Você está na página 1de 14

INTRODUCTION

Shallow foundations represent the simplest form of load transfer from a structure to the
ground beneath. They are typically constructed with generally small excavations into the ground,
do not require specialized construction equipment or tools, and are relatively inexpensive. In
most cases, shallow foundations are the most cost-effective choice for support of a structure. A
shallow foundation is also known as an open foundation, since such foundation is constructed by
open excavation. Hence those foundations, which have depth even greater than its width, but are
constructed by way of open excavation also come under shallow foundations. Shallow
foundation can divided into three types such as pad footing, strip footing and raft footing.
Pad foundation tend to be the simplest and cheapest foundation type and are used when
the soil is relatively strong or when the column loads are relatively light. They are usually square
or rectangular on plan, of uniform thickness and generally of reinforced concrete. They can be
stepped or haunched, if material cost outweigh labour costs. The reinforcement can vary from
nothing at one extreme through to a heavy steel grillage at the other, with lightly reinforced
section being the most common.

PAD FOOTING

Strip footings are commonly used for the foundations to load bearing walls. They are also
used when pad foundations for number of columns in line are so closely spaced that the distance
between the pads is approximately equal to the length of the side of pads. It is usually more
economic and faster to excavate and cast concrete in one long strip, than as a series of closely
spaced isolated pads. They are also used on weak ground to increase the foundation bearing area.

STRIP FOOTING
A mat foundation consists of a single heavily reinforced concrete slab, which underlies
the entire structure or a major portion of the structure. It also known as Raft foundation. Mat
foundations are often economical when spread footings would cover more than about 50 percent
of the footprint of the plan area of a structure. A mat typically supports a number of columns
and/or walls in either direction or a uniformly distributed load. The principal advantage of a mat
foundation is its ability to bridge over soft spots and reduce differential movement. Structures
founded on relatively weak soils or light weight structures may be economically supported on
mat foundations. Column and wall loads are transferred to the foundation materials through the
mat foundation. Mat foundations distribute the loads over a large area, thus reducing the intensity
of contact pressures.

MAT/RAFT FOUNDATION

WORK PROCEDURE
Even though shallow foundation has a several types with different characteristics which pad
foundation, strip foundation, and mate or raft foundation but the work procedure is still same.
The procedure are such a sequence below;
1.
2.
3.
4.
5.

Site clearing
Setting out
Excavation
Waterproofing
Installation(formwork, support, strut, spacer block, rebar, starter bar, and other services

involved)
6. Carried out inspection
7. Concreting
8. Concrete curing
9. Dismantling formwork
10. Backfilling foundation
11. Compacting backfilled foundation

2.1 Site Clearing


Before the construction of the shallow foundation is doing, the location of the
construction site must be clear such as trees get cut down and thrown up to the roots before the

construction is start. After the site clearing is done, fill and compacted soil work will do to obtain
a the compact and flat platform surface so that it is not will be easily damaged for access roads to
facilitate entry and exit machineries to construction sites.

2.2 Setting Out


The position for the shallow foundation will be set accurately by surveyors and marked
using the baseline for the building according to plan layout on the drawing, for example
rectangular shape of building four corners then we marking the four corners of the building that
has been offset at least 2 meter to the behind of the line gridline and so the peg would be more
durable.
The profile board to be installed around the building site based on the baseline and the
fence height profile should be at the level of finish floor level and the level of finish floor level
should be marked on the peg. Pull the thread between 2 gridline to get the intersection point for
pad footing and mark it on the ground. The surveyor is required to obtain assurance that the pad
footing position is right.

2.3 Excavation Of Footing


After already identified the actual position of the pad footing, the excavation work is
carried out according to the size and depth required. Excavation work should be done below lean
concrete level.

2.4 Waterproofing
Waterproofing is done to avoid concrete loosing water-cement ratio during concreting
work. There are two common technique to do the water proofing work which by using plastic
sheet. Lean concrete to be poured after the excavation work is completed, lean concrete thickness
is in the range of 50mm or according to the required specifications. Lean concrete works
required is to get a flat platform and hard surface for ease of installation work of reinforcement

bar carried out and it also serves to prevent moisture in the concrete is reduced due to seep into
the ground.

2.5 Installation
After water proofing work done such as lean concrete, then it comes to installation work.
Materials include in installation work are such rebar, spacer block, formwork, support/strut,
form-tie, starter bar and any other services attach to foundation. Sequence of work are such as
follow;
i.
ii.

