Escolar Documentos
Profissional Documentos
Cultura Documentos
CONTENTS
Clause No.:
6.1.2
6. 1.3
6.2
6.1.2.1
6.1 .2 .2
6.1.2.3
6.1.2 .4
General
..
..
...............
..
.
.
.
.,"
.
..
..
.
.
.
.
.
.
...,
"
.
6
2-11
6.2.2
6.2 .2 .2
6.2 .2 .3
6 .2 .2 .4
.
..
.
,..
.
....
.
..
.
....
.
.....
.6-2-8
Absorbing System..
6.2.2.5
0
Gypsum Dewa
term
g System. ... . . . . . . .
.
...
..
.......
...6
2-10
6.2.2.6
4
Gypsum Storage , Handling and Transportation System
..
6
2-14
6.2.2.7
.
.
. . . . . . . . . . . . ... 6-
2-155
6.2.2.8
.,....
...............
6-2-16
6 .2 .2.9
Void
6.2.2.10
7
Materials..
.
..
.
..
.
..
.
,......
..
..
.
..
.
.
6
2-1
6.2.2.11
Process Outline
...6-2-17
................
..
..
.
....
....
.
..
..
..
.
.
.
..
.
..
.
......
.
...
..
.
..6
2-17
and Pressure of Equipment
-- -
6.2.3
6.2 .4
6.3
1
General ..........
..
.
..
..
.
..
.
.........
.
..
. ..-
.......
..
.
.
6-3-1
6.3.2
1
Records and Certificate ....
........
.
..
.
..
...
.......
.
.6-3-1
6.3.3
2
Workshop Tests....
.
.
..
.
......
..
.
..
.
....
.
.....
..
.
.
.
.
6-3
6.3.3.1
..
.
.
.........
.. ..
.
.....
.
........
...
..
.
...
6-3-2
General
6.3.3.2
Mec
hanica
1 Wo
rks
..............
.
.
..
....
.6-3-33
6.3 .3 .2 .1
3
Tests on Materials ....
.
.
..
.........
6-3-3
6 .3.3 .2.2
4
Ultrasonic Examination
... .
.
..
......6-3-4
.
6 .3 .3 .2 .3
4
Rad
iographicExuinatlOn..
.......
.
..
..
.6-3-4
6 .3.3 .2.4
...
..-......,.....
.........6-3-5
6.3.3 .2 .5
5
Pipework
..
....
........
..
.,
6-3-5
6 .3.3.2 .6
Pumps....,
.
.
.....,
..
....
......,.
.............
..
6-3-6
6 .3.3.2 .7
Fans
..
.
..
,..
.
.
.
.,....
..
.
.
.
..
.6-3-7
6 .3 .3.2.8
Steel
S tructure
..
.
.....
"
.,.......
..
..
.6-3-7
6 .3 .3.2.9
Lift
in
1
g Equipment and Cra
nes
..
....
.. .6-3-7
..
.
......
..
.
.,....-......
.
. ..
6-3-7
6 .3.3.2 .10 Insulation Material
6 .3 .3 .2 .11 Lining
....
...,...........-.
.,.
6-3-7
6.3 .4
6.3.4.2
6.3 .4 .1.2
6.3 .4.1. 3
6.3 .4 .2.1
6.3 .4 .2.2
Site
6.3 .4 .2.3
Wlding
- II -
6.3 .4 .2 .4
6.3 .4.2 .5
6.3 .4 .2.6
6.3 .4 .2.7
6.3 .4 .2.8
6.3 .4.2 .9
6.3.6
Performance Test.
..
.
.....
.. ..
.
.
.
.
..
.
.
.
.
.
...
6-3-24
6.3.5.1
6 .3 .5 .2
.
..
.,...
...............6-3-24
.
6 .3 .5.3
By-product Gypsum .
..
.
........
.,
.
.
......
..
6-3
---2 5
6.3.5 .4
0ther Items
0 fPerforma
nce Guarantee
.
.
........
".
.
..
...........
..
.
.6-3-26
6.3.6.1
6.3.7
.. . . . . . . . . ... 6-3-2
5
..
.
...
.
Final Acceptance .
...
..
..
..
..
..
..
..
..
..
..
..
..
..
...
..
...
.. .
...
.........
..
.
..
.
..,..
..
..
..
..
..
..
..
..
...................
..
......
..
.6-3-27
6.3.7.1
General.
...
..
.
..
.....
.. ..
.. .
.. .
.............
..
..
..
..
..
..
..
..
..
..
..
...
.. ........
.,.. .. .. ........... 6-3-27
6 .3 .7 .2
7
Plant Inspection Prior to Final Acceptance .....
..
..
..
..
..
..
..
..
..
..
.... 6-3-2
- III -
(b) The quantities of equipment as mentioned in this Volume shall mean those for one (1)
unit , un1 ess otherwise specified.
(c) ldentical design d interchangeability shall be taken into consideration for all
equipment to the maximum extend.
(d) The commercial and general technical requirements shall be covered by the
Specification ofVolumes 1 and 2. The general rangement and system diagram shall
be generally as indicated in the relevant Bid Drawings.
