Você está na página 1de 138

IMPROVEMENT OF QUALITY MANAGEMENT FOR

HIGHWAY AND BRIDGE CONSTRUCTION AND


MAINTENANCE, PHASE II

GUIDEBOOK FOR
ROAD CONSTRUCTION AND
MAINTENANCE MANAGEMENT

2014

Department of Public Works and Highways

IMPROVEMENT OF QUALITY MANAGEMENT FOR


HIGHWAY AND BRIDGE CONSTRUCTION AND
MAINTENANCE, PHASE II

GUIDEBOOK FOR ROAD CONSTRUCTION


AND MAINTENANCE MANAGEMENT
SECOND EDITION

SEPTEMBER 2014

DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS


JAPAN INTERNATIONAL COOPERATION AGENCY

Republic of the Philippines


DEPARTMENT OF PUBLIC WORKS AND HIGHWAYS
OFFICE OF THE SECRETARY
Manila

TABLE OF CONTENTS
FOREWORD

TABLE OF CONTENTS..................................................................................

ii

LIST OF TABLES ...........................................................................................

vi

LIST OF FIGURES .........................................................................................

vii

ACKNOWLEDGMENT ...................................................................................

xii

ACRONYMS .................................................................................................

xiii

Chapter 1

INTRODUCTION.......................................................................

1- 1

1.1

Background ..................................................................................................

1- 1

1.2

Purpose ........................................................................................................

1- 2

Chapter 2

SOIL CLASSIFICATION AND MODULUS ..................................

2- 1

2.1

Unified Soil Classification .............................................................................

2- 1

2.2

Reference Data for Soil Classification ..........................................................

2- 2

2.3

Estimated Soil Modulus by N-value..............................................................

2- 4

Chapter 3

ROAD DRAINAGE ....................................................................

3- 1

Design of Drainage .....................................................................................

3- 1

3.1.1

Estimating Discharge ..............................................................................

3- 1

3.1.2

Capacity of Drainage ..............................................................................

3- 4

3.1.3

Specific Discharge Curve........................................................................

3- 5

Cross Drainage ............................................................................................

3- 7

3.1

3.2

3.2.1

Installation of Cross Drainage .................................................................

3- 7

3.2.2

Headwalls ...............................................................................................

3- 7

Underground Drainage .................................................................................

3- 8

3.3

3.3.1

Function of Underground Drainage.........................................................

3- 8

3.3.2

Typical Cross Section of Underground Drainage System .......................

3- 9

3.3.3

Treatment of Seepage from Mountainous Slope ....................................

3- 9

3.3.4

Underground Drainage on Cut and Embankment Portions ....................

3-10

Chapter 4
4.1

PAVEMENT ...............................................................................

4- 1

Types of Pavement.......................................................................................

4- 1

Guidebook for Road Construction and Maintenance Management

ii

4.1.1

Rigid Pavement.......................................................................................

4- 1

4.1.2

Flexible Pavement ..................................................................................

4- 2

Portland Cement Concrete Pavement ..........................................................

4- 2

4.2

4.2.1

Quality Control ........................................................................................

4- 2

4.2.2

Design Mix and Trial Paving....................................................................

4- 2

4.2.3

Admixture/Additive ..................................................................................

4- 3

4.2.4

Concrete Paving Activities.......................................................................

4- 3

4.2.5

Types of Formworks................................................................................

4- 4

4.2.6

Weakened Plane Joint ............................................................................

4- 4

4.2.7

Replacement of Deteriorated PCC Slabs................................................

4- 6

4.2.8

PCCP Widening ......................................................................................

4- 7

4.2.9

Temperature Control ...............................................................................

4- 7

4.2.10 Surface Texturing ....................................................................................

4- 8

4.2.11 Subbase ..................................................................................................

4- 8

4.2.13 Asphalt Concrete Overlay on PCCP .......................................................

4- 8

4.3

Introduction of Newly Approved Pavement Materials ...................................

4.3.1

Instapave ................................................................................................

4- 9

4.3.2

Pavement Dressing Conditioner .............................................................

4- 9

4.3.3

Polymer Modified Bitumen ......................................................................

4-10

4.3.4

Stone Mastic Asphalt ..............................................................................

4-10

Chapter 5
5.1

SLOPE PROTECTION WORKS ................................................

5- 1

Appropriate Slope .........................................................................................

5- 1

5.1.1

Cut Slope ................................................................................................

5- 1

5.1.2

Embankment Slope.................................................................................

5- 3

Slope Failure ................................................................................................

5- 4

5.2

5.2.1

Soil Slope Collapse .................................................................................

5- 4

5.2.2

Rock Slope Collapse...............................................................................

5- 5

5.2.3

Landslide.................................................................................................

5- 6

5.2.4

Road Slip ................................................................................................

5- 7

5.2.5

Debris Flow .............................................................................................

5- 9

Slope Failure Countermeasures ...................................................................

5-10

5.3

iii

4- 9

5.3.1

Soil Slope Failure Countermeasures ......................................................

5-10

5.3.2

Rock Slope Failure Countermeasures ....................................................

5-11

Guidebook for Road Construction and Maintenance Management

5.4

Slope Erosion Control ..................................................................................

5-11

5.4.1

Slope Drainage .......................................................................................

5-12

5.4.2

Vegetation Works ....................................................................................

5-13

5.4.3

Coconet Bio-engineering ........................................................................

5-16

Slope Protection Structures ..........................................................................

5-21

5.5

5.5.1

Retaining Walls .......................................................................................

5-22

5.5.2

Grouted Riprap .......................................................................................

5-23

5.5.3

Cribwall ...................................................................................................

5-24

5.5.4

Gabion Wall ............................................................................................

5-26

5.5.5

Mechanically Stabilized Embankment Wall (MSE Wall)..........................

5-27

Rock Slope Protection ..................................................................................

5-28

5.6

5.6.1

Cutting and Removal ..............................................................................

5-28

5.6.2

Shotcrete ................................................................................................

5-28

5.6.3

Rocknet...................................................................................................

5-29

5.6.4

Rock Catcher ..........................................................................................

5-30

5.6.5

Rock Shed ..............................................................................................

5-30

5.7

Countermeasures for Landslide ...................................................................

5-30

5.8

Provision of Underground Drainage Pipe thru Boring ..................................

5-30

5.9

Slope Stability Analysis ................................................................................

5-32

Chapter 6
6.1

RIVER AND COASTAL EROSIONS ..........................................

6-1

River Erosion ................................................................................................

6- 1

6.1.1

Examples of Road Damages caused by River Erosion ..........................

6- 2

6.1.2

Countermeasures for River Erosion........................................................

6- 2

Coastal Erosion ............................................................................................

6-13

6.2

6.2.1

Case 1: Scouring of Foundation .............................................................

6-13

6.2.2

Case 2: Washout of Backfill Materials.....................................................

6-15

6.2.3

Case 3: Collapse of Mainbody ................................................................

6-17

6.2.4

Countermeasures for Coastal Erosion ....................................................

6-18

Chapter 7
7.1

ROAD SAFETY .........................................................................

7- 1

Road Signs...................................................................................................

7- 1

7.1.1

Classifications .........................................................................................

7- 1

7.1.2

Standard Application ...............................................................................

7- 3

Guidebook for Road Construction and Maintenance Management

iv

7.1.3

Design .....................................................................................................

7- 4

7.2

Weighbridge Station .....................................................................................

7- 4

7.3

Road Warning System..................................................................................

7- 6

Chapter 8
8.1

8- 1

Weather Monitoring ......................................................................................

8- 1

8.1.1

Rain Gauges ...........................................................................................

8- 1

8.1.2

Weather Station ......................................................................................

8- 2

Visual Inspection of Pavement .....................................................................

8- 2

8.2

8.2.1

ROCOND ................................................................................................

8- 2

8.2.2

Portable Falling Weight Deflectometer (FWD) ........................................

8- 2

Slope Investigation .......................................................................................

8- 8

8.3

8.3.1

Measurement ..........................................................................................

8- 8

8.3.2

Visual Slope Investigation .......................................................................

8- 9

8.3.3

Digital Clinometer ....................................................................................

8-11

Slope Monitoring ..........................................................................................

8-16

8.4

8.4.1

Crack Monitoring .....................................................................................

8-16

8.4.2

Wire Extension Meter ..............................................................................

8-16

Soil Investigations.........................................................................................

8-17

8.5

8.5.1

Boring and Core Sampling ......................................................................

8-17

8.5.2

Sounding for Soil Strength Test...............................................................

8-18

Ground Water Survey and Monitoring ..........................................................

8-21

8.6

8.6.1

Ground Water Logging ............................................................................

8-21

8.6.2

Hand Held Water Quality Sensor ............................................................

8-23

Strain Gauge with PVC Pipe ........................................................................

8-24

8.7

MONITORING AND INVESTIGATION ........................................

8.7.1

Summary of Pipe Strain Gauge ..............................................................

8-24

8.7.2

Checklist for Installation of Pipe Strain Gauge ........................................

8-24

8.7.3

Strain Gauges Monitoring .......................................................................

8-24

8.7.4

Digital Strain Meter..................................................................................

8-27

Guidebook for Road Construction and Maintenance Management

LIST OF TABLES
Table 2.1

Unified Soil Classification System (Sands and Gravels) ...................

2- 1

Table 2.2

Unified Soil Classifications (Silts, Clays and Organic Soils) ..............

2- 2

Table 2.3

Soil Classification Reference Data for Preliminary Design ................

2- 3

Table 2.4

N-value and Internal Friction Angle (Sand) ........................................

2- 4

Table 2.5

N-value and Unconfined Compressive Strength (Clay) .....................

2- 4

Table 3.1

Drainage Area....................................................................................

3- 1

Table 3.2

Values of Runoff Coefficient, C ..........................................................

3- 2

Table 3.3

Design Flow Return Period................................................................

3- 3

Table 3.4

Mannings Roughness Coefficient .....................................................

3- 4

Table 3.5

Appropriate Range of Flow Velocity ..................................................

3- 5

Table 3.6

Installation of Cross Drainage ...........................................................

3- 7

Table 4.1

Requirements for Admixtures ............................................................

4- 3

Table 4.2

Types and Functions of PCCP Joints ................................................

4- 5

Table 4.3

Size and Length of Dowel/Tie Bars ...................................................

4- 6

Table 4.4

Preventive Measures for Reflection Cracks on AC Overlay ..............

4- 9

Table 4.5

Material Composition of Pavement Dressing Conditioner .................

4-10

Table 5.1

Cutting Height and Cut Slope ............................................................

5- 1

Table 5.2

Standard Cut Slope Gradient for Japan Highways ............................

5- 2

Table 5.3

Japans Standard Gradients for Road Embankment Slopes .............

5- 4

Table 5.4

Applicable Cut Slope .........................................................................

5-14

Table 5.5

Physical properties (Coconet) ...........................................................

5-16

Table 5.6

Physical properties (Cocolog) ............................................................

5-17

Table 5.7

Materials Requirement for Grouted Riprap and Stone Masonry........

5-24

Table 5.8

Required Safety Factor for Landslide Countermeasures...................

5-33

Table 6.1

Countermeasures against River Erosions .........................................

6- 3

Table 6.2

Required Depth and Width of Groundsill ...........................................

6-10

Table 6.3

Countermeasures for Coastal Erosion ..............................................

6-18

Table 7.1

Maximum Allowable Vehicle Weight ..................................................

7- 5

Table 8.1

Poisson's Ratio ..................................................................................

8- 4

Table 8.2

Specific Displacement Level for FWD ...............................................

8- 5

Table 8.3

Drop Height of Weight for Main Test ..................................................

8- 5

Table 8.4

Estimation of N-value from Nd-value of SDCP ..................................

8-20

Table 8.5

Criteria for Groundwater Logging ......................................................

8-22

Table 8.6

Objected Water Properties ................................................................

8-23

Table 8.7

Criteria for Evaluation of Data of Strain Gauges................................

8-25

Guidebook for Road Construction and Maintenance Management

vi

LIST OF FIGURES
Figure 3.1

Rainfall Intensity Duration Frequency (RIDF) Curves Source:


328 Baguio Synoptic Station..............................................................

Figure 3.2

3- 3

Rainfall Intensity Duration Frequency (RIDF) Curves Source:


646 Mactan Synoptic Station .............................................................

3- 3

Figure 3.3

Hydraulic Radius Formula .................................................................

3- 5

Figure 3.4

Specific Discharge Curve (Luzon) .....................................................

3- 6

Figure 3.5

Specific Discharge Curve (Visayas) ..................................................

3- 6

Figure 3.6

Specific Discharge Curve (Mindanao) ...............................................

3- 6

Figure 3.7

Typical Inlet and Outlet Headwalls .....................................................

3- 7

Figure 3.8

Structure of Headwall ........................................................................

3- 8

Figure 3.9

Relation of Water Content and CBR ..................................................

3- 8

Figure 3.10 Typical Underground Drainage for a 2-lane Road .............................

3- 9

Figure 3.11 Typical Underground Drainage for a 4-lane Road .............................

3- 9

Figure 3.12 Typical Underground Road Drainage for Mountainous Terrain ..........

3- 9

Figure 3.13 Treatment of Seepage from Mountainous Slope ...............................

3- 10

Figure 3.14 Underground Drainages on Cut and Embankment Sections .............

3- 10

Figure 4.1

Conceptual Figure Showing Load Distribution


for Rigid and Flexible Pavements ......................................................

4- 1

Figure 4.2

Flowchart for Preparatory Work for Concrete Paving ........................

4- 2

Figure 4.3

Concrete Paving Activities .................................................................

4- 3

Figure 4.4

Paving Works ....................................................................................

4- 4

Figure 4.5

PCCP Joints and Load Transfer Device ............................................

4- 5

Figure 4.6

Deteriorated PCCP ............................................................................

4- 6

Figure 4.7

PCCP Widening.................................................................................

4- 7

Figure 4.8

PCCP Widening Work .......................................................................

4- 7

Figure 4.9

Thermometer .....................................................................................

4- 7

Figure 4.10 Texturing of the Surface .....................................................................

4- 8

Figure 4.11 Laying of Base Materials by Means of Road Grader and Paver ........

4- 8

Figure 5.1

Geology and Slope Gradient .............................................................

5- 3

Figure 5.2

Typical Soil Slope Collapse ...............................................................

5- 5

Figure 5.3

Typical Rock Slope Collapse .............................................................

5- 5

Figure 5.4

Typical Landslide ...............................................................................

5- 6

Figure 5.5

Road Slip ...........................................................................................

5- 7

Figure 5.6

Typical Road Slip ...............................................................................

5- 7

Figure 5.7

Stages of Road Slip ...........................................................................

5- 7

vii

Guidebook for Road Construction and Maintenance Management

Figure 5.8

Landslide Caused by Water Infiltration from Road ............................

5- 8

Figure 5.9

Road Slip due to Slope Erosion .........................................................

5- 8

Figure 5.10 Surface Flow Concentrations ............................................................

5- 9

Figure 5.11 Road Slip caused by Leakage from Pipe Culvert ..............................

5- 9

Figure 5.12 Typical Debris Flow ...........................................................................

5-10

Figure 5.13 Selections of Soil Slope Failure Countermeasures ...........................

5-10

Figure 5.14 Selections of Rock Slope Failure Countermeasures .........................

5-11

Figure 5.15 Relation between Slope and Rainfall.................................................

5-11

Figure 5.16 Erosion on Cut Slope.........................................................................

5-12

Figure 5.17 Relations between Content Ratio of Fines


and Natural Water Content ................................................................

5-12

Figure 5.18 Surface Water Overtopping Slope Drainage .....................................

5-13

Figure 5.19 Inappropriate Vegetation Work ..........................................................

5-14

Figure 5.20 Wicker Works as Vegetation Base ....................................................

5-14

Figure 5.21 Vetiver Grass .....................................................................................

5-15

Figure 5.22 Sketch of slope to be protected with Vetiver Grass ...........................

5-15

Figure 5.23 Coconet (CGN 700) ...........................................................................

5-17

Figure 5.24 Cocolog/Fascine (CGR 200) .............................................................

5-17

Figure 5.25 Stakes ...............................................................................................

5-17

Figure 5.26 Coco Coir Peat ..................................................................................

5-18

Figure 5.27 Ropes ................................................................................................

5-18

Figure 5.28 Typical Cross Sections for Bio-Engineering Works ...........................

5-19

Figure 5.29 Site Preparation .................................................................................

5-20

Figure 5.30 Laying of Nets....................................................................................

5-20

Figure 5.31 Anchoring ..........................................................................................

5-21

Figure 5.32 Sewing...............................................................................................

5-21

Figure 5.33 Hydroseeding ....................................................................................

5-21

Figure 5.34 Gravity Type (Rock Catcher Retaining Wall) .....................................

5-22

Figure 5.35 Leaning Type Retaining Wall .............................................................

5-22

Figure 5.36 Construction steps for Stone Masonry ..............................................

5-23

Figure 5.37 Construction steps for Grouted Riprap ..............................................

5-23

Figure 5.38 Grouted Riprap ..................................................................................

5-24

Figure 5.39 Stone Masonry Cribwall.....................................................................

5-25

Figure 5.40 Reinforced Concrete Crib and Pitching Wall .....................................

5-25

Figure 5.41 Reinforced Concrete Frame with Vegetation Works ..........................

5-26

Figure 5.42 Gabion Wall .......................................................................................

5-26

Figure 5.43 Constructed Gabion Wall at a Location with Seepage ......................

5-27

Guidebook for Road Construction and Maintenance Management

viii

Figure 5.44 Mechanically Stabilized Embankment by means of Geotextile fabrics

5-27

Figure 5.45 Mechanically Stabilized Embankment Wall (Terree Armee Wall).......

5-27

Figure 5.46 Relation between Rock Slope Height and Height of Bounce of Stone

5-28

Figure 5.47 Cutting and Removal of Unstable Rock Slope...................................

5-28

Figure 5.48 Shotcrete ...........................................................................................

5-29

Figure 5.49 Rocknet .............................................................................................

5-29

Figure 5.50 Rock Catcher .....................................................................................

5-30

Figure 5.51 Rock Shed .........................................................................................

5-30

Figure 5.52 Rainfall and Groundwater Level ........................................................

5-31

Figure 5.53 Typical Underground Drainage Pipe Installations ..............................

5-31

Figure 5.52 Fellenius Method ...............................................................................

5-32

Figure 6.1

Degradation due to Riverbed Erosion................................................

6- 1

Figure 6.2

Riverbank Erosion at Bend ................................................................

6- 2

Figure 6.3

Riverbank Erosion caused by Overflow .............................................

6- 2

Figure 6.4

Riverbed Erosion ...............................................................................

6- 2

Figure 6.5

Selection of River Erosion Countermeasures Flowchart ...................

6- 3

Figure 6.6

Types of Revetment Works................................................................

6- 4

Figure 6.7

Design Procedure for River Revetment Work ....................................

6- 5

Figure 6.8

Typical Cross Section of Revetment Works.......................................

