Task
Mode
0
Task Name
Duration
Residential
Construction
152 days
Start
Jul 5, '15
F
T
Aug 2, '15
W
S
Tue
2/17/15
Tue 2/17/15
Finalize plans
20 days
and develop
estimate with
owner, architect
Sign contract and 1 day
notice to
proceed
Apply for
0 days
Permits
Secure
0 days
foundation
permit
Secure
0 days
framing
permit
Secure
0 days
electrical
permit
Secure
0 days
plumbing
permit
Secure HVAC 0 days
permit
Tue 2/17/15
Tue 3/17/15
4
5
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Tue 3/17/15
3/17
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 1
Oct
W
ID
Task
Mode
10
11
12
13
14
15
16
17
18
19
20
21
Task Name
Duration
Start
3/17
Secure
0 days
miscellaneous
permits
Site Work
3 days
Tue 3/17/15
Wed 3/18/15
Thu 3/19/15
Electric company
1 day
Fri 3/20/15
42 days
Mon 3/23/15
Excavate for
3 days
foundations
Form basement 13 days
walls
Place concrete 12 days
for foundations
& basement
walls basement 7 days
Cure
walls for 7 days
Strip basement 2 days
wall forms
Waterproof/insulate
2 days
basement walls
Mon 3/23/15
Install
underground
utilities
Foundation
Jul 5, '15
F
T
Aug 2, '15
W
S
Wed 3/18/15
Thu 3/26/15
Concrete contractor
Tue 4/14/15
Thu 4/30/15
Concrete contractor
Mon 5/11/15
Concrete contractor
Wed 5/13/15
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 2
Oct
W
ID
Task
Mode
22
23
24
25
26
27
28
29
30
31
32
33
34
35
Task Name
Duration
Start
Inspector
Jul 5, '15
F
T
Aug 2, '15
W
S
Perform
foundation
inspection
Backfill
foundation
Framing
1 day
Fri 5/15/15
2 days
Mon 5/18/15
22 days
Wed 5/20/15
2 days
Wed 5/20/15
2 days
Fri 5/22/15
4 days
Tue 5/26/15
1 day
Mon 6/1/15
2 days
Tue 6/2/15
2 days
Thu 6/4/15
3 days
Mon 6/8/15
2 days
Thu 6/11/15
3 days
Mon 6/15/15
Framing contractor
1 day
Thu 6/18/15
Inspector
22 days
Thu 6/18/15
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 3
Oct
W
ID
Task
Mode
36
37
38
39
40
41
42
43
44
45
46
47
Task Name
Duration
Start
Jul 5, '15
F
T
Aug 2, '15
W
S
Framing contractor
3 days
Fri 6/19/15
3 days
Wed 6/24/15
3 days
Thu 6/18/15
3 days
Mon 7/6/15
Roofing contractor
1 day
Thu 7/9/15
Framing contractor
3 days
Fri 7/10/15
3 days
Wed 7/15/15
19 days
Mon 7/20/15
Complete
exterior brick
Complete
exterior siding
Utility
Rough-B97Ins and
Complete Concrete
Rough-in
plumbing
16 days
Mon 7/20/15
3 days
Tue 8/11/15
21 days
Tue 6/23/15
5 days
Mon 6/29/15
Framing contractor
Framing contractor
Framing contractor
Framing contractor
Masonry contractor
Framing contractor
Plumbing contractor
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 4
Oct
W
ID
Task
Mode
Task Name
Duration
Start
Jul 5, '15
F
T
Inspector
Aug 2, '15
W
S
48
Mon 7/6/15
49
Tue 7/7/15
52
Rough-in HVAC
Tue 7/7/15
53
Fri 7/10/15
Inspector
54
Rough-in
2 days
communication phone, cable,
computer, alarm
Interior Finishes
30 days
Tue 6/23/15
50
51
55
56
57
Insulation
3 days
11 days
Place wall
1 day
insulation - 1st
floor
Concrete contractor
Electric contractor
Mon 6/29/15
Inspector
Mon 7/6/15
Electric contractor
Mon 7/20/15
Mon 7/20/15
Insulation contractor
Mon 7/20/15
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 5
Oct
W
ID
Task
Mode
58
59
60
61
62
63
64
65
66
67
Task Name
Duration
Place wall
insulation 2nd floor
Place ceiling