(e) The FGD system sha1 1 be of wet type limestone-gypsum with forced oxidation method
having a capacity of 300-330 MW/one (1) absorber module. The conceptual
configuration ofthe FGD system for Unit Nos. 1 and 2 is as shown in the Drawing No.
OM2FD-I001 in Volume 11 , but not be limited to.
(i) One (1) flue gas flow system and one (1) absorbing system shall be supplied to Unit
No. 2 exclusively.
(ii) The existing stand-by equipment currently common to Unit Nos. 1 and 2 shall be
employed for Unit No. 2 as normal operating equipment. Therefore, some
equipment shall be designed and installed without stand-by equipment. Other
equipment, if necessary, shall be provided to ensure the completeness of the
function as FGD system for Unit No.2.
(iii) FGD systems for Unit Nos. 1 and 2 shall be isolated from each other in case of
two (2) units in operation simuItaneously.
(t) The FGD system shall be provided with the following , but not
6-1-1
systm
limited to ,
6-1-2
_'
-\
\. ~ .
z li
} 3
(a) The FGD System shall be designed to reduce sulf dioxide emissions total
suspended particulate emission in accordance with Vietnamese Standard in Clause
sizd
(b) The FGD system shall have a capacity to operate with full gas flow at BMCR
satisfying the rquired S02 concentration at stack inlet. The flue gas conditions at
BMCR * per FGD system shown below shall be specified by the Bidder.
* :BMCR: Boiler Maximum Continuous Rating
JM
mR
mK
m
%
J
X
V
N
F
0
: N ot less than 90 %
whn
(f) The FGD system shall be capable of operating continuously at loads equal to and
above 20 % of rated out put when firing fuel oi l.
(g) The FGD system shall be of proven design. Designs incorporating componnts which
may be
considred
(h) The equipment and components shall b designed and suppoed to permit free
expansion and contraction without causing xcssive strains , distortion or leakag.
6-1-3
(i) Parts subject to wear, erosion, corrosion or other deterioration, or requiring adjustment ,
inspection or repair shall be accessible and capable of reasonably convenient removal ,
replacement and repair. All such parts shall be of suitable matria 1.
Parameter
Desulphurization efficiency
at stack inlet
N ot less than 90 %
S02 concentration
at stack inlet
Conditions
(at 100kP a,
298K, dry)
(ii)Limestone
Crushd limestone specified hereinafter will be supplied for the Absorber modules
as limestone slurry.
Parameter
Unit
Value
wt%
CaC0 3 content
95 - 98
Analysis:
wt%
wt%
wt%
--_.--"_--
k Wh/ton of limestone
kg/m J
mm
0.97
0.37
0.28
10 (estimated)
2400-2600
less than 20
(max.50)
The Bidder shall provide quantitatively the technical information along with all
MgO
Si0 2
Ah03
Bond work index
Solid limestone (density)
Solid limestone size
6-1-4
The Bidder shall provide quantitatively the technical information aloii with all
supporting explanation and data in case the CaC0 3 content is 10.'v?
above one with regard to the following , but not be limited to:
Parameter
Purity (CaS04. 2H2 0)
Particle size (Mean Particle
Moisture content
pH value
5 to 8
6-1-5
Item
Temperature
pH
Suspended Solid
Ca2+
Na+ + K+
Mg+
NH4+
cr
N0 3SO/COD (Mn)
Quantity
Unit
Oc
mg/l
m g/l
m g/ l
m g/l
m g/l
m g/l
m g/l
m g/l
m g/l
m3/d
< 56
5 to 8
41 ,000
< 500
< 2 ,700
< 7,000
< 17, 100
2,000
250
< 90 ,000
< 2,700
16
6-1-6
6-1-7
OMONTHER1ALPOWER
PLANT
6-1-8
6-1-9
6.2
MECHANICAL WORKS
6.2.1 General
(a) All material, designs, procedures, calculations, manufacture, construction, inspection
and testing shall conform to:
(i) The Vietnamese regulations as specified in Clause 2.2.1.1 and,
(ii) The criteria and recommendations of the relevant Standards and Codes of
practice as specified in Clause 2.2.1.1.
(b) The FGD system complete with all auxiliaries, shall be designed , constructed and
tested to conform to approved standards and shall meet the requirements of(a) (b).
(c) The FGD system shall include, but not be limited to , the following:
The conceptual configuration of FGD system for Unit Nos. 1 and 2 is shown in
Drawing No. OM2FD-I002 Flue Gas Desulphurization System, Process Flow
Diagram in Volume 11.
(i) One (1) existing limestone handling train , capable of unloading three hundred
(300) tons of limestone/four (4) hours and supplying the required limestone from
the limestone ship unloader to the limestone silo
The existing limestone conveyor to the limestone silo (Limestone Conveyor
01-BC-04) shall be modified to transfer the limstone to No. 1 Limestone Silo
and No. 2 Limestone Silo.
(ii) One (1) limestone silo, for one (1) FGD system. The silo shall have a net storage
capacity equivalent to limestone demand required for seven (7) days operation of
n FGD system on the design condition
(iii) One (1) 100 % limestone slurry milling train which is one (1) of the existing two
(2) trains and meets the requirements for one (1) FGD absorber system shall be
employed for Unit No. 2. One (1) limestone weigh feeder, Unit 2 reagnt feed
tank, pump and auxiliaries shall be provided.