6- 5

Figure 6.9

Laying of Concrete Blocks on River Slope ........................................

6- 6

Figure 6.10 Sample Arrangement of Groundsills ..................................................

6- 7

Figure 6.11 Typical section of Groundsill ..............................................................

6- 7

Figure 6.12 Design Procedure for Groundsill........................................................

6- 8

Figure 6.13 Arrangement of Groundsills Relative to the Direction of Flow ...........

6- 9

Figure 6.14 Details of Groundsill...........................................................................

6- 9

Figure 6.15 Typical Section of Groundsill .............................................................

6-10

Figure 6.16 Rechanneling Concept for Riverbank and Riverbed Protections .......

6-11

Figure 6.17 Type of Spur Dike ..............................................................................

6-11

Figure 6.18 Typical Cross Sections of Spur Dike..................................................

6-12

Figure 6.19 Examples of Road Damages caused by Coastal Erosion .................

6-13

Figure 6.20 Collapse of Coastal Revetment due to Scouring of Foundation Bed .

6-14

Figure 6.21 Conceptual Diagram of Scouring of Foundation Bed ........................

6-14

Figure 6.22 Collapse of Coastal Revetment .........................................................

6-15

Figure 6.23 Collapse of Coastal Revetment due to Washout of Backfill Materials

6-16

Figure 6.24 Washout of Backfill Material...............................................................

6-16

Figure 6.25 Collapse of Coastal Revetment due to Washed out Backfill Material

6-16

Figure 6.26 Collapse of Coastal Revetment due to Overtopping ..........................

6-17

ix

Guidebook for Road Construction and Maintenance Management

Figure 6.27 Levels of Erosion of Grouted Riprap Surface ....................................

6-17

Figure 6.28 Collapsed Revetment due to Progression of Cracks .........................

6-18

Figure 6.29 Conceptual Design of Coastal Slope Revetment ..............................

6-19

Figure 6.30 Selection of Countermeasures against Coastal Erosion ...................

6-20

Figure 6.31 Typical Foundation Water Cut-off Wall ..............................................

6-21

Figure 6.32 Considerations for Coastal Revetment Design ..................................

6-22

Figure 7.1

Regulatory Signs (Type R) ................................................................

7- 2

Figure 7.2

Warning Signs (Type W)....................................................................

7- 2

Figure 7.3

Guide or Informative Signs (Type G) .................................................

7- 2

Figure 7.4

Instructional Signs (Type S) ...............................................................

7- 3

Figure 7.5

Hazard Markers (Type HM) ...............................................................

7- 3

Figure 7.6

Weighbridge Stations ........................................................................

7- 4

Figure 7.7

Road Status and Information System ................................................

7- 6

Figure 8.1

Manual Data Collection from a Standard Rain Gauge.......................

8- 1

Figure 8.2

Standard Rain Gauge ........................................................................

8- 1

Figure 8.3

Weighing Precipitation Rain Gauge ...................................................

8- 1

Figure 8.4

Weather Station .................................................................................

8- 2

Figure 8.5

Setting up of FWD .............................................................................

8- 3

Figure 8.6

The Drop Rig .....................................................................................

8- 3

Figure 8.7

The Mainbody and Display Instrument ..............................................

8- 3

Figure 8.8

Measure Display of Portable FWD ....................................................

8- 4

Figure 8.9

Estimated Engineering Property ........................................................

8- 6

Figure 8.10 Example of Analysis Sheet for Portable FWD ...................................

8- 7

Figure 8.11 Rough Determination of Slope Height and Angle ..............................

8- 8

Figure 8.12 Road Slope Survey by Digital Distance Meter ...................................

8- 8

Figure 8.13 Digital Distance Meter .......................................................................

8- 8

Figure 8.14 Visual Slope Investigation (1/2) .........................................................

8- 9

Figure 8.15 Visual Slope Investigation (2/2) .........................................................

8- 9

Figure 8.16 Block Diagram of Complex Earth Slide/Earth Flow ...........................

8-10

Figure 8.17 Typical Configuration and Phenomena of Earth Slide .......................

8-10

Figure 8.18 Important Locations for Slope Investigation on Cut Slope .................

8-10

Figure 8.19 Strike and Dig ....................................................................................

8-11

Figure 8.20 Clinometer .........................................................................................

8-11

Figure 8.21 Parts of Digital Clinometer .................................................................

8-12

Figure 8.22 Usage of Digital Clinometer ...............................................................

8-12

Figure 8.23 Crack Displacement Measurement ...................................................

8-16

Figure 8.24 Wire Extension Meter ........................................................................

8-16

Guidebook for Road Construction and Maintenance Management

Figure 8.25 Sample Core Boring at Landslide Portion..........................................

8-17

Figure 8.26 Sample Core Boring at Soft Rock Slide .............................................

8-17

Figure 8.28 Schematic Diagram of Standard Penetration Test .............................

8-18

Figure 8.29 Dynamic Cone Penetrometer (Dual Mass Type) ...............................

8-18

Figure 8.30 Operation of DCP ..............................................................................

8-19

Figure 8.31 Simplified Dynamic Cone Penetrometer ............................................

8-19

Figure 8.32 Friction Loss on Simplified Dynamic Cone Penetrometer Test ..........

8-20

Figure 8.33 Simplified Dynamic Cone Penetrometer (Sample Output) ................

8-21

Figure 8.34 Schematic Diagram of Groundwater Logging ....................................

8-22

Figure 8.35 Sample Graph of Groundwater Logging ............................................

8-22

Figure 8.36 Pipe Strain Gauge .............................................................................

8-24

Figure 8.37 Sample Pipe Strain Gauge Monitoring ..............................................

8-25

Figure 8.38 Monitoring of Pipe Strain Gauge (Sample Output) ............................

8-26

Figure 8.40 Monitoring of Pipe Strain Gauge (Sample Profile) .............................

8-27

Figure 8.42 Connection with Half Bridge Type ......................................................

8-29

Figure 8.41 Strain Gauges with PVC Pipe ............................................................

8-29

xi

Guidebook for Road Construction and Maintenance Management

ACKNOWLEDGEMENT
In behalf of the CWG on Road Manuals Improvement, the Group Leader acknowledges the
TWG members and the regional project managers of pilot regions for their patience,
guidance, words of encouragement and useful critiques which really helped us a lot in
accomplishing this undertaking.
TWG Members:
Dr. Judy F. SESE, Chairperson, OIC-Director, Bureau of Research and Standards
Ms. Carolina S. CANUEL, Fmr. Vice Chairperson, Fmr. Div. Chief, DPD, P/S
Mr. Adriano M. DOROY, Asst. Director, Bureau of Design
Mr. Aristarco M. DOROY, OIC-Asst. Director, Bureau of Construction
Ms. Edna F. MEEZ, OIC-DE, Negros Occidental 4th DEO, DPWH-Region VII
Mr. Felipe S. RAMOS, Fmr. Chief, Technical Services and Evaluation Div., BRS
Mr. Nestor B. CAOILE, OIC-Division Chief, Materials Testing Division, BRS
Regional Project Managers:
Ms. Elsa T. NABOYE, Regional Project Manager, Asst. Chief, QAD, DPWH-CAR
Ms. Ramie B. DOROY, Regional Project Manager, DE, Negros Oriental 1st DEO,
DPWH-Region VII
Ms. Rowena P. JAMITO, Regional Project Manager, Engr. V, MD, RO-XI
Thank you also to CWG Members for their efforts and collaborations.
CWG Members:
Mr. Jay Jenner R. BIARES, Engr. III, CAR ; Group Leader
Mr. Elmer R. FIGUEROA, Engr. III, BOC
Mr. Ernante S. ANTONIO, Engr. III, BOM
Ms. Carina B. DIAZ, Engr. III, BOD
Ms. Nenita R. VALENCIA, Former Engr. III, BRS
Mr. Vicente R. VALLE, JR., Engr. IV, DPWH-Region VII
Ms. Aurora M. LACASANDILE, Engr. III, CD, DPWH-Region XI
Finally, we wish to thank our Expert, Mr. Ryoichi Yamasaki, Co-Team Leader, JICA TCP II
and his Asst. Engineer, Mr. Feliciano P. Carpio, for their support and encouragement
throughout this activity.

Guidebook for Road Construction and Maintenance Management

xii

ACRONYMS
A
AASHTO

American Association of State Highway and Transportation Official

AC

Asphalt Concrete

ACP

Asphalt Concrete Pavement

ASTM

American Society for Testing and Materials

B
BOC

Bureau of Construction

BOD

Bureau of Design

BOE

Bureau of Equipment

BOM

Bureau of Maintenance

BRS

Bureau of Research and Standards

BST

Bituminous Surface Treatment

C
CAR

Cordillera Administrative Region

CBR

California Bearing Ratio

CSB

Cold Seal Bitumen

CWG

Counterpart Working Group

D
DCP

Dynamic Cone Penetrometer

DE

District Engineer

DENR

Department of Environment and Natural Resources

DEO

District Engineering Office

DO

Department Order

DPWH

Department of Public Works and Highways

F
FCSEC

Flood Control and Sabo Engineering Center

FWD

Falling Weight Deflectometer

xiii

Guidebook for Road Construction and Maintenance Management

G
GIS

Geographical Information System

GOJ

Government of Japan

GOP

Government of the Philippines

GPS

Global Positioning System

GVW

Gross Vehicle Weight

H
HDM-4

Highway Development and Management Version 4

HE

Highway Engineer

I
IRI

International Roughness Index

J
JICA

Japan International Cooperation Agency

JCC

Joint Coordinating Committee

L
LAAV

Los Angeles Abrasion Value

M
ME

Materials Engineer

MO

Memorandum Order

MSE

Mechanically Stabilized Embankment

N
NEDA

National Economic and Development Authority

P
PAGASA

Philippine Atmospheric, Geophysical and Astronomical Services Administration

PCC

Portland Cement Concrete

PCCP

Portland Cement Concrete Pavement

PDC

Pavement Dressing Conditioner

PMB

Polymer Modified Bitumen

PMS

Pavement Management System

Guidebook for Road Construction and Maintenance Management

xiv

PS

Planning Service

Q
QA

Quality Assurance

QC

Quality Control

R
RCBC

Reinforced Concrete Box Culvert

RCP

Reinforced Concrete Pipe

RCPC

Reinforced Concrete Pipe Culvert

RIDF

Rainfall Intensity Duration Frequency

RMMS

Routine Maintenance Management System

RO

Regional Office

ROCOND

Visual Road Condition Rating System

ROW

Right-of-Way

RS

Road Safety

S
SDCP

Simplified Dynamic Cone Penetrometer

SMA

Stone Mastic Asphalt

SPT

Standard Penetration Test

T
TARAS

Traffic Accident Recording and Analysis System

TCP

Technical Cooperation Project

TOR

Terms of Reference

TWG

Technical Working Group

V
VCI

xv

Visual Condition Index

Guidebook for Road Construction and Maintenance Management

Chapter 1

Introduction

1.1 Background
The Department of Public Works and Highways, hereinafter referred to as DPWH and
Japan International Cooperation Agency, hereinafter referred to as JICA, agreed in 2006 to
implement the project for Improvement of Quality Management for Highway and Bridge
Construction and Maintenance, hereinafter called as " Phase I", aiming to enhance the
engineering knowledge of the engineers of DPWH.
For implementation of the said project, the DPWH organized the Joint Coordinating
Committee, hereinafter called as JCC, Technical Working Group, hereinafter called as TWG
and Counterpart Working group, hereinafter called as CWG and the JICA dispatched the JICA
Technical Cooperation Project Team, hereinafter referred to as "JICA TCP Team" from
February 2007 to February 2010.
Under Phase I, the following manuals/guidelines were prepared and issued for road
construction and maintenance through the CWG's activities.
*

Guidebook for Road Construction and Maintenance Management in the Republic of


the Philippines,

Road Project Management and Supervision Manual, Volume I: Main Text and

Road Project Management and Supervision Manual, Volume II: Appendices (Standard
Forms, Examples and References)

From October 2011 to September 2014, the DPWH and JICA TCP Team -newly
dispatched by JICA - implemented the project for Improvement of Quality Management for
Highway and Bridge Construction and Maintenance, Phase II, hereinafter called as Phase II to
aim further enhancement.
This manual, Guidebook for Road Construction and Maintenance was prepared under
Phase II through the revision work done by CWG based on the Guidebook mentioned above.
The Guidebook was made through consolidations of seminars and On-the-Job-Training
materials, texts, presentations and is mainly focused on the engineering knowledge necessary
for road and slope management.

Guidebook for Road Construction and Maintenance Management

1-1

1.2 Purpose
Engineers of the DPWH concerned with road and slope construction and maintenance
are the main targets of this Manual. The CWG made efforts to make this Reference easy to
understand by the young Engineers, especially beginners, hence, it would be an effective tool
related to the above areas.

1-2

Guidebook for Road Construction and Maintenance Management

Chapter 2

Soil Classification and


Modulus

2.1 Unified Soil Classification


Table 2.1 and 2.2 show the Soil Classification utilized for field identification.

Clean sand
(little or fines)

Gravel with fines


(applicable
amount of fine)

Clean gravel
(little or fines)

Unified Soil Classification System (Sands and Gravels)

Sand with fines


(applicable
amount of fine)

Gravels
More than half of coarse
Fraction is smaller than no.4 sieve size
Sands
More than half of coarse fraction is smaller
than no.4 sieve size
(for visual classification, the 1/4" size may
be used as equivalent to the no.4 sieve size)

Coarse grained soils


More than half of material is bigger than no. 200 sieve size

Table 2.1

Wide range in grain size


and substantial amount of
all intermediate particle
size
Predominantly one size or
a range of sizes with some
intermediate sizes missing
Non-plastic fines (for
identification procedures,
See ML)
Plastic fines (for
identification, See CL)
Wide range in grain size
and substantial amount of
all intermediate particle
size
Predominantly one size or
range of range of sizes with
some intermediate sizes
missing

Group
Symbols

Typical Names

GW

Well graded gravels,


gravel-sand mixtures
little or no fines

GP

GM

GC

SW

Well graded sands,


gravelly sands, little
or no fines

SP

Poorly graded sands,


gravelly sands, little
or no fines

Non-plastic fines (for


identification, See ML)

SM

Non-plastic fines (for


identification, See CL)

SC

Guidebook for Road Construction and Maintenance Management

Poorly graded gravels,


gravel-sand mixtures
little or no fines
Silty gravels, poorly
graded grave-sand silt
mixtures
Clayey
gravels,
poorly graded-sand
clay mixtures

Silty sand, poorly


graded
sand-silt
mixtures
Clayey sands, poorly
graded
sand-clay
mixtures

2-1

Table 2.2

Unified Soil Classifications (Silts, Clays and Organic Soils)

Silts and clays


Liquid limit less than 50
Silts and clays
Liquid limit greater than 50

Fine graided soils


More than half of material is smaller than no. 200 sieve size

Dry strength
(Crushing
characteristics)

Highly organic soil

Dilitancy
(Reaction to
shaking)

Toughness
(Consisten
cy near
plastic
limit)

Group
Symbols

None to slight

Quick to
slow

None

ML

Medium to
high

None to
very slow

Medium

CL

Slight to
Midium

Slow

Slight

OL

Slight to
medium

Slow to
none

Slight to
Medium

MH

High to very
high

None to
very slow

High

CH

Medium to
high

None to
very slow

Slight to
Medium

OH

Readily identified by color, odor, spongy feel


and frequently fibrous texture

P+

Typical Names

Inorganic silts and


very fine sands, rock
flour, silty or clayey
fine sands with slight
plasticity
Inorganic clays of
low
to
medium
plasticity
gravelly
clays, sandy clays,
silty-clays, lean clays
Organic silts and
organic silt-clays of
low plasticity
Inorganic
silts,
micaceous
or
diatomaceous
fine
sandy or silty soils,
elastic silts
Inorganic clay of high
plasticity < fat clays
Organic clays of
medium to high
plasticity
Peat and other highly
organic soils

2.2 Reference Data for Soil Classification


In DPWH, there is no available reference data for soil classification for use in
preliminary design. Table 2.3 shows a reference data for preliminary design of Japan
Expressway for DPWH Engineer's references.

2-2

Guidebook for Road Construction and Maintenance Management

Table 2.3

Embankment Material

Soil Type
Gravely soil
or
Sand with
some gravel
Sand
Sand
Sand and
Gravel
Fine grained
sand

Well grained
Compacted
Poor grained
Compacted
Compacted
Compacted

20

40

GW, GP

20

35

SW

19

30

SP

19

25

30 or less

SM, SC

18

15

50 or less

ML, CL
MH, CH

Gravel

Dense, or well
grained

20

40

GW

Gravel

Not dense, or
poor grained

18

35

GP

Dense

21

40

SW

Not dense

19

35

SP

Sand

Dense or well
grained

20

35

--

Sand

Loose or poor
grained

18

30

--

Silty Sand

Dense

19

30

30 or less

SM, SC

Silty Sand

Loose

17

25

SM, SC

Cray

Stiff, N-value is
8-15

18

25

50

ML,CL

Cray

Moderate,
N-value is 4-8

17

20

30

ML,CL

Cray

Soft, N-value is
2-4

16

15

15

ML,CL

Silt

Stiff, N-value is
8-15

17

25

50

CH,MH,ML

Silt

Moderate,
N-value is 4-8

16

15

30

CH,MH,ML

Silt

Soft, N-value is
2-4.

14

10

15

CH,MH,ML

Sand and
Gravel
Sand and
Gravel

Undisturved Material

Soil Classification Reference Data for Preliminary Design


Internal
Unit weight
Unified Soil
Cohesion
Condition
friction
angle
(kN/m3)
Classification
(kN/m3)
(degree)
Compacted

(Source: Design Guideline for Japan Expressway)

Guidebook for Road Construction and Maintenance Management

2-3

2.3 Estimated Soil Modulus by N-value


Table 2.4 shows the relation between internal friction angles and N-values (Reference :
Terzaghi and Peck).
Table 2.4

N-value and Internal Friction Angle (Sand)


Internal Friction Angle

N-value

Density

0 to 4

Very loose

less than 28.5

4 to10

Loose

28.5 to 30

10 to30

Medium

30 to 36

30 to50

Dense

36 to 41

More than 50

Very dense

More than 41

(Degree)

Table 2.5 shows the relation between unconfined compressive strength and N-value
(Reference: Terzaghi and Peck).
Table 2.5

N-value and Unconfined Compressive Strength (Clay)

0 to2

Very soft

Unconfined
Compressive
Strength
kN/m2
less than 25

2 to4

Soft

25 to 50

12.5 to 25

4 to8

Medium

50 to 100

25 to 50

8 to15

Stiff

100 to 200

50 to 100

15 to30

Very Stiff

200 to 400

100 to 200

30 or more

Hard

400 or more

200 or more

N-value

2-4

Consistency

Cohesion
(for short-time load)
kN/m3
less than 12.5

Guidebook for Road Construction and Maintenance Management

Chapter 3
3.1

Road Drainage

Design of Drainage

3.1.1 Estimating Discharge


The peak discharge can be estimated by the Rational formula as shown below:

Qd =
where:

1
C I A
3.6
Qd =

peak discharge (m3/s)

C=

runoff coefficient

I=

rainfall intensity (mm/hour) for a critical


time period

A=
3.1.1.1

drainage area (catchment area) (km2)

Drainage Area

The drainage area (catchment area) shall be identified or estimated through field survey
and utilization of topographic map. Each type of road drainage has its designated drainage
area as shown in Table 3.1.
Table 3.1
Type of Drainage

Drainage Area
Drainage Area (Catchment Area)

Road Surface Drain

Road surface (carriageway and shoulder)

Road Slope Drain

Roadside (including road slopes and mountain slopes)

Road Side Drain

Road surface and adjoining road slope, adjoining


residential area etc.