Install main formwork surrounding the footing as an actual size


Install support for the formwork to stabilize the main frame.

Formwork
Formwork means the surface of the form and framing used to contain and shape wet concrete
until it is self-supporting. Formwork includes the forms on or within which the concrete is
poured and the frames and bracing which provide stability. Although commonly referred to as
part of the formwork assembly, the joists, bearers, bracing, foundations and footings are
technically referred to as false work.
Design
The design of the final concrete structure can have a major effect on the ease of formwork
construction and the health and safety of people during construction. Generally the more basic
and simple the final concrete structure, the safer it is to construct, erect and dismantle the
formwork.
An experienced formwork designer should be consulted during the design of in-situ concrete
structures to enable the health and safety risks during formwork construction and dismantling to
be considered in the design.
The formwork designer must be competent in formwork design including documenting
temporary work platforms and special equipment needed for safe formwork construction on-site.
A designer may use a technical standard or a combination of standards and engineering
principles relevant to the design requirements as long as the outcome is a design that meets
regulatory requirements.

Formwork should be:

Rigid, watertight, braced and tied together to maintain position and shape during

construction , and
Able to be removed easily and safely without damaging the formed concrete, or have
components that remain as part of the finished structure so the rest can be removed
without damaging the structure.

GUIDE TO FORMWORK
Formwork drawings should include details of

Formwork and formwork joints


Sealing procedures
Ties
Size and spacing of framing
Details of proprietary fittings or systems proposed to be used, and
Air breakers, if used.

The formwork designer should determine the vertical pour rates for walls, columns and other
vertical concrete elements before completing the formwork design. Details of the construction
method and erection sequence should be included on the formwork drawings where appropriate.
Where special methods like external vibration are involved the formwork design should allow
for any resulting additional structural loads. Variations to a design of a system should be checked
and verified in writing by a designer, engineer or other competent person.
iii.

After that, prepare and install spacer block on the lean concrete inside of

iv.
v.

formwork. Thickness of the spacer block is depends on drawings specification.


Short way rebar then install before the long way
After that, long way bar was install and tighten with the short way by spacing

vi.

provided on specification.
Starter bar then install and tighten with the foundation rebar. Make sure lapping of

vii.

the starter bar for upper structure enough as per drawings.


After that is installation of other services that attach/punch through such as
sewerage pipe and cable for electrical used.

viii.

Then for bigger foundation, install form tie or strut to strengthen the formwork or
prevent formwork failure and concrete bulging.

However sequence of installation work was not necessary to follow as state above. It depends on
site condition that influence flow of work. Some criteria that may affect the flow of work is
materials, man power, weather, and also logistic on site.

2.6 INSPECTION OF WORK


When To Call For Inspection
When all form-work (boxing) has been completed, footings have been excavated and
reinforcement is in place.
What We Will Look At
Check that the siting of the building conforms with the building consent site plan. Boundaries
must be identified by location of boundary pegs or by survey. With building projects that are
critical in respect to distance from boundaries, height or daylighting requirements, building set
out must be confirmed by survey.

Footings are appropriate size and excavated to solid


Reinforcing is in place (size, spacing, laps and cover) adequately tied and secured and

conform with consent documents for ring foundations; sub-floor vents


That minimum floor levels/ground clearances can be achieved against datum
Advise on next inspection

What You Should Do


1

Ensure that boundaries are adequately defined


Ensure that building set out complies with consent documents
If required, a surveyors report is available
Approved plans and supporting documents are on site

Dont put us and the contractor under pressure by ordering concrete until after the
inspection has been carried out

After all

installation work have done, then inspection will be carry out before ordering a

concrete. Criteria that will be checked during inspection are:


i.
ii.
iii.
iv.
v.
vi.
vii.
viii.
ix.

Rebar
Starter bar
Spacer block
Size
Level
Position
Cleanliness
Materials for concreting work
Manpower

After inspection done, then concreting work will be proceed.