insulation 2nd floor
Conduct
insulation
inspection
Drywall
Start
1 day
Tue 7/21/15
1 day
Fri 7/31/15
1 day
Mon 8/3/15
9 days
Tue 7/21/15
Tue 7/21/15
Wed 7/29/15
Jul 5, '15
F
T
Aug 2, '15
W
S
Insulation contractor
Insulation contractor
Inspector
Drywall contractor
Drywall contractor
Thu 7/23/15
Drywall contractor
Mon 7/27/15
Drywall contractor
Drywall contractor
Mon 7/27/15
Drywall contractor
Fri 7/31/15
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 6
Oct
W
ID
Task
Mode
68
69
70
71
72
73
74
75
76
Task Name
Duration
Paint and
Wallpaper
Texture all
except entry
and kitchen 1st floor
Paint all
except entry
and kitchen 1st floor
Hang
wallpaper
entry and
kitchen - 1st
floor
Texture all 2nd floor
Paint all - 2nd
floor
Paint exterior
siding & trim
work
Cabinets
Start
Jul 5, '15
F
T
Aug 2, '15
W
S
17 days
Tue 7/28/15
1 day
Tue 7/28/15
Painting contractor
1 day
Wed 7/29/15
Painting contractor
1 day
Thu 7/30/15
Painting contractor
1 day
Wed 7/29/15
Painting contractor
1 day
Thu 7/30/15
Painting contractor
4 days
Fri 8/14/15
6 days
Fri 7/31/15
Fri 7/31/15
Painting contractor
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 7
Oct
W
ID
Task
Mode
Task Name
Duration
Start
Jul 5, '15
F
T
Aug 2, '15
W
S
77
Tue 8/4/15
78
Install 2nd
1 day
floor - hall
bath and
private bath
cabinets
Install chair
2 days
rails, crown
moldings, trim
Wed 8/5/15
80
Tue 8/4/15
81
Tue 8/4/15
Fri 8/7/15
79
82
83
Thu 8/6/15
Plumbing contractor
Plumbing contractor
Wed 8/5/15
Plumbing contractor
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 8
Oct
W
ID
Task
Mode
84
85
86
87
88
89
90
91
Task Name
Duration
Start
Jul 5, '15
F
T
Aug 2, '15
W
S
Inspector
Tue 8/11/15
Tue 8/11/15
Tue 8/11/15
Electric contractor
Wed 8/12/15
Electric contractor
Thu 8/13/15
Inspector
Complete
2 days
communications
wiring phone, cable,
computer,
alarm
Finish
HVAC
3 days
Wed 8/12/15
Electric contractor
Oct
W
Fri 8/14/15
Heating and AC contractor
Fri 8/14/15
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 9
ID
Task
Mode
92
93
94
95
96
97
98
99
100
101
102
Task Name
Duration
8 days
Start
Jul 5, '15
F
T
Aug 2, '15
W
S
Oct
W
Mon 8/17/15
Tue 8/18/15
Inspector
3 days
Wed
8/19/15
Wed 8/19/15
2 days
Mon 8/24/15
2 days
Wed 8/26/15
Flooring contractor
1 day
Fri 8/28/15
Appliance contractor
12 days
Thu 8/20/15
2 days
Thu 8/20/15
2 days
Mon 8/31/15
2 days
Wed 9/2/15
Flooring contractor
Flooring contractor
Concrete contractor
Fencing contractor
Landscape contractor
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 10
ID
103
104
105
106
107
108
Task
Mode
Task Name
Duration
Sod and
complete
plantings backyard
Final Acceptance
Complete final
inspection for
certificate of
occupancy
Cleanup for
occupancy
Perform final
walk-through
inspection
Complete punch
list items
Start
Jul 5, '15
F
T
Aug 2, '15
W
S
Oct
W
Landscape contractor
1 day
Fri 9/4/15
8 days
Mon 9/7/15
1 day
Mon 9/7/15
Inspector
1 day
Tue 9/8/15
Maid service
1 day
Wed 9/9/15
Owner
5 days
Thu 9/10/15
General contracto
Task
Inactive Task
External Milestone
Split
Inactive Milestone
Manual Summary
Deadline
Milestone
Inactive Summary
Start-only
Progress
Summary
Manual Task
Finish-only
Manual Progress
Project Summary
Duration-only
External Tasks
Page 11