Cross Drain

Road surface, adjoining road slope, adjoining residential


area and other basin area (if necessary)

3.1.1.2

Runoff Coefficient

The runoff coefficient, C, represents runoff rate of rainfall. The value is provided as
shown in Table 3.2.

Guidebook for Road Construction Maintenance Management

3-1

Table 3.2

Values of Runoff Coefficient, C

Type of Surface

Factor C

Cement Concrete or Asphalt Concrete Pavement

0.9 to 1.0

Bituminous Surface Treatment

0.7 to 0.9

Gravel Surface

0.3 to 0.6

Residential Area/City

0.3 to 0.6

Residential Area/Town & Village

0.2 to 0.5

Rocky Surface

0.7 to 0.9

Bare Clay Surface

0.7 to 0.9

Forested Land (sandy and clay)

0.3 to 0.5

Flattish Cultivated Areas (not flooded)

0.3 to 0.5

Steep or Rolling Grassed Areas

0.5 to 0.7

Flooded or Wet Paddies

0.7 to 0.8

(Source: DPWH, Design Guidelines, Criteria and Standards)


3.1.1.3

Rainfall Intensity

The rainfall intensity, "I", is derived from the maximum estimated rainfall for the design
flow return period and time of concentration.
Time of concentration, "Tc", is the time required for runoff from the farthest point of the
drainage area (catchment area) to reach the design target point. Generally, concentration time
can be estimated by the following formula:

Tc =
where:

L1.15
51H 0.385
Tc =

time of concentration in minutes

L=

length of watershed along the mainstream in


meters

H=

difference in elevation between the most


distant ridge in the watershed along the
mainstream and the target point in meters

The design flow return period for the rainfall intensity is provided in Table 3.3.

3-2

Guidebook for Road Construction and Maintenance Management

Table 3.3

Design Flow Return Period

Structure Type

Design Flow Return Period

Bridges

50 years

Box Culverts

25 years

Pipe Culverts

15 years

Side Drainage

5 years

Surface Drainage

2 years

(Source: DPWH, Design Guidelines, Criteria and Standards)


Rainfall intensity charts were prepared based on the data obtained from PAGASA as
shown in Figure 3.1 and 3.2.
500

200

100y

400

50y

350

25y

180

Return Period
100 years
50 years

160

25 years
10 years

300
10y

Rainfall R (mm/hr)

Rainfall R (mm/hr)

450

5 years

250

2 years

140

120

100

5y
200

80

150

60

2y

100

40

50

20

0
0

10

20

40

30

50

60

380

Figure 3.1

720

1050

1440

Duration t (min)

Duration t (min)

Rainfall Intensity Duration Frequency (RIDF) Curves


Source: 328 Baguio Synoptic Station

250

120

Return Period
100 years

100y
50y

25 years
10 years

25y

Rainfall R (mm/hr)

Rainfall R (mm/hr)

100

50 years

200

5 years
150

10y

2 years

5y

80

60

100
2y

40

50

20

0
0

10

20

30

40

50

60

360

Duration t (min)

Figure 3.2

720

1030

1440

Duration t (min)

Rainfall Intensity Duration Frequency (RIDF) Curves


Source: 646 Mactan Synoptic Station

Guidebook for Road Construction Maintenance Management

3-3

3.1.2 Capacity of Drainage


Discharge of drainage can be estimated by the following formula:

Qc = a v
1
R 2 / 3 i1 / 2
n
1
Qc = a R 2 / 3 i1 / 2
n
v=

where:

3.1.2.1

a=

effective cross-sectional area, m2

v=

flow velocity,m/s

n=

Mannings roughness coefficient

i=

hydraulic radius, m

R=

gradient of water surface

Mannings Roughness Coefficient

Table 3.4 shows Mannings Roughness Coefficient, n.


Table 3.4

Mannings Roughness Coefficient


Condition

Type of Channel

Good

Fair

Bad

Brick in cement mortar,brick sewers

.012

.013

.015

.017

Smooth cement surface

.010

.011

.012

.013

Concrete pipe

.012

.013

.015

.016

Concrete lined channel

.012

.014

.016

Cement rubble surface

.017

.020

.025

.030

Dredged earth canals

.025

.027

.030

.033

Canals with rough stone bed, weeded slope

.025

.030

.035

.040

Earth bottom, rubble side

.028

.030

.033

.035

Clean straight bank

.025

.027

.030

.033

Winding

.033

.035

.040

.045

Sluggish river weedy reaches

.050

.060

.070

.080

Very weedy reaches

.075

.100

.125

.150

Natural Stream

Best

(Source: DPWH Design Guidelines, Criteria and Standards)


3.1.2.2

Hydraulic Radius

Below are the different formulas in determining the hydraulic radius:

3-4

Guidebook for Road Construction and Maintenance Management

1:m(=H:L)

mH

H = r (1 cos )
R = 0.5r (1

a = r 2 (

R=

sin 2
)
2

BH
B + 2 H

m1 + m2

H sin(1 + 2 )
2 sin 1 + sin 2

R=

H
2

a=

H2
H2
( m1 + m2 )or =
(cot 1 + cot 2 )
2
2

1 + m12 + 1 + m22

or

H (B + m H )
B + 2 H 1 + m2

H ( B + H c o )t
o r
B + 2 H c o e s
c

1
sin( 2 ))
2

Figure 3.3
3.1.2.3

R=

R=

H
2 1+

a =

H2
m
2

m
1 + m2

mH

or

or =

H
cos
2 1 + sin

H2
cot
2

Hydraulic Radius Formula

Flow Velocity

Table 3.5 shows appropriate range of flow velocity by type of drainage structure and type
of drainage surface. In case the computed actual flow velocity is higher or lower than the
ranges, the structure should be redesigned.
Table 3.5

Appropriate Range of Flow Velocity

Structure
Drainage Surface

Type of

Type of

Types

Range of Flow Velocity (m/sec)

Road Side Drain

0.5 to 1.0

Pipe Culvert (910mm.)

0.6 to 1.0

Pipe Culvert (greater than 910mm.)

0.8 to 2.0

Cement Concrete

0.6 to 3.0

Asphalt Concrete

0.6 to 1.5

Stone/Brick

0.6 to 1.8

Gravel

0.6 to 1.0

Coarse Sand

0.3 to 0.6

Silt

0.1 to 0.2

3.1.3 Specific Discharge Curve


In case the watershed is vast, the specific discharge curve can be applied to estimate the

Guidebook for Road Construction Maintenance Management

3-5

peak discharge as shown in Figures 3.4 to 3.6 used by DPWH FCSEC and JICA in March,
2003 under the Project for the Enhancement of Capabilities on Flood Control and Sabo
Engineering.
100

Specific Discharge q; m3/s/(km2)

Luzon
Return Period
100 years
50 years
25 years
10 years
5 years

10

2 years

0.1
1

10

100

10,000

1000

100,000

Catchment Area A (km2)

Figure 3.4

Specific Discharge Curve (Luzon)

100

Specific Discharge q; m3/s/(km2)

Visayas
Return Period
100 years
50 years
25 years
10 years
5 years

10

2 years

0.1
1

10

100

1000

10,000

100,000

Catchment Area A (km2)

Figure 3.5

Specific Discharge Curve (Visayas)

100

Specific Discharge q; m3/s/(km2)

Mindanao

10

Return Period
100 years
50 years
25 years
10 years
5 years
2 years
1

0.1
1

10

100

1000

10,000

100,000

Catchment Area A (km2)

Figure 3.6

3-6

Specific Discharge Curve (Mindanao)

Guidebook for Road Construction and Maintenance Management

3.2 Cross Drainage


3.2.1 Installation of Cross Drainage
Basically there are three alternatives for vertical alignment of cross drainage as shown in
Table 3.6.
Table 3.6

Installation of Cross Drainage

Alternative-1

Alternative-2

Alternative-3

Figure

Advantages

Disadvantages

The construction and


maintenance costs will be
cheaper owing to its simple
design.
The slope of the embankment at
the outlet portion will be prone
to scouring hence, proper
drainage outlet structures
should be provided.

Water will be easily drained.

The flow might be controlled to


mitigate slope and pipe
damages.

There is no need to provide


drainage outlet along the
embankment slope however,
protective measures at the
outlet portion should be
provided to minimize the
scouring effect of the rapid
flow.

Construction and maintenance


costs are high due to longer
pipes.

3.2.2 Headwalls
Basically, inlet/outlet headwalls for cross drainage should be provided to prevent
scouring and erosion as shown in Figure 3.7.

Figure 3.7

Typical Inlet and Outlet Headwalls

Guidebook for Road Construction Maintenance Management

3-7

Joints between Culvert


Box, Wing Wall and
Apron shall be checked
to be connected water
tight.

Dumped Stone
with grouted
surface
Skirt (toe)

Figure 3.8

Apron and Skirt


(Toe) shall be
connected to prevent
water from seeping
into the bottom of
culvert.

Structure of Headwall

3.3 Underground Drainage


3.3.1 Function of underground drainage
High water contents in road base material enormously affect the strength(bearing
capacity) of the pavement . Figure 3.9 shows the relationship between CBR of road base
material and its water contents.
To keep the road base material in good condition, provision of underground drainage
system is recommended.
6

CBR (%)

0
60

Figure 3.9

3-8

80

100
120
Water Content (%)

140

160

Relation of Water Content and CBR

Guidebook for Road Construction and Maintenance Management

3.3.2 Typical Cross Section of Underground Drainage System


Figures 3.10 to 3.12 show typical cross sections of road with underground drainage.
Underground drainage should be recommended as required per existing condition.

Underdrains on both sides of the road

Figure 3.10

Typical Underground Drainage for a 2-lane Road

Underdrains on both sides and at the median

Figure 3.11

Typical Underground Drainage for a 4-lane Road

Underdrain on one side

Figure 3.12

Typical Underground Road Drainage for Mountainous Terrain

3.3.3 Treatment of Seepage from Mountainous Slope


In case of road embankment on the natural slopes, seepage and/or surface water from
mountainous slopes should be treated as shown in Figure 3.13.

Guidebook for Road Construction Maintenance Management

3-9

Construction of Road Embankment on the slope with


seepage from side slope
Seepage from side slope

Bench Cut

Base Rock Layer

Recommended treatment of underground water


Cutoff Trench
with Blind Pipe
Drain Layer wrapped with Geotextile
Drain Pipe

Figure 3.13

Treatment of Seepage from Mountainous Slope

3.3.4 Underground Drainage on Cut and Embankment Portions


Underground drainages shall be installed at cut and embankment portions as shown in
Figure 3.14.

Embankment
Under-drain
Cut Slope

Under-drain

Figure 3.14

3 - 10

Underground Drainages on Cut and Embankment Sections

Guidebook for Road Construction and Maintenance Management

Chapter 4

Pavement

4.1 Types of Pavement


Road pavement is of two major types - rigid pavement (PCCP) and flexible pavement
(ACP).

Figure 4.1

Conceptual Figure Showing Load Distribution


for Rigid and Flexible Pavements

4.1.1 Rigid Pavement


A rigid pavement generally consists of three layers: the concrete slab, subbase and
subgrad as described below:
Slab

The slab is made of reinforced or plain concrete which also includes


load transfer devices and joint sealing materials. The concrete slab
acts like a bridge girder over the subgrade.

Subbase

It is the portion of the pavement structure between the subgrade and


the slab. It usually consists of compacted layer/s of granular
materials.

Subgrade

It is the bottom portion of the pavement structure which consists of


suitable embankment materials or existing road bed.

Guidebook for Road Construction and Maintenance Management

4-1

4.1.2 Flexible Pavement


A flexible pavement generally consists of four layers: surface course, base course,
subbase and subgrade (which is the prepared roadbed) as described below:
Surface Course

It consists of a mixture of mineral aggregates and bituminous


materials constructed on a prepared base course.

Base Course

It is the portion of a pavement structure immediately beneath the


surface course. It consists of aggregates such as crushed stone,
crushed slug, crushed or uncrushed gravel and sand or a combination
of these materials placed and compacted on a prepared subbase.

Subbase

It is the portion of the pavement structure between the subgrade and


the base course. It consists of a compacted layer of granular
materials placed on a prepared subgrade.

Subgrade

It is the bottom portion of the pavement structure which consists of


suitable embankment materials or existing road bed.

4.2 Portland Cement Concrete Pavement


4.2.1 Quality Control
The Contractor shall perform all sampling, testing and inspection necessary to assure
quality control of the component materials of the concrete. The Contractor shall be
responsible for determining the gradation of fine and coarse aggregates and for testing the
concrete mixture for slump, air content and temperature. He shall conduct his operations so as
to produce a mix conforming to the approved mix design.

4.2.2 Design Mix and Trial Paving


The Contractor is obliged to formulate the design mix, conduct trial mix and trial paving
for approval of the Project Engineer before commencement of pavement construction as
illustrated in Figure 4.2.
Material Test

Figure 4.2

4-2

Design Mix
and Trial Mix

Trial Paving

Approval of
Design Mix and
Methodology

Start
Paving

Flowchart for Preparatory Work for Concrete Paving

Guidbeook for Road Construction and Maintenance Management

4.2.3 Admixture/Additive
Admixture/additive shall be added only to the concrete mix to produce some desired
modifications to the properties of concrete whenever necessary, but not as partial replacement
of cement. The admixtures shall conform to the requirements as tabulated below:
Table 4.1
Type
Air-entraining admixture
Chemical admixture
Fly Ash

Requirements for Admixtures


Requirement
AASHTO M154
AASHTO M194
ASTM C618

Remarks

As 20% partial replacement


of portland cement in
concrete mix

4.2.4 Concrete Paving Activities


The following photos show concrete pouring activities:

Preparation and cleaning

Moistening prior to
placing

Transport of concrete
(for slipform paver)

Placing of Concrete

Conduct of slump test

Checking of temperature
of the mix

Checking of the thickness

Finishing by means of a
floater

Finishing by means of a
screeder

Checking of the texturing


Tool

Texturing of the surface

Spraying of curing
compound

Provision of protective
cover sheets

Sawing of weakened plane


joint

Checking the depth and


width of the joint

Figure 4.3

Concrete Paving Activities

Guidebook for Road Construction and Maintenance Management

4-3

4.2.5 Types of Formworks


There are two types of formworks for concrete paving - fixed-form and slip form. The
use of slipform paver is required in DPWH road projects as per D.O. 219 Series of 2000.

Using Fixed Form

Using Slipform Paver

Figure 4.4

Paving Works

4.2.6 Weakened Plane Joint


All joints shall be protected from the intrusion of injurious foreign material until sealed.
All joints shall be cut within 4 to 24 hours after pouring and thereafter sealed with asphalt
sealant. The depth of the weakened plane joint shall not be less than 50 mm while the width
not more than 6 mm. Only concrete saw is permitted in the cutting of weakened plane joints.
According to international practice, dowel bars are required in all contraction joints (at 4.5m)
as load transfer device for PCCP with thickness of more than 200 mm. The PCCP slabs
without dowel bars at weakened joint will cause various defects in the medium to long term,
especially for the road route on which heavy trucks are dominant. However, this has not yet
become a standard practice of the DPWH due to cost constraints. Presently, the application is
by specific road section and upon approval of the concerned DPWH Office in consultation
with BOD.
The types and functions of PCCP joints are summarized below.

4-4

Guidbeook for Road Construction and Maintenance Management

Table 4.2

Category and Type

Transverse Joints**

Longitudinal Joints

Contraction
Joint/
Weakened
Plane Joint

Expansion
Joints
Construction
Joints

Formed
Joints
Formed
Joints
Sawed
Contrac
tion
Joint
Formed
Joints
Formed
Joints

Types and Functions of PCCP Joints

Function

Load Transfer Method


(Device)
Tie bar(Deformed)

Shrinkage Crack
Prevention
Construction by lane
Shrinkage Crack
Prevention
At every 4.5m
Shrinkage Crack
Prevention
At every 4.5m

With dowel bar*


Round Bar *
Without dowel

Expansion Force
Release
Joint for interruption of
work and end of days
construction

Dowel Bar(Round)
Tie Bar(Deformed)

* Bar size varies depending on pavement thickness


**No transverse joint shall be constructed within 1.50 m of concrete block.

Tie Bars for Longitudinal Joints (Deformed Bar)


Dowel Bars (Round Bar)

Figure 4.5

PCCP Joints and Load Transfer Device

Guidebook for Road Construction and Maintenance Management

4-5

Tie bars are installed across longitudinal joints to hold the two slabs in close contact or to
prevent them for separating. Tie bars are located at mid-depth of the pavement.
Dowel bars are placed in contraction joints and in some construction joints when it falls
at full block (4.5m) to transfer a portion of the load across the joint and to hold the two slab
ends at the same elevation. To function properly, dowels must be parallel to the surface and to
the centerline of the pavement.
Length and size of bars vary depending on pavement thickness as shown in Table 4.3.
Table 4.3

Type
Tie
Bar(Deformed)
Dowel
Bar(Round)*

Size and Length of Dowel/Tie Bars

PCCP
Thickness
(mm)
200
230
200
230
250
280

Size*
(mm)

Length
(mm)
12
16
25
28
32
36

Spacing
(mm)

1,000
600
600
600
600
600

600
750
300
300
300
300

* 1/8 of PCCP thickness

4.2.7 Replacement of Deteriorated PCCP Slabs


The replacement of shattered PCC slabs is one of the common works involved in both
rehabilitation and maintenance projects. Procedures are as follows:
(1) The Engineer and the Contractor conduct joint inspections prior to the commencement
of work to confirm the current conditions and identify the PCC slabs to be replaced.
(2) The Contractor removes broken/deteriorated PCCP slabs in accordance with the Plans,
Specifications or as directed by the Engineer.
(3) The subgrade and subbase course are prepared in accordance with the specifications or
as directed by the Engineer.
(4) Existing tie bars on longitudinal joints are to be retained if these are still in good
condition. Where necessary, new tie bars shall be installed on drilled holes and bonded
with high viscosity epoxy resin.
(5) Install forms; side surfaces of the
existing PCCP shall be cleaned.
(6) Pour concrete; perform the required
surface texturing, cutting and curing.
(7) Thoroughly clean the joints and apply
sealants adequately.
Figure 4.6

4-6

Deteriorated PCCP

Guidbeook for Road Construction and Maintenance Management

4.2.8 PCCP Widening


The widening of existing PCCP is one of the common works involved in upgrading work.
Procedures are likely the same as the replacement of deteriorated PCCP slabs.

