Você está na página 1de 60

o MON THERMAL POWER PLANT

VIETNAM ELECTRlCITY / TEPSCO

VOLUME 6 FLUE GAS DESULPHURIZATION SYSTEM

CONTENTS

Clause No.:

6. 1 GENERAL .......................................................................................................... 6-1-1


6.1.1

Introduction ......................................................................................... 6-1-1

6.1.2

Design Requirements ........................................................................... 6-1-3

6. 1.3
6.2

6.1.2.1

Basis of Design .................................................. 6-1-3

6.1 .2 .2

Process Conditions ... 6-1-4

6.1.2.3

By-product Conditions ................................................ .6-1-5

6.1.2 .4

Performance Guarantee ......................................................... 6-1-5

Drawings to be Submitted ....................................................... ~~~~ .. ~" .6-1-7

MECHANICAL WORKS ................................................................................. 6-2-1


6.2.1

General
..

..

...............

..

.

.
.

.,"

.
..
..

.
.

.
.
.

.
...,

"

.
6
2-11

6.2.2

Detail Specification .............................................................................. 6-2-3


6.2 .2 .1

Limestone Storage System .................................... .6-2-3

6.2 .2 .2

Absorbent Millin g/Preparation System ................................. 6-2-5

6.2 .2 .3

Flue Gas Flow System .......................................................... 6-2-7

6 .2 .2 .4

.
..

.
,..
.

....

.
..

.
....

.
.....

.6-2-8
Absorbing System..

6.2.2.5

0
Gypsum Dewa
term
g System. ... . . . . . . .

.
...

..
.......

...6

2-10

6.2.2.6

4
Gypsum Storage , Handling and Transportation System
..
6
2-14

6.2.2.7

FGD Make-up Water Supply System..

.
.

. . . . . . . . . . . . ... 6-
2-155

6.2.2.8

Building and Structure...

.,....

...............

6-2-16

6 .2 .2.9

Void

6.2.2.10

7
Materials..

.
..

.
..

.
..

.
,......

..

..

.
..

.
.

6
2-1

6.2.2.11

Process Outline

...6-2-17

................

..
..

.
....

....
.

..

..

..

.

.
.
..
.

6.2.2.12 The Margins for the Design Capacity


7
...
.
.....

..

.
......
.

...

..
.

..6
2-17
and Pressure of Equipment

-- -

VIETNAM ELECTRICITY / TEPSCO

6.2.3
6.2 .4
6.3

TEST AND INSPECTION ................................................................................ 6-3-1


6.3.1

1
General ..........

..

.
..

..

.
..

.

.........


.
..

. ..-

.......

..

.
.

6-3-1

6.3.2

1
Records and Certificate ....

........
.

..

.

..

...

.......

.
.6-3-1

6.3.3

2
Workshop Tests....
.
.

..

.
......

..
.
..

.
....

.
.....

..
.
.

.
.

6-3

6.3.3.1

..
.
.

.........

.. ..

.
.....

.
........

...

..

.
...

6-3-2
General

6.3.3.2

Mec
hanica
1 Wo
rks
..............

.
.

..

....

.6-3-33

6.3 .3 .2 .1

3
Tests on Materials ....
.

.
..
.........

6-3-3

6 .3.3 .2.2

4
Ultrasonic Examination
... .

.
..

......6-3-4
.

6 .3 .3 .2 .3

4
Rad
iographicExuinatlOn..

.......

.

..

..
.6-3-4

6 .3.3 .2.4

Hydrostatic Test .........

...
..-......,.....
.........6-3-5

6.3.3 .2 .5

5
Pipework
..

....

........
..

.,

6-3-5

6 .3.3.2 .6

Pumps....,

.
.
.....,

..

....

......,.
.............

..
6-3-6

6 .3.3.2 .7

Fans
..

.
..
,..
.

.
.
.,....

..
.

.

.

..
.6-3-7

6 .3 .3.2.8

Steel
S tructure
..

.
.....

"
.,.......

..

..
.6-3-7

6 .3 .3.2.9

Lift

in

1
g Equipment and Cra
nes
..

....

.. .6-3-7

..

.
......

..

.
.,....-......

.
. ..
6-3-7
6 .3.3.2 .10 Insulation Material
6 .3 .3 .2 .11 Lining
....

...,...........-.

.,.

6-3-7
6.3 .4

Test and Inspection at Site .................................................................. 6-3-9


6.3.4.1

6.3.4.2

General ................................................................................. 6-3-9


6.3 .4 .1.1

Inspection and Test Equipment .......................... 6-3-9

6.3 .4 .1.2

General Inspection Procedure .......................... 6-3-10

6.3 .4.1. 3

Painting Inspection Procedure ......................... 6-3-11

Mechanical Works ............................................................... 6-3-12


Documnts .................... 6-3-12

6.3 .4 .2.1

Welding and Welding

6.3 .4 .2.2

Site

6.3 .4 .2.3

Absorber and Other Equipment ....................... 6-3-20

Wlding

- II -

Control ........................................ 6-3-16

o MON THERMAL POWER PLANT

VIETNA1l1 ELECTRICITY / TEPSCO

6.3 .4 .2 .4

Unfired Pressure Vessels and Pipeworks ......... 6-3-20

6.3 .4.2 .5

Tank and Silo ................................................. 6-3-21

6.3 .4 .2.6

Rotating Equipment ......................................... 6-3-21

6.3 .4 .2.7

Lifting Equi pment ............................................ 6-3-21

6.3 .4 .2.8

Functional Tests ............................................... 6-3-22

6.3 .4.2 .9

Safety Valve Setting ......................................... 6-3-22

6.3 .4 .2.10 Plant Load Tests ............................................... 6-3-22


6.3.5

6.3.6

Performance Test.

..

.
.....

.. ..

.
.

.
.
..

.

.

.
.

.
...

6-3-24
6.3.5.1

General ............................................................................... 6-3-24

6 .3 .5 .2

Desulphurized Flue Gas...

.
..

.,...

...............6-3-24
.

6 .3 .5.3

By-product Gypsum .
..

.
........

.,

.

.
......

..

6-3
---2 5

6.3.5 .4

0ther Items
0 fPerforma

nce Guarantee

Auxiliary Power Consumption


..

.

.
........

".
.

..
...........

..
.
.6-3-26
6.3.6.1

6.3.7

.. . . . . . . . . ... 6-3-2
5

..

.
...
.

Auxiliary Power Consumption ........................................... 6 3-26

Final Acceptance .

...

..
..
..
..
..
..
..
..
..
..
..
..
..
...
..
...
.. .

...
.........
..
.
..
.
..,..

..
..
..
..

..
..
..
..
...................
..
......
..

.6-3-27
6.3.7.1

General.

...
..
.
..
.....
.. ..
.. .
.. .
.............

..
..
..
..
..
..
..
..
..
..
..
...
.. ........
.,.. .. .. ........... 6-3-27

6 .3 .7 .2

7
Plant Inspection Prior to Final Acceptance .....

..
..

..
..
..
..
..
..
..

..
.... 6-3-2

- III -

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

VOLUME 6 FLUE GAS DESULPHURIZATION SYSTEM


6.1 GENERAL
6. 1. 1 Introduction
(a
)

This Volume cm%


supply, construction, installation, testing , commissioning and inspection of Flue Gas
Desulphurization System (hereafter FGD System).

(b) The quantities of equipment as mentioned in this Volume shall mean those for one (1)
unit , un1 ess otherwise specified.
(c) ldentical design d interchangeability shall be taken into consideration for all
equipment to the maximum extend.
(d) The commercial and general technical requirements shall be covered by the
Specification ofVolumes 1 and 2. The general rangement and system diagram shall
be generally as indicated in the relevant Bid Drawings.
(e) The FGD system sha1 1 be of wet type limestone-gypsum with forced oxidation method
having a capacity of 300-330 MW/one (1) absorber module. The conceptual
configuration ofthe FGD system for Unit Nos. 1 and 2 is as shown in the Drawing No.
OM2FD-I001 in Volume 11 , but not be limited to.
(i) One (1) flue gas flow system and one (1) absorbing system shall be supplied to Unit
No. 2 exclusively.
(ii) The existing stand-by equipment currently common to Unit Nos. 1 and 2 shall be
employed for Unit No. 2 as normal operating equipment. Therefore, some
equipment shall be designed and installed without stand-by equipment. Other
equipment, if necessary, shall be provided to ensure the completeness of the
function as FGD system for Unit No.2.
(iii) FGD systems for Unit Nos. 1 and 2 shall be isolated from each other in case of
two (2) units in operation simuItaneously.
(t) The FGD system shall be provided with the following , but not

components and complete accessories.


(i) Wet type limestone-gypsum flu gas desulphurization
necessary auxiliary equipment
(ii) Limestone storage system
(iii) Absorbent milling and preparation system

6-1-1

systm

limited to ,

complete with all

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

(iv) Flue gas f1 0w system


(v) Absorbing system
(vi) Gypsum dewatering system
(vii) Void
(viii) Void
(ix) FGD make up water supply system
(x) Piping , valves and thermal insulation for all systems/equipment
(xi) All instrumentation and controls necessary for the safe , efficient and reliable
operation ofthe equipment included in this Specification - refer Volume 7.
(xii) Structural steel required to support the FGD and other equipment within the
scope of this contract
(xiii) Electric motors for plant - refer Volume 2
(xiv) Power, control and instrument cable and cabling - refer Volume 2
(xv) Cable trays , conduits and marshalling cubicles - refer Volume 2
(xvi) Grounding system - refer Volume 2
(xvii) Lighting system for all plant within the contract - refer Volume 2
(xviii) Permanent enclosures to give protection for plants and personnel against the
weather in the areas, where considered necessary
(xix) All tapping points and associated valves
(xx) Control valves , dampers and alllinkages, actuators and associated mountings
(xxi) All local panels of the instrumentation and control shall be cooled with
air-conditioner for the safe operation of system
(xxii) Spare pas and special tools
Note:
The Contractor shall provide any and all equipment, materials and accessories as required
for a complete set ofthe FGD system and include for installation and trial operation ofthe
equipment in addition to the items specified in the above.
Furthermore , the existing equipment currently common to Unit Nos. 1 and 2 are intenddto
serve for Unit Nos. 1 and 2 individually anor in common, and all necessary provisions
and equipment required for ensuring the completness of function as FGD system for Ut
No. 2 shall be providd by the Contractor.
Although not clearly specified in the above , any embedded materials for foundation , base
plates , grouting materials, suppos electric motors , accessory piping , valves , instruments
and blower silencers for the FGD system as weII as the piping rack foundation related to th
FGD system shall be included in the scope ofwork.

6-1-2

o MON TflERMAL POWER PLANT

VIETNAM ELECTRJCITY / TEPSCO

6. 1.2 Design Requirements

_'

-\

\. ~ .
z li
} 3

6. l. 2.1 Basis of Design

(a) The FGD System shall be designed to reduce sulf dioxide emissions total
suspended particulate emission in accordance with Vietnamese Standard in Clause

2. l. 3.5. Equipment shall be

sizd

based on the fuel oil firing.

