Escolar Documentos
Profissional Documentos
Cultura Documentos
Ali Abur
Talk Outline
Background and terminology
State estimation
Phasor measurements
Phasor-only state estimation
WLS: exact cancellations
LAV: improved robustness
Extension to 3-phase networks
Modeling
Gen
1
Load 1
Load 2
Transmission Network
[Lines + Transformers]
Gen
2
Load NL
Gen
NG
Measurements
4
Modeling [ SSE ]
SSE: Estimation of the snap-shot
at time t
Gen
1
Gen
2
Load 1
Load 2
Linear or NL
Pos Seq or 3-Phase
SCADA or Phasor or
Mixed SCADA/Phasor
Transmission Network
[Lines + Transformers]
Load NL
Gen
NG
Estimated Measurements
5
Modeling [ DSE ]
DSE: Single machine / zonal / wide-area
Detailed Gen and Load models
Frequency and power angle estimation
Gen
1
Load 1
Load 2
Zone-2
Zone-1
Gen
2
Transmission Network
[Lines + Transformers]
Load NL
Zone NZ
Estimated Measurements
Gen
NG
6
Timeline
[z(t)]
()
()
SSE
DSE
+ 2
DSE /
Local
+ 3
+ 4
SSE /
Wide-area
DSE /
Wide-area
7
Timeline
[z(t)]
()
()
DSE
+ 2
DSE /
Local
+ 3
+ 4
SSE /
Wide-area
DSE /
Wide-area
8
Talk Outline
Background and terminology
State estimation
Phasor measurements
Phasor-only state estimation
SCADA
Measurements
PM +
Topology Processor
Network Observability Analysis
WLS State Estimator
Bad Data Processor
Parameter and Topology Error Processor
Analog Measurements
Pi, Qi, Pf, Qf, V, I
State
Estimator
Topology
Processor
V,
Bad Data
Processor
Load Forecasts
Generation Schedules
Network
Observability Check
PM +
Topology Processor
Network Observability Analysis
Robust LAV State Estimator
Bad Data Processor
Parameter and Topology Error Processor
Analog Measurements
Pi, Qi, Pf, Qf, V, I
State
Estimator
Topology
Processor
V,
Bad Data
Processor
Load Forecasts
Generation Schedules
Network
Observability Check
Talk Outline
Background and terminology
State estimation
Phasor measurements
Phasor-only state estimation
Antenna
CT
GPS CLOCK
PMU 2
PT
PMU 3
CORPORATE
PDC
PDC
PMU 4
PMU K
DATA STORAGE
& APPLICATIONS
REGIONAL
PDC
DATA STORAGE
& APPLICATIONS
17
Reference phasor
+1
--3
--2
Reference
+1
--2
Reference
--3
18
Under the Recovery Act SGIG and SGDP programs, their numbers rapidly increased : 166 1126
PMU
V phasor
ALL 3-PHASES ARE TYPICALLY MEASURED
BUT
ONLY POSITIVE SEQUENCE COMPONENTS ARE REPORTED
= [] +
1
3
+ = [ + + ]
=
20
Talk Outline
Background and terminology
State estimation
Phasor measurements
Phasor-only state estimation
WLS: exact cancellations
LAV: improved robustness
Extension to 3-phase networks
Measurement equations
SCADA Measurements
Z = h( X ) + Non linear Model
H x : h ( X )
Phasor Measurements
Z = H X + Linear Model
H : Function of network parameters only
A.G. Phadke, J.S. Thorp, and K.J. Karimi, State Estimation with Phasor Measurements,
IEEE Transactions on Power Systems, vol. 1, no.1, pp. 233-241, February 1986.
22
Talk Outline
Background and terminology
State estimation
Phasor measurements
Phasor-only state estimation
ri 2
2
i
Subject to r = Z H X
T 1
1
X =G H R Z
residual
Direct solution
G = H T R 1 H ; R = E{ T } = cov( )
24
V
m
Z = m
I Branch currents
U
=
[V ] +
Yb A
U : identity matrix
Yb : branch admittance matrix
A : branch - bus incidence matrix
Note: Shunt branches are neglected initially, they will be introduced later.