Figure 4.7

PCCP Widening

Drilling of holes for Tie Bars

Placing Concrete

Note) Workers must wear safety gears.

Figure 4.8
*

PCCP Widening Work

The provision for widening blocks at curves shall be poured simultaneously with the
adjoining lane.

Weakened plane joints at curves shall be perpendicular to the centerline.

4.2.9 Temperature Control


The Engineer shall require that measures be taken into consideration to prevent the
temperature of concrete mix from exceeding 32oC because shrinkage cracks occur when the
concrete is placed at a high temperature, which may include any or all of the following:
a)

Addition of ice blocks in the water.

b)

Shading and water sprinkling of aggregates, formworks and steel bars.

c)

Shading of working area.

d)

In transporting concrete using trucks, provide necessary cover sheets.

e)

Placing of concrete at a time when the humidity is low.

Figure 4.9

Thermometer

Guidebook for Road Construction and Maintenance Management

4-7

4.2.10 Surface Texturing


Surface texturing is necessary to keep a skid resistant surface and is done after the
surface has hardened enough.

Figure 4.10

Texturing of the Surface

4.2.11 Subbase
The subbase materials shall be spread on the prepared subgrade and compacted to the
required thickness.

Figure 4.11

Laying of Base Materials by Means of Road Grader and Paver

4.2.13 Asphalt Concrete Overlay on PCCP


Asphalt concrete overlay is a standard repair work both for routine and preventive
maintenance. It is laid on the existing pavement after the repair of distress.
In overlaying, preventive measures against reflection cracks shall be considered.
Methods to prevent reflection cracks are as shown in Table 4.4.

4-8

Guidbeook for Road Construction and Maintenance Management

Table 4.4

Preventive Measures for Reflection Cracks on AC Overlay

Types

Methods

Aggregate
Intermediate

Required
Laying of aggregate base materials

Layer
Asphalt
Concrete Crack
Relief Layer

Remarks
minimum
thickness is 15cm.

Laid over the existing PCCP to prevent cracks from


extending to the newly laid asphalt concrete.

Required
minimum
thickness is 9 cm.

This item shall consist of either a single application of


bituminous material followed by a single spreading of
Surface
Treatment

aggregate (single bituminous surface treatment), or


two applications of bituminous material each followed
by a spreading of aggregate (double bituminous
surface treatment) in accordance with the Plans and
Specifications.

Crack and Seat


Technology

Cracking of the existing PCC pavement with


dimension of 0.5 x 0.5m. using guillotine or arrow
hammer and rolling it with pneumatic roller.

4.3 Introduction of Newly Approved Pavement Materials


4.3.1 Instapave
Instapave is a technology used for improving road surface condition. It consists of a
blend of Cold Seal Bitumen (CSB), aggregate, water and additives applied on a prime coated
base or on a tack coated concrete/asphalt pavement in accordance with the Plans and
Specifications.

4.3.2 Pavement Dressing Conditioner


Pavement Dressing Conditioner (PDC) is a surface treatment material for asphalt
concrete pavement consisting of a blend of coal tar and petroleum oil. It is designed to
penetrate the pavement surface to replace critical elements necessary to rejuvenate and
rehabilitate the asphaltic binder thereby increasing pavement plasticity and flexibility while
reducing viscosity. Since it has already become an integral part of the pavement, it does not
wear off under traffic and prevents raveling.

Guidebook for Road Construction and Maintenance Management

4-9

Pavement Dressing Conditioner (PDC) is composed of materials as shown below.


Table 4.5

Material Composition of Pavement Dressing Conditioner

Materials
1. Refined Coal-tar (Gravel RH2)
2. Light aromatic solvent
3. Naphtha or coal-tar solvent naphtha
4. Blend of tar oils
5. Elastomer

Remarks
30% to 40%
30% to 40%
30% to 40%
15% to 40%
0.01% to 13%

4.3.3 Polymer Modified Bitumen


Polymer Modified Bitumen (PMB) is a material for porous asphalt pavement. The
mixture is open graded asphalt wearing course applied on asphalt concrete or portland cement
concrete pavement.
The porous asphalt mixture is composed of large proportion of coarse aggregate, small
proportion of fine aggregate, mineral filler and PMB.
This mixture has air voids within the range of 18% to 25% that easily allows the passage
of water.

4.3.4 Stone Mastic Asphalt


Stone Mastic Asphalt (SMA) is a gap graded hot mix asphalt surface course composed of
high proportion of coarse aggregate, fine aggregate, mineral filler, bituminous material and
cellulose fiber. Cellulose fibers either pure or bitumen coated, shall be added to the mix to
absorb the excess binder and to improve the properties of the asphalt mix.
Generally, SMA is not applicable on bridge decks.

4 - 10

Guidbeook for Road Construction and Maintenance Management

Chapter 5

Slope Protection
Works

5.1 Appropriate Slope


5.1.1 Cut Slope
Natural ground is extremely complex and not uniform in its properties and cut slopes
tend to gradually become unstable after the completion of work. Therefore, stability
calculation is necessary only in rare cases when examining the stability of cut slopes. An
overall judgment shall be made by fully taking into account the requirements for its stability
described later by referring to the standard values of the gradient of slope listed in Table 5.1.
Table 5.1
Soil/Rock Properties

Soil

Cutting Height and Cut Slope


Cutting Height

Slope (Ratio)

(H:V)

Hard Rock

7.0 m

0.25:1 to0.5:1

Soft Rock

7.0 m (max)

0.5:1 to 1:1

2.0 m or less

2:1

Over 2.0 m

1.5:1

2.0 m or less

2:1 to 4:1

Over 2.0 m

1.5:1 to2:1

a. cohesive
b. less cohesive

Note:
1.

Indicated gradient (ratio) is subject to change


depending on the stability of soil materials.

2.

When the cutting height exceeds 7.0 m for rock


materials and 5.0 m. for soil, benching is applied.

3.

In case of heavy weathering or erosion, this table is


applicable only after adequate protection work is
applied.

(Source: DPWH FCSEC Technical Standards and Guidelines for Planning and Design Vol. IV)

Guidebook for Road Construction and Maintenance Management

5-1

For reference, shown below is Japans standard gradient for cut slope.
Table 5.2

Standard Cut Slope Gradient for Japan Highways


Cut slope height (m)

Materials of Ground

Slope (Ratio)
(H:V)

Hard rock

0.3:1 to 0.8:1

Soft rock
Loose and poor grain

Sand

Unconditional

0.5:1 to 1.2:1
1.5:1

size distribution.
5 m or less

0.8:1 to 1.0:1

5 to 10 m

1.0:1 to 1.2:1

5 m or less

1.0:1 to 1.2:1

5 to 10 m

1.2:1 to 1.5:1

Dense or well grain

10 m or less

0.8:1 to 1.0:1

Sandy soil with

size distribution

10 to 15 m

1.0:1 to 1.2:1

gravel or rock

Loose, bad grain size

10 m or less

1.0:1 to 1.2:1

distribution.

10 to 15 m

1.2:1 to 1.5:1

Silt, clay

10 m or less

0.8:1 to 1.2:1

5 m or less

1.0:1 to 1.2:1

5 to 10 m

1.2:1 to 1.5:1

Dense
Sandy soil
Loose

Fine-grained soil

Fine-grained soil with some cobbles, boulders


Notes:
When a single cut slope cannot be adopted
due to different soil composition or other
reasons, the cut slope height and gradient are
determined on the basis of the following

ha: Cut slope height for slope surface a

considerations:

hb: Cut slope height for slope surface b

The gradient does not include a berm.

The cut slope height to the relevant slope gradient means the total cut slope height
including all cut slopes above the relevant cut slope.

It is important that an overall judgment of critical slope gradient be based on observation


of similar type slopes.
As shown in Figure 5.1, the gradient of slopes varies depending on the geology. Berm is
generally installed at boundary of slope gradient difference.

5-2

Guidebook for Road Construction and Maintenance Management

Figure 5.1

Geology and Slope Gradient

On cut slopes, berms 1.0 to 2.0 m. wide are generally provided for every 5.0 to 7.0 m. in
height for the following purposes:
*

To enhance slope stability.

To reduce the speed of surface water flow thereby decreasing the scouring force on cut
slope.

To provide space for ditches.

To be used as pathwalk during inspection or as support area of scaffolding for repair


works.

A wider berm is recommended where rockfall protection fences are to be installed.


When drainage is not provided, about 5 to 10% of transversal gradient is normally
provided for the berm to drain water towards the toe of the slope.
If the slope is prone to erosion, the berm should be sloped inwards.

5.1.2 Embankment Slope


For the standard gradient for embankment slope, please refer to DPWH Highway Design
Guidelines, Criteria and Standards.

Guidebook for Road Construction and Maintenance Management

5-3

For reference, shown below is Japans standard gradient for road embankment slopes.
Table 5.3

Japans Standard Gradients for Road Embankment Slopes


Embankment slope height

Slope (Ratio)

(m)

(H:V)

Sand of well grain size

5 m or less

1.5:1 to 1.8:1

distribution

5 to 15 m

1.8:1 to 1.20:1

10 m or less

1.8:1 to 2.0:1

10 m or less

0.8:1 to 1.0:1

10 to 20 m

1.8:1 to 2.0:1

Sandy soil, stiff fine-grained

5 m or less

0.8:1 to 1.0:1

soil

5 to 10 m

1.0:1 to 1.2:1

Volcanic clay

5 m or less

1.8:1 to 2.0:1

Materials of Embankment

Sand of poor grain size


distribution
Rock lump, rock muck

Note: Embankment height is defined as from slope toe to slope shoulder.


Slope shoulder
Embankment Height

Slope toe

It is required that there is enough bearing capacity of embankment base and no expected
inundation.
(Source: Highway Earthwork Guideline, Japan Road Association, March 1999)

5.2 Slope Failure


5.2.1 Soil Slope Collapse

5-4

Part of the mountain side slope suddenly collapses on the road.

Mostly triggered by rainfall infiltration.

Collapsed/collapsible materials are soil and highly weathered rocks.

Prone to occur on steep slopes.

The volume involved is generally from 200 to 5000 cubic meters.

Guidebook for Road Construction and Maintenance Management

Figure 5.2

Typical Soil Slope Collapse

5.2.2 Rock Slope Collapse


*

Free falling or rolling down of rocks along the slope.

Falls occur due to gravity and are controlled by the distribution of joints. Materials are
hard, jointed rocks.

Prone to occur on steep slope and cliff.

Figure 5.3

Typical Rock Slope Collapse

Guidebook for Road Construction and Maintenance Management

5-5

5.2.3 Landslide
Landslide refers to all types of slope failures and defined as movement of a large mass of
soil and/or rocks.
Charateristics of a landslide are as follows:
*

A portion of the road bulges up by an inch or more.

It is triggered by water infiltration and/or earthquake.

Materials are soil and highly weathered rocks.

It usually occurs on a gentle and irregular mountain slopes.

The volume involved is generally more than 5000 cubic meters.

Figure 5.4

5-6

Typical Landslide

Guidebook for Road Construction and Maintenance Management

5.2.4 Road Slip


*

Road

slip

occurs

because

of

the

collapse/scouring/caving-in of the valley side


slope of the roadway.
*

Occurs mostly on road shoulder.

Occurs mostly along stream bends.

Mostly induced by infiltration/leakage of water


from road surface/damaged drainage facilities.

Materials are soil and highly weathered rocks.

Figure 5.5

Figure 5.6

Road Slip

Typical Road Slip

5.2.4.1 Road Slip Process


Infiltration of rainfall through the cracks accelerates the process of slipping.
Monitoring of these cracks and preventive measures to reduce road slip risks are
necessary such as filling of cracks with impervious materials. A typical process of the
development of open cracks on a shoulder slope is shown in Figure 5.7.

Expansion

Sliding/displacement

Figure 5.7

Compression

Stages of Road Slip

Guidebook for Road Construction and Maintenance Management

5-7

5.2.4.2 Road Slip due to Water Infiltration


Water infiltration is a major cause of road slope failure. It is important that inflow from
above cut slope should be controlled and discharged to proper outfall sites.

Road

Road
Drain

Swelling
Road

Slide

Road
(Source: Japan Highway Public Cooperation 1982, Slope Inspection Guide 1)
Figure 5.8

Landslide Caused by Water Infiltration from Road

5.2.4.3 Road Slip due to Slope Erosion and Inadequate Drainage


Road slip starts with slope erosion. Slope erosion results from infiltration of water into
the road bed due to inadequate drainage sytems which eventually lead to gradual sliding of the
slope. At this stage, countermeasures will become expensive hence, properly designed
drainage system should be undertaken.

Figure 5.9

5-8

Road Slip due to Slope Erosion

Guidebook for Road Construction and Maintenance Management

Also, concentration of surface water triggers road slip therefore, proper drainage
facilities shall be instituted to address such condition.

Figure 5.10

Surface Flow Concentrations

5.2.4.4 Road Slip due to Leakage from Damaged Pipe Culvert


Leakage from damaged culvert will also cause road slip. It is therefore important to
identify the cause and extent of the problem and to conduct immediate repair works.

Figure 5.11

Road Slip caused by Leakage from Pipe Culvert

5.2.5 Debris Flow


Debris flow refers to the rapid flow of boulders, gravel, sand, silt clay and trees mixed
with a large quantity of water that is mainly generated when a slope collapses during heavy
rainfall. Conditions of debris flow- prone stream are as follows;
*

Gradient of stream bed is more than 15 degrees (debris flow stops if less than 10
degrees).

Catchment area is more than 5 has.

Existence of debris beside the road (debris flow reoccurs frequently).

Guidebook for Road Construction and Maintenance Management

5-9

Figure 5.12

Typical Debris Flow

5.3 Slope Failure Countermeasures


5.3.1 Soil Slope Failure Countermeasures
The following countermeasures are applicable for soil slope:
*

Slope Drainage Works

Cribwall

Vegetation Works

Mechanically

Retaining Wall

Stabilized

Embankment

Wall(MSE Wall)
*

Gabion Wall

START

Is there high risk


of soil slope failure
or landslide?

YES

NO
Is there seepage
from slope?
Or do you assume
high water table?

YES

NO

Does the area have


many records of slope
failure?

YES

NO
Removal of unstable mass,
Retaining wall,
Masonry works,,
Catch wall for collapsed soil,
Slope drainage and/or
Combination of above.

Figure 5.13

5 - 10

Removal of unstable mass,


Retaining wall,
Masonry works
Catch wall for collapsed soil,
Vegetation works,
Slope Drainage
Combination of above.

Removal of unstable mass,


Retaining wall,
Gabion wall,
Vegetation works,
Slope drainage,
Underdrains,
Horizontal boring and/or
Combination of above.

Removal of unstable mass,


Retaining wall,
Gabion wall,
Crib wall,
Anchor works,
Pile works,
Vegetation works,
Slope daraiange,
Underdrains,
Horizontal boring and/or
Combination of above.

Selections of Soil Slope Failure Countermeasures

Guidebook for Road Construction and Maintenance Management

5.3.2 Rock Slope Failure Countermeasures


The following countermeasures are applicable for rock slope:
*

Removal and Cutting of

Retaining Wall

Unstable and Isolated

Shotcrete

Rocks

Rocknet

Slope Drainage Work

Cribwall

START

Is there high risk


of rock slope failure
or rock fall?

YES

NO
Is there seepage
from slope?
Or is the slope
weathered?

YES

NO

Does the area have


many records of slope
failure? Are there
isolated stones/rocks

YES

NO
Removal of unstable mass,
Retaining wall,
Masonry works,,
Catch wall for rolling stones,
and/or
Combination of above.

Figure 5.14

Removal of unstable mass,


Retaining wall,
Masonry works
Catch wall for rolling stones,
Vegetation works (if able),
Slope Drainage
Combination of above.

Removal of unstable mass,


Retaining wall,
Masory works,
Vegetation works (if able),
Horizontal boring,
Shotcrete and/or
Combination of above.

Removal of unstable mass,


Retaining wall,
Crib wall,
Anchor works,
Horizontal boring,
Shotcrete,
Rocknet,
Rockshed and/or
Combination of above.

Selections of Rock Slope Failure Countermeasures

5.4 Slope Erosion Control


Gentle slope is more stable however, the degree of exposure to erosion is higher. In such

Rainfall per slope area

condition, erosion countermeasures such as slope drainage, vegetation, etc. are required.

Slope (o)

Figure 5.15

Relations between Slope and Rainfall

Guidebook for Road Construction and Maintenance Management

5 - 11

There are many slope failures due to erosion after construction because cut slopes are left
bare and are not provided with necessary slope protection works. The countermeasure to be
provided shall be vegetation works as much as possible.

Figure 5.16

Erosion on Cut Slope

5.4.1 Slope Drainage


Figure 5.17 shows the primary causes of slope instability. Soil of 40 - 60% fines
proportion and contains high natural water contents (more than 40%) is prone to slope failure
because it is moderately pervious and easily saturated. In such case, it is necessary to provide

Natural Water Content of Colluvial Deposit (%)

a slope drainage.
Sample
Stable slope
Unstable slope

80

Unstable

60

40

Stable

20

Stable
0

20

40

60

80

100

Content Ratio of Fines (passing 74 micron sieve) in


Matrix of Colluvial Deposit (%)

(Source: Okusono 1979, Japan Highway Public Cooperation Laboratory Report)


Figure 5.17

Relations between Content Ratio of Fines and Natural Water


Content

5 - 12

Guidebook for Road Construction and Maintenance Management

The vertical and horizontal alignment of slope drainage shall be smooth curve without
sharp bends as shown in Figure 5.18.

Slope Drainage
(Vertical and Horizontal)

Sharp
Bend

Overtopping

Overtopping
Slope Erosion
Figure 5.18

Surface Water Overtopping Slope Drainage

5.4.2 Vegetation Works


5.4.2.1 Purpose
The purposes of vegetation are as follows:
(a) Reduce surface erosion caused by running water and rainfall impact.
(b) Reduce infiltration of rain water.
(c) Bind subsurface soil with root systems, and
(d) Improve the landscape of the cut slope.
5.4.2.2 Applicable Conditions
Slope vegetation can mitigate slope erosion only therefore, it is recommended on stable
soil slopes. The type of vegetation shall be selected considering important factors such as
rainfall, temperature, slope gradient, and soil properties.

Guidebook for Road Construction and Maintenance Management

5 - 13

Table 5.4
Geology
Soft rock, fine grained
soil
Coarse grained soils

Applicable Cut Slope

Gradient
Horizontal: Vertical
1.0 to 1.2:1 or less
(45 or 40 degrees or
less)
1.5:1 or less
(35 degrees or less)

Applicability

Generally, only vegetation work is


applied on this kind of soil slope.

