1.01
1.02
1.03
DEFINITION OF TERMS
A.
B.
Base Bid - the amount stated on the Bid Form for which the Bidder offers to
perform the Work as described in the Bidding Documents as a base to which
Alternate Bid work amounts may be added to or deducted from.
C.
Unit Price Bid - the amount stated in the Bid Form as a price per unit of
measurement for materials or labor as described in the Bidding Documents.
D.
BIDDING DOCUMENTS
A.
Complete sets of Bidding Documents may be obtained from the Owner as stated
in the Invitation to Bid. Complete sets of Bidding Documents shall be used by
bidders in preparation of bids; neither the Owner nor the Engineer assume any
responsibility for errors or misinterpretations resulting from the use of incomplete
sets.
B.
Addenda any changes to the Bidding Documents occurring after the Mandatory
Pre-Bid Meeting will be posted on the City website, and e-mail notification will
be sent to all eligible bidders. It is the bidders responsibility to review
modifications and base bids on the most recent information.
Bidders shall visit the site of the proposed work and become familiar with the
nature and extent of work to be performed and local conditions that may affect the
work.
B.
1.04
1.05
C.
Bidders shall examine existing site improvements, existing buildings, utilities and
streets to determine all conditions which will affect the work.
D.
Bidders are advised that no soils investigations have been performed for this
project. The Bidder may elect to provide his own soils investigation prior to bid,
to determine the conditions affecting the work.
B.
C.
D.
A bidder, prior to submitting his bid, shall ascertain that he has received all
Addenda issued, and shall acknowledge their receipt in the Bid Form.
SUBSTITUTIONS
A.
Bidders represent that their Bid is based upon the materials and equipment
described in the Bidding Documents.
B.
Requests for substitutions will be considered prior to receipt of bids if they reach
the Owner at least 10 days prior to the date for receipt of bids and are submitted in
accordance with requirements of Section 01600.
C.
D.
INB-2
1.06
PRE-BID MEETING
A.
B.
The Owner will review the entire project, including plans and specifications, and
answer any and all questions from the potential bidders. Any major modifications
or interpretations of the plans or specifications shall be included in a project
addendum.
Prior to the meeting, all questions related to the project shall be directed to the
Public Works Director, Mr. Rick Carper, 1200 Sandpiper Lane, Atlantic
Beach, FL 32233, at Tel. 904-247-5834. Examinations of documents and site as
noted in Section 1.04 shall be completed prior to the Pre-Bid Meeting.
C.
1.07
No bids will be accepted from Bidders who did not attend the Pre-Bid Meeting or
make the required site visits and documents review.
BID PREPARATION
A.
Prepare bids on the forms provided by the Owner with all blanks on the Bid Form
filled in by typewriter or written in ink.
B.
State bid unit price and bid amounts. In case of a discrepancy between the two,
the bid unit price shall govern.
C.
Bids shall include the legal name and address of the Bidder and indicate whether
the Bidder is a sole proprietor, a partnership, a corporation, or some other legal
entity.
1.
2.
3.
INB-3
1.08
1.09
D.
Bids shall include documentation required by the Florida "Trench Safety Act."
The prices presented in the Trench Safety Affidavit shall be inclusive of the
Bidders cost of compliance with the applicable trench safety standards. Bidders
may be disqualified and their bids rejected for failure to include documentation
required.
E.
Lump Sum and Unit Price Bids requested on the Bid Form shall be bid.
BID SUBMITTAL
A.
Submit three copies of the Bid Form, the bid security, the list of Subcontractors,
and other requested attachments, enclosed in a sealed opaque envelope, addressed
to the entity receiving the bids as stated in the Invitation to Bid. The envelope
shall be further identified with the Project name, the Bidder's name and address,
and the words "BID ENCLOSED".
B.
Deposit Bids at the designated location on or before the time and date for receipt
of Bids indicated in the Invitation to Bid. Bids received after the time and date
indicated for receipt of bids will be returned unopened.
BID SECURITY
A.
B.
Failure of the successful Bidder to enter into the Contract in accordance with his
Bid, or failure to furnish the required bonds will be just cause for an annulment of
the award with the amount of the bid security being forfeited to the Owner as
liquidated damages, not as a penalty.
C.
D.
The Owner may retain the bid security of those Bidders to whom an award may be
considered until successful execution of the Contract and bonds; or the specified
time for holding bids has elapsed; or all Bids have been rejected.