(b) The FGD system shall have a capacity to operate with full gas flow at BMCR
satisfying the rquired S02 concentration at stack inlet. The flue gas conditions at
BMCR * per FGD system shown below shall be specified by the Bidder.
* :BMCR: Boiler Maximum Continuous Rating

FGD inlet Sulfur Dioxide (S02)

JM

mR
mK
m
%

J
X

V
N

Flue Gas Temperature

F
0

Flue Gas Flow Rate

(c) The guaranteed performance at 100 % Rated Output is shown below.


S02 removal efficiency at stack inlet
S02 concentration at stack inlet

: N ot less than 90 %

: Not more than 500 m g!m 3


(at 100kP a , 298K , dry)
(d) The FGD system shal1 be capable of operating under the conditions stated in Clause
2.1 .4.
(e) The FGD system shall be operated

whn

the fuel oil is fired in the boiler.

(f) The FGD system shall be capable of operating continuously at loads equal to and
above 20 % of rated out put when firing fuel oi l.
(g) The FGD system shall be of proven design. Designs incorporating componnts which
may be

considred

of prototype in nature will not be accepted.

(h) The equipment and components shall b designed and suppoed to permit free
expansion and contraction without causing xcssive strains , distortion or leakag.

6-1-3

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

(i) Parts subject to wear, erosion, corrosion or other deterioration, or requiring adjustment ,
inspection or repair shall be accessible and capable of reasonably convenient removal ,
replacement and repair. All such parts shall be of suitable matria 1.

G) The equipment shall be designed to permit interchangeability of parts and ease of


access during inspection , maintenance and repair.
6.1 .2 .2 Process Conditions
(a) The FGD plant shall be designed based on the data tabled hereinafter.
(i) Desulphurized flue gas condition
Desulphurized flue gas shall meet the followings:
Limit

Parameter
Desulphurization efficiency
at stack inlet

N ot less than 90 %

S02 concentration
at stack inlet

Not more than 500 mg/m3

Water droplet content


at mist eliminator outlet

Not more than 150 mg/m 3 N ,


dry

Flue gas temperature


at stack inlet

Not less than 91 oC

Flue gas temperature


at stack outlet

Not less than 90 oC

Conditions

(at 100kP a,
298K, dry)

(ii)Limestone
Crushd limestone specified hereinafter will be supplied for the Absorber modules
as limestone slurry.
Parameter
Unit
Value
wt%
CaC0 3 content
95 - 98
Analysis:
wt%
wt%
wt%
--_.--"_--
k Wh/ton of limestone
kg/m J
mm

0.97
0.37
0.28
10 (estimated)
2400-2600
less than 20
(max.50)
The Bidder shall provide quantitatively the technical information along with all

MgO
Si0 2
Ah03
Bond work index
Solid limestone (density)
Solid limestone size

6-1-4

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

The Bidder shall provide quantitatively the technical information aloii with all
supporting explanation and data in case the CaC0 3 content is 10.'v?
above one with regard to the following , but not be limited to:

Evaluation ofthe impact on the performances , such as limestone ption


gypsum specification, power consumption, etc.

Evaluation of the impact on the specification of the equipment fof1he Original


Bid Proposal A, such as absorber, recycle pump , limestone ball mill , vacuum
filter, etc.
Evaluation of the impact on the specification of the equipment for the existing
eqmpment
(iii) Make-up Water
The clarified water for FGD system shall be supplied by the Water Treatment
Plant. The chlorine (CI) concentration of make-up water is 50 m g/l for design of
FGD system.
The specification ofthe clarified water is shown in Volume 2 of 14.
(iv) Chlorine Concentration
FGD system shall be designed so that the chlorine concentration in FGD system
may not exceed 2 ,000 m g/l under any circumstances. The material exposed to the
slurry shall be selected so that it may withstand 10,000 m g/l of the chlorine
concentration in the slurry.
6.1.2.3 By-product Conditions
(a) Gypsum
Value , Description

Parameter
Purity (CaS04. 2H2 0)
Particle size (Mean Particle

Not less than 95 % (dry basis)


Siz)

Not less than 50 micron meter

Moisture content

Not more than 10 %

pH value

5 to 8

(b) Waste water


Under normal operation, the evaporated water in hot f1 ue gas and moisture in gypsum
will be considered to be almost balanced in water consumption in FGD and the amount
of waste water to be bled off will be expected to be very smal l. The waste watr from
FGD system shall , therefore , be treated by the waste water treatmnt facility.
The accptable waste water specification is shown below:

6-1-5

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

Item

Temperature
pH
Suspended Solid
Ca2+
Na+ + K+
Mg+

NH4+

cr

N0 3SO/COD (Mn)
Quantity

Unit

Oc

mg/l
m g/l
m g/ l
m g/l
m g/l
m g/l
m g/l
m g/l
m g/l
m3/d

< 56
5 to 8
41 ,000
< 500
< 2 ,700
< 7,000
< 17, 100
2,000
250
< 90 ,000
< 2,700
16

6. 1.2.4 Performance Guarantee


(a) The following items shall be guaranteed when the flue gas as stipulated in Clause
6.1.2.1 Basis of Design is led to the FGD System.
Limestone/removed sulfur dioxide ratio
Limestone consumption
Desulphurization efficiency (at stack inlet)
Maximum S02 concentration-(at stack inlet)
Water droplet content (at mist eliminator outlet)
Flue gas temperature (at stack inlet and outlet: It shall be proved by the
theoretical calculation with the temperature at stack inlet that the
temperature at stack outlet is not less than 90 oC.)
Byproduct gypsum conditions: purity, particle size , moisture contntandpH
value
Make-up water consumption
(b) The correction curve of the guaranteed performance for each related parameter shall
be submitted for approval. In case that the actual operating conditions deviate from the
design conditions , the correction methods of the guaranteed performancs shall be
confirmed and approved by EVN in advance of operation.

6-1-6

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6. 1.3 Drawings to be Submitted


The following shall be submitted as a minimum , but not be limited to:
(1) Basic Engineering
Drawing List with Issue Date
Basic Design Requirement
. FGD System Description
Process Flow Diagram and Utility Flow Diagram
Material Balance Sheet or Stream Data
Equipment List
Capacity Calculation Sheet or Particular Study for Equipment
. General Arrangement
Correction Curve for Guarantee Value
Anticipated Performance Curve along Full Range ofLoad
Piping and Instrument Diagram (Process and Utilities)
Set Point List
The Contractor shall submit Correction Curves for Guaranteed Performance and
Anticipated Performance Curves on each different parneter* basis covering the
range between BMCR and 20% RO for EVNs approval before the kick-offmeeting.
The Contractors negligence to the above may result in rejection of approval of all
related drawings.
*: The parameters shall be as follows , but not be limited to .
Flue gas conditions:
FGD inlet S02 concentration including maximum S02 concentration to be
anticipated in operation
FGD inlet flue gas flow rate between BMCR and 20% RO
FGD inlet particulate matter concentration and composition
Limestone:
Purity of limestone
Limestone composition
. Operating conditions:
Liquid/gas ratio or no. of operating recycle pumps
pH value of absorber recycle slurry
(2) Absorber
. Engineering Drawing
. Assembly Drawing ofIntemals , Spray nozzle , Spray pipe network , Mist Eliminator
(ME) , ME wash nozzle , ME wash pipe net work , Air sparger, Air sparger network
including Dimension and Material of Construction

6-1-7

VIETNAM ELECTRICITY / TEPSCO

OMONTHER1ALPOWER

PLANT

Detail of Casing, Support and Structure


Calculation Sheet of Absorber
F oundation and Loading Data
Specification of Resin Lining
Lining Work Procedure
(3) Mechanical Equipment (Absorber Recycle Pump , Booster Fan , GGH , Oxidation Air
Blower and Others)
Data Sheet
Performance Curve
General Arrangement Drawing
Cross Section Drawing anor Assembly Drawing of M or Component (with
material of construction)
Lube Oil & Utility Flow Diagram, if any
Lube Oil & Utility Piping & Instrument Diagram, if any
Foundation and Loading Data
Utility List
Sound Insulation Calculation Sheet, if required
(4) T:lk Sump
Engineering Drawing
Foundation and Loading Data
Specification of Lining, if any
Lining Work Procedure , if any
(5) Piping
General piping rangement drawing , lists and calculations specifed in Clause
2 .2 .2.1.8 for the piping system in turbine island.
(6) Flue
Outline Drawing of Flue and Support including Dimension and Material
Calculation Sheet of Flue and Support
Foundation and Loading Data of Support
(7) Construction
. Installation Procedure for Absorber, GGH , BUF and Oxidation Air Blower
Oil Flushing Procedure
Commissioning Procedure
. Mechanical Run Procedure

6-1-8

o MON THERJI1AL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

(8) Quality Assurance


FGD Quality Management Manual
Inspection and Test Plan
Shop Test Procedure
Shop Test Report
Site Test Procedure
Site Test Report
Witness Test Procedure
Witness Test Report

(5) Operation & Maintenance


Operation Manual
Maintenance Manual
Overhaul Plan for Major Equipment
Spare Part List (Essenti a1 and Recommendable)
Lube Oil List
(6) Performance/Acceptance Test
Performance Test Procedure inc1 uding Chemical An alysis Manua1
Performance Test Report

6-1-9

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY ITEPSCO

6.2

MECHANICAL WORKS

6.2.1 General
(a) All material, designs, procedures, calculations, manufacture, construction, inspection
and testing shall conform to:
(i) The Vietnamese regulations as specified in Clause 2.2.1.1 and,
(ii) The criteria and recommendations of the relevant Standards and Codes of
practice as specified in Clause 2.2.1.1.
(b) The FGD system complete with all auxiliaries, shall be designed , constructed and
tested to conform to approved standards and shall meet the requirements of(a) (b).
(c) The FGD system shall include, but not be limited to , the following:
The conceptual configuration of FGD system for Unit Nos. 1 and 2 is shown in
Drawing No. OM2FD-I002 Flue Gas Desulphurization System, Process Flow
Diagram in Volume 11.
(i) One (1) existing limestone handling train , capable of unloading three hundred
(300) tons of limestone/four (4) hours and supplying the required limestone from
the limestone ship unloader to the limestone silo
The existing limestone conveyor to the limestone silo (Limestone Conveyor
01-BC-04) shall be modified to transfer the limstone to No. 1 Limestone Silo
and No. 2 Limestone Silo.
(ii) One (1) limestone silo, for one (1) FGD system. The silo shall have a net storage
capacity equivalent to limestone demand required for seven (7) days operation of
n FGD system on the design condition
(iii) One (1) 100 % limestone slurry milling train which is one (1) of the existing two
(2) trains and meets the requirements for one (1) FGD absorber system shall be
employed for Unit No. 2. One (1) limestone weigh feeder, Unit 2 reagnt feed
tank, pump and auxiliaries shall be provided.
(iv) One (1) 100 % capacity absorber module including oxidation system shall be
provided. One (1) existing oxidation air blower shall be employed for Unit No. 2.
(v) One (1) 100 % vacuum filter train which is one (1) ofthe two (2) trains shall be
employed for Unit No. 2. The vacuum filter shall dewater the spent slurry
produced by one (1) absorber module.
(vi) Flue from the break point to the connection point including inletloutlet dampers
and by-pass damper
(vii) Flue gas reheating system to prevent the corrosion of stack material and white
smoke
(viii) Void

6-2-1

VIETNAM ELECTRICITY / TEPSCO

OMON RMAL

P.'RPLANT

(ix) FGD make-up water system


(x) Pumps and motors (including a stand-by for each kind ofpump)
;
(xi) Tanks and agitators , and sumps
(xii) Utility piping, instrument piping and piping support
(xiii) A Il necessa alarms , control and instrumentation system (refer to Volume 7)
(xiv) A Il high and low voltage electrical equipment, cable and wiring (refer to
Volum 8)
(xv) Laboratory equipment and instruments
(xvi) Void
(xvii) Void
(xviii) Void
(xix) Civil work and site construction
(xx) Factory test and inspection
(xxi) Commissioning and adjustment at site
(xxii) Performance test
(d) The terminal points not shown in Volume 11 of 14 shall be provided by the
Contractor.