In this case, vegetation work alone is


not enough to prevent soil erosion
Intermediate condition between upper and lower
therefore, combinations with other
categories
countermeasures such as wicker works
are recommended.
Soft rock, fine grained
More than 0.8:1
Vegetation work is not applicable.
soil, coarse grained soils (More than 50 degrees)
(Source: Highway Earthwork Guideline, Published by Japan Road Association, March 1999)
5.4.2.3 Wicker Works
In case the slope of fine grained soil
is 45 degrees or more, a combination of
vegetation

and

wicker

works

is

recommended.
In Figure 5.10, Coconet was installed
with vegetation work but collapsed due to
slope erosion.
Figure 5.19

Figure 5.20

5 - 14

Inappropriate Vegetation Work

Wicker Works as Vegetation Base

Guidebook for Road Construction and Maintenance Management

5.4.2.4 Planting of Vetiver Grass


Vetiver grass is a kind of gramineous plant whose roots could penetrate up to 3 m. deep
and grows approximately 1m high.

Figure 5.21

Vetiver Grass

To determine the applicability of vetiver grass, trial planting is recommended considering


the following:
1) The top soil should be 0.5 to 2.0 m. deep.
2) Geological investigation should be conducted to verify the depth of solid strata
3) It should be planted at intervals of 1.0 m.
4) After a heavy rain, conduct field investigation to check possible occurrence and
depth of collapse.
5) The applicability of vetiver grass can now be evaluated.

(Reference: IDI November,2008)


Figure 5.22

Sketch of slope to be protected with Vetiver Grass

Guidebook for Road Construction and Maintenance Management

5 - 15

5.4.3 Coconet Bio-engineering


For controlling soil erosion, installation of coconut coir fiber made into geonets such as
coconets/mats, cocologs/fascines, cocotwines and coco peat as bioengineering materials is
advisable. The following terms are used in this technology.
Coconut Geonets

any coconut coir fiber-based placed on sloping ground and


embankments to hold the vulnerable soil and permit vegetative
growth to control surface erosion and preserve the productivity of the
soil.

Coconet

coconut coir fiber twine woven into blankets of different density.

Cocolog/Fascine

a tubular structure of coconut coir fiber blankets of different diameter


filled with coco coirand/or coco peat.

Coco Coir Twine

a string made of coconut coir strands twisted together.

Coco Coir Peat

a natural and residual materials from coconut coir which serves as


soil conditioner.

5.4.3.1 Material
(1)

Coconut Coir
Coconut coir fiber materials for use in fabrication of coconut geonets shall be a
multi-cellular fiber with 12 to 24 microns in diameter and the ratio of length to diameter
shall be 35. The fiber shall also be hygroscopic, with moisture content of 10% to 12% at
65% humidity and 22% to 55% at 95% relative humidity.

(2)

Coconet and Cocolog/Fascine


The hand-spun coco coir twine that is to be woven into coconut geonets shall have a
diameter of 5mm plus or minus 10%. The coco coir twine shall have a tensile strength of
not less than 150N. Coconet and cocolog/fascine shall conform to Tables 5.5 and 5.6,
respectively.
Table 5.5

Average Number of

Average Number of

Twines at Crosswise

Twines at

Direction

Lenghtwise Direction

Coconet 400

40

40

400

Coconet 700

40

70

700

Coconet 900

70

70

900

Type of Coconet

5 - 16

Physical properties (Coconet)


Density (min)
(gm/2 )

Guidebook for Road Construction and Maintenance Management

Table 5.6

Physical properties (Cocolog)


Diameter (min)

Weight (min)

(cm)

(Kg/m)

Cocolog 100

10

2.0

Cocolog 200

20

4.5

Cocolog 300

30

10

Cocolog 400

40

20

Cocolog 500

50

30

Type of Cocolog/Fascine

Figure 5.23

Figure 5.24
(3)

Coconet (CGN 700)

Cocolog/Fascine (CGR 200)

Bamboo Stakes
Bamboo stakes shall be mature and shall be 3 to 4 cm. wide and 25 to 30 cm. long.

(4)

Live Plants Stakes


Live plant stakes shall be kept moist and installed the same day they were prepared. Live

kakawate or equivalent local species maybe used.

Bamboo Stakes

Live Plants Stakes


Figure 5.25

Installation

Stakes

Guidebook for Road Construction and Maintenance Management

5 - 17

(5)

Coco Coir Peat (Soil Conditioner)


After the installation of coconut geonets, coco coir peat - soil mixture shall be
distributed evenly on the net protected slope. Thumping and raking shall follow to make
the mix settle underneath to ensure appropriate soil moisture and nutrients to the grasses
and other planting materials.

Figure 5.26
(6)

Coco Coir Peat

Ropes
Nylon rope or equivalent is used to tie cocologs to the stakes.

Figure 5.27

5 - 18

Ropes

Guidebook for Road Construction and Maintenance Management

5.4.3.2 Anchoring
(1)

Common Soil
The coconets shall be secured to the ground using bamboo pegs. An average of 3
pegs per square meter shall be used to ensure uniform contact and firm hold to the
ground.

(2)

Compacted Soil
A combination of bamboo pegs and U-shaped wire staples may be used for
compacted, hard to penetrate soil. An average of 3 pegs/staples per square meter shall be
used to ensure uniform contact of coco-net to the ground surface.

5.4.3.3 Vegetation
(1)

Vetiver Grass Hedgerow


Live hedgerow of vetiver grass (or any local suitable species) slips shall be planted
on the slopes at 10 to 50 cm. interval depending on the erodibility of the soil, the
steepness of the slope and the design water flow. Row distance shall likewise depend on
the steepness of the slope and shall range from 1 to 4 m.

(2)

Grass cover
Fast growing leguminous creeping grass shall be used on slope surfaces requiring
immediate vegetation cover. It shall be applied to the soil at a rate depending on the
desired density and the calculated on-site mortality rate of the plants.

(3)

Trees
If trees shall be used to stabilize a slope, species that have sturdy, long and
deep-penetrating roots shall be selected.

5.4.3.4 Cross Section

Figure 5.28

Typical Cross Sections for Bio-Engineering Works

Guidebook for Road Construction and Maintenance Management

5 - 19

5.4.3.5 Installation Procedure


(1)

Site Preparation
-

The area shall be graded and sloped to the approved design.

Any water runoff control such as diversions, berms or dikes shall be completed
prior to installation.

The face of the slope shall be smoothened and rocks, clods, vegetation (deemed
detrimental to the erosion control system to be installed), and other obstructions
shall be removed to ensure complete contact of the net with the soil.

In most cases, existing vegetation shall be retained, but shall be trimmed down to
facilitate the installation of the coconet.

(2) Laying of Nets


-

Installation shall begin at the top of the slope with the net laid down and securely
anchored 1 m. from the edge.

The net shall be unrolled downslope in the direction of the water flow.

The edges of adjacent rolls of coir fiber nets must be spliced together using coir
fiber twine ropes.

The coconet shall be laid loosely-not stretched- on the ground. Direct contact with
the soil shall be maintained at all times.

Figure 5.29
(3)

Site Preparation

Figure 5.30

Laying of Nets

Anchoring
The coir fiber net shall be secured to the ground using bamboo pegs 25 to 30 cm
long. An average of 3 pegs per square meter shall be used to ensure uniform contact of
net to the ground surface. For loose soils, longer pegs may be used to have sufficient
ground penetration to resist pullout. U-shaped wire staples may be used for compacted,
hard to penetrate soil.

(4)

Sewing
There are many ways of connecting the nets together to cover the slopes but sewing

5 - 20

Guidebook for Road Construction and Maintenance Management

them together is the best and most economical way of installing the nets.

Figure 5.31

Anchoring

Figure 5.32

Sewing

5.4.3.6 Planting of Grass Cover


Fast growing leguminous creeping/twining grasses shall be used for slope faces requiring
immediate vegetative cover. They are either hydroseeded or sowed by hand.
The dominant grass in the surrounding areas can be carefully uprooted and planted on
the slopes after the nets have been installed.

Figure 5.33

Hydroseeding

5.4.3.7 Watering
Watering is very important especially during the early days of germination of seeds,
when the roots are not established yet or when newly replanted. Upon seed germination, daily
watering is necessary for a month and fifteen days for transplanted grass.

5.5 Slope Protection Structures


Slope protection structures should be provided on the following conditions:
*

On rippable and solid rock slopes where vegetation is not applicable.

On slopes which cannot be stabilized for long term by vegetation only.

On slope that has potential to collapse.

Guidebook for Road Construction and Maintenance Management

5 - 21

5.5.1 Retaining Walls


5.5.1.1 Gravity Type (Concrete or Stone Masonry)
These walls can sustain the earth pressure by means of its own weight and can be built
more easily than the other types of retaining walls. They are often adopted when the height is
relatively low (less than 4 m.) and the ground foundation has a good bearing stratum. This
type of wall can be adopted also as catchwall as shown in Figure 5.33.

Figure 5.34

Gravity Type (Rock Catcher Retaining Wall)

5.5.1.2 Leaning Type (Concrete or Stone Masonry)


This type of wall acts against the soil pressure not only by its own weight but also by the
weight of soil as shown in Figure 5.34.
Leaning Type
Retaining Wall

where:
Wc

Wc = Weight of Concrete
Ws

Figure 5.35

Ws = Weight of Soil

Leaning Type Retaining Wall

The advantages in adopting stone masonry over concrete are that the gradient, length and
horizontal alignment could be done easily to match the profile of an existing section and it is
more economical. Moreover, if it will function as catch wall (with steel-framed catch fence),
reinforced concrete retaining wall is advisable.
Stone Masonry consists of stones with sizes as shown in Table 5.7 laid in accordance
with the lines and grades as shown in the plans or as directed by the Engineer, jointed by
cement mortar of 1 (cement) : 2 (sand) at trowel consistency.

5 - 22

Guidebook for Road Construction and Maintenance Management

The construction steps are shown below.


1. Prepare the foundation bed, compact and moisten as per
Specifications.

Mortar that is not used

2. Lay 5-10 cm thick mortar

within 90 minutes after the


water has been added shall
be discarded. Re-tempering

3. Embed Stones of specified size

of mortar is not permitted.


Weepholes

shall

be

provided unless otherwise


shown on the plans or as
4. Fill the spaces between stones with new mortar

directed by the Engineer.

5. Repeat steps 2-4 until the required dimension is attained.

Figure 5.36

Construction steps for Stone Masonry

5.5.2 Grouted Riprap


Grouted riprap shall consist of the furnishing and placing of riprap with filter backing,
furnished and constructed in accordance with the specification and as to lines and grades and
dimensions shown on the plans. This is commonly used in slope protections, abutments, lined
canals and other places called for in the plans.

(c)
Figure 5.37

(d)

(e)

Surfacing

Construction steps for Grouted Riprap

Guidebook for Road Construction and Maintenance Management

5 - 23

Grouted riprap shall be constructed in accordance with the following steps:


(a) Prepare the foundation bed, compacted
and

moistened

as

per

with

specifications.
(b) Lay 5-10 cm thick 1:3 mortar mixture
(cement 1: sand 3).
(c) Embed slightly moistened stones of
specified sizes into the fresh mortar.
(d) Fill the voids in between the stones with
mortar.
(e) Repeat the above steps a until the

Figure 5.38

Grouted Riprap

specified dimensions are attained.


Table 5.7
Item

Stones

Materials Requirement for Grouted Riprap and Stone Masonry


Grouted riprap
(Item 505
Class A: 15 kg to 25 kg
Class B: 30 kg to 70 kg
Class C: 60 kg to 100 kg
Class D: 100 kg to 200 kg

Mortar

Stone masonry
(Item 506)
Thickness: 150 mm or more
Width: 150% of respective
thickness or more
Length; 150% of respective width
or more
Cement (1): Sand (2)

Cement (1) : Sand (3)


Class A: 300 mm
Class B: 500 mm
Min. Thickness
As per design
Class C: 600 mm
Class D: 800 mm
Horizontally at the lowest points,
Not more than 2.0 m center to center in a staggered manner. The length
Weepholes
should not be less than the thickness of the walls, at least 100 mm dia.
PVC is recommended.
(Source: DPWH Standard Specifications for Highways, Bridges and Airports, 2013Edition)

5.5.3 Cribwall
5.5.3.1 Stone Masonry and/or Reinforced Concrete Cribwall
It is a type of retaining wall particularly made up of concrete or stone masonry (or a
combination of both) and supported with reinforced concrete frame. Generally, a double frame
type is adopted for a 3.5 to 5.5 m. height of slope.
On rock slopes with many joints or loose talus and where concrete spraying is
inappropriate, concrete cribwall is advisable.

5 - 24

Guidebook for Road Construction and Maintenance Management

Figure 5.39

Stone Masonry Cribwall

Fourth Level: Stone Masonry Cribwall

Third and Second Level: Concrete Cribwall

First Level: Concrete Retaining Wall

Second Level: Stone Masonry Cribwall

First Level: Concrete Cribwall

Figure 5.40

Reinforced Concrete Crib and Pitching Wall

Guidebook for Road Construction and Maintenance Management

5 - 25

5.5.3.2 Reinforced Concrete Frame with Vegetation Works


This type is ideal for high slope composed of weathered rock or unstable soil with
seepage or springs.

Figure 5.41

Reinforced Concrete Frame with Vegetation Works

Source: DPWH/JICA Technical Standards and Guidelines for Planning and Design Vol. IV,
2002 Natural Slope Failure Countermeasures

5.5.4 Gabion Wall


Gabions are used where there are
springs on a slope and sediments are likely to
be washed out and where a collapsed portion
is to be restored.
The lengths should be multiples of two
(2), three (3) or four (4) times the width of
the gabions and the height should be 0.50
meter to 1.0 meter. The horizontal width
should not be less than 1.0 meter. Gabion

Figure 5.42

Gabion Wall

furnished shall be of uniform width.


Gabion wires are double twisted meshed conforming to ASTM 641 or 856 or 809. Rock
pieces must be uniformly graded 100 mm to 200mm. No rock size shall exceed 2/3 the
mattress depth. Filled gabions shall have a minimum density of 1,400 kg/m3.
If spring water amount is big, drainage should be installed at the foot of the gabion. Filter
fabric shall be placed between the slope surface and gabion materials. The filter fabric shall be
rolled out into a flat non-rutted surface free from sharp objects.

5 - 26

Guidebook for Road Construction and Maintenance Management

Figure 5.43

Constructed Gabion Wall at a Location with Seepage

5.5.5 Mechanically Stabilized Embankment Wall (MSE Wall)


Reinforced embankment walls are of two types 1) Geotextile-reinforced and 2) Terre
Armee.

Figure 5.44

Mechanically Stabilized Embankment by means of Geotextile fabrics

Road
Embackment
Work
Embankment

Front View

9.0 m

Ground line before road slip

Collapse surface of road slip


Terre Armee Wall

Bedrock

Rear View

Slip Connection Clamp


Figure 5.45

Slip Bars

Mechanically Stabilized Embankment Wall (Terree Armee Wall)

Guidebook for Road Construction and Maintenance Management

5 - 27

5.6 Rock Slope Protection


As per experience, the height of bounce of rolling stone is within two meters regardless
of the slope length as shown in the figure below and should be considered in designing
rockfall protection works.

Figure 5.46

Relations between Rock Slope Height and Height of Bounce of


Stone

5.6.1 Cutting and Removal


Cutting and removal of isolated and overhanging rocks is the most effective rockfall
countermeasures.

Figure 5.47

Cutting and Removal of Unstable Rock Slope

5.6.2 Shotcrete
To prevent further weathering of the rock slope, shotcreting is one of the applicable
measures.
The following are the specified requirements for shotcreting:

5 - 28

Guidebook for Road Construction and Maintenance Management

Weepholes shall be installed at least one for every 4 m.2 in a staggered manner.

Before shotcreting, wire mesh shall be laid and anchored over the face of the slope.
The standard number of anchor pin is 1 to 2 per square meter. Main anchor pin shall be
16 mm diameter of 1.0 m. length, sub-anchor pins shall be 10 mm diameter of 0.3 m.
length.

The spraying thickness of concrete is 10-15 cm. (Mortar spraying of 8-10 cm. thick is
adopted as per Japan Standards.)

The standard mix proportion by weight of cement and aggregates shall be 1:3:1 to
1:5:2 (C: S: G) for concrete spraying. The water-cement ratio shall be 40 to 45% for
concrete spraying.

Notes:
*

The lower side of the convex part should be of uniform thickness.

To avoid clogging the weepholes, the exposed end should be capped/covered during
the operation.

Spraying by two layers should be adopted where a lot of ruggedness exist on the
surface. Wire mesh should be spread on each layer. The concrete for the second layer
should be sprayed within one hour after the first layer was sprayed.

The work should be suspended during rain and strong wind.

Figure 5.48

Shotcrete

5.6.3 Rocknet

Figure 5.49

Guidebook for Road Construction and Maintenance Management

Rocknet

5 - 29

5.6.4 Rock Catcher

Figure 5.50

Rock Catcher

5.6.5 Rock Shed

Figure 5.51

Rock Shed

5.7 Countermeasures for Landslide


The countermeasures for landslide are mainly categorized into two types namely 1) risk
mitigation and 2) structural countermeasures.
The risk mitigation countermeasure is to reduce the landslide movement by means of the
following:
*

Slope surface drainage works

Underground water drainage works

Earth removal works (of the sliding mass head)

Counterweight filling works

The structural countermeasure is a prevention work by constructing structures that will


resist the movement of landslide as follows:
*

Pile Works

Shaft Works

Anchor Works

5.8 Provision of Underground Drainage Pipe thru Boring


In case the slope is not stable due to the presence of underground water pressure,

5 - 30

Guidebook for Road Construction and Maintenance Management

provision of underground drainage pipe is one of the recommended countermeasures.


Underground water pressure basically increases as groundwater level increases due to rainfall
infiltration as illustrated below. Therefore, it is important to conduct groundwater logging to
monitor and establish the waterlevel to be applied for this method and also to verify its effect.
Rainfall infiltration

Landslide Mass

level of
water-table

Sliding plane

Figure 5.52

Figure 5.53

Rainfall and Groundwater Level

Typical Underground Drainage Pipe Installations

Guidebook for Road Construction and Maintenance Management

5 - 31

5.9 Slope Stability Analysis


(1)

Fellenius Method
The stability of the existing slope which has a potential to slide can be analyzed by the

Fellenius method as follows:

Fs

Fr

Fd

N U tan c L
T

where:

Fs=

safety factor

Fr=

the sum of the resisting forces

Fd=

the sum of the driving force

W=

gravity of segment (slice)

A=

area of segment (slice)

soil density

N=

normal force by gravity, W * cos

T=

tangential force by gravity, W * sin

L=

length of sliding plane in segment

U=

pore water pressure

c=

cohesion of sliding plane

internal friction angle of sliding plane

inclination of sliding plane

N
W

Sliding Plane

Figure 5.52

Fellenius Method

In case the output, Fs, is less than 1.0, the slope is evaluated as unstable. And if it is
equal or greater than 1.0, the slope is evaluated as stable.