25
V m e m + jf m
Let m = m
m
I c + jd
U
=
[e + jf ] +
( g + jb) A
= [H F ] [e + jf ] +
26
em U
U e
f =
+
m
c gA bA f
m
d bA gA
e
[ Z ] = [H ] +
f
27
U
U
U
U
G = HT H =
gA bA gA bA
bA gA bA gA
U + AT g T g + bT b A
0
=
T
T
T
U + A b b + g g A
0
[G] matrix:
Is block diagonal
Has identical diagonal blocks
Is constant, independent of the state
28
[ Z ] = ( H + H sh ) X + = H X + u
u = H sh X +
E{u} = H sh E{ X }
1
T 1
E{ X } = X = G H R Z
X
= G H R ( Z H sh X )
= X G 1 H T R 1 H sh X
corr
Very sparse
29
Number of
Buses
Number of
Branches
Number of
Phasor
Measurements
159
198
222
265
340
361
3625
4836
4982
Cases simulated:
Case-1: No bad measurement.
Case-2: Single bad measurement.
Case-3: Five bad measurements.
30
Case
1
2
3
1
2
3
1
2
3
WLS
0.59
0.59
0.62
0.61
0.61
0.62
0.59
0.58
0.58
MSE
Decoupled
WLS
0.59
0.59
0.62
0.61
0.60
0.63
0.59
0.59
0.59
31
Case
1
2
3
1
2
3
1
2
3
32
Talk Outline
Background and terminology
State estimation
Phasor measurements
Phasor-only state estimation
L1 (LAV) Estimator
m
Minimize
| r |
i =1
Subject to Z = H X + r
c = [1,1, ,1]
T
34
Wrong data
35
x
Wrong data
(leverage point)
36
Mili L., Cheniae M.G., and Rousseeuw P.J., Robust State Estimation of Electric Power
Systems IEEE Transactions on Circuits and Systems, Vol. 41, No. 5, May 1994, pp.349-358.
H x+e = z
LEVERAGE
MEASUREMENT
x x x
x x x
x x x
1
R H =
x
x
x
Y Y Y
x
x
x
Scaling both the measured value and the measurement jacobian row will
eliminate leveraging effect of the measurement.
Leave zero injections since they are error free by design.
Incorporate equality constraints in the formulation.
37
Properties of L1 estimator
Efficient Linear Programming (LP) code exists
to solve it for large scale systems.
Use of simple scaling eliminates leverage
points. This is possible due to the type of
phasor measurements (either voltages or
branch currents).
L1 estimator automatically rejects bad data
given sufficient local redundancy, hence bad
data processing is built-in.
38
min c y
s.t. My = z
min c | r |
s.t. Hx + r = z
y0
c = [0 n
T
y = [X
T
a
M = [H
0n
X
T
b
cm
U
I
cm ]
T
T T
V ]
I]
x = Xa - Xb
r = U V
39
40
Leverage Measurements
Bad data
Leverage Measurements
No scaling
Bad data
With scaling
Case-1
Case-2
Case-3
V (pu)
(deg)
V (pu)
(deg)
V (pu)
(deg)
5.2
1.0118
-3.5462
5.2
-3.74
0.9999
-3.74
-3.74
0.9952
0.13
1.004
-3.8964
0.9952
0.13
0.9992
-4.81
0.9992
-4.81
0.9992
-4.81
-9.02
0.9999
-9.02
-9.02
0.9851
-7.41
0.9851
-7.41
0.9851
-7.41
0.9869
-8.88
0.9869
-8.88
0.9869
-8.88
42
Case b
Case c
LAV
3.33 s.
3.36 s.
3.57 s.
WLS
2.32 s.
9.38 s.
50.2 s.
43
L1 (LAV):
Linear solution
Linear programming (single solution)
computationally competitive in s-s
Requires bad-data analysis
Does not require bad-data analysis[*]
Normalized residuals test
Re-weighting (not applicable) No deficiency in the presence of leverage
No deficiency in the presence of
leverage measurements, with scaling.
Talk Outline
Background and terminology
State estimation
Phasor measurements
Phasor-only state estimation
3-phase operation:
motivation and observations
State estimators implicitly assume balanced
operating conditions and use positive sequence
network model and measurements. This
assumption is sometimes questionable.
Power measurements are non-linear functions
of state variables.
Phasor measurements are linearly related to the
states.
46
Further motivation
Develop a state estimator capable of solving
state estimation for three-phase unbalanced
operating conditions,
yet:
Utilize existing, well developed and tested
software as much as possible.
47
Proposed approach:
Modal decomposition revisited
Decompose phasor measurements into their
symmetrical components
Estimate individual symmetrical components
of states separately ( in parallel if such
hardware is available )
Transform the estimates into phase domain to
obtain estimated phase voltages and flows.