6-2-2

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.2.2

Detail Specification

6.2.2.1 Limestone Storage Svstem


(a) The crushed limestone of which grain size is 20 mm in average (max. 50mm) is
conveyed to the limestone silo by the existing limestone bucket elevators and
conveyors. The existing belt conveyor (l imestone belt conveyor 01-BC-04) transfers
the limestone to No. 1 limestone silo. This limestone conveyor -BC-04 shall be
modified or replaced with new one of the same capacity completely, in order to
supply limestone to both NO.1 Limestone Silo (existing) and NO.2 Limestone Silo
(to be supplied by Unit 2 Contract). The Conveyor shall be reversible. The
construction time shall be completed within a week, not to affect th limestone
supply to Unit 1. In case of modification of the existing conveyo the warranty
period for it shall be two (2) years even though it contains the equipment and parts
supplied in Unit 1 Contract.
(b) The existing system upstream of the bucket elevator is so designed that the block of
limestone is unloaded by the limestone unloader from barges (300to n/ship) at the
jetty and transported to a limestone silo by the conveyors and the bucket elevators
through a limestone crusher for four (4) hours .
(c) Void
(d) The conveyors have been designed , manufactured and constructed to prevent ingress
of rain and emission of fine limestone particles.
(e) The existing equipment to remove effectively detonators and scrap iron is installed
on the conveyor system between the limestone receiving hopper and limestone
crusher.
(

The block of the limestone is crushed by the existing limestone crusher installed
between the limestone unloader and the limestone silo.

(g) The existing limestone crusher is designed , manufactured and constructed to prevent
vibration , noise and emission of fine lmestone particles under all operating
conditions.
(h) The amount of the

limstone

is measured with the limestone weighing measure.

6-2-3

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

(j) One (l) silo (N o .2 Limestone Silo) to be

installd

nearby the existing limestone silo


and one (1) limestone weigh feeder shall be supplied. The limestone shall be fed by
the modified limestone conveyor (01-BC-04) and shall be discharged to one (1)
limestone ball mill (N o. 2 limestone ball mill) through the limestone weigh feeder.
The limestone silo shall be provided with one (l) spare nozzle for the future weigh
feeder.

(k)

le

net capacity of the NO.2 Limestone Silo is equivalent to the limestone demand
for seven (7) days operation of an FGD system on the design conditions but is not
less than 1,000 t.

(1) All necessary provisions shall be made by the Contractor in order to employ the
eXlstmg eqmpment.

(m) Specification ofthe existing equipment


The specifications of the existing conveyor system and the limestone silo , for the
Bidder s reference , are as follows:
. Equipment Name: Limestone bucket elevator for limestone silo
Quantity:
1
Capacity:
90 h
. Equipment Name: Limestone belt conveyor 01-BC-04
Quantity:
1
Capacity:
90 t/h
. Equipment Name: NO.l Limestone Silo
Quantity:
1
Capacity:
1,000 t
As for

th

terminal points ofthe above , refer to Volume 11 of 14.

6-2-4

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.2.2.2 Absorbent MillinglP reoaration Svstem


(a) The absorbent millinglpreparation system consists of two (2) limestone weigh
feders a ball mill train, a reagent feed tank and associated pumps and a agitator.
The ball mill train consists of a ball mill , a mill product tank, a mill product pump, a
classifier, a distributor and auxiliaries.

(b) Two (2) existing ball mill trains shall be used for Unit Nos. 1 and 2 commonly, but
isolated from each other while two (2) units in operation simultaneously. The
limestone shall be led to a weigh feeder from NO.2 limestone silo and to No. 2
limestone ball mill. NO.2 limestone ball mill is fed with the limestone from either of
NO.l limestone silo or NO.2 limestone silo and the reclaim water from either of Unit
Nos.l or 2. The limestone solids shall be ground to suitable particle size in the
milling system and finally fed to Unit Nos. 1 and 2 reagent feed tanks accordingly.
(c) Th e system shall be capable of supplying the limestone slurry to one (1) FGD
absorber system through its own reagent feed tank.
(d) The reagent feed tank shalI be installed downstream of the mi lI ing systems, to store
the limestone slurry before it is fed to the absorber module. The tank shalI be sized
for five (5) hours operation storage on the design conditions. Reagent slurry sha lI be
fed to the absorber module by the regent slurry feed system.
(e) The reagent slurry feed system of 100 % capacity shall be provided for reagent feed
tank.

(f) The sump common to Unit Nos. 1 and 2 has been insta lI ed. The drainage from the
systems sha lI be collected in the sump and retumed to the system adequately by the
existing sump pumps.
(g) All necessary provisions shall be made by the Contractor in order to employ the
eXlstmg equipment.
(h) Specifications ofthe existing equipment
The specifications of the existing ball mill system , for the Bidder s
follows:
. Equipment Name:
Quantity:
Capacity:

No. 1 / No. 2 Ball Mill


2
7

t1

6-2-5

refernce

are as

VIETNAM ELECTRICITY / TEPSCO

Motor rating:
. Equipment Name:
Quantity:
Capacity:
Dimension:
Accessory:

No. 1 / No. 2 Mill Product Tank


2
12 m 3
2,438 ID x 2,753 H
Agitator

Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:

No. 1/ No. 2 Mill Product Pump


2
46.8 m3fh

Equipment Name:
Quantity:
Capacity:
Dimension:
Accessory:

H
M M

E
m N
@ m W

5 mAq
37kW

Reagent Preparation Area Sump


25 m3
3,050 x 3,050 x 3,650 H
Agitator
Reagent Preparation Area Sump Pu mp
2
60 m3fh
18 .3 mAq
15 kW

As for the terminal points of the above , refer to Volume 11 of 14.

6-2-6

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.2.2.3 Flue Gas Flow Svstem


(a) The dirty flue gas leaving the ESP (electrostatic precipitator) will flow into the
absorber module through the GGH (gas-gas-heater). The dirty flue gas shall be
distributed in the absorber module as even as possible.
(b) The c1 ean gas leaving the absorber module shall flow through the GGH into the
stack which is shown in the Drawing Nos. OM2CV-12 to 1208 in Volume 11.
(c) The bypass flue shall be provided between the FGD inlet flue and the FGD outlet
flue. In the event of emergency, this 100 % bypass flue shall enable the entire flue
gas to flow to the stack directly without being introduced to the FGD system.
(d) There are three shut-off pe dampers associated with the FGD system. Th ese
dampers shall be located at FGD inlet, FGD outlet and the bypass flue. During
normal operation, the bypass damper is closed in order to direct the entire flue gas to
the absorber module for treatment. In case where the FGD has to be bypassed for
operationaI reasons , the absorber shall be isolated cI osing dampers at the inlet and
outlet ofFGD.
(e) GGH system shall be provided for prevention of stack tube material from corrosion
and ofwhite smoke dispersion.
(f) The sound pressure level measured at a position 1 meter distant from the machine or
enclosure outline shall not exceed the values specified in Clause 2.2.1.6, at 100 %
Rated Output.

6-2-7

o MON THERMAL PQ!R PLANT

VIETNAM ELECTRICITY I TEPSCO

:A;
\:1

6.2.2 .4 Absorbing Svstern


7

J*

/ .0)

(a) The flue gas from the electrostatic precipitator (ESP) sha lI be directed thro'flue
to the absorber module for removal of sulfur dioxide. The absorber mod.t:e shall
consist of an absorbing section and a mist eliminator section. The flue gas shall be
induced by the booster fan located downstream ofthe absorber and the GGH.
(b) Sulfur dioxide removal shall be accomplished by the absorbing slurry in the
absorbing section. The sulfur dioxide shall be captured by the absorbing slurry and
finally converted to calcium sulfate hydrate (CaS04 . 2H20).
As the hot flue gas enters the absorber and passes through the absorbing section, the
flue gas shall be quenched to saturation and sulfur dioxide shall be removed.
The flue gas shall pass through the absorbing section, thereby assuring optimum
liquid-gas contact, hence completing the sulfur dioxide removal process.
(c) After completing the sulfur dioxide capture , the flue gas shall flow into the mist
eliminator located in the flue downstream of or in the up most position of the
absorber and the water droplets shall be collected on the mist eliminator.
(d) The absorbing slurry shall be stored in the lower section of the absorber module
which is referred to as the absorbing slurry tank.
(e) Fresh limestone slurry shall be added to the absorber in order to control recycle
slurry pH. The agitators ofthe absorbing slurry tank shall make the solid float in the
absorbing slurry.
(f) The sulphur dioxide removal process shall also involve an enforced oxidation system.
This oxidation system shall force the calcium sulfite (CaS03' 112 H 20) formed
through the S02 removal process to be oxidized to calcium sulfate (CaS04 . 2H20).
One (1) oxidation air blower having 50 % ofthe required capacity shall be supplied
and one (1) ofthe existing three (3) blowers shall be employed for Unit No. 2. The
capacity of each existing blower is 50 % of the required capacity. The oxidation air
system for each Unit Nos. 1 and 2 consists oftwo (2) oxidation air blowers.

(g) The drainage from the system sha lI be collected in the absorber area sump for Unit
No. 2 and returned to Unit 2 absorber. The absorber slurry shall be transferred to the
existing blow down tank and returned to the Unit No. 2 absorber by the exiting blow
down return pump when the absorber is required to be empty, such as overhau l.
(h) All

necssary

provisions shall be made by the Contractor in order to employ the

6-2-8

o MONTHER'A L POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

eXlstmg eq Ul pment.
(i) Specification ofthe existing common equipment
The specifications ofthe existing common equipment, for the Bidder s reference, are
as follows:
Equipment name:
Quantity:
Capacity:
Head:
Motor rating:

No. 3 Oxidation Air Blower

Equipment Name:
Quantity:
Capacity:
Dimension:
Accessory:

Blow down Tank


1,864 m3
13 ,564ID x 14, 151 H
Agitator

Equipment Name:

Blow down

Quantity:
Capacity:
Head:
Motor rating:

5,000 m3Nfh (dry)


11 ,250 mmAq
200kW

Rtum

Pu mp

180 m3fh
29mAq
30kW

As for the terminal points of the above , refer to Volume 11 of 14.

