Escolar Documentos
Profissional Documentos
Cultura Documentos
Reference Guide
Revision 0
Capital line item projects with a total project cost greater than $20M
All large and/or high-risk projects for which LBNL management
determines that EVM is appropriate.
The EVMS provides for effective project planning and control and is
designed around the integration of technical scope, schedule, and budget
with existing LBNL policies and procedures as defined in the Earned
Value Management System (LBNL-EVMS) Description. The primary
objective of the EVMS is to verify that all elements of a project are
planned, authorized, monitored, and controlled in a consistent, flexible,
and cost-effective manner.
This reference guide should be useful to all project personnel, including
CAMs, Project Managers, Functional Managers, and project office staff.
However, EVMS users are responsible for being familiar with and
following the LBNL EVM System Description and applicable
procedures, which take precedence over this reference guide. The System
Description and implementing procedures are available on the EVMS
website (http://www.lbl.gov/PMO)
CV = BCWP ACWP
CV%
CV% = CV x 100
BCWP
CPI = BCWP
ACWP
Schedule-Related Calculations:
Schedule Variance (SV)
SV = BCWP BCWS
SV% =
SV%
Schedule Performance Index
(SPI)
SV x 100
BCWS
SPI = BCWP
BCWS
Other Calculations:
% Spent =
ACWP(cum) x 100
BAC
EAC may be substituted in the denominator to determine the % of EAC spent (total
funds required).
% Spent
% Complete =
% Complete
To-Complete Performance
Index (TCPI)
BCWP(cum) x 100
BAC
TCPI =
BAC BCWP(cum)
BAC ACWP(cum)
EAC may be substituted for BAC in the
denominator to determine efficiency
needed to complete within the EAC.
Definitions:
ACWP
BAC
Budget at Completion
BCWP
BCWS
EAC
Estimate at Completion
40
39
Float or Total Float. The amount of time an activity can slip before it
affects another activitys finish date. It is the difference between when an
activity can happen and when an activity must happen.
Free Float. The amount of time that the early start of an activity can be
delayed without delaying the early start of a successor activity.
Lag. An offset or delay from an activity to its successor.
Late Dates. Late start and finish dates are the latest dates an activity can
be performed without delaying a successor activity.
Milestone. A schedule event marking the due date for accomplishment
of a specified effort (work scope) or objective. A milestone may mark
the start, an interim step or interface point, or the end of one or more
activities.
Original Duration. The planned estimate of the number of work periods
required to accomplish an activity.
Predecessor. An activity that must occur before another activity. A
predecessor activity controls the early start or early finish date of its
successors. An activity can have multiple predecessors, each with a
different relationship type.
Relationship (Logic) Type. The condition that controls how an activity
is related to its predecessors or successors.
Remaining Duration. The number of work periods forecasts to
complete the activity.
Schedule Contingency. Duration added to a schedule to allow for the
probability of possible or unforeseen events.
Start-to-Finish Relationship (SF). A relationship in which the start of
the predecessor activity controls the Finish of a successor activity.
Start-to-Start Relationship (SS). A relationship in which the start of the
predecessor activity controls the start of a successor activity.
Successor. An activity that occurs after another activity. An activity can
have multiple successors, each with a different relationship type.
38
Baseline Schedule. The version of the schedule that reflects all formally
authorized scope and schedule changes.
Critical Activity. Activity on the projects critical path.
Critical Path. The series of tasks in a network schedule representing the
longest duration for a project. Any slippage of tasks along the critical
path increases the duration of the project. In a project network diagram,
the series of logically linked activities that determine the earliest
completion date for the project. The Critical Path might change from
time to time, as activities are completed ahead of or behind schedule.
Although normally calculated for the entire project, the Critical Path can
also be determined for a milestone or a subproject. The Critical Path is
usually defined as those activities with float less than or equal to a
specified value, often zero.
Critical Path Method (CPM). A network analysis technique used to
predict project duration by analyzing which sequence of activities (which
path) has the least amount of scheduling flexibility (the least amount of
float). Early dates are calculated by means of a forward pass using a
specified start date. Late dates are calculated by means of a backward
pass starting from a specified completion date to result in zero total float
for each activity.
Current Schedule. The schedule that reflects the actual start and finish
dates plus forecasted start and finish dates from today forward.