5 - 32

Guidebook for Road Construction and Maintenance Management

(2)

Required Safety Factor


In designing structures such as pile, shaft and anchor works against the driving force of

the landslide, necessary resisting force to be added can be estimated by the following formula.

PFs Fs

Pr

N U tan c L P
T

where:

Fs=

safety factor of the existing slope

Pr=

necessary resisting force to be added

PFs= required safety factor of countermeasure

Pr PFs T ( N U ) tan c L
Shown in Table 5.8 are the required safety factors that were established and being adopted by
Japan as their design criteria in designing landslide countermeasures.
Table 5.8

Required Safety Factor for Landslide Countermeasures


Condition

Rivers, railroads, national highways and/or residential area will be


affected by landslide disaster, if it occurs.
Prefectural roads and some houses only will be affected by landslide
disaster, if it occurs.
Only small village road will be affected by landslide disaster, if it
occurs.
Countemeasure works will be buit as temporary works only during the
construction project.

Guidebook for Road Construction and Maintenance Management

Required Safety
Factor PFs
1.20
1.15
1.12
1.05 to 1.10

5 - 33

Chapter 6

River and Coastal


Erosions

6.1 River Erosion


The natural process by which the surface is worn away by the action or
movement of water e.g. current from stream flow, wave, rise and fall of water is
called erosion.
Along the river sides, erosion of the riverbed and banks due to stream flow or
current is a common scene and likewise, damage of structure foundation due to
scouring effect of the water with the eroded soil material.,

Figure 6.1

Degradation due to Riverbed Erosion

Guidebook for Road Construction and Maintenance Management

6-1

6.1.1 Examples of Road Damages caused by River Erosion


6.1.1.1
(1)

Riverbank Erosion

Riverbank Erosions along the Bends

River
Road
Deposit
Affected area

Figure 6.2
(2)

Riverbank Erosion along the Bend

Riverbank Erosions caused by Overflow

Over flow

Road

Debris Flow
Deposit
River Bed

Figure 6.3
6.1.1.2

Riverbank Erosion caused by Overflow

Riverbed Erosion

Scouring of river
bed

Collapse of Gabion
Wall

Insufficient depth
of embedment

Note)

Sufficient depth of embedment should be

at least 2.0 m or as per result of scour analysis.

Figure 6.4

Riverbed Erosion

6.1.2 Countermeasures for River Erosion


6.1.2.1

Riverbank Protection

Table 6.1 shows applicable works to protect the riverbank and/or bed from damages due

6-2

Guidebook for Road Construction and Maintenance Management

to river erosions. Also, shown in Figure 6.5 is a flowchart for the selection of appropriate
countermeasures against river erosion.
Table 6.1
Countermeasure

Countermeasures against River Erosions

Types of Work
Slope Pitching Work (Boulder/Riprap, Brick, Conrete, Concrete Block)
Gabion (Cylinder, Mattress)

Riverbank Revetment
Works

Stone Masonry
Concrete Retaining Wall
Piling (Steel ,Concrete)
Bed Pitching Work (Boulder/Riprap, Brick, Concrete, Concrete Block)

Riverbed Protection
Works

Block Pitching
Gabion (Cylinder,Mattress)
Groundsill/Check Dam
Floodway, Dredging

Rechanneling
Spur Dike

START

Small (>5.0m)

Effect of erosion on road


(Distance between
Road/River)

Large (5.0m)

Location of erosion

Temporary work

Both of riverbank/riverbed

Riverbank

- Wire cylinder
- Gabion revetment
- Wicker revetment
- Timber crib consolidation

Figure 6.5

- Masonry revetment
- Concrete revetment
- Concrete block revetment

- M asonry revetment
- Concrete revetment
- Concrete block revetment
- Check dam
- Concrete consolidation
- Concrete spur dike

Riverbed

- Check dam
- Concrete consolidation
- Concrete spur dike

Selection of River Erosion Countermeasures Flowchart

Guidebook for Road Construction and Maintenance Management

6-3

(1) River Revetment Works


River revetment works are commonly adopted on riverbank and slope as a
countermeasure against erosion as shown in Figure 6.6
Bank line before river erosion

Stone masonry revetment

Road

Road

Soil slope

Rock slope

Rock slope
Backfill

River erosion
a) Section View of River Erosion

Road

b) Section View of Revetment

Road

Backfill

Road

Backfill
Wire cylinder

Steel sheet pile


a) Stone Massonry

b) Inverted T-type Concrete Wall

Figure 6.6

c) Concrete Sheet Pile

Types of Revetment Works

In order to protect the river and road slope from erosion by water infiltration and/or
scouring, revetment works shall be provided.
Prior to planning and designing, preliminary investigations covering the following;
river erosion, history, longitudinal and cross sections, gradient,slope, bank geology and
proximity locations should be conducted to determine the exact location and appropriate
type of revetment.
Figure 6.7 shows a flowchart of design procedures for river revetments. The
following parameters such as roughness of the riverbed, velocity of river flow and
slope/gradient of the riverbank are important factors to consider in the design.

6-4

Guidebook for Road Construction and Maintenance Management

START

River and geological surveys

Preliminary planning:
- Location, cross and longitudinal sectional details
- Alignment of river and revetment
- Height of revetments

Selection :
- Flow velocity and slope gradient.

Design

-Design load computation


- Stability Analysis of river slope/bank (overturning, tensile
stress, sliding, bearing capacity of foundation)
- Structural design computation

Design of foundation
- Consolidation ,settlement and scouring analysis of foundation
- Footing protection works

END
Figure 6.7

Design Procedure for River Revetment Work

Shown below is a typical section of river revetments works.


a b

Road

Road

Weep hole
H: V=0.5:1

a=0.20m

Design riverbed

b=0.35m
H: V=0.4:1

a=0.20m
b=0.10m

b
a c

Body

filling

H: V=0.3:1
concrete
Design riverbed

b=0.35m
H: V=0.2:1

Backfill

2.0 m

Backfill

Stone masonry

Figure 6.8

2.0 m

Concrete block masonry

Typical Cross-section of Revetment Works

Guidebook for Road Construction and Maintenance Management

6-5

(2) Concrete Block Slope Pitching


Concrete block pitching work can be designed as grouted riprap. Basically, large
and heavy concrete blocks are more stable against strong river current and generally
designed for workability. However, in case the laying is done manually, the weight of the
block should be considered.
Concrete block of 400mm (width) x 400mm (length) x 100mm (thickness) which
weighs about 36 kgs. is used wherein the river flow design velocity is 3.5 m/s or less.

Figure 6.9

6-6

Laying of Concrete Blocks on River Slope

Guidebook for Road Construction and Maintenance Management

6.1.2.2

Riverbed Protection Works

Although there are different types of riverbed protection works, groundsill (head and/or
non-head type) is popularly used.
Sample arrangement of groundsills is shown in Figure 6.10.
River flow

River flow

Road

Road
Riverbed erosion
Potential bank collapse
due to riverbed erosion
Groundsills

b) Plan View of Groundsill Arrangment

a) Plan View of River Erosion

Figure 6.10

Sample Arrangement of Groundsills

Figure 6.11 shows a typical section of groundsill. Groundsills regulate the flow of water
to prevent the occurrence of scouring velocity that would damage the riverbed.

Head Type

Non-head Type

Flow direction
Design flood level
Existing riverbed

Figure 6.11

Typical section of Groundsill

Groundsills function to stabilize the riverbed as follows:


1.

Decrease the scouring force of water flow for the stabilization of the riverbed in the
upstream side (Head Type).

2.

Prevent the scouring and degradation of the riverbed (Non-head Type).

3.

Ensure the stability of revetment foundations (Both types).

Its right location and arrangement should be determined taking into consideration,

Guidebook for Road Construction and Maintenance Management

6-7

among others, the following:


1.

Sections with riverbed erosion or degradation.

2.

Sections immediately downstream and on the same side of the collapsed riverbank.

3.

The downstream area of the structures to be protected.

In case the damaged portions and banks or scoured areas are vast, several groundsills
should be installed.
Figure 6.12 shows a flowchart of design procedures for groundsill. The following
parameters such as roughness of the riverbed, velocity of river flow and slope/gradient of the
river are important factors to consider in the design.

START

River and geological surveys

Preliminary planning:
- Location, cross and longitudinal sectional details
- Alignment of groundsills
- Height of groundsills

Selection of type:
- Consider flow velocity and slope gradient

Design:
-Design load computation
-Stability Analysis of groudsills (overturning, tensile
stress, sliding, bearing capacity of foundation)
-Structural design computation

Design of apron and side wall

END
Figure 6.12

Design Procedure for Groundsill

The position of groundsill should be linear and at right angle to the direction of the water
flow as shown in Figure 6.13.

6-8

Guidebook for Road Construction and Maintenance Management

Flow
Flowingdirection
direction

Figure 6.13

Arrangement of groundsills relative to the direction of flow

A detailed drawing of groundsill is shown below:


B
Design flood level

H=height of groundsill body (m)

H1
H

Height of groundsill

1:m

1:0.2

h1

B=Thickness of crest opening (m)


H1=Height of fall (m)
h1=Overflow depth (m)
b=Embedment depth of main body
(m)
m=Upstream slope of groundsill

Figure 6.14

Details of Groundsill

The depth of embedment is the most important factor for the stability of groundsill (refer
to the table below).

Guidebook for Road Construction and Maintenance Management

6-9

Table 6.2

Required Depth and Width of Groundsill


Symbol

Part of Groundsill

(See

Condition of Foundation
Sand and gravel

Soft rock

Hard rock

1.5 to 2.0 m

1.5 to 2.0 m

1.5 to 2.0 m

b1

2.0 m or more

1.5 m or more

1.0 m or more

b2

2.0 m or more

1.5 to 2.0 m

1.0 m or more

Width of Wing (Bottom)

b3

2.0 m or more

1.0 m or more

0.5 m or more

Depth of embedment of Wing

b4

1.0 m or more

0.5 m or more

0.5 m or more

Depends on

1.0 : 2.0

1.0 : 2.0

Excavation Line

(H : V)

(H : V)

Fig.)

Depth of Embedment (Main


Body)
Width of Wing (Top)
Embedded Width
of Wing (Top)

Inclination Degree of Wing


Edge

Note: Refer to Figure 6.16

Figure 6.15
6.1.2.3

Typical Section of Groundsill

Rechanneling

Rechanneling is considered as a countermeasure against riverbank and riverbed erosions.


The concept of this countermeasure is shown in Figure 6.16

6 - 10

Guidebook for Road Construction and Maintenance Management

River flow
Road

River flow
Road

Potential bank collapse


New channel
by excavation

a) Plan View of River Erosion

Figure 6.16

b) Relocation of channel

Rechanneling Concept for Riverbank and Riverbed Protections

Construction of spur dike is also an effective countermeasure against riverbank and


riverbed erosions. Spur dike change the river flow direction to protect river bank and also
controls sedimentation of the riverbed.
There are three types of spur dikes namely; 1) perpendicular; 2) upward and 3)
downward- as shown in Figure 6.17. For riverbanks, upward spur dike is recommendable. For
reference, shown in Figure 6.18 is a typical cross-section of spur dike.

Figure 6.17

Type of Spur Dike

Guidebook for Road Construction and Maintenance Management

6 - 11

Low Crest Type

High Crest Type

W: river width
Lspur: Length of spur dike
Flow Deflector
Figure 6.18

6 - 12

Hspur: Height of Spur dike

Typical Cross Sections of Spur Dike

Guidebook for Road Construction and Maintenance Management

6.2 Coastal Erosion


At sea front on coastal areas, earth surface is worn away by wave and wind actions
which instantaneously change the configuration of the surrounding areas after typhoon that
generates big waves.
The rise and fall of water known as tide continuously and gradually changes the sea bed
configuration due to the influence of under current and littoral transport activities.
Basically, waves and surges mainly cause the damages on coastal road. There are three
cases; 1) scouring of foundation; 2) washout of backfill materials 3) collapse of the main
body.

Figure 6.19

6.2.1

Examples of Road Damages caused by Coastal Erosion

Case 1: Scouring of Foundation

Figure 6.20 illustrates the collapse of coastal revetment due to the scouring of the
foundation bed. Waves and surges scour the foundation bed which triggers the collapse of the
revetment.

Guidebook for Road Construction and Maintenance Management

6 - 13

Over Flow
Erosion

Over Flow
Road
Wave

Wave

Road

Erosion

Figure 6.20
(a) Road Body Collapse

Collapse of Coastal
Revetment
(b) Slope
Revetmentdue
Slip to Scouring of Foundation
Bed
Road

Roadside

Collapse of Grouted Riprap


Not so Eroded
High Water Level

Outflow of behind materials


Eroded Portion
Average Sea Level
Sea

Figure
6.21out of Backfilling
Conceptual
Diagram of Scouring of Foundation Bed
(c) Wash
Material

6 - 14

Guidebook for Road Construction and Maintenance Management

High Tide Level :


+1.0 m ~ 1.7 m

Figure 6.22

Collapse of Coastal Revetment

6.2.2 Case 2: Washout of Backfill Materials


Washing out of backfill materials also cause the collapse of coastal revetments as
illustrated in Figures 6.23, 6.24 and 6.25.

Guidebook for Road Construction and Maintenance Management

6 - 15

Figure 6.23

Collapse of Coastal Revetment due to Washout of Backfill


Materials

Inside this line, materials are


not grouted well.

This portion, filling materials are not grouted well.

Collapse inside the Masonry

RoadsideRoad

Masonry and backfill materials


are
not
grouted
and
compacted well.respectively.

Figure 6.24

Figure 6.25

Washout of Backfill Material

Collapse of Coastal Revetment due to Washed out Backfill


Material

The water overtopping the revetment accelerates the displacement of backfill materials as
explained below:

6 - 16

1.

Wave surge overtops the revetment and then scours the road shoulder.

2.

Water infiltrates into the backfill and washes it away.

3.

Cracks are then generated on the revetment.

Guidebook for Road Construction and Maintenance Management

Top Left: Wave surge scours the shoulder.


Top Right: Scoured portion progresses down
to the backfill materials.
Bottom Left: The revetment then collapses.
Figure 6.26

Collapse of Coastal Revetment due to Overtopping

6.2.3 Case 3: Collapse of Mainbody


Big wave surge can erode the concrete surface. Figure 6.28 shows the eroded surface of
grouted riprap.

Levels of erosion at the upper, middle and

Upper: Lightly eroded.

lower portions.

Middle: Moderately eroded.


Figure 6.27

Lower: Heavily eroded.

Levels of Erosion of Grouted Riprap Surface

Guidebook for Road Construction and Maintenance Management

6 - 17

Consequently, cracks will develop on the revetment.

Insuffient grouting cannot withstand wave surge

Inadequate thickness of concrete surface

Cracked and broken concrete surface.


Figure 6.28

Collapsed Revetment due to Progression of Cracks

6.2.4 Countermeasures for Coastal Erosion


Countermeasures to be applied are similar to that of river bank protection. Design
strategies for countermeasures are shown below.
Table 6.3

Countermeasures for Coastal Erosion

Cause of Damage

Countermeasure

Erosion of foundation bed

Provide adequate depth of embedment.

Washout of backfill

Backfill and cover with concrete slab, joints shall be properly

materials

sealed.

Collapse of mainbody

Appropriate structure shall be selected. Basically, riprap is not


advisable.

Coastal slope revetments are provided to prevent road bank erosion from the impacts of
waves, flood tides and tsunami. Figure 6.30 illustrates a conceptual design for coastal slope
revetment commonly and widely used. The revetment shall be designed for the following
purposes:

6 - 18

To minimize the impact of seawater due to flood tide or tsunami,

To reduce overtopping by waves, and

Guidebook for Road Construction and Maintenance Management

To prevent erosion due to wave action.


Recurved Parapet
C
L

ROAD

Wave Breaking
Side Drain Ditch
Foot
Protection

Waterside Slope
Revetment
Foundation

Figure 6.29

Conceptual Design of Coastal Slope Revetment

Generally, coastal revetments are composed of a slope revetment, foundation, foot


protection, wave breaker and curved parapet wall, which are required in consideration of the
tidal level, wave force and sub-soil ground condition and should be accounted for in the
design.
Shown in Figure 6.30 is a flowchart for the selection of countermeasures against coastal
erosion.

Guidebook for Road Construction and Maintenance Management

6 - 19

START

Not Large

Large

Affect of erosion to road


or behind area

Damage level
(Impact to road body)

Serious Impact

Caused of damage
Not Serious
Impact

- Repairing Work
- Restoration of damage section
- Regular inspection and
maintenance

Not enough strength of


revetment structure

- Revetment work
- Foundation work
- Wave breaking work

Scouring at
slope toe portion

- Foot protection work


- Foundation work
- Water cut-off work

Washing out
backfilling material

Overflowing wave

Figure 6.30

- Revetment work
- Foundation work
- Water cut-off work

- Recurved parapet work


- Wave breaking work

Selection of Countermeasures Against Coastal Erosion

As to the types of damages, the following describes basic countermeasure requirements.


a)

Not enough strength of slope revetment to withstand wave force


*

Reconstruct slope revetment and foundation to meet the technical requirements.

Install wave breakers to reduce wave force that will act on the surface of the slope
revetment.

b)

6 - 20

Scouring at toe by wave force


*

Ensure that the required embedment depth of the foundation is provided.

Provide foot protection on the toe or in front of the foundation.

Guidebook for Road Construction and Maintenance Management

Embedded
Depth

Wall
Thickness

Sheet Pile

(a) by Concrete Wall

Figure 6.31
c)

(b) by Sheet Pile

Typical Foundation Cut-off Wall

Scouring at the toe by seepage water


*

Replace the backfill materials of the revetment and/or embankment material with
impermeable materials.

Ensure the required embedment depth of the foundation is provided and/or


provide water cut-off wall.

d)

Washing out of backfill material


*

Replace revetment with water-proof structure.

Replace backfill material of the revetment with impermeable materials.

Ensure that the required embedment depth of the foundation is provided and/or
provide water cut-off wall

e)

Wave surge overtopping


*

Install wave breakers in front of the revetment slope.

Provide a curved parapet wall connected to the existing revetment body.

Weep holes shall be installed.

Carriageway and shoulder at shoreline shall be paved with cement concrete.

As shown in Figure 6.32, for construction of coastal revetment, the following should be
considered.
1.

Behind/ inside the masonry, filling materials should be compacted/ grouted well.

2.

Enough depth of foundation should be provided.

3.

Road shoulder should be paved with concrete.

4.

Weepholes should be placed in appropriate position to drain overtopped water.