6-2-9

p
-

(a) System flow

/A

6.2.2.5 Gvpsum Dewatering Svstem

O WN

VIETNAM ELECTRICITY / TEPSCO

(i) The gypsum dewatering system shall consist of a hydroclone , a filter feed tank,
filter feed pumps and a vacuum filter train. The vacuum filter train consists of a
vacuum filter with associated auxiliary equipment, a reclaim water tank, a
reclaim water pump and a chloride purge pump mainly.
(ii) One (1) hydroclone, one (1) filter feed tank, filter feed pumps and auxiliaries
shall be supplied for Unit No. 2. Two (2) existing vacuum filter trains shall be
used for Unit Nos. 1 and 2 commonly, but isolated from each other while two (2)
Units in operation simultaneously. A portion of the absorbing slurry in the
absorber module shall be fed to the hydroclone to control the absorbing slurry
tank level and slurry concentration. The underflow of the hydroclone shall be fed
to the filter feed tank. A part of the overflow of the hydroclone shall be drawn to
the existing sludge storage basin in the waste water treatment facility via the
existing FGD waste water transfer system.
(iii) The filter feed pump shall transfer the slurry from the filter feed tank to either of
the existing two (2) vacuum filter trains. The slurry is dewatered by the vacuum
filter. The dewatered byproduct gypsum is discharged to the existing gypsum
conveyor and transferred to the storage area in the gypsum dewatering and
storage house.
(iv) The filtrate from the vacuum filter is withdrawn to the filtrate rceiver by th
vacuum pressure induced by the vacuum pump. The filtrate is withdrawn from
the filtrate receiver to the reclaim water tank by the filtrate pump.
(v) The reclaim water shall be fed to Absorbent MillingIPreparation System by the
reclaim pump and discharged to FGD waste water receiving tank from by
Chloride purge pump. Unit No. 1 is with provided three (3) header pipes to
separate the reclaim water of each vacuum filter train for Unit Nos. 1 and 2,:
Pump suction header pipe for a1l pumps which connects with the reclaim tanks
Pump delivery header pipe for reclaim water pumps
Pump delivery header pipe for Chloride purge pumps
Unit No. 2 piping shall connect with the above header pipes. The relaim water
shall be fed or discharged as one for Unit Nos. I or 2 respectively from the
rclaim water tanks through the header pipes by the valve operation.

6-2-10

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

(vi) In the event of failure of the vacuum filter train in service due to some trouble or
in case of maintenance , the spent slurry produced by the absorber module is
transferred to the blowdown tank and stored tentatively.
(b) Vacuum filter train
(i) The existing two (2) vacuum filter trains are used for Unit Nos. 1 and 2.
(ii) The accessory of the gypsum cake washing is provided for the vacuum filter.
(iii) The water in the slurry is removed by the vacuum system. The filter cloth
restrains the cake while aliowing passage of the water and air. The filtrate drains
into the filter media and then into the filtrate receiver where the air is separated
from the filtrate. The vacuum pump with a liquid seal ring is provided to create
the necessary vacuum.
(c) The sump common to Unit Nos. 1 and 2 has been installed. The drainage from the
system shall be collected in the sump and retumed to the system adequately by the
eXlstmg sump pumps.
(d) All necessary provisions shall be made by the Contractor in order to employ the
eXlstmg eqUlpment.
(e) Specification of the common equipment
The specifications of the existing equipment, for the Bidder s reference , are as
follows:
Equipment Name:

No. 2 Vacuum Filter

Quantity:
Filter area:

14.9 m2

Product humidity:

10wt%

. Equipment Name:
Quantity:
Type:
Capacity:
Head:
Motor rating:
. Equipment Name:

No. 2 Vacuum Pump


NASH
4 ,320 m 3N /h
68 kP a
90 kW
No. 2 Filtrate Receiver

6-2-11

o MON TlIERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

Quantity:
Capacity:
Dimension

0.82 m3
1 067 x 2, 134

Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:

No. 2 Filtrate Pump

Equipment Name:
Quantity:
Capacity:
Dimension

Separator / Cake Wash tank 2A / 2B


2
0.18 m3
406 x 1,435 H

Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:

No. 2 Cake Wash Pump

Equipment Name:
Quantity:
Capacity:
Dimension
Accessorj:

No. 2 Reclaim

Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:

No. 2 Re cI aim Water Pump

Equipment Name:

No. 2 Chloride Purge Pump

Quantity:
Capacity:
Head:
Motor rating:
Equipment

Nam:

25 m3fh
11 mAq
7.5 kW

3 m 3fh
15 mAq
2.2kW
WaterTa

105 m3
5 500 x 5,950

Ag
itator

27 m 3fh
32mAq
11 kW

4.5 m3/h
13.7 m
4kW
Sludge Storage Basin

6-2-12

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

Quantity:
Capacity:
Dimension:
Accessory:
Equipment Name:
Quantity:
Capacity:
Dimension:
Accessory:
Equipment Name:
Quantity:
Capacity:
Head:
Motor rating:

90 m3
6,000 x 6,000 x 3,000
Agitator

Gypsum Dewatering Area Sump


25 m3
3,050 x 3,050 x 3,650 H
Agitator
No.1 / No.2 Gypsum Dewatering Area Sump Pump
2
60 m3fh
18 .3 mAq
15 kW

As for the terminal points of the above , refer to Volume 11 of 14.

6-2-13

o MON THERMAL P"ER PLANT

VIETNAM ELECTRICITY / TEPSCO

(a) The dewatered gypsum is discharged from the vacuum filter in the dewatering area
and transferred to the storage ara in the gypsum dewatering and storage house.
(b) The gypsum storage house has a capacity of 5,000 tons (equivalent to the capacity of
gypsum transported ship) of gypsum storage.
(c) The stored gypsum of 5,000 tons is transferred from the gypsum storage house to the
gypsum shiploader at the jetty by the gypsum reclaimer and conveyor~ for eight (8)
hours.
(d) The amount ofthe gypsum shall be measured with the gypsum weighing measure.
(e) The conveyors, weighing measure and gypsum shiploader are designed,
manufactured and constructed to prevent ingress of rain and emission of fine
gypsum particles and to permit interchangeability of parts and ease of access during
inspection, maintenance and repair.

(f) In case of supplying the by-product gypsum to domestic consumers, 20 tons capacity
trucks shall be used. Such a truck shall be prepared by the consumers nominated by
EVN.
(g) One (1) 2 ton capacity wheel loader is provided to scoop up the by-product gypsum
on the truck.

6-2-14

o 10N THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.2.2.7 FGD Make-up Water Supplv Svstem


(a) The clarified water is used for FGD make up water system. The clarified water is
supplied from the existing clarified water receiving tank to the existing FGD
make-up water tank by the existing FGD mce-up water transfer pumps.
(b) The FGD make-up water is supplied from the existing FGD make-up water tank by
the existing two (2) FGD make-up pumps. The necssary piping shall be provided to
supply the water to Unit No. 2 FGD equipment.
(c) The mist eliminator wash water is supplied from the existing FGD make-up water
tank by the existing two (2) mist eliminator wash pumps. The necessary piping shall
be provided to supply the water for the mist eliminator wash.
(d) Specification of the existing equipment
The specifications of the existing equipment, for the Bidder s reference are as
follows:
Equipment Name:
Quantity:
Effective Capacity:
Dimension:
. Equipment name:
Quantity:
Capacity:
Head:
Motor rating:
. Equipment name:
Quantity:
Capacity:
Head:
Motor rating:

FGD Make-up Water Tank


1,323 m 3
15 510x

9 ,190H

FGD Make-up Water Pump 1A/ 1B


2
3

140 m fh

48.8 m
55kW
Mist Eliminator Wash Pump 1A / 1B
2
95 m 3/h
67m
37kW

6-2-15

o MON THERMAL POWER PLANT

VIETNAM ELECTRJCJTY / TEPSCO

shall not effect on the existing equipment and structures or minimize the effect on them
and shaIl not disturb the operation of the existing equipment.
(a) FGD electrical and control building
The control system and related equipment shall be installed on 1st floor in the
existing electrical and control building.
The electric system shall be located below the control system floor.
As for the details, refer to Volume 3 of 14.
(b) Void
(c) Li mestone ball mill house
The roofhas been provided over the ball mill to enable the milling system to function
even under inclement wcather conditions.
The crane has been provided for the maintenance of each ball mill as follows:
Capacity:
3 tons
7,600 mm
Span:
Length ofRunway:
15 ,300 mm
Hook path:
8,110 mm
As for the details, refer to Volume 3 of 14.
(d) Oxidation air blower house
The roof has been provided over the oxidation air blower to enable the air supply
system to function in inclement weather conditions.
The crane has been provided for the maintenance of the oxidation air blowers as
follows:
4 tons
Capacity:
Span:
10,400 mm
Lenh ofRunway:
23 ,700 mm
Hook path:
5,257 mm
As for the

dtails

refer to Volume 3 of 14.

(e) Gypsum dewatering and storage house


The roof has been provided over the vacuum filter to

6-2-16

nable

the dewatering system to

o MON THERMAL PO 'ER PLANT

VIETNAM ELECTRICITY / TEPSCO

function in inclement weather. The gypsum storage house and the gypsum
transportation facility are located below the vacuum filter.
As for the details, refer to Volume 3 of 14.
6.2.2.9 Void
6.2.2.10 Materials
(a) Materials of construction shall be cOITosion and erosion resistant.
(b) Main piping with slurry shall be of carbon steel with the rubber lining or FRP (Fiber
Reinforced Plastic) or equivalent and the tank shell shall be made of carbon steel
with the flake resin lining or equivalent.
(c) Materials of the flue and its intemal support shall be steel with the flake resin lining
or equivalent from the untreated gas outlet of GGH to the treated gas inlet of GGH.
(d) Materials of the flue , its intemal support and damper located in the range from the
treated gas outlet of GGH to the stack inlet shall be cOITosion-resistant stee l.
6.2.2.11 Process Outline
(a) FGD system shall be designed in accordance with layout and process flow diagram
as shown in Drawing Nos. OM2FD-l 00 1 and OM2 FD-l 002 in Volume 11.
6.2.2.12 The Manzins for the Des $m Caoacitv and Pressure ofEouioment
(a) The margins in design capacity and pressure shall be allowed for, but not be limited
to , the following;
(i) Booster fan
The design capacity of the booster fan sha l1 be not less than 1.1 5 times BMCR
gas treatmen t.
The design static pressure sha lI be not less than 1.25 times the pressure required
at BMCR.
(ii) Pump , GGH and Agitator
The design perforrnance of this equipment shaIl be decided taking into
consideration the performance deterioration due to erosion and cOITosion for each
mamtenance term.

