Rev.

Date

Description

Prepared

Checked

Approved

No.

ORIGINATOR

EDOPEC ENERJ PETROL MHENDSLK SANAY VE


TCARET LMTED RKET
Head Office :
Palmiye Mah. Adnan menderes Bulv. Oktay
Sitesi No: 9/8 PK = 33100 Yeniehir /Mersin
TURKEY
P:+90 324 3260595
F:+90 324 3260596
Ankara Office :
UUR MUMCU CAD(krolu cad) ERDL APT
87/13 Gop-ankaya -Ankara-TURKYE
P: +90 312 447 17 18 / 20
F:+90 312 447 17 21
stanbul Office:
Burhanye Mahalles amlca Caddesi
hlamur villalar no 28 / 6^RD3K Villa ^
Beylerbeyi skdar stanbul / TURKEY
P : +90 216 4220414 PBX
F: +90 216 4220415
www.edopec.com. info@edopec.com

Document Title

BAKU - TBILISI - CEYHAN CRUDE OIL PIPELINE PROJECT


Lot B
Document No.
EDP

WMS

COE

COR

INT

Co. Org.
Cod

Doc Type

Disc.
Code

Unit Code

Prj. Type

014

178

206

Prj.

Prj.

NO

Year

Prj
Seq.No

DCC
Seq.No

XXX

Rev

Scale

Page

16

Page 2

of 16

TABLE OF CONTENTS
1

SCOPE

CODES AND STANDARDS

DESCRIPTION

SITE EQUIPMENTS AND MAN POWER

METHODOLOGY

5.1

Survey Procedure

AUTHORITY AND PERMITS REQUIREMENTS

LAND ACQUISITION REQUIREMENTS

H&S REQUIREMENTS

ENVIRONMENT ASSESSMENT

10

COMMUNITY RELATIONS ASSESSEMENTS

11

SECURITY ASSESSEMENT

12

QA / QC

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 3

of 16

1. SCOPE
This Work Method Statement is prepared for DC Voltage Gradient Survey
(DCVG Survey) on BTC LOT-B crude oil pipeline.
DC Voltage Gradient Survey (DCVG Survey) is carried out on buried
pipelines to locate and assess the severity of coating defects.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 4

of 16

2. CODES AND STANDARDS


BS-736

Cathodic Protection Part 1: Code of


Practice for Land and Marine Applications

IEEE 81

Guide for Measuring Earth Resistivity,


Ground Impedance, and Earth Surface
Potentials of a Grounded System

NACE RP0169

Control of External Corrosion on


Underground or Submerged Metallic
Piping Systems

NACE RP0190

External Protective Coatings for Joints,


Fittings, and Valves on Metallic
Underground or Submerged Pipelines
and Piping Systems

NACE RP0274

High Voltage Electrical Inspection of


Pipeline Coating Prior to Installation

NACE RP0286

The Electrical Isolation of Cathodically


Protected Pipelines

NACE RP0572

Design, Installation, Operation and


Maintenance of Impressed Current Deep
Ground Beds

NACE RP0792

Standard Format for Computerized Close


Internal Survey Data

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 5

of 16

3. DESCRIPTION
The Direct Current Voltage Gradient (DCVG) is a technique for coating
surveys on buried pipelines. It has been used for not only locating but also
sizing coating defects. The technique is fundamentally based on measuring
the voltage gradients in the soil above a buried pipeline.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 6

of 16

4. SITE EQUIPMENTS AND MAN POWER


-

High sensitivity centre zero voltmeter.

Current Interrupter (suitable for current to be interrupted and with a switching


speed compatible with the survey meter).

Reference (Ski) probes compatible with the survey meter.

Temporary dc current source and ground bed equipment (required if pipeline


not protected by impressed current or system cannot be interrupted).