(iv) One (1) 100 % capacity absorber module including oxidation system shall be
provided. One (1) existing oxidation air blower shall be employed for Unit No. 2.
(v) One (1) 100 % vacuum filter train which is one (1) ofthe two (2) trains shall be
employed for Unit No. 2. The vacuum filter shall dewater the spent slurry
produced by one (1) absorber module.
(vi) Flue from the break point to the connection point including inletloutlet dampers
and by-pass damper
(vii) Flue gas reheating system to prevent the corrosion of stack material and white
smoke
(viii) Void
6-2-1
OMON RMAL
P.'RPLANT
6-2-2
6.2.2
Detail Specification
The block of the limestone is crushed by the existing limestone crusher installed
between the limestone unloader and the limestone silo.
(g) The existing limestone crusher is designed , manufactured and constructed to prevent
vibration , noise and emission of fine lmestone particles under all operating
conditions.
(h) The amount of the
limstone
6-2-3
installd
(k)
le
net capacity of the NO.2 Limestone Silo is equivalent to the limestone demand
for seven (7) days operation of an FGD system on the design conditions but is not
less than 1,000 t.
(1) All necessary provisions shall be made by the Contractor in order to employ the
eXlstmg eqmpment.
th
6-2-4
(b) Two (2) existing ball mill trains shall be used for Unit Nos. 1 and 2 commonly, but
isolated from each other while two (2) units in operation simultaneously. The
limestone shall be led to a weigh feeder from NO.2 limestone silo and to No. 2
limestone ball mill. NO.2 limestone ball mill is fed with the limestone from either of
NO.l limestone silo or NO.2 limestone silo and the reclaim water from either of Unit
Nos.l or 2. The limestone solids shall be ground to suitable particle size in the
milling system and finally fed to Unit Nos. 1 and 2 reagent feed tanks accordingly.
(c) Th e system shall be capable of supplying the limestone slurry to one (1) FGD
absorber system through its own reagent feed tank.
(d) The reagent feed tank shalI be installed downstream of the mi lI ing systems, to store
the limestone slurry before it is fed to the absorber module. The tank shalI be sized
for five (5) hours operation storage on the design conditions. Reagent slurry sha lI be
fed to the absorber module by the regent slurry feed system.
(e) The reagent slurry feed system of 100 % capacity shall be provided for reagent feed
tank.
(f) The sump common to Unit Nos. 1 and 2 has been insta lI ed. The drainage from the
systems sha lI be collected in the sump and retumed to the system adequately by the
existing sump pumps.
(g) All necessary provisions shall be made by the Contractor in order to employ the
eXlstmg equipment.
(h) Specifications ofthe existing equipment
The specifications of the existing ball mill system , for the Bidder s
follows:
. Equipment Name:
Quantity:
Capacity:
t1
6-2-5
refernce
are as
Motor rating:
. Equipment Name:
Quantity:
Capacity:
Dimension:
Accessory:
Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:
Equipment Name:
Quantity:
Capacity:
Dimension:
Accessory:
H
M M
E
m N
@ m W
5 mAq
37kW
6-2-6
6-2-7
:A;
\:1
J*
/ .0)
(a) The flue gas from the electrostatic precipitator (ESP) sha lI be directed thro'flue
to the absorber module for removal of sulfur dioxide. The absorber mod.t:e shall
consist of an absorbing section and a mist eliminator section. The flue gas shall be
induced by the booster fan located downstream ofthe absorber and the GGH.
(b) Sulfur dioxide removal shall be accomplished by the absorbing slurry in the
absorbing section. The sulfur dioxide shall be captured by the absorbing slurry and
finally converted to calcium sulfate hydrate (CaS04 . 2H20).
As the hot flue gas enters the absorber and passes through the absorbing section, the
flue gas shall be quenched to saturation and sulfur dioxide shall be removed.
The flue gas shall pass through the absorbing section, thereby assuring optimum
liquid-gas contact, hence completing the sulfur dioxide removal process.
(c) After completing the sulfur dioxide capture , the flue gas shall flow into the mist
eliminator located in the flue downstream of or in the up most position of the
absorber and the water droplets shall be collected on the mist eliminator.
(d) The absorbing slurry shall be stored in the lower section of the absorber module
which is referred to as the absorbing slurry tank.
(e) Fresh limestone slurry shall be added to the absorber in order to control recycle
slurry pH. The agitators ofthe absorbing slurry tank shall make the solid float in the
absorbing slurry.
(f) The sulphur dioxide removal process shall also involve an enforced oxidation system.
This oxidation system shall force the calcium sulfite (CaS03' 112 H 20) formed
through the S02 removal process to be oxidized to calcium sulfate (CaS04 . 2H20).
One (1) oxidation air blower having 50 % ofthe required capacity shall be supplied
and one (1) ofthe existing three (3) blowers shall be employed for Unit No. 2. The
capacity of each existing blower is 50 % of the required capacity. The oxidation air
system for each Unit Nos. 1 and 2 consists oftwo (2) oxidation air blowers.
(g) The drainage from the system sha lI be collected in the absorber area sump for Unit
No. 2 and returned to Unit 2 absorber. The absorber slurry shall be transferred to the
existing blow down tank and returned to the Unit No. 2 absorber by the exiting blow
down return pump when the absorber is required to be empty, such as overhau l.