6-2- 17

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.2.2.13 Soecification ofMain Eauioment

'^~

(a) Absorber module


(i) Absorbing Section
Quantity
Materials
Absorbing Section
Spray Headers
in Absorbing Section
(ii) Mist Eliminator
Quantity
Type
Material

One (1) per unit


Carbon steel + flake resin lining or equivalent

Stainless steel or equivalent

One (1) per unit


Horizontal, vertical or equivalent
Polypropylene or equivalent

(b) Absorber Recycle Pumps (if necessary)


Quantity
Four (4) per unit (One (1) is a stand-by)
Type of Pump
Centrifugal
Casing Material
Carbon steel + rubber lining or equivalent
Impeller Material
Carbon steel + rubber lining, duplex alloy or
equivalent
(c) Oxidation Air Blower
Quantity
Type ofBlower
Casing Material
Impeller Material

One (1) to be supplied newly (One (1) of the


three (3) existing ones also is for Unit No. 2.)
Roots or equivalents
Carbon steel or equivalent, if necessary
Carbon steel or equivalent, if necessary

(d) Booster Fan


Quantity
Type

One (1) per unit


Centrifugal

(e) Reagent Feed Tank


Quantity
Capacity
Material

One (1) per unit


Hold for fve (5) hours operation
Carbon steel + flake resin lining or equivalnt

6-2-18

VIETNAM ELECTRlCITY I TEPSCO

(f) Limestone Silo


Quantity
Capacity

0 MON THERMAL POWER PLANT

One (1) per unit


Seven (7) days operating demand (not less than
1,000 tons) for one (1) absorber module

(g) void

6-2-19

VIETNAM ELECTRICITY / TEPSCO

o MON THERMAL POWER PLANT

6.2.3 Electrical Requirements


(
) For
a
rtl

he

e
lect
e

r
lC

a
c

1
re
q

ullrem

me

nts

tso

FGD
f

Sy

Volume 2 Clause 2.2.3 titled Electrical Works. Technical Schedules e FGD


Electrical equipment shall follow the format ofVolume 13 Schedule 13
6.2.4 C & 1 Requirements
(a) The control and instrumentation system shall be designed to operate and control
FGD system, fully and smoothly automatically following the boiler operating
conditions.
(b) The control and monitoring system for the FGD System shall be provided in
accordance with Volume 7 Clause 7 .4 .10 , Clause 7 .4.1 5 and Volume 2 Clause 2.2.3.
Technical Schedules for the FGD C&I equipment shall follow the format of Volume
13 Schedule 13.6.
(c) All necessary measuring and detecting devices required for control and monitoring
of the FGD plant shall be supplied and installed.

6-2-20

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.3 TEST AND INSPECTION


6.3.1 General
(a) All costs required to caY out all tests to ensure the satisfactory design , manufacture ,
installation, commissioning and performance of his supply in accordance with the
Specifications and Standards shall be included in the Bid.
(b) The Contractor shaIl be responsible for the timely delivery of the relevant and
appropriate sections of Specification to sub-contractors, if applicable, and the proper
execution of all tests on works and materials shall be supplied by sub-contractors,
wherever such tests are carried out, to the same extent as if the tests on works and
materials were carried out by the Contractor himsel f.
(c) The cost of all tests and inspections, including any repeated test or inspection carried
out at subcontractors works shall be included in the B id.
(d) The Contractor shall submit to EVN inspection and test procedures covering a Il
materials and equipment. Agreement shall be established on the scope of inspection
and tests to be witnessed by EVN or his nominees before start of the work.
(e) If without giving necessary advance notice the Contractor carries out any test
requiring the witness by EVN, such tests shall be deemed unsatisfactory and the
concemed part of supply shall not be accepted.

(f) Tests not requiring the witness by EVN shall b in any case, notifid in advance. The
Contractor shaIl then proceed with the tests and shaIl submit reports to EVN.
6.3.2 Records and Certificate
(a) Thirty (30) days after completion of any test, triplicate sets of all principal test records,
test certificates and correction and performance curves shaIl be supplied to EVN.
(b) These test records , certificates and performance curves shall be supplied, whether or
not those tests were witnessed by EVN or his nominated Representative. Th
information given on such test certificates and curves shall be sufficient to identify the
material or equipment to which the crtificate refers and also bear the contract
reference title.
(c)

Whn

equipment has been tested , all test certificates shall be

6-3-1

compild

by the

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

Contractor into volumes and bound in an approved form complete


copies ofeach volume shall be supplied to EVN.

wit1}iex

and the

.~

(d) The following records and certificates shall be submitted.


(i) Chemical analysis and mechanical propeies of materials
(ii) Heat tratment process certificates of forging
(iii) Reports of all required tests
(iv) Type test certificates
(v) Affidavit of compliance stating that all materials and works supplied will comply
or have complied with the applicable requirements of these specifications.
(e) The Contractor shall make the following available to EVN upon request:
(i) Films of all radiographic examinations
(ii) All welding procedures and performance qualification certificates
(iii) All non-destructive test procedures
6.3.3 Worksbop Tests
6 .3.3 .1 General
(a) Where applicable, tests must comply with the Vietnamese regulations as included in
Clause 2.2.1.1.
(b) Where no specific test is specified , then the various items of plant, equipment and
materials shall be tested in accordance with the applicable standard, acceptable to
EVN. Where no appropriate standard is available , tests shall be caic out in
accordance with the manufacturers standard practice, subject to the prior approval of
EVN.
(c) All tests to be performed during manufacture , fabrication and inspection shall be
agreed by EVN prior to commencement of the work. The Contractor shall prepare the
details ofthe schedule and submit these to EVN for approva l. It must be ensured that
adequate relevant information on the design code/standard employed , the
manufacture/fabricatio n/assembly procedure and the attendant quality control steps
proposed are made available to EVN. EVN will mark in the appropriate spaces his
intention to attend or waive the tests or inspections.
(d) EVN shall be notified of impending tests by the Contractor sixty (60) days in advance ,
and the Contractor sha lI prepare all testing equipment and personnel for such tests.

6-3-2

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

(e) The subject items should remain available for inspection and test up to minimum ten
(1 0) days after the date ofwitnessing the test unless otherwise agreed by EVN. Every
facility in respect of access , drawings , instruments and manpower will be provided by
the Contractor and his Sub-Contractor to enable EVN or his designated representative
to caY out the necessary inspection and testing of the equipment.
(t) No equipment shall be packed, prepared for shipment, or dismantled for the purpose
of packing for shipment, unless it has been satisfactorily inspected , or approved for
shipment, or altematively inspection has been waived.

(g) The extent ofworkshop tests and method ofrecording the results shall be submitted to,
and agreed by EVN in sufficient time to enable the tests to be satisfactorily witnessed
or, ifnecessary, any changes ofthe proposed programme oftests to be agreed.
(h) A Il instruments and apparatus used in the tests shall be subject to the approval ofEVN,
and , if required by EVN, shall be calibrated to an agreed standard.
(i) The cost of carrying out such calibrations shal1 be bome by the Contractor in all cases.
(j) EVN reserves the right to visit the Contractors Works at any reasonable time during
fabrication of equipment in order to survey the progress made.

6.3 .3 .2 Mechanical Works


(a) The Contractor shall carry out the following test in accordance with the Standards and
Specifications as included in Clause 2.2. 1.1.
6.3 .3 .2.1 Tests on Materials
(a) Representative samples and mill certificates of all plates, bars, pipes, etc., which form
components of the plant shall be tested and submitted as required by the relevant
approved standard or code or at the request ofEVN.
(b) A lI test pieces shall be prepared and supplid by the Contractor at his own cost. If any
test piece fails to comply with the requirements ofthe specifications for the matrial in
question , EVN may rct the whole ofthe material reprsented by that test piece.
(c) AII important forgings shall be xamined at the manufacturers works by jointly EVN
or his nominee together with the representatives of the manufacturers during forging
and heat treatmen t.

6-3-3

o MON THERMAL POJJRPLANT

VIETNAM ELECTRICITY I TEPSCO

(d) The test sha lI be conducted on the fo lI owing, but no be limited to:
(i) Fan Shafts

(e) The mill certificats shall be submitted for approval of EVN on work
equipment ofthe fo lI owing, but not be limited to:
(i) Absorber
(i i) Flue and Damper
(iii) Structure and Reinforcing Bar
(iv) Valve
(v) Piping
(vi) Tank and Silo
(vii) Rotating Equipment
6.3.3.2 .2 Ultrasonic Examination
(a) A lI tubes and pipes for pressure piping shall be ultrasonically examined for detection
of injurious defects before fabrication is started.
(b) Tube and steel plate surfaces shall be free from mill scales, etc. , to allow a c1 ear
interpretation of ultrasonic signa l. If necessary, a suitable treatment of surfaces shall
be performed.
(c) Ultrasonic inspection shall be in accordance with Vietnamese Regulation and/or
ASME Section 11 Sa-655 , ASTM E164-94a or equivalent.
(d) Imperfections found by ultrasonic examination shall be judged against the acceptance
- rejection standards outlined in ASME Code Section VIII Div.l , Appendix 12,
paragraph 12.3 or equivalent.
6.3 .3 .2 .3 Radiographic Examination
(a) Radiographic examination shall be the main quality control of welding; where not
possible , other approved method shall be applied.
(b) For all shop welded
(i) Pressure vessels

pas

the following percentage of seam shall be examined:


: 25 %

(c) A lI pressure pas shall be tested in accordance with the requirements of Vietnamese
Regulation and/or ASlE Unfired Prssure Vessel code or equivalent.

6-3-4

o MON THERlrlAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.3 .3 .2 .4 Hydrostatic Test


(a) Hydrostatic test at 150 % of the design pressure shall be carried out for a period of 30
minutes or longer at the manufacturer s factory on pressure vessels in accordance with
Vietnamese Regulation and/or the ASME Code or equivalent.
(b) A lI hydrostatic tests shall be carried out prior to surface coating or painting and cast
iron enclosures may be subjected to hammering as required by EVN.
(c) Hydrostatic tests of equipment manufactured of austenitic steel should be carried out
using water having chloride content ofless than 30 ppm.
(d) Anti-rust additives shall be used to prevent oxidation of surfaces. As an altemative,
the surface may be dried up upon completion oftests.
6.3.3.2.5 Pipework
(a) The fabricated pipework shall be tested in accordance with the standards as specified
by ANS I. B3 1.1 /ASME B3 1.1 or equivalent.
(b) Temperature records ofhot forming and heat treatment operations shall be made , filed
and submitted to EVN.
(c) The walI thickness of hot formed bends shall be checked by ultrasonic method.
Records ofthese shall be kept and made available to EVN.
(d) Where random radiography is specified, this shall refer to the final weld only at EVNs
selection and discretion.
(e) For the purposes ofradiographic inspection, a root pass is defined as the first complete
weld run.
(t) AII piping not covered by 100 % radiography shall be tested as follows.
(i) Lined piping shall be tested for leak ofwater with the f1 0wing water in the piping.
(ii) Piping f1 0w without lining shall be hydrostatically tested at 1.5 times ofthe design
pressure.
(iii) Piping for air and gas f1 0w shall be tested with pneumatic pressure.

(g) In addition to the NDT requirements stated in ANSI B3 l.l/ASME 83 1. 1 paragraph

6-3-5

:--.""

