Escolar Documentos
Profissional Documentos
Cultura Documentos
NIHAL WICKRAMASURIYA
GENERAL MANAGER
CEYLON ELECTRICITY BOARD
Contents:
SRI LANKA
Total Area
Population
Population Growth
Average Household Size
Life Expectancy
Literacy Rate
Human Development Index
Access to Safe Drinking Water
- Electricity
- Telephone
Per Capita GDP
GDP Growth
Implementing Strategies
ELECTRICITY SECTOR
Regulated Industry
Generation
- State Owned- 1758 MW
- IPP
- 742 MW
- NCRE
- 184 MW
Maximum Demand
- 1868 MW
Load Factor
- 60%
T + D Losses
- 14.6%
Average Cost of Electricity - 0.157 $
Demand Growth
- 10%
Demand (MW)
1200
Peaking
Plant
1000
Peaking Plant
800
Peaking Plant
Intermediate Plant
600
400
0
0
10
11
12
Time of Day
13
14
15
16
17
18
19
20
21
22
23
24
Background
Under consideration since mid 1970s
Pre-feasibility study conducted with the
assistance of USAID in 2002 by Nexant Inc.
Review of the Pre-feasibility study with
assistance of USAID in 2006 by Nexant/ Power
Grid Corporation of India
Considered under SAARC and BIMSTEC Regional
Grid
Background
Bilateral discussions by Secretary , Ministry of
Power and Energy Sri Lanka and Secretary
Ministry of Power, India in Dec 2006.
Cabinet of Ministers approved in principle in
Dec 2006, to study the feasibility of power
interconnection and to appoint a Steering
Committee Co- Chaired by Secretaries of Power
Ministries and to appoint a Task Force for
technical, commercial ,regulatory and legal
aspects.
Background
First Task Force meeting was held in September
2007 in Colombo.
TOR of the feasibility study prepared by ADB
discussed at Task Force Meeting
Steering Committee meeting was not held
MOU was prepared by the two Governments in
2008
Background
Estimated
Cost
Million
Scope of Work
1. System studies for the Interconnection
2. Design Studies and equipment Parameter
Finalization
3.
150 km
Pannaikulam
127
km
Mannar
110 km
New
Anuradhapura
Possibilities of Quantum of
Power Exchange
2015 onwards 2020 onwards -
500 MW
1000 MW
Present Status
Present Status
Marine survey
Both marine environmental survey and
oceanographic surveys assigned to National
Institute of Oceanography, Goa, India
Clearances from Sri Lankan authorities provided
for marine surveys
Concurrence of CEB sent to PGCIL to engage a
consultant for soil investigation on the sea route
(for pile foundation design of HVDC line)
Present Status
Environmental Clearance
CEB and PGCIL have commenced the
environmental approval process
Economic studies
To be completed