a local climate scale, vegetated areas will lower air temperatures through the
process of transpiration. A 21-meter canopy tree, for example, can transpire the
equivalent of 375 litres of water per day, which has the cooling effect of 5 airconditioners operating for 20 hours. This cooling effect is the result of evapotranspiration
and lowers ambient daytime temperatures.
Tree canopies can also slow the escape of heat from urban surfaces at night.
Combined, these effects lower ambient temperatures. More vegetation lowers air
temperature, reducing the need for air-conditioning and lowering energy consumption.
NICM AR
PROJECT REPORT
102
This translates into direct cost savings to residents. It also can reduce global warming
(less electrical demand implies less burning of fossil fuels at power generation plants).
Recomm ended Practices
Use rooftop plantings to reduce heat absorption into buildings through their roofs
Plant broad-leaf deciduous shade trees to intercept solar radiation near ground level
parking areas and other paved surfaces.
Acer platanoides will allow only 10% of solar radiation to penetrate its canopy in
summer, while allowing 65% in the winter. Shaded areas can be as much as 10oC
cooler than areas in full sun.
Plant self-supporting vines to climb south facing walls to reduce summer solar
gains. A 16-cm blanket of plants can increase the R-value of a wall by as much as
30%5. Less vigorous species will not compromise cladding.
Plant deciduous trees to shade the first 3 to 5 storeys of an apartment buildings
south and/or west elevations.
NICM AR
PROJECT REPORT
103
PROJECT REPORT
104
IIC Ratings
The IIC (Impact Insulation Class) rating applies to noise transmission due to
structural impact and vibration through floor and ceiling assemblies. The ratings in the
attached graphic illustrate improved design objectives.
DESI GN CONSIDERATIO NS
Noise control strategies must be addressed at the design stage, as retrofit costs to
improve acoustic performance can be very high. Designers must consider the noise
implications of the architectural, structural, mechanical, and electrical design. The
designer must address sound transmission through airborne and structural routes.
Verification
Sound levels should be ver ified by field measurements using the ASTME336
standard, allowing construction defects to be corrected prior to occupancy.
NICM AR
PROJECT REPORT
105
Doors
Noise transmission is a common complaint in high-rise buildings with pressurized
corridors. More innovative ventilation strategies (such as compartmentalized suites) may
allow for better sealing of entry door systems. The accompanying chart demonstrates the
potential noise reduction from alternative door assemblies.
Windows
Windows have typically been the weakest acoustical link in exter ior walls.
Improvements in windows for thermal comfort purposes (for example multi-pane glazing
and thermally broken frames) have also improved their acoustical performance. Sound
transmission (especially when close to transportation routes) can be reduced by
increasing glass thickness (laminated glass), and increasing the width of the air space
between panes. These two strategies can increase the STC rating by as much as 8 to 10
points. Eliminating r igid mechanical coupling of the window to the frame structure, using
resilient or gasketed mounting, will further enhance performance.
Air-Borne Noise
Strategies to deal with air-borne noise include:
selection of envelope and party wall assemblies with good sound insulation
characteristics.
Impact Noise
Strategies to reduce noise transmitted through the structure include:
providing an improved f loor design e.g., a floating f loor above the structural floor
and/or absorbent materials within the floor cavity,
providing an increase in floor layer mass and resiliently suspended ceilings,
reducing the impact at source through the use of resilient materials such as carpet
and underlay (with due consideration to their effect on IAQ),
NICM AR
PROJECT REPORT
106
NICM AR
PROJECT REPORT
107
CONCLUSION
NICM AR
PROJECT REPORT
108