VJETNAM ELECTRJCJTY ITEPSCO

O MONTHERM'l._POWER PLANT

\
136 .4 or equivalent, the Contractor shall radiograph all butt welds 0/ing over 50
mm in accordance with the requirements outlined in the table belo 7
EEg

Auxiliary steam
Soot blower steam

Root Pass
None
None

Final Pass
(After PWHT* where applicable)
10 %
10 %

* PWHT : Post Weld Heat Treatment


(h) Examination shall be made on the entire weld. Percentages refer to the total number of
weld and shall be representative of the range of sizes. The above requirements are
applicable to both site and shop welds.
(i) All nozzles, branch connections, butt welds and attachment welds in alloy steel pipe
shall be subject to magnetic particle or dye penetrative inspection.

U) Magnetic particle inspection shaIl be carried out in accordance with ASTM E709-95 or
equivalent.
(k) When dye penetrative method is applied , it shall be conducted in accordance with
ASTM E165-95 or equivalent and application directed by the penetrate manufacturer.
6.3.3.2.6 Pumps
(a) All pumps shall be tested in accordance wth the approved standards. Prior to any tests,
the Contractor shall submit a test procedure showing the layout of the testing
equipment with the positions of pressure measurement points and f1 0w measuring
devices, for approval of EVN. In addition , the details of calibration of the f1 0w
measuring device , motor power vs. efficiency curve, a specimen of the test record
sheet and details of the performance calculations shall be provided.
(b) The performance test shall be conducted over the fuIl operating range of the pump.
Curves indicating f1 0w rate vs. head , f1 0w rate vs. power consumed, and f1 0w rate vs
pump efficiency shall be provided. In addition, the curve of f1 0w rate vs. NPSH
required shall be providd.
(c) On completion ofthe tests the Contractor shall submit a report showing the test results
obtained together with the curves corrected to the site operating conditions.

6-3-6

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.3.3.2.7 Fans
(a) Booster fan shall be subjected to full performance test including static and dynamic
balancing which shall be witnessed by EVN.
(b) The test shall be in accordance with the latest applicable ASME test codes or
equivalent.
6.3 .3 .2.8 Steel Structure
(a) Radiographic examination shall form the main quality control ofwelding; where not
possible, other approved method shall be applied. The examination shall be applied to
25 % of all shop welded parts for main structure.
(b) Dimension check for main structure shall be carried out.
6.3 .3 .2.9 Lifting Equipment and Cranes
(a) Th e Contractor shall caY out the tests as required by the approved standards, to prove
the capacities of cranes and lifting equipment. Test certificates shall be submitted and
shall include the material Iist of equipment, welding record and non-destructive test
record for electricaI equipment, wire ropes, hooks, chain blocks, shackles, runway
beam, eye bolts and any other related items which are provided.
(b) Upon completion of the tests, the equipment shall be clearI y marked with the safe
working load (SWL) and any other markings that EVN may require.
6.3 .3.2.10 Insulation Material
(a) The Contractor shall provide the thermal conductivity test repo for the last five (5)
years applications ofthe product or shall conduct the test ofthermal conductivity in
accordance with ASTM codes or equivalent.
6.3.3.2.11 Lining
(a) Alllined components ofthe plant shall be tested for proper lining in accordance with
the lining manufacture s instaIl ation procedure and applied to the specified thickness
oflining.
At least the spark test for the whole lined surface and random test ofhardness shall be
conducted.

6-3-7

VIETNAM ELECTRICITY / TEPSCO

6-3-8

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.3 .4 Test and Inspection at Site


6.3 .4 .1 General
(a) All equipment and plant shaIl pass tests on site as required by EVN to pro'v
compliance with the speci
fica
tio
n independently of any tests which may have already
been carried out at the manufacturer's works.
(b) The tests at site shall include, but not necessarily be limited to , those specified in this
sectln.
(c) In paicular all functional and pressure tests on fully assembled and complete items
of plant which have not been carried out at the manufacturers works , shall be caied
out on slte.
(d) The commissioning shall be carried out in accordance with the requirements ofClause
2. 1. 11.
(e) The Contractor shall be responsible for all site inspection and tests as required by
EVN and for the providing of the reports. Detailed proposal for all tests shalI be
submitted to EVN for approva l.
(f) During the course of erection ofthe plant, EVN is to have access to the plant an d/or its
components for inspecting the progress of the work and checking its accuracy to any
extent that may be required.

(g) Th e Contractor shalI provide a lI temporary scaffolding, ladders, platforms with


adquate and safe flooring, and handrails essential for proper access of EVN or his
nommees to caY out inspections.
(h) The Contractor shall also provide all personnel , materials, and instruments and other
resources necessary for such tests.
6.3 .4 .1.1 Inspection and Test Equipment
(a) The Contractor shaIl supply the instruments for tests and inspection of totaI plant to
E'N at site (refir to Clause 5.3 .4)
(b) Before the PAC , the above instruments shall be handed over to EVN in proper
working ordr.

6-3-9

O MON:~'I1AL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

;:~h
,Y:'://

(c) Where necessary, specialized training for operators for any in~nents above shall be
provided and the cost associated with such training shall be included in the Bid.
(d) It is the Contractors responsibility to provide certified calibration curves for
instruments, comprehensive operating and maintenance instruction manuals,
electrical circuit diagrams , maintenance tools and spare parts catalogue. AIl
documents shall be in clear, simple and correct English.
6.3 .4.1. 2 General Inspection Procedure
(a) Equipment Arrival at Site
Contractor shaIl notify EVN of arrival of equipment for any physical inspection.
(b) ErectionlInstaIlation of Equipment
(i) General Inspection
During erection stage, EVN wiII inspect erectio n/instalIation of equipment
generaIly from the foIIowing aspects.
- Any non-conformance
- Workmanship
- Materials used are of approved type/quality.
(ii) Official Inspection by EVN
Inspection on major equipment which is listed by EVN and the Contractor w ilI be
made by EVNs inspection staff officially in accordance with site quality control
(QC) procedure submitted by the Contractor and approved by EVN and the steps
given below shalI be foIlowed.
Step 1 Request for Inspection/Attendance (Refer Note * 1)
The prescribed form "Request for Inspection/Attendance" shaIl be
submitted by the Contractor to EVN twenty four (24) hours prior to the
inspection and include the following information.
i) Location ofWork to be inspected
ii)Purpose of inspection
iii) Relevant drawings , sketches, calculation, etc
iv)Reference No. of applicable document
Note * 1
Weekends, public holidays and times when EVN office is officially c1 0sed shall be
not considered as notice .
AIl requests shall be registered by EVN with time/date ofreceipt stamped on each
request.

6-3-10

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

Step 2 Inspection Check Sheet


Upon approval of the Step 1, EVN and the Contractor w iIl inspect e item~
in accordance with the inspection check sheet prepared by the Contractor
which w iIl be handed over to EVNs inspector at site. After inspection, both
parties will endorse on the above sheet as an evidence of inspection. Should
there be any discrepancy, another similar inspection will be called for.
Step 3 Verification Certificate
Upon completion ofthe inspection of each item, the inspection results shall
be summarized in the verification certificate and reviewed by EVN.
Step 4 Conformity Certificate
Upon completion ofthe inspections of all, all the inspection results will be
summarized in the conformity certificate and reviewed by EVN.
6.3 .4.1. 3 Painting Inspection Procedure
The painting work shall be carried out as specified in Clause 2.2. 1. 13 and inspected in
accordance with the following procedures.
(a) Submission of check documents to EVN
The Contractor shall submit the following documents to EVN for approva l.
(i) Colors items not specified in the EVN Standards
(ii) A list of paint suppliers
(iii) A list of applicators
(iv) A quality assurance program
(v) Painting methods for corrosion resistant paints for places exposed to corrosive
conditions
(b) To check all paints and cleaning materials which are to be of approved quality
(c) To check coats which are to be produced by same manufacturer or to be of the same
quality
(d) To check the cleaning works to be executed in accordance with the approved quality
assurance program
(e) To check the painting works to be executed in accordance with the approved quality
assurance program

6-3-11

VIETNAM ELECTRICITY / TEPSCO

(f) Random check ofpaining coat thickness

(g) To check finish to satis :ty EVN Standards


(i) Color codes to be in accordance with EVN s color code standard or that approved
byEVN
(ii) Smoothness of finished surface
(i ii) Rests ofthe high voltage sparking test on the surfaces to be exposed to corrosive
conditions
6.3 .4 .2 Mechanical Works
6 .3.4.2 .1 Welding and Welding Documents
(a) Welding works carried out by the Contractor shaIl be inspected by EVN in accordance
with the requirements of Clause 2. 1. 10 and the further requirements given below.
(b) In cases where the Contractor employs subcontractors who are to caY out certain site
works , e.g. non-destructive testing (ND it is stiIl the Contractor' s responsibility to
prepare such quali control documents related to the site works.
Furthermore, it is specificaIIy requir'd that such documents shall be, after the
Contractor obtains the necessy approval by EVN, forwarded to the subcontractors
for their compliance. It is the Contractors responsibility to retrain, if necessary, his
subcontractors' personnel anor procure additional equipment in order to meet the
requirements ofthe approved quality control documents.
(c) Before commencement of the site welding, the Contractor shall prepare the following
documents and submit them to EVN at site for approva l.
(i) Welding Procedure Specifications (WPS) and Procedure Qualification Records
(PQR)
A Il welding on pressure parts or non-pressure pas shall be carried out in
accordance with the approved qualified WPS. Th Contractor shall compile all the
WPS and their respective PQR to be used for site welding in one volume and submit
them to EVN for approval at site before commencement ofwork. EVN shall accept
any or all the WPS without prejudice to his rights to call for re-qualifications of any
or all of the WPS at site, should it be deemed necessary. If such a pre-qualification
is required , the WPS test shall be conductd at no extra cost to EVN , based on
agreed national or international standards.

6-3-12

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

(ii) Welders Qualification Test Procedures


The Contractor shall prepare a Welders Qualification Tests Procedures
summarizing the different types of site welders tests. Such test procdures shall be
based on the agreed standard. The number and type of tests required shaIl be
determined by the essential parameters such as:
- Welding process
- Material
- Filler material
- Pipe or plate
- Size - diameter anor thickness
- Position
- Type of joints - butt an d/or fillet joints
Each test procedure shall be specified in detail to include, but not be limited to
information on specimen size, methods oftests: non-destructive an d/or destructive,
assessment of test results, and rejection and acceptance criteria.
The Contractor shall prepare weld maps of all the joints to be welded at site. These
weld maps shall be prepared for piping. The weld map shall show diagrammatically
the location of each joint, the identification numbers of the joints (each joint shall
have its own unique number) , the dimensions and edge preparation of each joint
and the WPS applicable.
The weld maps shall be submitted to EVN at site for approva l.
(iii) Weld Application Table
It is mandatory that the Contractor prepares a Weld Application Table before
commencement of work. A Weld Application Table is a summary of the
requirements of each individual joint to be welded. An example of the format of a
Weld Application Table is as below.
(Example)
System : MAIN STEAM PIPE
MSF-l
SA 335 P22
SA217 WC9

Joint No.
Base Metals
Pipe Size, dia.
WPSNo.
PQRNo.

t (mm)

406 .4 x 67

55TA-SRl
P-55TA-l

6-3-13

VIETNAM ELECTRJCITY / TEPSCO

Filler Metal : Spec. No.