(h) All
necssary
6-2-8
eXlstmg eq Ul pment.
(i) Specification ofthe existing common equipment
The specifications ofthe existing common equipment, for the Bidder s reference, are
as follows:
Equipment name:
Quantity:
Capacity:
Head:
Motor rating:
Equipment Name:
Quantity:
Capacity:
Dimension:
Accessory:
Equipment Name:
Blow down
Quantity:
Capacity:
Head:
Motor rating:
Rtum
Pu mp
180 m3fh
29mAq
30kW
6-2-9
p
-
/A
O WN
(i) The gypsum dewatering system shall consist of a hydroclone , a filter feed tank,
filter feed pumps and a vacuum filter train. The vacuum filter train consists of a
vacuum filter with associated auxiliary equipment, a reclaim water tank, a
reclaim water pump and a chloride purge pump mainly.
(ii) One (1) hydroclone, one (1) filter feed tank, filter feed pumps and auxiliaries
shall be supplied for Unit No. 2. Two (2) existing vacuum filter trains shall be
used for Unit Nos. 1 and 2 commonly, but isolated from each other while two (2)
Units in operation simultaneously. A portion of the absorbing slurry in the
absorber module shall be fed to the hydroclone to control the absorbing slurry
tank level and slurry concentration. The underflow of the hydroclone shall be fed
to the filter feed tank. A part of the overflow of the hydroclone shall be drawn to
the existing sludge storage basin in the waste water treatment facility via the
existing FGD waste water transfer system.
(iii) The filter feed pump shall transfer the slurry from the filter feed tank to either of
the existing two (2) vacuum filter trains. The slurry is dewatered by the vacuum
filter. The dewatered byproduct gypsum is discharged to the existing gypsum
conveyor and transferred to the storage area in the gypsum dewatering and
storage house.
(iv) The filtrate from the vacuum filter is withdrawn to the filtrate rceiver by th
vacuum pressure induced by the vacuum pump. The filtrate is withdrawn from
the filtrate receiver to the reclaim water tank by the filtrate pump.
(v) The reclaim water shall be fed to Absorbent MillingIPreparation System by the
reclaim pump and discharged to FGD waste water receiving tank from by
Chloride purge pump. Unit No. 1 is with provided three (3) header pipes to
separate the reclaim water of each vacuum filter train for Unit Nos. 1 and 2,:
Pump suction header pipe for a1l pumps which connects with the reclaim tanks
Pump delivery header pipe for reclaim water pumps
Pump delivery header pipe for Chloride purge pumps
Unit No. 2 piping shall connect with the above header pipes. The relaim water
shall be fed or discharged as one for Unit Nos. I or 2 respectively from the
rclaim water tanks through the header pipes by the valve operation.
6-2-10
(vi) In the event of failure of the vacuum filter train in service due to some trouble or
in case of maintenance , the spent slurry produced by the absorber module is
transferred to the blowdown tank and stored tentatively.
(b) Vacuum filter train
(i) The existing two (2) vacuum filter trains are used for Unit Nos. 1 and 2.
(ii) The accessory of the gypsum cake washing is provided for the vacuum filter.
(iii) The water in the slurry is removed by the vacuum system. The filter cloth
restrains the cake while aliowing passage of the water and air. The filtrate drains
into the filter media and then into the filtrate receiver where the air is separated
from the filtrate. The vacuum pump with a liquid seal ring is provided to create
the necessary vacuum.
(c) The sump common to Unit Nos. 1 and 2 has been installed. The drainage from the
system shall be collected in the sump and retumed to the system adequately by the
eXlstmg sump pumps.
(d) All necessary provisions shall be made by the Contractor in order to employ the
eXlstmg eqUlpment.
(e) Specification of the common equipment
The specifications of the existing equipment, for the Bidder s reference , are as
follows:
Equipment Name:
Quantity:
Filter area:
14.9 m2
Product humidity:
10wt%
. Equipment Name:
Quantity:
Type:
Capacity:
Head:
Motor rating:
. Equipment Name:
6-2-11
Quantity:
Capacity:
Dimension
0.82 m3
1 067 x 2, 134
Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:
Equipment Name:
Quantity:
Capacity:
Dimension
Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:
Equipment Name:
Quantity:
Capacity:
Dimension
Accessorj:
No. 2 Reclaim
Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:
Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:
Equipment
Nam:
25 m3fh
11 mAq
7.5 kW
3 m 3fh
15 mAq
2.2kW
WaterTa
105 m3
5 500 x 5,950
Ag
itator
27 m 3fh
32mAq
11 kW
4.5 m3/h
13.7 m
4kW
Sludge Storage Basin
6-2-12
Quantity:
Capacity:
Dimension:
Accessory:
Equipment Name:
Quantity:
Capacity:
Dimension:
Accessory:
Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:
90 m3
6,000 x 6,000 x 3,000
Agitator
6-2-13
(a) The dewatered gypsum is discharged from the vacuum filter in the dewatering area
and transferred to the storage ara in the gypsum dewatering and storage house.
(b) The gypsum storage house has a capacity of 5,000 tons (equivalent to the capacity of
gypsum transported ship) of gypsum storage.