Guidebook for Road Construction and Maintenance Management

6 - 21

3. Road shoulder should be paved with concrete


1. Behind/inside the masonry,
filling
materials
should
be
compacted/ grouted well

Shoulder

Road

2. Enough depth of foundation should be provided

Figure 6.32

6 - 22

Considerations for Coastal Revetment Design

Guidebook for Road Construction and Maintenance Management

Chapter 7

Road Safety

7.1 Road Signs


Road signs contain instructions that the road user is required to obey. These provide
warning of hazards that may not be self-evident and information about directions, destinations
and points of interests. Also, since signs are essential part of the road network system, the
information provided should be concise, consistent and most importantly, these should be
installed at conspicuous or designated spots along the roadway. Moreover, prior approval of
the DPWH Secretary or the Head of the Office concerned for the installation of the same
should be sought.
No road signs shall bear any advertising or commercial message, or any other messages
that are not essential to traffic control.
Placement of unauthorized signs within the road right-of-way or close to the roadway is
not allowed. The display of unofficial and non-essential sign is likewise not permitted.

7.1.1 Classifications
Road signs are classified as follows:
Type R

Regulatory Signs

Type W

Warning Signs

Type G

Guide or Informative Signs

Type S

Instructional Signs

Type HM

Hazard Markers

(1)

Regulatory Signs (Type R)


Regulatory signs indicate the application of legal or statutory requirements, e.g.
obligation to give way at intersections, speed limits, prohibition of movements at
intersections and control of parking of vehicles.
Most regulatory signs are circular in shape with white inscriptions and either red or
blue background as shown in Fig. 7.1 The notable exceptions to this are STOP
(octagonal), GIVE WAY (triangular) and some manually operated banners used in road
works. It is important that these shall be removed promptly if the legal requirements
become inconsistent with the present conditions.

Guidebook for Road Construction and Maintenance Management

7-1

Priority
Direction
Figure 7.1
(2)

Regulatory Signs (Type R)

Warning Signs (Type W)


Warning signs notify road users of the condition on or adjacent to the road that may
be unexpected or hazardous. Should not be used if, under normal conditions, the driver
can see the potential hazard ahead.

Figure 7.2
(3)

Warning Signs (Type W)

Guide or Informative Signs


These inform and guide the road users of directions, distances, locations of services
and points of interests.

Figure 7.3
(4)

Guide or Informative Signs (Type G)

Instructional Signs (Type S)


These are used at locations where ordinary guide or regulatory signs do not achieve

7-2

Guidebook for Road Construction and Maintenance Management

the desired results. Also, these guide motorists of the direction or follow a course of
action.

Figure 7.4
(5)

Instructional Signs (Type S)

Hazard Markers (Type HM)


These are used to emphasize a marked change in the direction of travel and the presence

of an obstruction.

Figure 7.5

Hazard Markers (Type HM)

7.1.2 Standard Application


Uniformity of application is as important as standardization with respect to design and
placement.
Identical conditions should always be treated with the same type of signs so that road
users can readily anticipate the course of action required.
Basic requirements for road signs are as follows:
1.

Fulfill a need

2.

Command attention

3.

Convey a clear, simple message

4.

Command respect

5.

Give adequate time for proper response

Guidebook for Road Construction and Maintenance Management

7-3

7.1.3 Design
Uniformity in the design facilitates easy identification by the road user.
Standardization of shape, color, dimensions, inscriptions and illumination or reflectivity
is important so that various classes of signs can be easily recognized.
The following design principles are considered:
*

The driver should not be distracted by a road sign from his driving.

Road signs should be understood by the driver traveling at any given speed and
must have sufficient time to take appropriate response safely.

Note: For necessary details, please refer to DPWH Road Signs and Pavement Markings
Manual, February, 2012 Edition and DPWH Road Safety Manual, 2012 Edition.

7.2 Weighbridge Station


National roads and bridges are damaged by freight trucks and trailers whose gross
weights exceed the allowable limits. In line with this, DPWH has installed weighbridge
stations at strategic locations along national roads.

Figure 7.6

Weighbridge Stations

Shown in Table 7.1 is the Maximum Allowable Gross Vehicle Weight (GVW) based on
the maximum allowable axle loads of 13,500 kgs as per Republic Act No. 8794.

7-4

Guidebook for Road Construction and Maintenance Management

Table 7.1

Maximum Allowable Vehicle Weight

MAXIMUM ALLOWABLE GROSS VEHICLE WEIGHT (GVW) PER RA 8794 (REVISED 2012)

Note: Special Permit to Travel shall be required for vehicles loaded with inseparable/or special cargoes exceeding
the corresponding GVW and vehicles with configuration different from those shown in the above matrix.

Guidebook for Road Construction and Maintenance Management

7-5

7.3 Road Warning System


For reference, an example of Road Status and Information System is shown in Figure 7.7.
This can be accessed thru the DPWH Website.

Figure 7.7

7-6

Road Status and Information System

Guidebook for Road Construction and Maintenance Management

Chapter 8

Monitoring and
Investigation

8.1 Weather Monitoring


8.1.1 Rain Gauges
To obtain rainfall data and provide road users with rainfall information, rain gauges are
installed and utilized. There are two types 1) standard rain gauge and 2) weighing
precipitation gauge (self-recording type).
Figure 8.2 illustrates the standard rain gauge and the rainfall is measured manually as
shown in Figure 8.1. Figure 8.3 illustrates the weighing precipitation gauge which measures
the rainfall by mass automatically.
Generally, both types of rain gauges should be installed at the same location in order to
avoid missing data in case one does not work well.

Figure 8.1

Figure 8.2

Manual Data Collection from a Standard Rain Gauge

Standard Rain Gauge

Figure 8.3

Weighing Precipitation
Rain Gauge

Guidebook for Road Construction and Maintenance Management

8-1

8.1.2 Weather Station


The main purpose of a weather station is to give notice to the public of the current
weather conditions such as rainfall, temperature, wind direction and speed. Weather data
repository is important in setting up warning criteria. It is useful particularly in construction
management since scheduling of works can be made by knowing the forecast weather
condition.
Weather station should be installed in a place where there is no obstruction for accurate
data collection.
Solar battery and
micro wave data
connection

Data logger and


data repository to
computer
Figure 8.4

Weather Station

8.2 Visual Inspection of Pavement


8.2.1 ROCOND
ROCOND is a visual road condition assesment system which includes a manual
entitled Visual Road Condition Assessment Manual Vol. 9. ROCOND was designed mainly to
provide road condition data for Pavement Management System (PMS) and also for Routine
Maintenance Management System (RMMS). Therefore, ROCOND functions also as a part of
Asset Management System and Database System in DPWH.
Currently, DPWH intends to develop a mechanized system for road inspection such as
International Roughness Index Testing Vehicle and/or Road Condition Survey Vehicle. When
this system is completed, this will be utilized in addition to ROCOND.

8.2.2 Portable Falling Weight Deflectometer (FWD)


(1)

Applicable Scope
This apparatus is used for the evaluation of subgrade reaction, subbase and base
course elasticity. However, it is not applicable with foundations having gravel or stone of
size 3.3 cm. or more.

8-2

Guidebook for Road Construction and Maintenance Management

(2)

Measurement method
1)

Prepare a smooth and level


surface. Remove loose material.
If surface is rough and hard, fill
with sand for leveling.

2)

Set the equipment to level and


confirm by a spirit level.
Figure 8.5

Figure 8.6
3)

Setting up of FWD

The Drop Rig

Initially drop the weight 5 times


from about 10 or 15 cm height prior
to testing.

4)

Connect main body and the display.

5)

Turn on the display instrument.


Refrain from touching the main
body until the standby window
appears on the display.
The instrument conducts initial
measurement automatically.

Figure 8.7

The Mainbody and

Display Instrument
3

6)

Push

CONDITION

at standby mode and input

diameter of load plate (100 mm only


available), estimated Poissons ratio

and file name. Table 8.1 shows how to


evalue Poisson's ratio.

Guidebook for Road Construction and Maintenance Management

Display

8-3

Table 8.1
N-Value by
standard
penetration test
(times/30cm)
0 to 8
8 to 15
15 or more
0 to 10
10 to 20

Nd-Value by
dynamic cone
penetration test
(times/10cm)
0 to 10
10 to 20
20 or more
0 to 5
15 to 30

Slightly
dense

20 to 30

30 to 45

0.35

Moderately
dense

30 to 50

45 to 75

0.30

Soft-medium
Stiff
Very Stiff
Loose
Medium

Finegrained
soil

Sand

Very dense
-

Rock
7)

Poisson's Ratio

Poissons Ratio

0.45
0.40
0.35
0.40
0.35

50 or more
75 or more
(Source: Japan Tunnel Design Standard)

0.30
0.25

Conduct initial measurement as follows:


Push buttons in the order of

5
MONITOR

/BAL (Balance).

Confirm that the Arabic numerals on the windows are almost 0 as shown below:

To return to stanby mode push

ESC

8)

Push

MEAS.

at standby mode, drop the weight and confirm Displacement and

Modulus of Subgrade Reaction as a preliminary test.

Figure 8.8

8-4

P0: Load [N]


D0:Displacement [mm]
K-TML:

Modulus

of

Subgrade

Reaction by TML type FWD-Light


[kN/m3]

Measure Display of Portable FWD

Guidebook for Road Construction and Maintenance Management

In case of evaluation on Subgrade Reaction by using of 100 mm diameter plate,


required displacement is 0.417 mm.
Try droping with various heights of weight until you attain the required displacement.
If the displacement is 0.417mm or more when 5cm height or less applied, stop
this preliminary test and replace the load plate with a bigger size.
When 300 mm diameter load plate is used, standard level of displacement shall be
1.25 mm. In case other diameter load plate is utilized, specific displacement can
be estimated by the following formula, SDL = 1.25 x (Di/300).
Where,
SDL = Specific displacement level (mm),
Di = Diameter of load plate (mm).
Required displacement level of each diameter of load plate is summarized in Table 8.2.
Table 8.2

Specific Displacement Level for FWD

Diameter of load plate

Required displacement

Allowable gravel size

(mm)

(mm)

(mm)

100 mm

0.417

less than 33mm

150 mm

0.625

less than 50mm

200 mm

0.832

less than 66mm

300 mm

1.250

less than 100 mm

9)

Find a testing drop height of weight for main test as shown inTable 8.3.
Table 8.3

Drop Height of Weight for Main Test


Drop height of weight for main test

Status

1st stage

2nd stage

3rd stage

X- 5cm

X cm

X+5 cm

X-10cm

X cm

X+10cm

5cm

10cm

15cm

Approximate drop height to obtain specific


displacement is X cm, and
K-TML: elastic modulus on displaying installment
is 50 MN/m3 or less
Approximate drop height to obtain specific
displacement is X cm, and
3

K-TML: elastic modulus is bigger than 50 MN/m


5cm drop of weight get the displacement of
0.417mm or more, stop the preliminary test.
10) Push

at standby mode, drop the weight and confirm Load and

Displacement (Main Test).

Guidebook for Road Construction and Maintenance Management

8-5

Conduct six times drops of each stage of drop height. If you have some failures,
additionaly drop again up to you get six appropriate results.
After dropping, push

to trigger waiting status. Record the load and

displacement in FWD-Light Test Recording Sheet.


11) Analyze main test data
Input main test data into FWD-Light Analysis Sheet. The sheet calculates
engineering properties of the ground as shown in Figure 8.9.
Measurement of load and displacement

Modulus of Subgrade
reaction
of
Portable
FWD : KP.FWD
(MN/m3) and/or (pci)
a)
Modulus of Subgrade
Reaction, Equivalent to 30
inch (76.2 cm) diameter
plate static load test:
K30inch
(MN/m3) and/or (pci)
Figure 8.9

Elastic modulus of Portable


FWD: EP.FWD
(MN/m2) and/or (psi)
b)
Site CBR (%)
c)
Design CBR (%)

d)
Unconfined
Compression
Strength: qu
(MN/m2)
and/or (psi)

Estimated Engineering Property

Estimation
Necessary values for design can be estimated or converted from the test data as
follows:
a)

K30inch = K P.FWD/(0.260* K P.FWD0.373)/2.54


K30inch, K P.FWD in MN/m3

b)

Site CBR (%) = EP.FWD/10, experimentally

c)

Design CBR =( Average Site CBR) - ( standard deviation) CBR in %

d)

qu = EP.FWD/250, experimentally
qu, EP.FWD in MN/m2 and/or psi
(Source: Abe Nagato 2003, Japan Pavement Journal)

8-6

Guidebook for Road Construction and Maintenance Management

Portable FWD Analysis


THE PROJECT FOR IMPROVEMENT OF QUALITY MANAGEMENT FOR HIGHWAY AND BRIDGE CONSTRUCTION AND MAINTENANCE
Job Title
January 9, 2009
Weather
Cloud
Test Date
KM. 280 +380
Test Location TUBLAY, KAPANGAN & KIBUNGAN Test Point
Poisson's
ratio
Gravelly Soil
0.35
Weight Mass
5
kg
Soil Type
Load Plate Diameter
150
Inspector
Mikihiro Mori
mm
Drop Height of 3rd Stage
30 cm
Modulus of
Elastic Modulus of
Load
Displacement
Load Stress
Subgrade Reaction
No.
Portable FWD
of Potable FWD
p.FWD MN/m3
p.FWD MN/m2
N
mm
kN/m2
7639
0.571
432
379
100
1
7636
0.573
432
377
99
2
7628
0.574
432
376
99
3
7671
0.600
434
362
95
4
7624
0.598
431
361
95
5
7663
0.595
434
364
96
6
7644
0.588
433
368
97
Average
Drop Height of 2nd Stage
40 cm
Modulus of
Elastic Modulus of
Load
Displacement
Load Stress
Subgrade Reaction
No.
Portable FWD
of Potable FWD
p.FWD MN/m3
p.FWD MN/m2
N
mm
kN/m2
8352
0.610
473
387
102
1
8395
0.606
475
392
103
2
8392
0.611
475
389
102
3
8401
0.627
475
379
100
4
8382
0.622
474
381
100
5
8413
0.636
476
374
99
6
8397
0.620
475
383
101
Average
Drop Height of
50 cm
Modulus of
Elastic Modulus of
Load
Displacement
Load Stress
Subgrade Reaction
No.
Portable FWD
of Potable FWD
p.FWD MN/m3
p.FWD MN/m2
N
mm
kN/m2
9139
0.687
517
376
99
1
9195
0.661
520
394
104
2
9187
0.665
520
391
103
3
9203
0.662
521
393
104
4
9220
0.667
522
391
103
5
9231
0.655
522
399
105
6
9207
0.662
521
394
104
Average

DisplacementLoad Stress Chart

0.59
0.62
0.66

1000

Load Stress
N/m 2

900

433
475
521

0.625 mm Displacement
8448
N
Load Stress of 0.625 mm Displacement
478
kN/m2
Load of

97
101
104

800

7644

700

8397

382
MN/m3
Modulus of Subgrade Reaction,

9207

Equivalent to 30 inch diameter plate

600
500

-266

400

Modulus of Subgrade Reaction

static load test : K 30inch


63

-1

MN/m3

Elastic Modulus of Potable FWD :EP.FWD

300

MN/m2

101

200

Estimated CBR by Elastic Modulus,


2

CBR(%) = EP.FWD/10 (MN/m )

100

10

0
0

0.5

1
Displacementmm

1.5

qu (MN/m2) = EP.FWD/250 (MN/m2)

0.40

Figure 8.10

Estimated unconfined compressive strength

MN/m2

Example of Analysis Sheet for Portable FWD

Guidebook for Road Construction and Maintenance Management

8-7

8.3 Slope Investigation


8.3.1 Measurement
8.3.1.1

Visual Measurement

The slope height and angle


can be estimated roughly by using
a tape measure and a range pole as
shown in Figure 8.11.

Figure 8.11

Rough Determination

of

Slope

Height and Angle


8.3.1.2

Portable Laser Distance Meter

Profile survey using portable "Laser


Distance Meter" is recommended for the
evaluation of road slope condition as shown
in Figure 8.12. The range of capability is 10
to 300 meter distance.

Figure 8.12

Road Slope Survey by


Digital Distance Meter

Figure 8.13

8-8

Digital Distance Meter

Guidebook for Road Construction and Maintenance Management

8.3.2 Visual Slope Investigation


8.3.2.1

Important Tips on Slope Investigation

Visual slope investigation should


be conducted from a distance with the

Many cracks

aid of topographic maps and aerial

can be seen

photographs or satelite images to


grasp an overall situation of the target

Observation
from
a
Distance

slope as shown in Figure 8.14. Then


field reconnaissance survey should be
carried out to obtain a detailed
condition of the slope.
In addtion to this, the slope shall
be observed from top to bottom
during the field reconnaissance as
Figure 8.14

shown in Figure 8.15.

Visual Slope Investigation


(1/2)

Easy to identify

Difficult
identify

Easy to identify

to

Open cracks caused by


toppling

Figure 8.15
8.3.2.2

Open cracks caused


by sliding

Visual Slope Investigation (2/2)

Geophysical Feature

Figure 8.16 and 8.17 illustrate the terms and definitions utilized in Slope Investigations.

Guidebook for Road Construction and Maintenance Management

8-9

Lc: Length of Surface


D: Total Length
L:

Depth of Displaced Mass

Vc: Vertical Height of Surface of


Rapture
Hc: Horizontal Distance of
Surface of Rapture

(Source: Varnes, 1978)


Figure 8.16

Block Diagram of Complex Earth Slide/Earth Flow

(Source: Japan Landslide Association)


Figure 8.17
8.3.2.3

Typical Configuration and Phenomena of Earth Slide

Checklist for Slope Investigation

Figure 8.18 shows important locations to be investigated.


Check
the
boundary
with
natural
slope

Check the deformation of the


upper portion of the slope
shoulder

2
1
2
1

Observe swelling,
water seepage etc.
Check a void by
hammer sounding

Figure 8.18

8 - 10

Check overall status, sketch and take


photos

Important Locations for Slope Investigation on Cut Slope

Guidebook for Road Construction and Maintenance Management

8.3.3 Digital Clinometer


Clinometer is an apparatus used for geological reconnaissances and surveys. It can
measure Strike and Dip. Strike and Dip are geological words which means a direction, a point
of compass, and an inclination of plane, slope or stratum as illustrated in Figure 8.19.

strike

Surface of slope
/geological layer

Directio
n of dip

Angle of
dip

Horizontal plane

Figure 8.19

Strike and Dig

Analog type of Clinometer as shown in Figure 8.20 (Left) used to utilized but Digital
Clinomete is popularly utilized currently.

Analog Clinometer

Digital Clinometer (Geo Clino)


Figure 8.20

Clinometer

Wait for a while till the oscillation of the needle of compass stops in case of Analog
Clinometer. But Strike and Dip of inclined plane are displayed instantly in case of Digital
Clinometer.

Guidebook for Road Construction and Maintenance Management

8 - 11

8.3.3.1

Name of Parts

Mainbody

Display
Figure 8.21

8.3.3.2

Parts of Digital Clinometer

Usage
Figure 8.22 shows the usage of Digital Clinometer.

Step 1

Step 2
Step 1:

Set the clino plate.

Step 2:

Place the GeoClino on the plate to

measure Strike.
Step 3:

Place the GeoClino on the plate to

measure Dip.
Step 3
Figure 8.22

8 - 12

Usage of Digital Clinometer

Guidebook for Road Construction and Maintenance Management

(1)

Power-ON/OFF
Keep pressing "POWER Button" more than 1
second to power on.After the power is on, keep pressing
"POWER Button" more than 1 second to power off.