48
Modal decomposition of
measurement equations
Z = HV + e
Z T = [ ZVT Z IT ]
VS = TVP
&I
= TI P
T 0 0
0 T
TZ =
0
0 0 T
T: 3mx3m
TZ Z = TZ HV + TZ e
49
Modal decomposition of
measurement equations
T 1 0 0
0 T 1
TV =
1
0 T
0
V = TV VM
Zero sequence
Z M = H M VM + eM
Z 0 = H 0V0 + e0
Z r = H rVr + er
Z M = TZ Z
H M = TZ HTV
eM = TZ e
V0 = G01H 0T R01Z 0
Vr = Gr1 H rT Rr1Z r
G0 = H 0T R01 H 0
Gr = H rT Rr1 H r
50
Case a
Case b
LAV
LAV
LAV
WLS
3.78 s.
25.51 s.
3.66 s.
26.01 s.
3.62 s.
24.82 s.
Zero Seq.
WLS
WLS
Case c
51
Talk Outline
Background and terminology
State estimation
Phasor measurements
Phasor-only state estimation
State
SCADA
Meas.
Bad Data
Estimator &
Processor
Estimated/Corrected
PMU&SCADA Meas.
Estimated State
53
Numerical Example
: Power Injection
: Power Flow
: PMU
: Voltage Magnitude
54
Numerical Example
Error in bus 1 phase angle
TEST A
Bus 1 is used as the reference bus
TEST B
No reference is used
Test A
Measurement
Test B
Normalized
residual
Measurement
7.5
p47
p56
12
5.73
5.6
V1
4.53
p47
p56
12
5.2
Normalized
residual
10.53
7.2
5.48
5.35
4.96
55
56
Robust Metering
Bad data appearing in critical measurements
can NOT be detected.
Adding new measurements at strategic locations
will transform them, allowing detection of bad
data which would otherwise have been missed.
Note:
When a critical measurement is removed from
the measurement set, the network will no longer be
OBSERVABLE.
57
13
Type
F41-43
F36-35
F42-41
F40-56
I-11
I-24
I-39
I-37
I-46
10
I-48
11
I-56
12
I-57
13
I-34
58
29
13
P
P
P
P
P
P
P
P
P
P
59
Impact of PMUs on
Parameter Error Identification
Are there cases where errors in certain
parameters can not be identified without
synchronized phasor measurements?
Cases where more than one set of parameters
satisfies all SCADA measurements.
60
Illustrative Example
Pkl =
Plm =
k l
xkl
l m
xlm
Pkl =
Plm =
Vk
J ( x, p1 , p2 ) = J ( x, p1, p2 )
k l
xkl
l m
xlm
Vl
Pl=Plm - Pkl
Vm
61
Illustrative Example
Pkl =
Plm =
k l
xkl
l m
xlm
Pkl =
Plm =
k l
xkl
l m
xlm
Vk
J ( x, p1 , p2 ) = J ( x, p1, p2 )
x 'kl k l ' x 'lm l ' m
=
=
xkl
k l xlm l m
Pl=Plm - Pkl
Vl
Vm
62
Related Publications:
Gl, M. and Abur, A., A Hybrid State Estimator for Systems with Limited Number of PMUs, accepted for
publication in IEEE Transactions on Power Systems, 2014.
Gl, M. and Abur, A., LAV Based Robust State Estimation for Systems Measured by PMUs, IEEE Transactions
on Smart Grid, Vol. 5, No: 4, July 2014, pp.1808 -- 1814.
Gl, M. and Abur, A., A Robust PMU Based Three-Phase State Estimator Using Modal Decoupling, IEEE
Transactions on Power Systems, Nov. 2014, Vol. 29, No: 5, pp.2292-2299.
Gl, M. and Abur, A., Observability Analysis of Systems Containing Phasor Measurements, Proceedings of
the IEEE Power and Energy Society General Meeting, 22-26 July 2012.
Gl, M. and Abur, A., Effective Measurement Design for Cyber Security, Proceedings of the 18th Power
Systems Computation Conference, August 18-22, 2014, Wroclaw, Poland.
Gl, M. and Abur, A., PMU Placement for Robust State Estimation, Proceedings of the North American
Power Symposium, Sep. 22-24, 2013, Manhattan, KS.
Acknowledgements
Thank You
Any Questions?
66