(c) The stored gypsum of 5,000 tons is transferred from the gypsum storage house to the
gypsum shiploader at the jetty by the gypsum reclaimer and conveyor~ for eight (8)
hours.
(d) The amount ofthe gypsum shall be measured with the gypsum weighing measure.
(e) The conveyors, weighing measure and gypsum shiploader are designed,
manufactured and constructed to prevent ingress of rain and emission of fine
gypsum particles and to permit interchangeability of parts and ease of access during
inspection, maintenance and repair.
(f) In case of supplying the by-product gypsum to domestic consumers, 20 tons capacity
trucks shall be used. Such a truck shall be prepared by the consumers nominated by
EVN.
(g) One (1) 2 ton capacity wheel loader is provided to scoop up the by-product gypsum
on the truck.
6-2-14
9 ,190H
140 m fh
48.8 m
55kW
Mist Eliminator Wash Pump 1A / 1B
2
95 m 3/h
67m
37kW
6-2-15
shall not effect on the existing equipment and structures or minimize the effect on them
and shaIl not disturb the operation of the existing equipment.
(a) FGD electrical and control building
The control system and related equipment shall be installed on 1st floor in the
existing electrical and control building.
The electric system shall be located below the control system floor.
As for the details, refer to Volume 3 of 14.
(b) Void
(c) Li mestone ball mill house
The roofhas been provided over the ball mill to enable the milling system to function
even under inclement wcather conditions.
The crane has been provided for the maintenance of each ball mill as follows:
Capacity:
3 tons
7,600 mm
Span:
Length ofRunway:
15 ,300 mm
Hook path:
8,110 mm
As for the details, refer to Volume 3 of 14.
(d) Oxidation air blower house
The roof has been provided over the oxidation air blower to enable the air supply
system to function in inclement weather conditions.
The crane has been provided for the maintenance of the oxidation air blowers as
follows:
4 tons
Capacity:
Span:
10,400 mm
Lenh ofRunway:
23 ,700 mm
Hook path:
5,257 mm
As for the
dtails
6-2-16
nable
function in inclement weather. The gypsum storage house and the gypsum
transportation facility are located below the vacuum filter.
As for the details, refer to Volume 3 of 14.
6.2.2.9 Void
6.2.2.10 Materials
(a) Materials of construction shall be cOITosion and erosion resistant.
(b) Main piping with slurry shall be of carbon steel with the rubber lining or FRP (Fiber
Reinforced Plastic) or equivalent and the tank shell shall be made of carbon steel
with the flake resin lining or equivalent.
(c) Materials of the flue and its intemal support shall be steel with the flake resin lining
or equivalent from the untreated gas outlet of GGH to the treated gas inlet of GGH.
(d) Materials of the flue , its intemal support and damper located in the range from the
treated gas outlet of GGH to the stack inlet shall be cOITosion-resistant stee l.
6.2.2.11 Process Outline
(a) FGD system shall be designed in accordance with layout and process flow diagram
as shown in Drawing Nos. OM2FD-l 00 1 and OM2 FD-l 002 in Volume 11.
6.2.2.12 The Manzins for the Des $m Caoacitv and Pressure ofEouioment
(a) The margins in design capacity and pressure shall be allowed for, but not be limited
to , the following;
(i) Booster fan
The design capacity of the booster fan sha l1 be not less than 1.1 5 times BMCR
gas treatmen t.
The design static pressure sha lI be not less than 1.25 times the pressure required
at BMCR.
(ii) Pump , GGH and Agitator
The design perforrnance of this equipment shaIl be decided taking into
consideration the performance deterioration due to erosion and cOITosion for each
mamtenance term.
6-2- 17
'^~
6-2-18
(g) void
6-2-19
he
e
lect
e
r
lC
a
c
1
re
q
ullrem
me
nts
tso
FGD
f
Sy
6-2-20
(f) Tests not requiring the witness by EVN shall b in any case, notifid in advance. The
Contractor shaIl then proceed with the tests and shaIl submit reports to EVN.
6.3.2 Records and Certificate
(a) Thirty (30) days after completion of any test, triplicate sets of all principal test records,
test certificates and correction and performance curves shaIl be supplied to EVN.
(b) These test records , certificates and performance curves shall be supplied, whether or
not those tests were witnessed by EVN or his nominated Representative. Th
information given on such test certificates and curves shall be sufficient to identify the
material or equipment to which the crtificate refers and also bear the contract
reference title.
(c)
Whn
6-3-1
compild
by the
wit1}iex
and the
.~
6-3-2
(e) The subject items should remain available for inspection and test up to minimum ten
(1 0) days after the date ofwitnessing the test unless otherwise agreed by EVN. Every
facility in respect of access , drawings , instruments and manpower will be provided by
the Contractor and his Sub-Contractor to enable EVN or his designated representative
to caY out the necessary inspection and testing of the equipment.
(t) No equipment shall be packed, prepared for shipment, or dismantled for the purpose
of packing for shipment, unless it has been satisfactorily inspected , or approved for
shipment, or altematively inspection has been waived.
(g) The extent ofworkshop tests and method ofrecording the results shall be submitted to,
and agreed by EVN in sufficient time to enable the tests to be satisfactorily witnessed
or, ifnecessary, any changes ofthe proposed programme oftests to be agreed.