2.7 CONCRETING OF SHALLOW FOUNDATION


The design of the foundations will need to be approved by the Local Authority (Client
representative). The plans submitted for approval will detail the type and depth of the
foundations. However, prior to concreting the foundations, the excavation works will need to be
inspected and approved by the District Surveyor. Many factors have to be taken into account but,
during his site visit he will be establishing that the base of the trench is of good load bearing
capacity and that there are no adverse factors such as nearby trees which may affect the
foundations. Trees can draw a large amount of moisture from the surrounding ground and the
height and species of nearby trees will be taken into consideration so that there is no risk of
ground movement.
Concrete Specification
Also included in the plans approved by the Local Authority will be the specification for the
concrete mix to be used for the foundations. Mix ratios are commonly specified as a proportion
of cement : sand : aggregate. Typically this will be 1:3:6 for foundations such as those shown in

the accompanying pictures. This mix is 1 part cement : 3 parts sharp sand : 6 parts aggregate. In
practice, it is often easier to order ballast where the sand and aggregate is pre mixed. When using
readymix, mixes are specified by grade. You must ensure that the mix you use is as specified in
the approved documents.

Mixing Concrete Versus Ready Mix

Mixing the concrete by hand would not be practical for this job - even mixing concrete with a
mixer is a labour intensive process. Having concrete delivered by a ready mix lorry is the most
practical solution for anything more than a small volume. When ordering the concrete you will
need to specify what mix you require as well as agree a time slot for delivery. The amount of
concrete you are ordering will affect the price and remember that you may have to pay a
surcharge for any cubic metres less than a full load. There are also other preparations you will
need to make aside from ensuring that the work is absolutely ready before the lorry arrives. You
need to be sure that there will be room for the lorry to park up as near to the work as possible
the less barrowing the better. Talk to neighbours and if needs be mark out an area of the street
with cones in advance. The last thing you want is a load of concrete turning up and not being
able to offload it. The access route between the lorry and the foundation trenches should be
completely clear so that a steady flow of barrow loads can go back and forth.

Barrowing and Pouring Concrete


When the lorry arrives, make sure that you have enough people ready to barrow the
concrete to the excavations. You cannot expect the lorry to hang about so, if needs be, rope in a
few helpers. As a rough guide, a cubic metre of concrete is about 25 barrow loads and weighs
over 2 tonnes. The driver will set up the chute so that the concrete can be discharged into the
barrows. Hold the barrow steady as it is loaded concrete is heavy and can easily tip the barrow
as it drops in.

Remember that concrete can cause alkali burns so wear protective gear and avoid skin
and eye contact. The easiest way to work is have one person working the concrete as it is tipped
into the trench and two or three people barrowing it from the lorry. Work the concrete so that it
fills all the space without leaving any pockets, voids or trapped air. Use a shovel to work it into
place. The level for the top of the concrete should be clearly marked on site so you know when
youve reached it. Once the trench has been filled to this level, tamp the surface with a batten so
that it is flat and level ready to receive the brickwork when it has set.
As soon as all the concrete has been poured, clean up the area. There will inevitably be a
few slops and spills along the way and this will set hard if its not cleared up straight away. Use a
shovel to pick up any spilled concrete then thoroughly hose the area down. Make sure you
include the street where the lorry was loading the barrows.

2.8 CURING OF SHALLOW FOUNDATION


Curing is the maintenance of a satisfactory moisture content and temperature in concrete for a
period of time immediately following placing and finishing so that the desired properties may
develop . The need for adequate curing of concrete cannot be overemphasized. Curing has a
strong influence on the properties of hardened concrete; proper curing will increase durability,
strength, watertightness, abrasion resistance, volume stability, and resistance to freezing and
thawing and deicers.
Curing Methods And Materials
Concrete can be kept moist (and in some cases at a favorable temperature) by three curing
methods:
Methods that maintain the presence of mixing water in the concrete during the early
hardening period. These include ponding or immersion, spraying or fogging, and
saturated wet coverings. These methods afford some cooling through evaporation, which
is beneficial in hot weather.

Methods that reduce the loss of mixing water from the surface of the concrete. This can
be done by covering the concrete with impervious paper or plastic sheets, or by applying
membrane-forming curing compounds.

Methods that accelerate strength gain by supplying heat and additional moisture to the
concrete. This is usually accomplished with live steam, heating coils, or electrically
heated forms or pads. The method or combination of methods chosen depends on factors

such as availability of curing materials, size, shape, and age of concrete, production
facilities (in place or in a plant), esthetic appearance, and economics.
As a result, curing often involves a series of procedures used at a particular time as the concrete
ages. For example, fog spraying or plastic covered wet burlap can precede application of a curing
compound. The timing of each procedure depends on the degree of hardening of the concrete
needed to prevent the particular procedure from damaging the concrete surface
How Long Should a Concrete Foundation Cure Before Erecting the Building?
Between 3 and 9 days

Concrete should be allowed to cure from anywhere between three and nine days,
depending upon the temperature and moisture levels, according to the National Ready
Mixed Concrete Association. Lower temperatures and higher moisture levels result in a
longer curing time.