INB-4
1.10
1.11
1.12
Prior to the time of bid opening, a Bidder may withdraw his Bid at any time, but
may not resubmit it. Bids may not be modified after submittal.
B.
After the bid opening, no Bid may be withdrawn, canceled or modified for a
period of 90 days after the time and date designated for the receipt of bids.
OPENING OF BIDS
A.
Bids submitted will be opened publicly and read aloud at the time and place stated
in the Advertisement for Bids.
B.
The City of Atlantic Beach reserves the right to postpone the date and time
announced for opening of bids. Such postponement may be made at any time
prior to the time announced for the opening of bids; City of Atlantic Beach will
give written notice of any such postponement to each party to whom bid
documents have been issued, followed by issuance of an addendum confirming
the changing of the announced date and time for opening of bids.
Bidders shall be familiar with all federal, state, and local laws, ordinances, rules,
and regulations that may in any way affect the Work.
B.
C.
Public Entity Crimes: A person or affiliate who has been placed on the convicted
vendor list following a conviction for a public entity crime may not submit a bid
on a contract to provide any goods or services to a public entity, may not submit a
bid on a contract with a public entity for the construction or repair of a public
building or public work, may not submit bids on leases of real property to a public
entity, may not be awarded or perform work as a contractor, supplier,
subcontractor, or consultant under a contract with any public entity, and may not
transact business with any public entity in excess of the threshold amount
provided in Section 287.C17, for CATEGORY TWO for a period of 36 months
INB-5
from the date of being placed on the convicted vendor list. (Section 287.133(2),
FLORIDA STATUTES).
D.
1.13
LIQUIDATED DAMAGES
A.
1.14
The Owner will incur financial loss if the Work is not substantially complete by
the date set forth in the Bid Form. The Contractor (and his Surety) shall be liable
for liquidated damages in accordance with the Supplementary Conditions and the
Agreement.
With the execution and delivery of the Contract, the Bidder shall furnish the
following Surety bonds of the forms contained herein:
1.
2.
B.
C.
INB-6
1.15
1.16
1.17
SUBCONTRACTOR LIST
A.
In conjunction with the Bid Form, Bidder shall submit a list of names of the
subcontractors and major material suppliers proposed for the principal portions of
the Work. Submit list on form provided by the Owner.
B.
Prior to award of Contract, the Owner will notify the Bidder in writing if the
Owner has an objection to any person or entity listed. Upon such reasonable
objection, the Bidder shall propose an acceptable substitute person or entity in
accordance with Article 6.06 of the General Conditions.
Until final award of Contract, the Owner reserves the right to reject any and all
Bids, with or without cause; to waive any informality or irregularity; or to accept
the Bid which is in the best interest of the Owner.
B.
It is the intent of the Owner to award a Contract to the lowest responsible Bidder
whose Bid is in conformance with the Bidding Documents and does not exceed
the funds available.
C.
Upon acceptance of a Bid and award of Contract, the successful Bidder shall
deliver the executed Contract, along with required bonds and any other items requested, to the Owner within 10 days. Failure to do so will be deemed as a breach
of agreement by the Bidder and result in forfeiture of bid security as described in
the Instructions to Bidders.
D.
Failure on the part of the successful bidder to execute the Contract as required or
to perform under the Purchase Order will be cause for the annulment of the award
and, in the event of annulment of the award, the bidder shall forfeit the bid
guaranty. The award may thereafter be made to the next lowest acceptable bidder,
or the work re-advertised as the City Commission may elect.
PRECONSTRUCTION CONFERENCE
A.
Before starting any construction work on this project, a conference will be held in
the Owners office for the purpose of verifying general procedures, reviewing
schedules and traffic plans, and other items as described in the specifications and
General Conditions.
B.
1.18
UNABLE TO BID
A.
If the Contractor cannot submit a bid at this time, the City requests they complete
the No Bid Form. If not submitting a bid, do not return the entire bid package, but
only the completed No Bid Form to Mr. Rick Carper, Public Works Director,
1200 Sandpiper Lane, Atlantic Beach FL 32233 or Fax the form to
904-247-5843.
END OF SECTION
INB-8
Name of Firm
______________________________________
Address
______________________________________
______________________________________
______________________________________
Signature
______________________________________