Project
Project
Execution
Execution
Plan
Plan
Project
Project
Planning
Planning
WBS
WBSDictionary
Dictionary
Planning
Documents
OBS
OBS
CAP/WA
CAP/WA
Scope
Scope
Responsibility
Responsibility
Assignment
Assignment
Matrix
Matrix(RAM)
(RAM)
Scope
Scope
Schedule
Schedule
Basis
Basisof
of
Estimate
Estimate
Project
Project
IDs
IDs
Budget
Budget
Level
Level1,1,22or
or33
Milestones
Milestones
Detail
DetailSchedule
Schedule
and
andlogic
logicties
ties
Establish
Establish
Performance
Performance
Measurement
Measurement
Baseline
Baseline
Signed
SignedWork
Work
Authorization
Authorization
Time
TimePhased
Phased
Budgets
Budgets
Principle No. 4:
Objectively Measure Progress and Performance
Progress Status Reports
Accounting
Accounting
Download
Download
Accruals
Accruals
Schedule
Schedule
Updates
Updates
EAC
EAC
Updates
Updates
EVMS
Database
Executive
Executive
Summary
Summary
Report
Report
Cost
Cost
Performance
Performance
Report
Report
Actual
Cost
Actual
Cost
Report
Report
Variance
Variance
Analysis
Analysis
Report
Report
Time-Phased
Time-Phased
Data
Data
Progress
Progress
Updates
Updates
Subcontractor
Subcontractor
Information
Information
Schedules
Schedules
Updates
Updates
Baseline
Baseline
Changes
Changes
Milestone
Milestoneand
and
Detail
Detail
Schedule
Schedule
Review
Review
Cost/Schedule
Cost/Schedule
Action
Action Item
Item
List
List
Project
Project Cost
Cost
Report
Report
Project
Review
& Analysis
Process
Progress
Progress
Reports
Reports
Performance
Performance
Curves
Curves
Management
Management
Approval
Approval
Project
Project Status
Status Data
Data
Schedule
Schedule
Analysis
Analysis
These
integrated
schedules
are
maintained
in schedule
database
Variance
Variance Analysis
Analysis
Reports
Reports
Final
Final Trend
Trend
&
& Analysis
Analysis
Reports
Reports Issued
Issued
EAC
EAC Analysis
Analysis
Principle No. 7
Management Actions and Change Control
BCP
BCP Approval
Approval
Process
Process
Change
Change
Requirement
Requirement
Identified
Identified
Baseline
Baseline Change
Change
Proposal
Proposal
(BCP)
(BCP)
Prepared
Prepared
BCP
BCP APPROVED
APPROVED
Revised
Revised
Schedule
Schedule
Approved
Approved
Funding
FundingPlan
Plan
(If
(IfRequired)
Required)
Entered
Entered in
in BCP
BCP
Log
Log
Revised
Revised
Scope
Scope
Revised
Revised
Budget
Budget
Revised
Revised&&
Approved
Approved
Baseline
Baseline
Documents
Documents
Management
Management
Actions
Actions &
& Risk
Risk
Mitigation
Mitigation
AUTHORIZED
AUTHORIZED
WORK
WORK
Project
Project
Baseline
BaselineLog
Log
&&Schedules
Schedules
Total Project Cost (TPC). Total cost for the project, including all costs
regardless of sources or type of funds.
Undistributed Budget (UB). Budget associated with specific work
scope or contract changes that have not been assigned to a control
account or summary-level planning package. Not used at LBNL
Work Breakdown Structure (WBS). A product-oriented grouping of
project elements that organizes and defines the total scope of the project.
The WBS is a multilevel framework that organizes and graphically
displays elements representing work to be accomplished in logical
relationships. Each descending level represents an increasingly detailed
definition of a project component. Project components may be products
or services. It is the structure and code that integrates and relates all
project work (technical, schedule, and cost) and is used throughout the
life cycle of a project to identify and track specific work scopes.
Work Breakdown Structure Dictionary. A listing of work breakdown
structure elements with a short description of the work-scope content in
each element.
Work Package. A task or set of tasks performed within a control
account.
Scheduling Terminology
Schedules are organized in a hierarchy that is logically tied within a
critical-path method (CPM) network. The resource-loaded schedule
becomes the basis for scheduling work activities, time-phasing resources,
monitoring and evaluating deviations, and exercising schedule control.
Detailed schedules are monitored and updated first and are then summarized upward to summary-level schedules (see the following figure).
Project schedules are maintained in a database that allows summarization
as well as vertical and horizontal integration.
35
The standard DOE acquisition process (Critical Decisions 0-4) can be tailored on a project-specific basis (e.g., CDs and reviews can
be combined to accommodate alternative acquisition strategies). See the Appendix for definition of acronyms.