(2)

Mode of Measurement:
There are three modes of measurement.

PLANE

mode is to measure the strike and the dip of the bedding plane (or
any other surface) automatically by simply placing GeoClino onto
the plane.

LINEATION

mode is to measure trend and plunge of a lineation and


simultaneously the strike and the dip of the plane on which the
lineation lies.

MANUAL

mode is to measure the orientation of the plane and lineation


separately, with higher resolution.

The method to change a mode is as follows:


Keep pressing "SET Button" more than 1 second to
show the Setting Menu display. Move the cursor to
1.MEASURE MODE. And press "SAVE Button" or
"HOLD Button". Move the cursor to 1.[PLANE],
2.[LINEATION], or 3.[MANUAL], and press "SAVE
Button".
(3)

Measuring in PLANE mode


Place the back of GeoClino onto the bedding
plane (or else) in any direction. The strike and dip of
any surface of any orientation are measured
automatically.
Measured data come up digitally on display.
P shows PLANE mode, followed by number of
measurement, then date and time in the upper line,
the strike and dip on the lower line.
Accuracy of dip is low in PLANE mode. Use MANUAL mode for higher accuracy.

Guidebook for Road Construction and Maintenance Management

8 - 13

(4)

Measuring in LINEATION Mode


Place the back of GeoClino on a bedding plane
(or else) and align the longer edge onto a lineation,
with the arrow on upper right of GeoClino to the
plunging direction.
Measured

data

come

up

on

display

automatically.
L shows LINEATION mode, followed by
number of measurement, then date and time in the
upper line.
Next come the strike and dip of the bedding plane on which the lineation lies,
followed by the trend and plunge of the lineation in the lower line. Read as the plane
strikes in N 24E with dip 41to W, the trend of lineation is N 68W with the plunge of
40, for example.
(5)

Measuring in MANUAL Mode


Use this mode to measure strike and dip of a bedding plane (or else), and trend and
plunge of a lineation separately.
(a)

To measure strike and dip of a plane


Place the back of GeoClino onto the
bedding plane.
Rotate GeoClino to make the long

Green Level light (2)

edge horizontal, keeping the back on the


plane, until the plunge becomes zero.
Green Level light (2) is turned on when
the plunge becomes zero. Strike and dip
of the plane are on display.
On display, M shows MANUAL
mode

followed

by

number

of

measurement, then date and time in the


upper line, and the strike and dip of the
surface in the lower line.
Plunge is of course 0. Read as strike in N 34 E and dip 38 to W, for example.

8 - 14

Guidebook for Road Construction and Maintenance Management

(b)

To measure trend and plunge of a lineation


Place the back of GeoClino on the bedding plane (or else). Align the longer edge

onto the lineation, with the arrow in the upper right to the plunging direction. Read the
data on display.
On display, you see M showing MANUAL mode followed by number of
measurement, then date and time in the upper line.
In the lower line, you read the trend of the lineation, maximum dip of the plane and
plunge of the lineation.
Read as the trend of the lineation is N 30 W,
maximum dip of the plane on which the lineation lies is
72to W and the plunge of the lineation is 24, for example.
Cautions
*

Place the longer edge of GeoClino parallel to the lineation holding the arrow to the
plunging direction. If you want to measure the upward direction of the lineation, for
instance the direction of fault movement, place GeoClino with the arrow to that
direction. The plunge angle is shown with minus sign.

The dip of the overturned plane is shown as "180 - measurement angle". An


overturned plane dipping 30 is shown as 150.

Guidebook for Road Construction and Maintenance Management

8 - 15

8.4 Slope Monitoring


8.4.1 Crack Monitoring
The displacement of a crack is recommended to be recorded in three different
dimensions (X, Y and Z). Boards and sticks will help gather displacement data and estimate
the deformation rate as shown in Figures 8.23.
Displacement: X

Displacement: Z
Crack

Displacement: Y

Crack

Crack

Crack

Displacement
Sticks:
5-10 m interval

Displacement Board
Displacement measurement

Z (+)
Y

X
Z (-)

Displacement
Stick

(Source: Japan Highway Public Cooperation 1982, Slope Inspection Guide 1)


Figure 8.23

Crack Displacement Measurement

8.4.2 Wire Extension Meter


Wire extension meter
is a kind of self-recording
equipment and monitor the
movement of soil or slopes.

Figure 8.24

8 - 16

Wire Extension Meter

Guidebook for Road Construction and Maintenance Management

8.5 Soil Investigations


8.5.1 Boring and Core Sampling
Drilling/boring and sampling are described in the DPWH Design Guidelines, Criteria
and Standard, Volume I chapter 4, Subsurface Investigation.
Appropriate equipments and technical capacity are required for good core recovery.
Displaced material by landslide
Core feature: clayey detritus
Color tone: brown (mostly by iron oxide)

Boundary of different colors means slip


surface of landslide

Non- displaced material: Base Rock


Core Feature: Rod-Shaped
Color Tone: Original Color
Figure 8.25

Figure 8.26

Sample Core Boring at Landslide Portion

Sample Core Boring at Soft Rock Slide

Guidebook for Road Construction and Maintenance Management

8 - 17

8.5.2 Sounding for Soil Strength Test


8.5.2.1

Standard Penetration Test

The standard penetration tests (SPT)


shall be carried out to obtain the necessary
data for planning and design in accordance
with the DPWH Design Guidelines, Criteria
and Standards Volume I.
-

A test-drive for 300 mm penetration


of a split tube sampler with a shoe.

N-value indicates the number of


drives for 30cm penetration of split
tube sampler.

Figure 8.28

Schematic Diagram of

Standard Penetration Test


8.5.2.2

Handle

Dual Mass Dynamic Cone

Sigle Mass or Dual Mass


Hammer, 8 kg or 4.6 kg

Penetration Test

famous field testing apparatus to sound the


soil

strength

in

Shallow

575 mm

Dynamic Cone Penetrometeris one of


Upper Rod

Pavement

Applications.

Anvil with
Quick-Connect Pin

In case the subgrade and/or roadbed are

Upper
Attachment

firm and DCP is not able to penetrate a Dual


Dynamic

Cone

Penetrometer

is

advisable. It can measure the shear strength

Drive Rod
16mm dia.

Variable
(1000 mm)

Mass

of soil with a CBR between 0.5 and 100.

Vertical
Scale

Note:
Dynamic Cone Penetrometer and Dual
Mass Dynamic Cone Penetrometer conform

Tip
(Reusable Hardend Point
or Disposable Cone)

Foot

to ASTM D6951 and ASTM D6951 3,

Figure 8.29

respectively.

Penetrometer (Dual Mass Type)

8 - 18

Dynamic Cone

Guidebook for Road Construction and Maintenance Management

Dynamic Cone Penetrometer requires


only one operator to do a test basically.

Figure 8.30
8.5.2.3

Operation of DCP

Simplified Dynamic Cone Penetration Test

Simplified Dynamic Cone Penetration (SDCP) is a small


type of dynamic cone penetrometer, developed in Japan, Japan
Geotechnical Society Standard (JGS) 1433-1955, for slope soil
investigation

Advantage

of

Simplified

Dynamic

Cone

Penetration is light than ASTM Dynamic Cone Penetration, so


that it's easy to carry on to the slopes.
Five (5) kg hammer is dropped from a height of 50cm
freely, and dropping numbers to penetrate 10 cm depth into the
ground is recorded as Nd value (nos./10 cm).
For convenience and effective use of the Dynamic Cone
Penetration (DCP) test equipment, a rubber stopper that can be
fixed at the upper end of the rod that can help maintain constant
height of drop should be provided.

Figure 8.31 Simplified


Dynamic Cone
Penetrometer

Procedure
(1) Attach the cone to the bottom tip of the rod, attach guide rod and hammer on the top of
the rod.
(2) Set cone and rod perpendicularly on the sounding point.
(3) Confirm penetration depth by the self weight of the hammer (49 N or 5kgf)
(4) Record Nd-value: required numbers of 50 cm height free dropping to penetrate 10 cm
into the ground, The frequency of the dropping is made about once for three seconds.
(5) If penetration depth is less than 2 cm by 10 times dropping, the test should be
terminated.
(6) Friction cut (drill by auger/catch, 2 pieces shovel, or rotation rod of more than 10
times) before dropping the weight. Each 10 cm depth is recommended (especially for
soft clay, sands under ground water level).

Guidebook for Road Construction and Maintenance Management

8 - 19

Recording
(1) Intrusive depth and hammering times for every 10cm depth shall be recorded.
Nd-value are automatically calculated by the spreadsheet.
(2) In case of self weight penetration, penetration depth and dropping times = 0 are
inputted. Then Nd value = 0
Friction Cut
The rod skin friction affects DCP

Nd-values, it is especially remarkable for


1

soft clay/or saturated sands. Therefore,


friction cut is required. Method of friction

Depth (m)

cut is as follows:

Dig up hole to the examination


depth so that the rod should not

touch the soil by hand auger.


-

Rotate rod ten times or more


before the hammer dropping.

7
0.00

0.20

0.40

0.60

0.80

1.00

Coefficient of friction loss

Pour

oil/dope

into

the

surroundings of the rod in the test


Figure 8.32

Friction Loss on

Simplified Dynamic Cone


Penetrometer Test

hole before the hammer dropping.


The Figure on the left shows an
example of coefficient of friction loss on
Nd-value for common soils.

Coefficient of friction loss = Nd-value with friction cut/ Nd-value without friction cut
Relation of Nd-value and N-value are shown in Table 8.X.
Table 8.4

Estimation of N-value from Nd-value of SDCP

Nd: Nd-value
(Value by dynamic
cone penetration test)

Gravel

Sand

Fine-grained Soil
(Clay/Silt)
or Unknown

more than 4

N0.7+0.34Nd

N1.1+0.30Nd

N1.7+0.34Nd

4 or less

N0.50Nd
N0.66Nd
N0.75Nd
N= N-value by standard penetration test
Nd= Nd-value by dynamic cone penetration test
(Source: Okada Katuya et. al 1992, Soil and Foundation, Japanese Geotechnical Bulletin)

8 - 20

Guidebook for Road Construction and Maintenance Management

Sample Graph

Figure 8.33

Sample Output/Simplified Dynamic Cone Penetrometer

8.6 Ground Water Survey and Monitoring


8.6.1 Ground Water Logging
This measurement equipment is to be installed for monitoring the water table and
obtaining necessary data for slope stability analysis.
Pure water has high electric resistance while salt water has low electric resistance. The
logging detects ground water flow in salted borehole water by dilution phenomena.
1.

The electric resistance of groundwater in the borehole should be measured at 0.5m


intervals as initial value.

Guidebook for Road Construction and Maintenance Management

8 - 21

2.

Salt should be put into the borehole and


stirred to provide approximately 1%
concentration of electrolyte.

3.

After 5, 10, 30, 60, 120, 180min, the


electric resistance of groundwater in the
borehole should be measured at 0.5 meter
depth each.
Figure 8.34

Schematic Diagram

of Groundwater Logging
If groundwater fluid beds exist, salt water
should be replaced with pure water between the
depths of groundwater fluid bed, so the electric
resistance of groundwater will be increased.
A sample graph of groundwater logging is
shown in Figure 8.35. Electric resistance
increase as the time passes at some depths of
water table.

Figure 8.35

Sample Graph of

Groundwater Logging
Table 8.5

Classification
Obvious groundwater
flow bed
Semi-obvious
groundwater flow bed
Potential water flow
bed

8 - 22

Criteria for Groundwater Logging

Increase of Electric Specific Resistance


(-cm)
30
60
120
min
min
min
More than
Dilution to
103
initial value
More than
More than
More than
2 x 102
5 x 102
103
More than
More than
More than
102
2 x 102
3 x 102
(Source: Japan Landslide Association)

Geological
possibility of slip
surface
Possible
Possible
Possible

Guidebook for Road Construction and Maintenance Management

8.6.2 Hand Held Water Quality Sensor


Usually water quality tests on groundwater is carried out together with water logging.
Hand-Held Water Quality Sensor is portable and a useful apparatus to conduct with water
logging.
Table 8.6

Objected Water Properties

Item

Indication range

Accuracy (Main unit)

Potential Hydrogen (PH) or


Oxidation-reduction
potential (ORP)

- 14.00

0.05 pH

-2000 -2000mV

5mV

- 0.00 mg/L, 0 - 200%

0.00 - 20.00 S/cm*

1%

Dissolved oxygen (DO)


Electronic conductivity
(COND)
Salinity (SALT)
Total dissolved solid (TDS
Temperature (TEMP)
Turbidity (TURB

- 4.00%
- 40.00 (sea water salt)
0.0 - 100.0 g/L
-5.00 - 55.00
- 800.0 NTU
0.0 - 800.0 mg/L

0.1%
2g/L
Degree
3%

1) Connect reading unit 2) Push start button

3) pH value appears

and sensor

4) Push channel buttun


5) DO, COND, SALT, TDS,
TEMP, and TURB values appear

Guidebook for Road Construction and Maintenance Management

8 - 23

8.7 Strain Gauge with PVC Pipe


8.7.1 Summary of Pipe Strain Gauge
The strain gauge PVC pipe is installed to detect the depth of slip surface and monitor its
movement.
When the pipe (installed in a borehole) is bent by the movement of a landslide, one side
o is compressed and the other side is extended. Strain gauges with PVC Pipes are measuring
instruments which can judge a slip surface and determine the degree of displacement by
measurement of small changes in electric resistance value caused by the bending of PVC
pipes. Generally, strain gauges are put on PVC pipes at 1 meter intervals.

Figure 8.36

Pipe Strain Gauge

8.7.2 Checklist for Installation of Pipe Strain Gauge


*

Place marked side of PVC pipes (a side of strain gauges are attached) where the
direction of landslide moving is expected.

Be careful not to cut lead wires. Do not grasp lead wires alone, grasp PVC pipes.

8.7.3 Strain Gauges Monitoring


Sample graph of strain gauges monitoring is shown in Figure 8.37. In this graph, the
value of strain increases at the depth of slip surface. If a landslide moves, the value of strain
will be accumulated. Data not accumulated (only one time movement) is just accidental.

8 - 24

Guidebook for Road Construction and Maintenance Management

Drilling
Log

Symbo

Depth

2000 strain

Graph of Strain Gauges

5m

10m

10m
10

15m
15

15

15

15

15

15

15

15

15

15

Cumu
lative

move
ment

strain

10m

6000
4000
2000
0

Daily

Rainf
all
(mm)

100

50

Day

Month

10

20
4

30

10

20

30

10

20
7

30

10

20

30

10

20
9

30

10

20

30

10

10

20

30

11

10

20
12

30

10

20

30

1)
2)

10

20
3

Value of
accumulation
(/month)
More than 5,000
More than 1,000

Sample Pipe Strain Gauge Monitoring


Criteria for Evaluation of Data of Strain Gauges

Variability Characteristics
accumulatio

Very High
High

of slip

Status of moving

surface

n
Accumulative1)
Accumulative

Overall judgments

possibility
of existence

Tendency of

Possible
Possible

Classification of

Activity and Type of

slip surface

landslide

Determined
Semi-

More than 100

Low

Intermissive/
Destabilizing/

More than 100


(Short term)

Debris Landslide
Slowly moving creep
Impossible to conclude

Possible

Potential

Destabilizing

Need to continue
Slip surface is not existent.

None

2)

/regressive

Accumulative: The amount of the strain increases in the time series.


Regressive: The amount of the strain decrease in the time series.

Guidebook for Road Construction and Maintenance Management

existence of slip surface.


observation.

Intermissive/
None

Active Rock Landslide-

determined

Regressive
D

20
2

2005

Accumulative/
C

10

Table 8.7

10

Graph of Strain Gauges

Figure 8.37

of Movement

30

2004

Year

Classification

20
6

Abnormal

Caused by other factors,


except landslide.

Source: Strain Gauge Criteria in


Japan

8 - 25

Borehole BV-1 (Road Shoulder)

GL-3m
Semi-deter
mined slip
surface
GL-6m
Semidetermined
slip surface

Borehole BV-2

GL-2m
Determined slip
surface
GL-12m
Semi-determined
slip surface

Figure 8.38

8 - 26

Monitoring of Pipe Strain Gauge (Sample Output)

Guidebook for Road Construction and Maintenance Management

GL-2m
Semi-determined
slip surface

GL-6m
Potential slip surface

GL-2m
Determined slip surface
GL-12 m
Semi-determined
slip surface

Figure 8.40

Monitoring of Pipe Strain Gauge (Sample Profile)

8.7.4 Digital Strain Meter


Digital Strain Meter
is

necessary

Name of Parts

to

determine Strain Gauge.

Guidebook for Road Construction and Maintenance Management

8 - 27

Usage
The strain meter is turned on by pressing
"POWER" key.
To turn off the strain meter, press
"POWER" key again.
Every individual depth of pipe strain gauges

Normal Mode

are measured by "Normal Mode" is selected.


Press F2/CH key to select channel setting mode.(Channel number display is highlighted.)
Normal mode and multi-channel mode is selected alternately at every time SHIFT key is
pressed. However, mode changeover is not settled by this operation only.
A.

Mode is settled by pressing ENT key.

B.

Mode changeover is quitted and former mode remains effective by pressing DEL key.

Contrast of main Liquid Crystal Display (LCD) is adjusted by and keys in


monitoring mode.
key: Contrast is increased.
key: Contrast is decreased
Back light of main Liquid Crystal Display (LCD) is turned on by pressing F1/LIGHT
key in monitoring mode.
To turn off the back light, press F1/LIGHT key again.
When back light is turned on, power consumption increases about twice as that of
without back light. Back light is automatically turned off by approximately 30 seconds while
TC-31K is powered by battery.
This is an operation to specify the sensor
mode of connected sensor.
Press "1/SENSOR" key to enter the sensor
mode setting.
(Sensor mode number display is highlighted.)
Sensor Mode
A.

Input sensor mode number "15" for Half Bridge Type Strain monitoring.

B.

Input sensor mode number using and keys.


key: Mode number is increased.

8 - 28

Guidebook for Road Construction and Maintenance Management

key: Mode number is decreased


C.

Sensor mode is settled and setting mode is finished by pressing ENT key.

D.

Former sensor mode remains effective and setting mode is quitted by pressing DEL
key.

Refer to Figure 8.41 and 8.42 for connection


Moving
direction

of pipe strain gauges namely half bridge type (2

Lead Wire

gauges).
Water Proof
Coverage

Strain
Gauge
PVC Pipe
Direction
Mark

Figure 8.42

Connection with Half Bridge

Figure 8.41

Type

Strain Gauges with PVC


Pipe
Name of Parts

Connection of A and C are changed for every depth and values are recorded as Normal
and Reverse. The values measured shall be recorded into the recording sheets for Pipe Strain
Gauge Analysis.

Guidebook for Road Construction and Maintenance Management

8 - 29

Você também pode gostar