(h) A Il instruments and apparatus used in the tests shall be subject to the approval ofEVN,
and , if required by EVN, shall be calibrated to an agreed standard.
(i) The cost of carrying out such calibrations shal1 be bome by the Contractor in all cases.
(j) EVN reserves the right to visit the Contractors Works at any reasonable time during
fabrication of equipment in order to survey the progress made.
6-3-3
(d) The test sha lI be conducted on the fo lI owing, but no be limited to:
(i) Fan Shafts
(e) The mill certificats shall be submitted for approval of EVN on work
equipment ofthe fo lI owing, but not be limited to:
(i) Absorber
(i i) Flue and Damper
(iii) Structure and Reinforcing Bar
(iv) Valve
(v) Piping
(vi) Tank and Silo
(vii) Rotating Equipment
6.3.3.2 .2 Ultrasonic Examination
(a) A lI tubes and pipes for pressure piping shall be ultrasonically examined for detection
of injurious defects before fabrication is started.
(b) Tube and steel plate surfaces shall be free from mill scales, etc. , to allow a c1 ear
interpretation of ultrasonic signa l. If necessary, a suitable treatment of surfaces shall
be performed.
(c) Ultrasonic inspection shall be in accordance with Vietnamese Regulation and/or
ASME Section 11 Sa-655 , ASTM E164-94a or equivalent.
(d) Imperfections found by ultrasonic examination shall be judged against the acceptance
- rejection standards outlined in ASME Code Section VIII Div.l , Appendix 12,
paragraph 12.3 or equivalent.
6.3 .3 .2 .3 Radiographic Examination
(a) Radiographic examination shall be the main quality control of welding; where not
possible , other approved method shall be applied.
(b) For all shop welded
(i) Pressure vessels
pas
(c) A lI pressure pas shall be tested in accordance with the requirements of Vietnamese
Regulation and/or ASlE Unfired Prssure Vessel code or equivalent.
6-3-4
6-3-5
:--.""
O MONTHERM'l._POWER PLANT
\
136 .4 or equivalent, the Contractor shall radiograph all butt welds 0/ing over 50
mm in accordance with the requirements outlined in the table belo 7
EEg
Auxiliary steam
Soot blower steam
Root Pass
None
None
Final Pass
(After PWHT* where applicable)
10 %
10 %
U) Magnetic particle inspection shaIl be carried out in accordance with ASTM E709-95 or
equivalent.
(k) When dye penetrative method is applied , it shall be conducted in accordance with
ASTM E165-95 or equivalent and application directed by the penetrate manufacturer.
6.3.3.2.6 Pumps
(a) All pumps shall be tested in accordance wth the approved standards. Prior to any tests,
the Contractor shall submit a test procedure showing the layout of the testing
equipment with the positions of pressure measurement points and f1 0w measuring
devices, for approval of EVN. In addition , the details of calibration of the f1 0w
measuring device , motor power vs. efficiency curve, a specimen of the test record
sheet and details of the performance calculations shall be provided.
(b) The performance test shall be conducted over the fuIl operating range of the pump.
Curves indicating f1 0w rate vs. head , f1 0w rate vs. power consumed, and f1 0w rate vs
pump efficiency shall be provided. In addition, the curve of f1 0w rate vs. NPSH
required shall be providd.
(c) On completion ofthe tests the Contractor shall submit a report showing the test results
obtained together with the curves corrected to the site operating conditions.
6-3-6
6.3.3.2.7 Fans
(a) Booster fan shall be subjected to full performance test including static and dynamic
balancing which shall be witnessed by EVN.
(b) The test shall be in accordance with the latest applicable ASME test codes or
equivalent.
6.3 .3 .2.8 Steel Structure
(a) Radiographic examination shall form the main quality control ofwelding; where not
possible, other approved method shall be applied. The examination shall be applied to
25 % of all shop welded parts for main structure.
(b) Dimension check for main structure shall be carried out.
6.3 .3 .2.9 Lifting Equipment and Cranes
(a) Th e Contractor shall caY out the tests as required by the approved standards, to prove
the capacities of cranes and lifting equipment. Test certificates shall be submitted and
shall include the material Iist of equipment, welding record and non-destructive test
record for electricaI equipment, wire ropes, hooks, chain blocks, shackles, runway
beam, eye bolts and any other related items which are provided.
(b) Upon completion of the tests, the equipment shall be clearI y marked with the safe
working load (SWL) and any other markings that EVN may require.
6.3 .3.2.10 Insulation Material
(a) The Contractor shall provide the thermal conductivity test repo for the last five (5)
years applications ofthe product or shall conduct the test ofthermal conductivity in
accordance with ASTM codes or equivalent.
6.3.3.2.11 Lining
(a) Alllined components ofthe plant shall be tested for proper lining in accordance with
the lining manufacture s instaIl ation procedure and applied to the specified thickness
oflining.
At least the spark test for the whole lined surface and random test ofhardness shall be
conducted.
6-3-7
6-3-8
6-3-9
;:~h
,Y:'://
(c) Where necessary, specialized training for operators for any in~nents above shall be
provided and the cost associated with such training shall be included in the Bid.
