Escolar Documentos
Profissional Documentos
Cultura Documentos
What is PPP
When PPP
Why PPP
PPP - Benefits
Financial Advantages
Long term assurance about the cost. Most PPP contracts
are long-term agreements with a term ranging from 20 to 30
years. Clients no longer need to provide advance financing,
but the investment sum is spread out over the term of the
project, offering long-term predictability of expenditure.
Total project costs are lower due to the optimal coordination
of design, construction, maintanance, operation and
supporting services over the contract term (life cycle
management)
Risks are placed with the parties best able to control them,
another cost-lowering factor.
PPP - Benefits
Qualitative and Operational Advantages
The client is assured of a high-quality and sustainable project
The client assumes only a general directive role, thus
requiring only a small internal project organisation mainly
limited to functional and performance specification and
contract issues. Client spends significantly less time on
technical specifications for the design and construction
process.
Timely delivery, Since the contractor effectively finances the
investment in the construction asset and only receives
payment when this is complete, this logically forms a serious
incentive for completing the construction phase in time.
PPP - Benefits
Performance Advantages
Risk allocation, both in terms of time and money, is agreed at
an early stage between the parties. The client contracts out
the services he requires according to clear and measurable
performance criteria.
If the quality of the services does not meet the agreed
performance requirement, the contractor is penalised by
reductions to his periodic payment. Contractors will therefore
make every effort to meet the agreed performance standards.
PPP Models
New Projects
Design Design
Design
Build
Build
Build
Maintain Operate
Public Responsibility
Service Management
Contracts Contracts
Design
Build
Operate
Maintain
Build
Own
Operate
Transfer
Build
Own
Operate
Private Responsibility
Objective of
Outsourcing/
PPP
Ownership of
Capital Assets
Responsibility
for Investment
Choice of
PPP Model
Assumption of
Risks
Duration of
Contract
Service
Contracts
Management
Contracts
Lease
Contract
BOT
Concessions
Financing
Investment
Public Sector
Public Sector
Public Sector
Private Sector
Private Sector
Financing
Working
Capital
Public Sector
Public Sector
Private Sector
Private Sector
Private Sector
Contractual
Relations
with
customers
Public Sector
Private Sector
on behalf of
Public Sector
Private Sector
Private Sector
Private Sector
Private
Sector
Responsibilit
y&
Autonomy
Low
Low
Low to
Medium
High to
Medium
High
Need for
private
capital
Low
Low
Low
High
High
Financial risk
for private
sector
Low
Low
Low to
Medium
High
High
Service
Contracts
Management
Contracts
Lease
Contract
BOT
Concessions
Duration of
Contract/
License
- 2 Years
3 5 Years
5 15 Years
15 30 Years
20 30 Years
Ownership
Public
Sector
Public Sector
Private Sector
Private then
Public Sector
Public Sector
Management
Mainly
Public
Sector
Private Sector
Private Sector
Private Sector
Private Sector
Setting Prices
Public
Sector
Public Sector
Contract or
Regulator
Public Sector
Contract or
Regulator
Collecting Bills
Public
Sector
Private Sector
Private Sector
Public Sector
Private Sector
Work Done/
Unit Price/
Lump sump
Proportions of
Tariff
Tariff
Tariff
Improve
Operating
Efficiency
Improve
Technical
Efficiency
Improve
Technical
Efficiency
Mobilise
Private Capital
and/ or
expertise
Mobilise
Private Capital
and / or
expertise
Mode of
Payment
Main Objective
of PPP
Inception
Feasibility
Study
Procurement
Edition and
publication of tender
documents
Engineering, design
and financial due
diligence
Selection of qualified
bidders
Evaluation of the
bids and negotiations
Identifications of
goals and priorities
Construction
Prior to construction,
creation of the SPV
and financial close is
reached
Operation
Operation of the
facility
Maintenance
Construction of the
infrastructure
End of contract
Awarding of the
contract
Types of Risk
All Risk
Government
Demand Risk
Commercial Risk
Demand side
operation Risk
Private partner
(government may
provide guarantee
to mitigate Risk
Supply side
operation Risk
Private partner
Construction
Risk
Private partner
Supply Risk
Project
Stakeholders
PPP
risk management
Project Life
Cycle
Risk
management
process
Pre - Qualification
Objectives & priorities; Defining of PPP Service
Technical, Economic, Commercial, Financial, Environmental
reviews;
Pre-feasibility study & Project Information Memorandum;
Bid evaluation criteria determined;
Prequalification notice issued
Tendering
Preparation of bid documents and contracts;
Preparation for detailed Information Memorandum for lenders;
Issue request for bids to Pre - qualifiers
Formation of SPC
Detailed negotiations on concession, PPA, FSA, etc.;
SPC formation and equity allocation;
Approve licences, taxation regime, etc.
Negotiate Government Undertakings
Concessionaire negotiates loan agreements
Financial Closure
Complete all necessary documentation and conditions
precedent
Typical Timeline
PreQualification
2-3 Months
Tendering
3-6 Months
Formation of
SPC
Financial
Closure
Negotiations
3 Months
3-9 Months
3-6Months
PPP Financing
Certain
Cash
Flow
Public
Guarantees
Bankable
PPP
Projects
Step-in
Provisions
Security
Output
Specification
Service
Delivery
Payment
Mechanism
Performance
Monitoring
Advantages
Disadvantages
Inherently complex
Higher development cost (time
and money) for government
Likewise, very significant bidding
costs for sponsors
Committed equity required
Funding Options
Debt
Equity
Bankable
PPP
Projects
Grants
Subsidies
Guarantees
PPP
Project
Financial
Structure
Project Cycle
& Cash Flows
Taxes
Financial Risk
& Flexibility
Cost of Capital
Developing
Cash Flow
Model
Capital Structure
Operating Cost
Assumptions
Revenue Stream
Analysis of
Financial
Indicators
Sensitivity
Analysis
Concessional Life
Inflation Rates
Interest Rates
Thank You