Você está na página 1de 5

DETAILS OF MEASUREMENT

Name of work:- The Proposed Construction of Rest House for Church of God at Haobam Marak Lourembam
Leikai,Imphal.
Item 1. Earth work in excavation in fdn.
a)Hard/Dense soil.
Footings
5x3=15Nosx1.50x1.50x1.80
Trenches
3x0.90 =2.70
9x3.00 =27.00
5x2.70 =13.50
5x1.50 =7.50
=50.70x0.45x0.60
Step
1x2.70x1.00x0.30

=60.75m3

=13.69m3
= 0.81
=75.25m3

Item 2. Filling available excavated earth1/3rd of item No. 1.


=1/3x75.25
=25.08m3
Item 3. Filling in plinth with sandy soil1x2.20x4.00
=8.80m2
1x2.20x2.80
=6.16
3x4.00x4.30
=51.60
3x2.80x4.30
=36.12
=102.68m2x0.60
=61.61m3
Item 4. P/L cement concrete 1:4:8Footings
15x1.50x1.50x0.15
=5.06m3
Trenches
3x2.10 =6.30
9x4.20 =37.80
5x3.90 =19.50
5x2.70 =13.50
=77.10x0.45x0.15
=5.20m3
Step
1x2.70x1.00x0.15
=0.41
Floors
1x102.68x0.15
=15.40
=26.07m3
Item 5. P/L 50mm D.P.C.
1x77.10x0.25 =19.28m2
Item 6. RCC work in foundation footings 1:1.5:315x1.35x1.35x0.30
=8.20m3
15x1.352+0.302x0.45 =6.45
2
15x0.30x0.30x0.90
=1.22
15x0.30x0.30x0.75
=1.01
=16.88m3
Item 7. RCC work in suspended floors,roofs,landings 1:1.5:3Grade beams 1x77.10x0.30x0.45
=10.41m3
Lintels
1x2.10 =2.10
10x4.20=42.00
1x2.60 =2.60
1x1.50 =1.50
=48.20x0.125x0.15
=0.90m3
Roof beams
3x16.20=48.60
5x7.50 =37.50
=86.10x0.30x0.45
=11.62
Stair case beam 1x2.10x0.30x0.45
=0.28
Landing
1x2.10x0.90x0.15
=0.28
Slab
1x16.20x7.50x0.15
=18.23
=41.72 m3
Less stair case(-)
1x3.30x2.10x0.15
= 1.04
Entrance beam 2x1.20x0.30x0.45
Slab
2x1.20x1.50x0.15

=0.32
=0.54

=41.54m3
First floor
Roof beam Qnty. Same as above=11.62m3
Stair cases beam
-do=0.28m3
Landings
-do=0.28
Lintels
-do=0.90
Slab
-do=18.23
=31.31m3
Less for stair cases(-)
= 1.04
=30.27m3
2nd floor Roof beam Qnty. Same as above
=11.62m3
Lintels
-do=0.90
=12.52m3
Item 8. RCC work in columns,pillars,post 1:1.5:315Nosx0.30x0.30x3.00
=4.05m3
First floor
15Nosx0.30x0.30x3.00
=4.05m3
2nd floor
15Nosx0.30x0.30x3.00
=4.05m3
Item 9. RCC work in stair cases2x2.75x1.05x0.15
2x9x1.05x x0.25x0.15
Qnty. Same as above

=0.87m3
=0.35
=1.22m3
=1.22m3

Item 10.RCC work in chajjas7x2x1.05x0.45x0.08


First floor qnty. Same as above
2nd floor
-do-

=0.53m3
=0.53m3
=0.53m3

First floor

Item 11.Reinforcementn for RCC work a)Tor steel bars.


a)Foundation 0.80% of 16.88m3
=0.135m3
b)Columns 2.50% of 12.15m3
=0.304
c)Beams 2.00% of 45.80m3
=0.916
d)Slab 1.00% of 41.03m3
=0.410
=1.765m3x7851.30Kgs/m3
=13858.00Kgs.
Item 12.Providing form worka)Foundation,footings4x15x1.35x0.30
=24.30m2
4x15x1.35+0.30x0.45 =22.28
2
4x15x0.30x0.90
=16.20
4x15x0.30x0.75
=13.50
=76.28m2
b)Flat surface such as suspended floorsi)Floors etc. upto 200mm in thickness.
Slab Bottom
1x16.20x7.50 =121.50m2x2Nos
=243.00m2
2x1.20x1.50
= 3.60
Edges
2x2x(16.20+7.50)x0.15
=14.22
2x1.50x0.15
=0.45
2x1.20x0.15
=0.36
Landings
2x2.10x0.90
=3.78
2x2x(2.10+0.90)x0.15
=1.80
=267.21m2
c)Columns,pillars,posts4x15x0.30x3.00=54.00m2x3Nos
=162.00m2
d)Sides and soffits of beamsGrade beams 2x77.10x0.45 =69.39m2
Lintels
2x48.20x0.15 =14.46
Beams
2x86.10x0.45 =77.49
Bottoms
1x86.10x0.30 =25.83
Stair case beam 2x2.10x0.45
=1.89

Bottoms

1x2.10x0.30

=0.63

Entrance beam 2x2x1.20x0.45


Beams
2x86.10x0.45
Bottoms
1x86.10x0.30
Stair case beam 2x2.10x0.45
Bottoms
1x2.10x0.30
Lintels
2x48.20x0.15
Roof beam
2x86.10x0.45
Bottoms
1x86.10x0.30
Lintels
2x48.20x0.15