IPR Optional
IPR Optional
Identify long-lead
procurements
Identify long-lead
procurements
Refine risk
assessment
Assess risk
Develop rough
cost and schedule
estimate
Address DOE
issues in final PEP
EIR/CR
EIR/CR
Optional
Finalize closeout
documents
Complete RA/
ORR (as
applicable)
Conduct start-up
testing
Complete Title II
design package
Review project risk
and contingencies
Obtain user scope
input
Complete NEPA
checklist/determination
Conduct final
inspections and
commissioning
Update ES&H
documentation
Prepare ES&H
documentation
Establish preliminary baseline
Select Project
Manager and initial
project team
Establish project
organization
Start operations
Bid/award
construction
Update PEP (as
required)
Refine/update
PEP
Prepare CDR to
evaluate options
Establish mission
need
Operations and
Closeout
Construction
Final Design
Preliminary
Design
CD-4 Approve
Start of Operations
CD-3 Approve
Start of Construction
CD-2 Approve
Performance Baseline
CD-1 Approve
Alternate Selection/
Cost Range
Conceptual
Design
Mission Need
Initiation
Phase
CD-0 Approve
Mission Need
Definition
Phase
Execution
Phase
Transition/
Closeout
Phase
34
Planned Value (PV). The sum of the budgets for all work (work
packages, planning packages, etc.) scheduled to be accomplished
(including in-process work packages), plus the amount of level of effort
and apportioned effort scheduled to be accomplished within a given time
period. Also referred to as Budgeted Cost for Work Scheduled (BCWS).
Planning Package. A logical aggregate of work, usually future efforts
that can be identified and budgeted, but which is not yet planned in detail
at the work package or task level.
Program Office. The DOE headquarters organizational element
responsible for managing a program.
Project. In general, a unique effort that supports a program mission; has
defined start and end points; is undertaken to create a product, facility, or
system; and contains interdependent activities planned to meet a
common objective or mission. A project is not constrained to any
specific element of the budget structure (e.g., operating expense or plant
and capital equipment). Construction, if required, is part of the total
project. Projects include planning and execution of construction,
renovation, modification, environmental restoration, decontamination
and decommissioning efforts, and large capital equipment or technology
development activities. Tasks that do not include the above elements,
such as basic research, grants, ordinary repairs, maintenance of facilities,
and operations, are not considered projects.
Project Execution Plan (PEP). The plan for the execution of the
project, which establishes roles and responsibilities and defines how the
project will be executed. Every project implementing Earned Value
management will have a unique project execution plan.
Remaining Duration. The time needed to complete an activity.
Responsibility Assignment Matrix (RAM). A structure that relates the
project organization structure to the work breakdown structure to help
ensure that each element of the projects scope of work is assigned to a
responsible individual.
Risk. A measure of the potential inability to achieve overall project
objectives within defined cost, schedule, and technical constraints, and
has two components: (1) the probability/likelihood of failing to achieve a
33
These procedures provide the basis and this document provides guidance
for performance of the LBNL EVMS Surveillance Review.
ANSI EIA-748-B-2007 identifies 32 guidelines for establishing and
applying an integrated EVMS and categorizes these guidelines into five
functional groups. The LBNL EVM System Description addresses these
guidelines and functional areas in detail. This Reference Guide is
organized around the five functional groups as follows:
Organization
Planning, Scheduling, and Budgeting
Accounting Considerations
Analysis and Management Reports
Revisions and Data Maintenance.