(d) It is the Contractors responsibility to provide certified calibration curves for
instruments, comprehensive operating and maintenance instruction manuals,
electrical circuit diagrams , maintenance tools and spare parts catalogue. AIl
documents shall be in clear, simple and correct English.
6.3 .4.1. 2 General Inspection Procedure
(a) Equipment Arrival at Site
Contractor shaIl notify EVN of arrival of equipment for any physical inspection.
(b) ErectionlInstaIlation of Equipment
(i) General Inspection
During erection stage, EVN wiII inspect erectio n/instalIation of equipment
generaIly from the foIIowing aspects.
- Any non-conformance
- Workmanship
- Materials used are of approved type/quality.
(ii) Official Inspection by EVN
Inspection on major equipment which is listed by EVN and the Contractor w ilI be
made by EVNs inspection staff officially in accordance with site quality control
(QC) procedure submitted by the Contractor and approved by EVN and the steps
given below shalI be foIlowed.
Step 1 Request for Inspection/Attendance (Refer Note * 1)
The prescribed form "Request for Inspection/Attendance" shaIl be
submitted by the Contractor to EVN twenty four (24) hours prior to the
inspection and include the following information.
i) Location ofWork to be inspected
ii)Purpose of inspection
iii) Relevant drawings , sketches, calculation, etc
iv)Reference No. of applicable document
Note * 1
Weekends, public holidays and times when EVN office is officially c1 0sed shall be
not considered as notice .
AIl requests shall be registered by EVN with time/date ofreceipt stamped on each
request.
6-3-10
6-3-11
6-3-12
Joint No.
Base Metals
Pipe Size, dia.
WPSNo.
PQRNo.
t (mm)
406 .4 x 67
55TA-SRl
P-55TA-l
6-3-13
VIIPT
RT
MT
UT
Remarks
100 %
100 %
100 %
100 %
6-3-14
~-0~
6-3-15
6-3-16
EVN may require a welder to be re-qualified ifEVN deems the skill ofthe welder has
deteriorated , and the Contractor shall promptly remove the said welder from the job.
At the discretion of EVN , the re-qualification test may be conducted in the same
manner as the original one or in a similar form. If a welder produces bad welds~ for
example, in the spray pipe region , the re-qualification test may not be just welding a
single test piece but may be welding five pipes (of which size is equal to spray pipe
size) and in the similar position. All costs of re-qualification tests shall be bome by the
Contractor.
(d) Control of Welding Activities
The Contractor shall at all times control its welding activities in a manner whereby the
quality requirement of its Field Quality Assurance Programme (FQAP) is never
compromised, but at the same time no delay to the Welding progress is experienced.
The Contractor shall draw up a working procedure to accommodate EVN participation
at Site in accordance with the following:
Activities
(i)Material Receiving checks
(ii) Cleaning of Components
(iii)Alignment of component
EVN Scope
100 % Checking
(ix) PWHT
Spot Checking
100 % Checking
6-3-17
O 10N
In all cases, the Contractor s scope shall be 100 %. In case where EVN participation is
also 100 %, such inspection may be caied out jointly at the same time when the
Contractor carries out his inspection. However, EVN may insist that the Contractor
carries out his inspection first and correct whatever defects found before caIling for
EVN participation.
The Contractor shaIl submit a daily report on welding works indicating the distribution
of welders , the number and identification of joints welded, and the number and
identifications ofjoints to be subjected to NDT and PWHT.
The Contractor shall prepare all check sheets for the inspections, and the check sheet
format shaIl be approved by EVN at site. Such check sheets must be signed by the
relevant pties immediately after the inspection. The Contractor shaIl submit to EVN
these check sheets bound in volumes, appropriately titled when the project is
completed.
The radiographic films , after review by EVN at site, shall be retumed to the Contractor.
The Contractor shall then classify the films , put them in appropriately labeled boxes
and store them in cI ean , dry, pest-free air-conditioned room. The Contractor shall keep
the films in such good conditions for the determined years after the completion ofthe
project. EVN shaIl have access to these films at any time during the storage period.
(e) Control ofWelding Consumables
The Contractor shall follow the manufacturers' recommendations in storage and
handling of all welding consumables.
It is Contractors responsibility to confirm the purity ofwelding gases. The Contractor
shall have accurate instruments for measurement of gas tlow and oxygen
concentration.
6-3-18
The Contractor shall only bring to site welding electrodes and other filler materials
complying with the approved WPS.
Each consignment ofthese welding consumables to site sha Il be accompanied with the
manufacturers mill certificates. The Contractor shall not change the brands of the
welding consumables without prior approval ofEVN.
The Contractor shall provide electric ovens with suitable timers and temperature
indicators for the purpose of preheating the welding electrodes before issuing to the
welders. The quantity of electrodes issued shall only be for four (4) hour use. The
contractors shall provide his welders with electrically heated quivers to cay the
electrodes to working areas. Furthermore, in order to ensure compliance with the
requirement that the quantity of electrodes for only four (4) hour use is issued at one
time, the Contractor is required to provide two (2) colour-coded quivers to each welder,
such that, for example, only red quivers are used in the morning and blue ones in the
aftemoon (after lunch). It is the strict requirement of this Specification that the
Contractor ensures that his welders return unused welding electrodes to store after
every four (4) hour shift and fresh electrodes for use in the next four (4) hours is issued
in diffrent quivers.
