Escolar Documentos
Profissional Documentos
Cultura Documentos
Buggies (manual/powered)
Rarely used
Concrete Placer 1
Concrete Placer 2
6,090
Foreman 1 x 63 x $24
1,512
Laborers 12 x 63 x $21
15,876
Operators 2 x 63 x $30
3,780
Totals
21,168
6,090
7.06
2.03
7,500
1,272
Laborers 14 x 53 x $21
15,582
Operators 2 x 53 x $30
3,180
Totals
Price per Cy (/3000)
20,034
6.68
7,500
2.50
C. Conveyors: 2; 72 cy/hr
Crew: 1 foreman, 18 laborers, 2 operators
Time required = (3000 cy/72 cy/hr) + 3 hrs for
startup and finishing = 47 hours
Cost
4,600
1,128
Laborers 18 x 47 x $21
17,766
Operators 2 x 47 x $30
2,820
Totals
Price per Cy (/3000)
21,714
7.24
4,600
1.53
3. Properties of Concrete
Formwork
Cost of Material
Cost of fabrication of form system
Cost of setting up (erecting) the system
Cost of stripping the system, including the cost of
cleaning, oiling, and repairing the system
Other costs such as transportation, handling, and
storage
Formwork Productivity
In addition to the general Job factors and
Labor & Management factors, productivity of
formwork maybe particularly affected by
1.
2.
3.
4.
1. Number of Reuses
Gang Formwork
Pricing Formwork
31.00
31.00
Carpenter
28.00
140.00
Laborers
21.00
42.00
213.00
0.59
Labor - Fabrication
0.71
Labor - Erecting
2.84
Labor - Stripping
0.70
0.12
Total
4.96
Reinforcing Steel
Reinforcing Bars
Welded Wire Mesh
Cost of material
Cost of handling, cutting and bending
Cost of delivery to site
Cost of accessories such as spacers, ties,
chairs.
Labor cost for placement
Cost of preparation of shop drawings
Normally by
Subcontractor
Supply of material
Delivery of Material
Labor cost of placement