32
Organization
Project organization is the first and most important function of project
management. The project organization process ensures that the work is
adequately defined, identifies the organizations responsible for performing the work, and assigns responsibilities for managing and performing
the work to the appropriate internal or external organization. An effective
project organization uses the following tools (illustrated in the following
figures):
Physical
Sciences Facility
Selected
WBS
Elements
and
Designated
Contract
Reporting
Levels
Engineering &
Design
Preliminary
Design
WBS
Extension
Planning &
Evaluation
Schematic
Design
Final Design
Design Services
Design
Development
Construction
Engineering
Inspection
Commissioning
Plan
Facility Safety
Analysis
Sustainability
30
Sustainability
LBNL
PNNL
10
Control Account
Control Account
Control Account
Control Account
Control Account
Control Account
Control Account
Control Account
Control Account
Commissioning Plan
Design Services
Planning & Evaluation
WBS
Extension
Engineering Inspection
Preliminary Design
Final Design
Construction
Engineering & Design
Selected
WBS
Elements and
Designated
Contract
Reporting
Levels
Quality
Assurance
Engineering
Construction
Design
Drafting
Electrical
Mechanical
/Piping
Responsibility Assignment
Matrix (RAM) Aligns the WBS
Civil/
Structural
O R G A N IZ A T IO N A L D A T A S U M M A R IZ A T IO N
C on tr o l A c c ou n t
C on tr o l A c c ou n t
C on tr o l A c c ou n t
P la n n in g
P a ck a ges
B CW S , B CW P,
A CW P , B A C , E A C
V a ria n c e s
C on tr o l A c c ou n t P la n
W o rk
P a ck ag es
C on tr o l A c c ou n t
C on tr o l A c c ou n t
C on tr o l A c c ou n t
C on tr o l A c c ou n t
F ac ility S a f e ty
A n a ly s is
D es ig n
D e v e lo p m e n t
S c h e m a tic
D es ig n
C om m is s io n in g
P la n
D es ig n S e r v ic es
P la n n in g &
E v a lu a tio n
E n g in e e r in g
In s p ec tio n
P r elim in a r y D es ig n
F in a l D es ig n
C on s tru c tio n
Quality
Assurance
ORGANIZATIONATRUCTURE STRUCTURE
PNNL
P h ys ic al
S c ie n c es F ac ility
E n g in e e r in g
& D es ig n
C on tr o l A c c ou n t
Engineering
Construction
W BS
E xte n s io n
C on tr o l A c c ou n t
Design
S ele c te d
W BS
E le m e n ts
and
D es ig n a te d
C on tr ac t
R ep o r tin g
L e v e ls
Drafting
Electrical
S u s ta in a b ility
Mechanical
/Piping
11
Civil/
Structural
28
OPC
ORR
PBB
PEP
PMB
PP
QA
RAM
RA
SAR
SBMS
SOW
SPI
SV
TAB
TCPI
TEC
TPC
UB
VAC
WBS
EVMS Terminology
Accrual Method. An accounting method in which revenue is recognized
when earned rather than when collected, and in which expenses are
recognized when incurred rather than when paid. Accrual-basis
accounting is essential to accurate performance and progress information
on contracts.
Acquisition Executive (AE). The individual designated by the Secretary
of Energy to integrate and unify the management system for a program
portfolio of projects, and implement prescribed policies and practices.
Acquisition Strategy. A high-level business and technical management
approach designed to achieve project objectives within specified resource
constraints. It is the framework for planning, organizing, staffing,
controlling, and leading a project. It provides a master schedule for
activities essential for project success, and for formulating functional
strategies and plans.
Actual Cost of Work Performed (ACWP). Total costs incurred (direct
and indirect) in accomplishing an identified element or scope of work
during a given time period. Also referred to as Actual Cost (AC).
27
12
Establish
Cost/Schedule
Range
Develop
Detailed Cost
Schedule
Refine Project
Scope, WBS,
OBS
Refine Control
Accounts and
Assign CAMs
Develop
Detailed
Schedule
Conduct
Alternative
Analysis
Selection
Plan/Define Earned
Value Techniques
Cost/Schedule
Baseline (BCWS)
CD-2
Approval
Risk Assessment (Technical, Cost, and Schedule)
CD-1
Approval
13
Appendix A
A list of acronyms
EVMS terminology
Scheduling terminology
Acronyms
ACWP
BAC
B&R
BCR
BCWP
BCWS
CA
CAM
CD
CDR
CPI
CPM
CPR
CV
D&D
DOE
EAC
EIR
ES&H
ETC
EVMS
G&A
GPP
ICE
IPR
IPS
IPT
LOE
M&O
NEPA
MR
NNSA
OBS
DOE/HQ
(Level 1)
Budget
Increase in excess of
$25M or 25%
(cumulative) of the
original cost baseline.
Schedule
6 months or greater
delay in the project
completion date
3-month delay of a
Level 1 milestone date
Technical scope
Technical scope
Budget
DOE/BSO Federal
Project Director
(Level 2)
LBNL Project
Manager (Level 3)
The three key components for EVMS metrics are Actual Cost for Work
Performed (ACWP), Budgeted Cost for Work Performed (BCWP) or
Earned Value (EV), and Budgeted Cost for Work Scheduled (BCWS) or
Planned Value (PV) (see table below). These values are always
expressed in dollars. Two other key performance elements are schedule
variance (SV) and cost variance (CV).
Performance Metrics
ACWP
BCWP
BCWS
CV
SV
The three basic methods for measuring performance are listed below:
Schedule
1-month delay of a
Level 2 or 3-month
delay of a Level 3
milestone date.
25
Discrete effort. Discrete tasks are those tasks that are quantifiable to
individual work products or predetermined tangible measurements.