Seven to 28 days

According to Concrete Network, concrete should be allowed to cure for at least seven
days before it's built on. However, waiting longer will greatly reduce the risk of the
concrete cracking. Concrete continues to cure up to 28 days after it is poured, at which
point it reaches maximum strength.

Bottom Line

When a contractor or engineer is in charge of a project, follow the professional's advice,


since the result of curing is his responsibility, according to Builder Bill. For small,
nondocumented jobs, wait a minimum of three daysalthough seven days is better,
Builder Bill advises.

2.9 DISMANTLING FORMWORK OF SHALLOW FOUNDATION


Dismantling formwork should be done at least 12 hours after concreting or depends on
specification. Dismantling formwork of foundation can be done before cube test has pass
because it can give a better concrete curing after backfilling.

ERECTING, ALTERING AND DISMANTLING FORMWORK AND FALSEWORK


Formwork and false work should be systematically erected and dismantled by competent and
tied in progressively to stabilize the structure in accordance with the designers or
manufacturers instructions. Prefabricated formwork and false work should be erected and used
in accordance with the manufacturers instructions.
Where scaffolding is used to construct formwork and false work it must comply with the
requirements for scaffolding including using licensed of scaffolder.
Safe systems of work should be developed depending on the type and complexity of the
formwork and false work design. The system of work should seek to eliminate or minimize
risks, for example to:

Minimize working at height by assembling components on the ground

Provide safe temporary work platforms where work at height is required

Provide for the safe handling and operating of plant and equipmentlarge structures may
require scaffolding or mobile plant to be located on suspended floors
Provide suitable plant and material handling, placement and storage arrangements to
minimize manual tasks, and
Include regular inspection and maintenance.

Erecting formwork and false work safely


Erecting formwork and false work safely will include preparing the foundations and footings
where required, and erecting, altering and dismantling the formwork and false work including for
adequate access and work platforms in a way that minimize risk to workers and people who may
work on or near the formwork and false work.

2.10 BACKFILLING OF FOUNDATIONS


There are four key elements to proper backfilling:

Protecting the foundation wall from damage during backfilling


Using the right backfill materials
Compacting the backfill
Final finishing the subgrade to ensure that water drains away from the foundation

Done correctly, these four steps help to ensure that a well-built basement functions the way its
supposed.

Protecting the foundation during backfilling


The surest way to protect foundations from damage during backfilling is to backfill only after the
basement floor slab and the first-floor deck are in place. For the deck, sill plates should be bolted
down and joists nailed to the sill plate. This provides the restraint needed to make the
foundations strong enough to resist earth pressures caused by backfilling.

Choosing the right backfill material


Some people recommend backfilling with a free- draining granular material. When you dig a
hole in the ground for a foundation, water moves toward the hole just as it does in a well. A
granular fill makes it easier for water to move toward the foundation wall. And if the drain tile
system gets plugged, that could cause problems. avoid backfilling with large clumps of clay or
with soil full of roots, tree branches, or other organic materials .These materials wont compact
well and will hold a lot of water even if the ground slope is steep enough to carry surface water
away from the house. Splash blocks for downspouts dont usually carry water more than a foot or
two away from the foundation So most of the water that comes off the roof may still end up next
to the foundation if the backfill is porous.

2.11 COMPACTING THE BACKFILL


Compaction is needed to reduce the amount of soil settlement that occurs with time. Failure to
compact the soil can cause basement leakage even before the house is completed. In this case,
during rainy weather, water collected in the trough caused by settlement and started leaking
through shrinkage cracks in the foundation wall. Correcting the faulty drainage stopped the
leaking. Be careful when compacting backfill. Some compactors are powerful enough to damage
the foundation. One way to avoid this problem is to place the backfill in 6-inch-thick lifts and
have the laborers tamp it with foot pressure or hand rammers. Vibrating plate compactors also
can be used for granular backfill without damaging the foundation. It takes more time to compact

thin layers, but the method provides insurance against foundation damage and against call-backs
related to drainage problems.

3.0 CONCLUSION
Shallow foundation has 3 major types which are pad foundation, strip foundation, and raft
foundation.

Você também pode gostar