Depending on the number of crew; for one crew a man who is used to the survey
technique to evaluate results in the field can undertake the DCVG survey. An assistant
may be required in difficult terrain and one 4x4 vehicle would be necessary.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 7

of 16

5. METHODOLOGY
The system works by the application of a cyclically switched d.c. current to
the pipeline and measurement of the magnitude and direction of the voltage
gradients in the soil.
Either an existing or a temporary impressed current system is used as a
source of d.c. current to the pipeline. The d.c. source is interrupted
cyclically, usually about the ratio 2:1 (off:on). This provides a rapidly pulsing
d.c. source that can be easily identified with an analogue millivoltmeter.
Special measurement instruments are required that are able to respond to
the rapidly changing voltage. The analogue instrument is centre zeroed so
that the direction, as well as the magnitude, of the pulsing d.c. voltage can
be measured.
The d.c. voltage gradients are measured by placing reference electrodes on
the ground about 1 m to 1,5m apart. The operator usually walks parallel to
the pipeline, placing the reference electrodes on the ground about every 2
m, and observing the analogue instrument indication.
When the d.c. current flows to a coating defect the potential gradient in the
soil will change, becoming greater as the defect is approached, and
decreasing to zero when the epicentre of the coating defect is mid-way
between the two reference electrodes.
There are many variations that can be applied in the field, and the correct
interpretation of the measured data is dependent upon the competence of
the operator.

The defects found during a DCVG survey can be mapped by GPS


coordinates and will fully documented on special developed defect sheets.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 8

of 16

5.1 Survey Procedure


Prior to commencement of any survey section a current interrupter is
installed in the existing cathodic protection stations or temporary current
source which may be established as necessary.
Typically, a minimum potential swing of 500-600 mV is sought and the
current source output is adjusted accordingly. The application of a pulsed
current enables coating defects to be distinguished from stray traction and
telluric currents.
The difference between 'on' and 'off' potentials is recorded at the test point
nearest the survey start point, and all other test points encountered, and the
survey commenced.
The operator traverses the pipeline route using the probes as walking sticks.
One probe is in contact with the ground at all times and for a short duration
between strides both probes must be in ground contact. One probe can be
on the centerline of the pipeline and the other maintained at a lateral
separation of 1-2 m or probes can leap-frog along the centre line. If no
defects are present the needle on the voltmeter registers no movement.
As a defect is approached a noticeable fluctuation is observed on the
voltmeter at a rate similar to the interruption cycle. The amplitude of the
fluctuation increases as the defect is approached and adjustment of
voltmeter sensitivity is made as necessary. The swing on the voltmeter is
directional, providing the probes are maintained in similar orientation parallel
to the pipeline.
Thus, the defect is centered by detailed maneuver around the epicenter and
the size of the defect estimated by considering signal strength at the defect,
difference between 'on' and 'off' potential at adjacent test point and the
distance from those points.
A sensitive milli-voltmeter and two copper-copper sulfate reference
electrodes (placed about one meter apart by the operator) are typically used
for measuring purposes. The nature of the milli-voltmeter signal during a
DCVG survey is illustrated in the diagram below, in relation to the defect
epicenter.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 9

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

of 16

Page 10 of 16
6. AUTHORITY AND PERMITS REQUIREMENTS
The Natural Gas Pipeline and NATO Pipelines rectifiers must be turned off during
the DCVG Survey. If any such additional permits to be obtained, the same will be
obtained in accordance with the requirements.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 11 of 16
7. LAND ACQUISITION REQUIREMENTS
Presently no additional land requirement is foreseen, if any such requirement an
addendum will be prepared and submitted to Employer for approval.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 12 of 16
8. H&S REQUIREMENTS
Refer attached JSEA and Risk assessments .

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 13 of 16
9. ENVIRONMENT ASSESSMENT
No special environmental assessments is required any how
All environmental incidents will be reported.
All debris and waste materials will be removed from the easement
each working day to Employer approved location.
Toilet facilities will be provided on the easement at all times.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 14 of 16
10. COMMUNITY RELATIONS ASSESSEMENTS
Whenever and wherever the COL department service required, they will be
informed in advance in a timely manner to carry out their work.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 15 of 16
11. SECURITY ASSESSEMENT
None.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014

262605545.doc

Page 16 of 16
12. QA / QC
All the works will be carried out in accordance with approved procedure and
specifications.

Project:

BAKU-TBLS-CEYHAN CRUDE OL PPELNE PROJECT

Prj. Identification:

Document Title:

WORK METHOD STATEMENT FOR DCVG SURVEY

Document No.:

Revision:

Date: 05.02.2014