Techniques used for discrete effort include the following:
Material or subcontract items also use an effective performance measurement that allows for earned value to be claimed in the same accounting period as actual costs. In general, material performance is earned as
follows:
The purpose of establishing and controlling changes to the project baseline is not only to control scope creep but also to facilitate measurement of actual performance in relation to planned performance. Performance can only be assessed against baseline activities. If effort is expended
against additional work that is not in the baseline, performance will not
be recognized, therefore, it is imperative that changes to the scope be
formally made through the change control processor something
similar. Poor performance is not a valid reason for requesting a change to
a baseline.
The following table illustrates a typical change control methodology.
15
24
Budget Overrun
VAC
BAC
Time
Now
Definitions
Percent Spent =
23
ACWPcum
BAC
BCWP cum
Percent Complete =
Overall Status
CV = BCWP ACWP
SV = BCWP BCWS
Performance Formulas
BCWS
ACWP
Time
Schedule Variance
BCWP
Management Reserve
Cost Variance
PMB
Total Authorized
Budget (TAB)
Completion
Date
Time Delay
EAC
Accounting Considerations
Existing LBNL financial and business management systems are used as
the basis for cost and commitment reporting (as illustrated in the following figure). Actual costs and obligations are gathered through several
systems including the time card system, travel system, procurement system, and subcontracts management system. Costs and obligations are
collected at the lowest level of the WBS and imported into the integrated
project controls system on a monthly basis. Direct cost is brought into
the integrated project controls system consistent with the way budgets
have been established to ensure effective performance management.
The LBNL financial management system complies with all applicable
federal financial requirements, including Federal Acquisition
Regulations, Cost Accounting Standards, the DOE Accounting
Handbook, and the current LBNL Management & Operations (M&O)
Performance-Based Management Contract (PBMC) for the management
and operation of the Ernest Orlando Lawrence Berkeley National
Laboratory (LBNL). DOE approves all labor and overhead rates annually
as required by the M&O contract.
Retroactive changes to accounting records are not allowed. Prior period
adjustments and corrections for mischarges, rate adjustments, or accounting errors are made in the current accounting month before the next
month-end closeout. Accounting adjustments and cost transfers from one
charge code to another are proposed by the project team and approved
and processed by Business Support Services staff, consistent with LBNL
cost-charging guidelines. Actual cost and commitment information
reported in the projects Cost Performance Reports (CPRs) is reconciled
each month and is consistent with the costs recorded in LBNLs financial
system. The following paragraphs describe how costs are incorporated.
Cost collection. The cost-charging structure within LBNLs financial
management system ensures that actual costs collected are directly compared with associated budgets for all work elements. Project IDs are
established that uniquely identify costs down to WBS work packages and
CAs, which allows costs to be accumulated and summarized to higher
levels of the WBS.
16
An EAC based on predictive performance measures increases the probability that the project can be executed within the overall budget objectives. Monthly EAC reviews are essential for management decisions,
including planning for future project funding requirements. On a monthly
basis, CAMs review the status of expended effort and the achievability of
the forecast using all available information to arrive at the most accurate
EAC.
The following figure illustrates cost and schedule performance metrics
and their relationship with the Total Authorized Budget (TAB) (the PMB
plus the management reserve/Contingency).
17
22
No
Prepare
CPR and
VAR
Yes
Adjust
EAC
Review and
Analyze
CPI/SPI
Variances
Corporate
Financials
ACWP
Financial
Processing
System
Actual Cost:
- Time sheets
- Material
- Indirects
Variance Analysis Reporting and Cost Performance Report Production Process Flow
Issue
CPR
Review/
Approve
CPR/VAR
Initial
Reports
Cost
Processor
Plan.Net
(BCWP calculated
in Cost Processor)
Physical %
Complete
BCWS
Baseline
Data:
- Scope
- Budget
- Schedule
Performance Data:
- Field Verification
- Schedule Status
21
18
Effective analysis of deviations from the project plan for both schedule
and cost allows management to rapidly and effectively implement corrective actions (see the following figures).
Conceptual design/project
development
Using the monthly CPR, the CAM can complete the following activities:
Construction
Equipment
Design criteria
Selection of architect/engineer
CAMs are required to review, analyze, and report on all CAs with variances exceeding specified thresholds for the current month, cumulative,
or at completion, as established in the PEP for the project. Variance
analysis provides the means for the CAM to communicate scope, budget,
schedule, and estimate at completion (EAC) divergences from the PMB.
The following figure shows the activities associated with the monthly
variance analysis and CPR process.
19
20