The Contractor shall establish and follow diligently an Electrode Record Procedure
whereby the amount and type of electrodes issued to each welder at every issue are
recorded in either a Record Book or Card. Such record shall be made available to EVN
at site for scrutiny whenever requested.
F or fiHer matrials to be usd in TIGwlding process, the Contractor shall ensure that
the filler materials are clean, dry and rust-free. They shalI also be positively identified
either by using tags , colour codings, or both. Alternatively, their specification numbers
shall be stamped on the rods at regular intervals in such a manner that when cut in
shorter len!hs such stamps will still be visible. The f1 ags or colours to identity rods
shall also present in full lenh. The filler materials shall be carried to work-areas in
suitable containers.
6-3-19
The Contractor sha lI employ only mature and experienced NDT ope'r#rs. The
Contractor sha lI ensure that the NDT operators hold current and relevant <;irtificates
from the Certification bodies approved by relevant Vietnames authority.
Notwithstanding such a certificate, the Contractor shall promptly aange for the
demonstration ofthe skill ofhis NDT operators to EVN , should EVN reques t.
Radiographic works shall comply with all the Vietnamese regulations and shall be
carried out after normal working hours only. However, EVN may delay issue of
permission to sta or suspend the work for any duration during the permitted hours
when urgent construction works an d/or plant operational activities is needed to
proceed without interference.
If the Contractor desires to subcontract the pa or the whole ofthe NDT works within
his scope, the Contractor shall first obtain the approval from EVN at site. The
Contractor shall prove to satisfy EVN that the sub -c ontractor s work is good enough.
The Contractor shall aange NDT works promptly after completion of welding.
Where welding requires PIT the NDT sha lI be conducted after the PWHT.
6.3.4 .2 .3 Absorber and Other Equipment
(a) Soap Solution Test
Soap solution tests shall be performed prior to the commissioning ofthe FGD in order
to demonstrate the gas tightness of the absorber, air piping, flue , mist eliminator and
GGH.
The flue shall be temporarily sealed at the outlet of FGD and the soap solution test
sha lI be carried out with a forced draught fan or air compressor.
6.3.4 .2 .4 Unfired Pressure Vessels and Pipeworks
(a) Hydrostatic Tests
Hydrostatic test or pneumatic test shall be carried out on a lI unfired prssure vessels
and pipeworks by the Contractor in accordance with Vietnamese Regulation an d/or
ASME test code or equivalent.
For the purpose of the hydrostatic or pneumatic test , the Contractor shalJ provide
temporary seal , where necessary.
The hydrostatic tests of unfired
prssure
6-3-20
6-3-21
(b) Subsequent to the satisfactory completion ofthe above tests , the tests shall be repeated
in the presence of Authority in Vietnam.
t/
(c) The Contractor shall be responsible for preparing test blocks for the
6 .3.4 .2.8 Functional Tests
(a) All installed equipment shall be tested for correct operation and functioning.
6.3 .4 .2.9 Safety Valve Setting
(a) It shall be confirmed that the settings of all safety valves are properly made as required
by ASME Code or equivalent.
(b) All safety valves shall be gagged except the one to be set.
(c) For the auxiliary steamlsootblower safety valves , the setting will be made
manipulating the pressure controller for the auxiliary steam header pressure.
(d) Acceptance
(i) The principle of setting pressure of the safety valves shall be based on ASME
Unfired Pressure VesseI Code or equivalent.
(ii) The cIosing and popping pressures shall be judged based on ASME code, PG-72
and PG-72.2 or equivalent.
(iii)Lift value shall be not less than the design value.
6.3 .4 .2.10 Plant Load Tests
(a) After the plant is synchronized, the following tests shall be carried out to verify the
specified conditions.
(i) Automatic change over of all stand-by equipment.
(ii) Verification of stable operation at any load under the specified conditions.
(i ii) Instantaneous load variation test
(iv) Tripping of the plant at loads 25 %, 50 %, 75 % and 100 % of Rated Output and
BMCR.
(v) Capability ofHouse Load Operation
After raising th power plant load up to Rated Output, the unit shall be
disconnected from the network and it will remain in operation at "House Load"
feeding only the unit auxiliary service.
(vi) Rapid load reduction whn the load is above 50 % of Rated Output, manually
6-3-22
6-3-23
anor
={(Si-So)/Si}
where
100
= Desulphurization efficincy(%)
Si = S02 values at FGD inlet (kglh) on a dry gas basis
So = S02 values at stack inlet (kglh) on a dry gas basis
6-3-24
Parameter
Pu rity (CaS04' 2H2 0)
Moisture content
pH value
5 to 8
6-3-25
VIETNA 1
ELECTRICITY / TEPSCO
6-3-26
e
3
(i ii) Agitators
6-3-27
Inspect bearings .
Check the wear condition of impeller.
Check and inspect all seals gaskets for
wear or corros lO n.
Check bearings.
(vii) Conveyor
Checkcon'veyo
r for wea
r.
.
Check drive for wear.
Inspect bearings.
6-3-28
r
JjJ
(
(iv) GGH