Root Run
Subsequent Runs

Preheat Temp. (oC)


PWHT Procedure No.
Soaking Temp. e C)
Soaking Time (Minutes)
Heating Rate (OC/min)
Cooling Rate eC/min)
NDT Required

VIIPT
RT
MT
UT
Remarks

100 %
100 %
100 %
100 %

(iv) Non-Destructive Testing (NDT) Procedure


All NDT to be carried out at site shall follow the approved procedures. Such
procedures shall not be just a reference to or a copy ofthe agreed Standard, but shall
be tailor-made, taking account of the actual works to be carried 0t at site such as
the availability and type of equipment at site and the skill of NDT operators
employed. The NDT equipment shall be ofwell-known make and comply with the
requirements of the approved Standards.
The NDT operators shall be certified in accordance with a Certification Scheme.
The Certification Scheme shall be approved by EVN. Even if an operator has been
certified, EVN has the right to conduct practical tests. Such tests shall be carried out
by the Contractor at no extra cost to EVN.
(v) Heat Treatment Procedures
For the purpose of this Clause, heat treatment incJ udes post fabrication heat
treatment, pre-heat treatment and post-heat treatment of welding. Th e Contractor
shall prepare Heat Treatment Procedures based on the agreed Code and Standard
and/or Manufacture s provn practice. The procedures shall not b just a reference
to or a copy of the agreed Standard, but shall be tailor-made to suit the site
conditions: type of joints, accessibility, type and availability of equipment at site,
and skill ofheat treatment operator employed.

6-3-14

o MON TlIERMAL POWER PLANT

VIETNAM ELECTRJCITY / TEPSCO

~-0~

The procedures sha Il cover the fo lI owing items:


method (s) ofheating
type of equipment, temperature recorders, thermocouple , wires, heating
elements
calibration of temperature recorders and thermocouple wires; frequency of
calibration
calibration cente methods of calibration
number of joints to be heated at the same time
number ofthermocouples per joint
methods of attachment of thermocouples to joints
locations of thermocouples on the joints
number ofheating elements per joint
size ofheating elements
methods of securing heating elements to joints
methods of prevention of direct heating(shorting) ofthe thermocouples
undemeath the heating elements : the use ofhigh temperature putty
type of insulation blankets
size of insulation blankets : width x length x thickness
coverage of insulation blankets over heating elements
methods of securing blankets over joints
emrgency procedures : what to do if there is a temporary power cut or a
permanent power cut or shorting of the thermocouple wires, additional
precautions to take during rainy weather: water chilling of joints while
heatin g/soaking/cooling
restrssing of a joint : aHwable fri quency of stress exertion
the use of portable hardness-tester to check efficacy ofheat treatment
confirmation of the efficacy of the heat treatment procedures by in-situ
metallography
stampin g/recording ofthe heat treatment recorders' charts: information needed
and format
(vi) Repair Procedures
The Contractor shaIl prepare a Repair Procedure based on the fabricationlwelding
requirements of this Specification and approved Standards. The procedure shall be
prepared in detai! enough with regard to equipment to be used , methods of repair,
acceptance/rejection criteria, inspctions required , etc. , taking account of the site
constrants.

6-3-15

o MON THERMAL PO :vER PLANT

VIETNAM ELECTRICITY / TEPSCO

(vii) Other Documents


The Contractor shall submit to EVN one (1) copy of other reletdocu such
as mancturer's practice, technical pape where such documents .;~ng
referred to in his site welding documents.
'. "\:\
6.3.4 .2 .2 Site Welding Control
(a) In order to monitor and maintain welding quality at site, the Contractor shall establish
in his site organization an independent Quality Control Section, whose function would
be solely to enforce the Contractors field quality assurance programme and the site
quality plans.
(b) Site Quality Control Section
The Contractors Quality Control (QC) Section shall be headed by an experienced
Quality Control Engineer. He shall be assisted by at least one Welding Supervisor. The
Section shall be an independent one in the Contractor s Site Office and shall be under
control of Contractors Company Quality System Management.
The Contractors QC Section shall keep close communication with EVN personnel in
charge of Quality Assurance/Quality Contro l.
(c) Control ofWelders
The Contractor shall employ only experienced welders. However, all welders , with or
without previous qualifications, shall be tested to meet Test Procedures. Holders of
current welding certificates from the relevant Vietnamese authority shall not be
exempted from the test. Howver EVN site ce may, at his discrtion aIlo these
welders to work if they can demonstrate their skill on five (5) production joints, of
which the sizes and locations shall be selected by EVN, without any defects as
revealed by visual inspection and radiography. The same rule shall apply bona fide to
welders from the Contractors manufacturing works.
All welders qualification test shall be conducted, at the Contractors expense, and
witnessed by EVN who makes final decision of the suitability of the welders.
In case that Vietnamese legal requiremnt asks the welders to be registered in the
relevant Vietnamese authority and welders qualification test be conducted in their
mspctor s presence , it is the responsibility of the Contractor to aange for the
Inspectors attendance.
The Contractor shall monitor the performance of his welders throughout the projec t.

6-3-16

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

EVN may require a welder to be re-qualified ifEVN deems the skill ofthe welder has
deteriorated , and the Contractor shall promptly remove the said welder from the job.
At the discretion of EVN , the re-qualification test may be conducted in the same
manner as the original one or in a similar form. If a welder produces bad welds~ for
example, in the spray pipe region , the re-qualification test may not be just welding a
single test piece but may be welding five pipes (of which size is equal to spray pipe
size) and in the similar position. All costs of re-qualification tests shall be bome by the
Contractor.
(d) Control of Welding Activities
The Contractor shall at all times control its welding activities in a manner whereby the
quality requirement of its Field Quality Assurance Programme (FQAP) is never
compromised, but at the same time no delay to the Welding progress is experienced.
The Contractor shall draw up a working procedure to accommodate EVN participation
at Site in accordance with the following:
Activities
(i)Material Receiving checks
(ii) Cleaning of Components
(iii)Alignment of component

EVN Scope
100 % Checking

(iv) Fit-up Checks

100 % Checking. The Contractor shall not proceed until


EVN approval is obtained.
Spot Checking

(v) Issue ofElectrodes


lF iller material
(vi) Inspection during
actual welding
vii) Visual Inspection after
welding
(viii) NDT before PWHT

(ix) PWHT

Spot Checking
100 % Checking

Spot Checking; but EVN shall witness the sta of


welding at new areas or systems.
100 % Checking. The contactor shall not proceed to NDT
or other work until EVN gives approva l.
A Il NDT shall be witnessed by EVN. For radiography,
EVN may not be present at all times. However, joints
shall be selected by EVN , and the radiographs together
with their Interpretation Reports shall be submitted to
EVN. EVN decision on the acceptabili or otherwise, as
per the agreed Standard, of the radiographs and/or the
joints shall be final and binding on the Contractor.
Spot Checking during PWHT. The Contractor shall
submit to EVN each joint PWHT Chart. The chart shall
be stamped with the relevant data.

6-3-17

VIETNAM ELECTRICITY / TEPSCO

O 10N

THERMAL POWER PLANT

(x) NDT after PWHT


(xii) Hydrostatic Test

All NDT ancr PWHT shallabbeow


;
scd by EVN in a
manner similar to Item (viii)
100 % Checking
Requirements that the hydrostatc test shalI be witnessed
by the Inspector from the relevant Vietnamese authority,
the Contractor shall aange for the said Inspector s
attendance. All costs required only for conducting such
tests shall be bome by the Contractor.

In all cases, the Contractor s scope shall be 100 %. In case where EVN participation is
also 100 %, such inspection may be caied out jointly at the same time when the
Contractor carries out his inspection. However, EVN may insist that the Contractor
carries out his inspection first and correct whatever defects found before caIling for
EVN participation.
The Contractor shaIl submit a daily report on welding works indicating the distribution
of welders , the number and identification of joints welded, and the number and
identifications ofjoints to be subjected to NDT and PWHT.
The Contractor shall prepare all check sheets for the inspections, and the check sheet
format shaIl be approved by EVN at site. Such check sheets must be signed by the
relevant pties immediately after the inspection. The Contractor shaIl submit to EVN
these check sheets bound in volumes, appropriately titled when the project is
completed.
The radiographic films , after review by EVN at site, shall be retumed to the Contractor.
The Contractor shall then classify the films , put them in appropriately labeled boxes
and store them in cI ean , dry, pest-free air-conditioned room. The Contractor shall keep
the films in such good conditions for the determined years after the completion ofthe
project. EVN shaIl have access to these films at any time during the storage period.
(e) Control ofWelding Consumables
The Contractor shall follow the manufacturers' recommendations in storage and
handling of all welding consumables.
It is Contractors responsibility to confirm the purity ofwelding gases. The Contractor

shall have accurate instruments for measurement of gas tlow and oxygen
concentration.

6-3-18

o MON THERMAL POWER PLANT

VIETNAM ELECTRJCITY / TEPSCO

The Contractor shall only bring to site welding electrodes and other filler materials
complying with the approved WPS.
Each consignment ofthese welding consumables to site sha Il be accompanied with the
manufacturers mill certificates. The Contractor shall not change the brands of the
welding consumables without prior approval ofEVN.
The Contractor shall provide electric ovens with suitable timers and temperature
indicators for the purpose of preheating the welding electrodes before issuing to the
welders. The quantity of electrodes issued shall only be for four (4) hour use. The
contractors shall provide his welders with electrically heated quivers to cay the
electrodes to working areas. Furthermore, in order to ensure compliance with the
requirement that the quantity of electrodes for only four (4) hour use is issued at one
time, the Contractor is required to provide two (2) colour-coded quivers to each welder,
such that, for example, only red quivers are used in the morning and blue ones in the
aftemoon (after lunch). It is the strict requirement of this Specification that the
Contractor ensures that his welders return unused welding electrodes to store after
every four (4) hour shift and fresh electrodes for use in the next four (4) hours is issued
in diffrent quivers.
The Contractor shall establish and follow diligently an Electrode Record Procedure
whereby the amount and type of electrodes issued to each welder at every issue are
recorded in either a Record Book or Card. Such record shall be made available to EVN
at site for scrutiny whenever requested.
F or fiHer matrials to be usd in TIGwlding process, the Contractor shall ensure that
the filler materials are clean, dry and rust-free. They shalI also be positively identified
either by using tags , colour codings, or both. Alternatively, their specification numbers
shall be stamped on the rods at regular intervals in such a manner that when cut in
shorter len!hs such stamps will still be visible. The f1 ags or colours to identity rods
shall also present in full lenh. The filler materials shall be carried to work-areas in
suitable containers.

(f) Control ofNDT


The Contractor shall be responsible for controlling all NDT activities under his
contract, even when he sub-contracts the job to a NDT specialist company.
The Contractor shall ensure that his NDT equipment are reliable, modern , calibrated
and comply with all relevant requirements ofthe agreed Standards.