=2.16
=77.49
=25.83
=1.89
=0.63
=14.46
=77.49
=25.83
=14.46
=429.93m2
e)Stair cases
2x2x2x2.75x0.15
=3.30m2
2x2x2.75x1.05
=11.55
2x2x9x1.05x0.15
=5.67
2x2x2x2.75x0.15
=3.30
=23.82m2
f)Chullah,hoods,weathers shade chajjas2x7x3x1.05x0.45
=19.85m2
2x7x3x1.05x0.08
=3.53
2x7x3x0.45x0.08
=1.51
=24.89m2
Item 13.Brick work in foundation and plinth 1:3Plinth
1x77.10x0.25x0.75
=14.46m3
Steps
2.70x1.00x0.30
=0.81
2.70x0.75x0.15
=0.30
2.70x0.50x0.15
=0.20
2.70x0.25x0.15
=0.10
=15.87m3
Item 14.Half brick masonary 1:31x2.10 =2.10
12x4.20=50.40
3x3.90 =11.70
4x2.70 =10.80
2x1.50 =3.00
2x2.75 =5.50
=83.50x3.00 =250.50m2
Less opening(-)
D1
5x1.05x2.10
=11.03
D2
1x0.75x2.10
=1.58
W
7x1.50x1.65
=17.33
V
1x0.50x0.60
=0.30
D
1x1.50x2.40
=3.60
=216.66m2
First floor Qnty. Same as above
=216.66m2
2nd floor
-do=216.66m2
Item 15.Providing wood work in frames of doors,windowsa)Uningthou wood.
D
2x2.40
=4.80
1x1.50
=1.50
D1
5x2x2.10
=21.00
5x1x1.05
=5.25
D2
2x2.10
=4.20
1x0.75
=0.75
W
7x4x1.65
=46.20
7x2x1.50
=21.00
V
2x0.60
=1.20
2x0.50
=1.00
=106.90x0.10x0.075=0.80m3x3Nos

=2.40m3

Item 16.P/F 40mm thick paneled,glazeda)Uningthou wood.


D
1x1.50x2.40
=3.60m2
D1
5x1.05x2.10
=11.03
D2
1x0.75x2.10
=1.58
W
7x1.50x1.65
=17.33
V
1x0.50x0.60
=0.30
=33.84m2x3Nos
=101.52m2
Item 17.P/F M.S.round or square bars16mm dia. security barsW
7x10x1.45
=101.50Rm
V
3x0.45
= 1.35
=102.85Rmx1.58kg/Rm=162.50Kgs.
Item 18.Prov iding 40x3mm hold fastD
21x2x3
=126 Nos.
W
21x2x2
= 84
V
3x2x2
= 12
=222 Nos.
Item 19.P/F 75x60mm moulded hand rails1x4x2.75
=11.00Rm
Item 20.P/F 75 to 60mm caps turned1x3
=3 Nos.
Item 21.P/F 25x25mm wood balusters2x2x9x0.90
=32.40Rm
Item 22.P/F Brass sliding boltsa)250x16mm. 7x3
=21 Nos.
Item 23.P/F Brass tower bolts
a)200x10mm
Doors 7x3x2
=42 Nos.
b)150x10mm
W
21x3x2
=126 Nos.
V
1x2x3
= 6
=132 Nos.
Item 24.P/F Brass handlesa)125mm
D
21x2
=42 Nos.
W
21x3
=63
V
1x3
=3
=108 Nos.
Item 25.P/F M.S. hooks and eyesa)150mm
W
21x3
=63 Nos.
V
1x3
=3
=66 Nos.
Item 26.P/F Collapsible steel shutters1x2.10x2.40
=5.04m2
Item 27.White glazed tiles in flooring1x102.68m2
=102.68m2
2x16.20x7.50 =243.00
=345.68m2
Item 28.C.G.I.sheet roofing2x9.00x17.70 =318.60m2
Item 29.Ridges/hips
1x17.70=17.70Rm
Item 30.Steel work in built up tubular trussesa)Electric resistant welded tube(Conforming to IS:1611-1979).
1x17.70x9.00 =159.30m2
Item 31.12mm cement plaster 1:3Walls 2x(216.66x3) =1299.96m2
Item 32.15mm cement plaster 1:3 with a floating coat of neat cement-

Plinth 2x(16.20+7.50)x0.75
Step 4x2.70x0.25
4x2.70x0.15

=35.55m2
=2.70
=1.62

2x1.00x0.15
2x0.75x0.15
2x0.50x0.15
2x0.25x0.15

= 0.30
=0.225
=0.15
=0.075
=40.62m2
Less(-)1x2.70x0.60
=1.62
=39.00m2
Item 33.Distempering with oil bound washableWalls 1x1299.96m2
=1299.96m2
Beams 3x3x16.20x0.30
=43.74
5x3x7.50x0.30
=33.75
2x5x3x7.50x0.45
=101.25
2x3x3x16.20x0.45
=131.22
Col.
4x3x0.30x3.00
=118.80
Under roof
2x16.20x7.50
=243.00
=1852.92m2
Item 34.Providing and applying plaster of paris putty of 2mm.
Qnty. Same as above =1852.92m2
Item 35.Applying ready mixed priming coat on steel workQnty. B.F. item No. 17 =102.85Rmx0.05

=5.14m2

Item 36.Painting two coats with white paintQnty. Same as above =5.14m2
Item 37.Varnishing(two or more coats) with copal varnishOpening Qnty. Same as item No. 16
=101.52m2x2sides

=203.04m2

Você também pode gostar