SI No

Description/Scope

Major Equipments
33kV Switchgear
Engineering, Manufacturing, Testing at Works,
Transportation, Supply, Unloading, Delivered at Site
Supply,Installation/fixing of Base frames, chequer plates
and connected building works
Installation of the panels,Bolting/ tack welding of the panels
to base frames
Testing & Commissioning of the Switchgear including
ADDC witness testing
Coordination with ADDC, Final approval

1.1
a
b
c
d
e
f

1.2
a
b
c
d
e

ADDC Power Source at remote end to feed 33kV


Substation at AGSI premises - Arrangement to re configure
and test the allocated feeders
11kV Switchgear
Engineering, Manufacturing, Testing at Works,
Transportation, Supply, Unloading, Delivered at Site
Supply,Installation/fixing of Base frames, chequer plates
and connected building works
Installation of the panels,Bolting/ tack welding of the panels
to base frames
Testing & Commissioning of the Switchgear including
ADDC witness testing
Coordination with ADDC, Final approval

1.3 Power & Distribution Transformer


a
Engineering, Manufacturing, Testing at Works,
Transportation, Supply, Unloading, Delivered at Site
b
Supply of Power & Distribution Transformer
c

Supply of 11kV Neutral earthing Resistor (NER)

Lifting arrangements in the roof of transformer opening to


facilitate the placement of Transformer
Transfomer foundations, rails/channel over the foundation
to suit transformer wheel base
Erection of the Transformer
Testing & Commissioning of the Power Transformer
including ADDC witness testing.excluding Type tests.
Coordination with ADDC, Final approval

e
f
g
h

AGSI STEEL PROJECT


Division of Responsibilities (DOR)
ANNEXURE E
EPC
OWNER
CONTRACTOR

X
X
X
X
X
The remote end works are to be essentially carried out by OEM/ADDC.
NA

X
X
X
X
X
X
X
X
X
X
X
X
X
X

1.5 LV Switchgear
a
Engineering, Manufacturing, Testing at Works,
Transportation, Supply, Unloading, Delivered at Site
b
Supply,Installation/fixing of Base frames, chequer plates
and connected civil works
c
Installation of the panels,Bolting/ tack welding of the panels
to base frames
d
Testing & Commissioning
e
Coordination with ADDC, Final approval of LV System

b
c
d
e
f
g
h
2.2
a
b

Design, Supply of MV Cable 33kv, 3c*300sq.mm ( inside


Project substations-1260 meters)
Design, Supply of HV Cable 11kv, 3c*300sq.mm ( inside
Project substations)
Design, Supply of LV Cable 1*630 sq.mm (Between
Transformer to LVAC panel)
Laying, dressing of the Cables
Necessary Testing, commissioning at the end of works
Supply of all Termination kits
Cable cutting, making of cores, fixing of cables, Installation
of Termination Kits
Control cables
Supply of control cables
Installation of control cables

NA

1.4 48V DC System


a
Engineering, Manufacturing, Testing at Works,
Transportation, Supply, Unloading, Delivered at Site
b
Supply,Installation/fixing of Base frames, chequer plates
and connected civil works
c
Installation of the panels, Bolting/ tack welding of the panels
to base frames and batteries
d
Testing & Commissioning of the DC system including
ADDC witness testing
e
Coordination with ADDC, Final approval

Other Equipments
2.1 MV, LV Power Cables & Terminations
a
Design, Supply of MV Cable 33kv, 3c*300sq.mm (Between
Primary Substation to Project Substation-12000 meters)