6-3-19

o MON THERMAL PV,wER PLANT

VIETNAM ELECTRICITY / TEPSCO

The Contractor sha lI employ only mature and experienced NDT ope'r#rs. The
Contractor sha lI ensure that the NDT operators hold current and relevant <;irtificates
from the Certification bodies approved by relevant Vietnames authority.
Notwithstanding such a certificate, the Contractor shall promptly aange for the
demonstration ofthe skill ofhis NDT operators to EVN , should EVN reques t.
Radiographic works shall comply with all the Vietnamese regulations and shall be
carried out after normal working hours only. However, EVN may delay issue of
permission to sta or suspend the work for any duration during the permitted hours
when urgent construction works an d/or plant operational activities is needed to
proceed without interference.
If the Contractor desires to subcontract the pa or the whole ofthe NDT works within
his scope, the Contractor shall first obtain the approval from EVN at site. The
Contractor shall prove to satisfy EVN that the sub -c ontractor s work is good enough.
The Contractor shall aange NDT works promptly after completion of welding.
Where welding requires PIT the NDT sha lI be conducted after the PWHT.
6.3.4 .2 .3 Absorber and Other Equipment
(a) Soap Solution Test
Soap solution tests shall be performed prior to the commissioning ofthe FGD in order
to demonstrate the gas tightness of the absorber, air piping, flue , mist eliminator and
GGH.
The flue shall be temporarily sealed at the outlet of FGD and the soap solution test
sha lI be carried out with a forced draught fan or air compressor.
6.3.4 .2 .4 Unfired Pressure Vessels and Pipeworks
(a) Hydrostatic Tests
Hydrostatic test or pneumatic test shall be carried out on a lI unfired prssure vessels
and pipeworks by the Contractor in accordance with Vietnamese Regulation an d/or
ASME test code or equivalent.
For the purpose of the hydrostatic or pneumatic test , the Contractor shalJ provide
temporary seal , where necessary.
The hydrostatic tests of unfired

prssure

vessels , such as air compressor receivers shall

6-3-20

o MON THERMAL POWER PLANT

VIETNAM ELECTRJCITY / TEPSCO

be also inspected by the local authority.


(b) Lined piping
Lined piping shall be tested with the f10wing water in the piping.
(c) B uried Pipework
Notwithstanding any test perfonned at works , the pipework coatings shall be tested in
accordance with the mentioned below.
The protective coating shaIl be inspected visually while being applied.
After priming, coating and mapping operations have been completed, the surfaces
shaIl be tested with an approved electrical thickness detector. An y missed spots in the
coating shaIl be repaired with overwrapping.
6.3 .4 .2.5 Tank and Silo
(a) Li mestone Silo
The limestone silo shaIl be subjected to vacuum test in accordance with applicable
standard. Equipment used for the testing shall be subject to the approval by EVN.
(b) Slurry and Water Tanks
A Il ta(s operating at atmospheric pressure sha lI be tested for at the minimum 30
minutes by fiIIing to maximum level and being subjected to an additional hydrostatic
pressure of 15 mm Aq.
6 .3.4 .2.6 Rotating Equipment
(a) Rotating equipment such as fans , milIs, conveyors and pumps shaIl be subject to a
running test prior to commissioning for checking correct rotation , vibration and noise.
(b) Sound pressure and vibration levels emitted from equipment sha Il be measured in
accordance with approved codes and standards to demonstrate compliance with the
reqUJrements.
6.3.4.2.7 Lifting Equipment
(a) After the works have been completed, all lifting equipment shall be tested to confinn
correct operat lO n.

6-3-21

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

(b) Subsequent to the satisfactory completion ofthe above tests , the tests shall be repeated
in the presence of Authority in Vietnam.

t/

(c) The Contractor shall be responsible for preparing test blocks for the
6 .3.4 .2.8 Functional Tests

(a) All installed equipment shall be tested for correct operation and functioning.
6.3 .4 .2.9 Safety Valve Setting
(a) It shall be confirmed that the settings of all safety valves are properly made as required
by ASME Code or equivalent.
(b) All safety valves shall be gagged except the one to be set.
(c) For the auxiliary steamlsootblower safety valves , the setting will be made
manipulating the pressure controller for the auxiliary steam header pressure.
(d) Acceptance
(i) The principle of setting pressure of the safety valves shall be based on ASME
Unfired Pressure VesseI Code or equivalent.
(ii) The cIosing and popping pressures shall be judged based on ASME code, PG-72
and PG-72.2 or equivalent.
(iii)Lift value shall be not less than the design value.
6.3 .4 .2.10 Plant Load Tests
(a) After the plant is synchronized, the following tests shall be carried out to verify the
specified conditions.
(i) Automatic change over of all stand-by equipment.
(ii) Verification of stable operation at any load under the specified conditions.
(i ii) Instantaneous load variation test
(iv) Tripping of the plant at loads 25 %, 50 %, 75 % and 100 % of Rated Output and
BMCR.
(v) Capability ofHouse Load Operation
After raising th power plant load up to Rated Output, the unit shall be
disconnected from the network and it will remain in operation at "House Load"
feeding only the unit auxiliary service.
(vi) Rapid load reduction whn the load is above 50 % of Rated Output, manually

6-3-22

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

tripping of one booster fan or any other important auxiliaries


(vii) Any other tests required by EVN to check the specified conditions ofthe plant.

6-3-23

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

6.3.5 Performance Test


6.3.5.1 General
(a) After the commissioning of the plant is completd the performance tests including
auxiliary power consumption test shall be conducted by the Contractor to verify the
guaranteed or specified values ofthe equipment, in accordance with the requirements
ofClause 2. 1.1 3.
(b) Auxiliary power consumption test are specified in Clause 6.3.6.
6.3 .5 .2 Diesulohurized Flue Gas
(a) The Performance tests at site shall include the measurement and evaluation
demonstration ofthe following at 100 % Rated Output:

anor

(i) Desulphurization Eciency


Desulphurization efficiency at stack inlet shall be confirmed to meet the
guaranteed value of not less than 90 %.
S02 concentration in the flue gas , as measured at the approved representative
points selected by results oftraverses at FGD inlet and stack inlet.
Desulphurization efficiency is calculated by the following equation.
T)

={(Si-So)/Si}
where

100

= Desulphurization efficincy(%)
Si = S02 values at FGD inlet (kglh) on a dry gas basis
So = S02 values at stack inlet (kglh) on a dry gas basis

(ii) S02 Concentration at Stack lnlet


S02 concentration at stack inlet shall be confirmed to meet the guaranteed value of
not more than 500 mglm 3 (dry base , at 100 kP a, 298K).
S02 concentration in the flue gas, as measured at the approved representative
points selected by results oftraverses at FGD inlet and stack inlet.
(iii) Water Droplet Content
Water droplet content in the f1 ue gas , as measured at the approved representative
points selected by results oftraverses at mist eliminator outle t.
Water droplet content shall be confirmd to meet the guaranteed valu ofnot more
than 150 mglm 3N (dry base).

6-3-24

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

(iv) Flue Gas Temperature at Stack Inlet


Flue gas temperature, as measured at the approved representative points selected
by results oftraverses at stack inlet.
Flue gas temperature at stack inlet shall be confirmed to meet the guaranteed value
of not less than 91 0 C. It shall be proved by the theoretical calculation with the
temperature at stack inlet that the temperature at stack outlet is not less than 90 oC.
6.3.5 .3 Bv-oroduct Gvosum
By-product gypsum composition and quality shall be confirmed to meet the following
guaranteed values between 100 % Rated Output and 20% Rated Output:
Value, Description

Parameter
Pu rity (CaS04' 2H2 0)

Not less than 95 % (dry basis)

Particle size (Mean Particle Size)

Not less than 50 micron meter

Moisture content

Not more than 10 %

pH value

5 to 8

6 .3 .5 .4 Other Items ofPerformance Guarantee


(a) Other Items of Performance Guarantee shall be confirmed to meet the following
guaranteed values at 100 % Rated Output:
(i) Limestone/removal sulfur dioxide ratio
The ratio is calculated by the following equation.
Limestone/ removal sulfur dioxide ratio = Tc / (Tc - Co)
where Tc = total calcium concentration in absorbing slurry (mol/l)
Co = calcium carbonate concentration in absorbing slurry
(mo l/l)
(ii) Limestone consumption (1)
(iii) Make-up water consumption (t/h)

6-3-25

VIETNA 1

ELECTRICITY / TEPSCO

6.3.6 Auxiliary Power Consumption


6.3.6.1 Auxiliarv Power Consumption
(a) Electrical power consumption shall be measured in accordance with the provisions of
Volume 8 - Section 8.5.

6-3-26

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITYI TEPSCO

6.3.7 Final Acceptance


6.3.7.1 General
(a) The Contractor shall caY out inspection work prior to expiry of the waanty period
pursuant to Clause 2.1.15 and shall include the cost required in his Bid price.
(b) All defective work found during the inspection work shall be remedied free of charge
by the Contractor under the terms of the guarantee of the Contract. The costs of the
inspection work and replacement of any defective item shall be bome by the
Contractor. The Contractor shall submit to EVN an inspection schedule for approval
prior to the work.
(c) A Il inspection work will be witnessed by EVN. The Contractor shall prepare adequate
records , including a final report, of the inspection work and shall submit records to
EVN before issue ofFinal Acceptance Certificate.
(d) The Contractor shall submit the number and grade of personnel who wi lI be involved
in their specified inspection work and shalI state separately from those shown for
construction and commissioning work.
(e) As for the findings ofthe inspection, it may be necessary to operate the plant (either
individual system or complete unit) in order to demonstrate that the replacement of
parts or adjustment made during the inspection work are satisfactory. The time and
duration ofthose tests shall be agreed between the Contractor and EVN.
6.3.7 .2 Plant Inspection Prior to Final Acceptance
(a) The minimum requirements are listed below and the scope may, however, be
expanded depending on inspction findings.
Item
(i) Absorber and Tanks
P

e
3

(i ii) Agitators

Remarks/ Tvpe of Inspection


Open and check absorber/tank intemals.
Inspect each pump .
Inspect bearings .
Check the wear condition of casing liner
and impeller.
Inspect each agitator.

6-3-27

o MON THERMAL POWER PLANT

VIETNAM ELECTRICITY / TEPSCO

Inspect bearings .
Check the wear condition of impeller.
Check and inspect all seals gaskets for
wear or corros lO n.
Check bearings.

(v) Mist Eliminator

Check mist eliminator internals.

(vi) Booster Fan

Inspect bearings and runners .


Check fan balance.

(vii) Conveyor

Checkcon'veyo
r for wea
r.
.
Check drive for wear.

(viii) Oxidation Air Blower

Inspect bearings.

(ix) Valves, Piping and Fitting


Wh ere operational problems are encountered and leaks are suspected, such parts
shall be subject to disassembly and internal inspection. Valve stem and seats shall
be checked for cracks, erosions.
(x) Painting conditions as specified in Clause 2.2.1.13

6-3-28

r
JjJ
(

(iv) GGH

Você também pode gostar