Remarks

X
X
X
X
X

X
X
X
X
X

X
X
X
X
X
X
X
X
X

Page 1 of 4

SI No

Description/Scope
c

Supply of glands, lugs, ferrules, ties & tags

AGSI STEEL PROJECT


Division of Responsibilities (DOR)
ANNEXURE E
EPC
OWNER
CONTRACTOR
X

Page 2 of 4

Remarks

SI No

Description/Scope
d

2.3
a
b
c

2.4
a
b
c

2.5
a
b
c
d
e
f
g
3
a
4
a
b
c
d
5
a
b
c
d
e
6
a

c
d

5
6
7
7
a
b
c
d
e
f

Making of cable core, Termination of the cables, ferruling &


testing
Station Earthing
Supply & Installation of Y/G Earth cables and Bare
Cu.conductors
Supply & Installation of Earth bars, Earth rods, chambers,
clamps, lugs, washers,PVC glands, couplers, studs
Excavation,Deep boring/Augering, Drilling,De-watering (if
necessary), leveling of chamber, backfilling and connected
civil work
Cutting of cables/conductors/tapes, installation of all, make
connections at equipments, earth bars and pits, testing and
fixing of chamber.
Station Lightning Protection
Supply & Installation of Y/G Earth cables and Bare
Cu.conductors
Supply & Installation of Earth bars, Earth rods, chambers,
clamps, lugs, washers,PVC glands, couplers, studs
Excavation,Deep boring/Augering, Drilling,De-watering (if
necessary), leveling of chamber, backfilling and connected
civil work
Cutting of cables/conductors/tapes, installation of all, make
connections at equipments, earth bars and pits, testing and
fixing of chamber.
Cable trays/ladders, trunking, cantilever arms, anchor
bolts,couplers, earth strips & supports
Supply of Cable trays/ladders, trunking, cantilever arms,
anchor bolts,couplers, earth strips & supports
Providing opening/core cutting on walls, necessary
builders' works for routing of cable trays
Installation of Cable trays/ladders, trunking, cantilever arms,
anchor bolts,couplers, earth strips.
Modification & Installation of cable supports to suit site
requirement
Marking of cable trays/ladders
Fire sealant for openings on the internal side of the
substation
Providing Waterproofing / finish on the external side
Factory Acceptance Test (FAT)
Witnessing of FAT at manufacturer's premises
Substation Accessories
Auxilary DB's, Lighting & Small Power works inside/outside
subtation, Ventilation, Air Conditioning equipments
Fire retardant paints, Epoxy Painting on surface, floor mats,
Name plates, Sign boards as per ADDC requirements

AGSI STEEL PROJECT


Division of Responsibilities (DOR)
ANNEXURE E
EPC
OWNER
CONTRACTOR
X

X
X
X

X
X
X

X
X
X
X
X
X
X
Not applicable
X
X

Fire extingusihers, Fire protection sytems as may required


First Aid Box & Key Box
Distribution Management System (DMS)
Supply, Testing & Commissioning of DMS-RTU, FOTB
Installation of DMS-RTU, FOTB
Supply of all cables necessary for connection of DMS-RTU
Installation of DMS Cables within substation between RTU
& Switchgear
DMS Integration
33kV Cable Laying works- Civil
Route survey,Excavation, backfilling, dune sands,
protection tiles, warning tape, route markers, joint markers,
upvc ducts, cleats/clamps, FOC pull pits, Thermal resistivity
of the soil,Protection of existing services, removal of
surplus excavated materials from the site and disposal.
HDPE pipes, road crossing, aspahalt cutting, coring,
NDRC/HDD works, Dewatering, access arrangements,
resinstatement works.
Cables Delivery at Site, Cable unloading at erection
location, Transport to Erection location
Provisions of winch machine, rollers, cable drum trailers to
pull the cables and other installation equipments and
machineries
Laying of Cable as per drum schedule provided
Cables testing, cleaning, dressing of laid cables
Manufacturer supervision
Cable Jointing
Supply of Cable Joint kits-Heat Shrink Straight Through
Jointing Kit
Installation of Cable Joint kits
Supply of FO Splicing Kits, enclosure, joint boxes
Supplier testing of FOC Cables
Installation of FOC joints
Installation of FO Cable Termination kits at Distribution
Substation

Remarks

X
X
Not included, Only DMS Interface shall be provided
Not included
Not included
Not included
Not included

X
X
X
X
X
X
X
X
X
X
X
X

Page 3 of 4

SI No
8

Description/Scope
33kV SERIES REACTORS
a
Supply & installation of 33kV Series Reactor as specified
b
b
c
d

9
a
b
c
d

Supply,Installation/fixing of Base frames, chequer plates


and connected building works
Installation of base frame and Bolting.
Testing & Commissioning of the Sseries reactor
LV works package
Supply & Installation of SMDB's, DB's
Supply & Installation of Lighting, Small Power & Lightning
Protection
LV power & Control Cables, Cable Terminations, cable
trays
Supply & Installation of Split A/C units, HVAC

X
X
X
X
X
X
X
X

Street lighting inside the plant

Earthing

a
b
c
d
e
f
g
h
i
j
k
l
m
n
o
p
q
r

General Facilities
Access to Site
Mobilization & Demobilization
Custom Fees & Duties
Transportation from Customs, warehouse, port to site
Unpacking & Material Inspections
Providing Instructions for Installation
Tools & Testing Devices for commissioning
Plant & Machinery for subcontract works (Crane, Forklift,
trailer, truck)
Site Office with basic communication facility
Labour rest area
Closed, Covered Store with lockable facility
Water & Sewage Cleaning
Temporary Power
Diesel Generator
Site Security 24x7, Site safety warning signs
Waste Disposal
Watch & Ward
Supervision of 33KV installation from ADDC substation till
plant substation
Supply of Spare Parts of equipments and Maintenance
Tools

Remarks

10

11

Rating of 33kV Furnace breaker and 33kV Serires Reactor

AGSI STEEL PROJECT


Division of Responsibilities (DOR)
ANNEXURE E
EPC
OWNER
CONTRACTOR

X
X
X
X

For IMPORTED Supply items


For IMPORTED Supply items

X
X
X
X
X
X
X
X
X
X
X
X
X
X
X

Note : "X" means "incharge" and " to bear the cost"