Você está na página 1de 4

FEED MILL 4 PROJECT:

Date:18/09/2014

report for Feed mill-04 Project


Sl.
No

Job Site location

Job Descripction

Balance

Finish

Total

Percentage

12

41.67

trusses erection

1
0
1
22

5
0
1
16

6
2
2
38

83.33
0.00
50.00
42.11

cat walk erection

227.2

59.76

365.2

16.36

Horizontal columns erection

40

32

72

44.44

Installation of elevator casing

2
14

14
2

16
16

87.50
12.50

Installation and fabrication of batch bin

27

36

75.00

Installation and fabrication of finish silo

23

24

95.83

Installation and fabrication of railings for stair

50.00

21

24

12.50

0
14
18
12
20

26

0.00

Full welding & vertical plate fixing of towers

Corn silos

Fabrication of steel structure upside the corn silo


Assembling of catwalk for corn silos
Assembling of conveyor downside of silos

Soya Warehose

Installation of belt assembly

Main Building

Installation of slide bin for finish silo


Painting of slide bin for finish silo/weigher batch bin

Painting Works

Sand Blasting

Painting of beams
Painting of columns
sand blasting of columns
sand blasting of beams

Total man
work

Remarks
continuation of welding works
continuation of fabrication
continuation of assembly
continuation of assembly
continuation of assembly
continuation of installation and
fabrication
continuation of installation
continuation of installation
stop
continuation of fabrication and
installation
continuation of fabrication
continuation of fabrication of
railings
continuation of intallation
painting for primer first

FEED MILL 4 PROJECT:


Date:20/09/2014
Daily Accomplishment report for Feed mill-04 Project
Sl.
No

Job Site location

Job Descripction

Finish

Total

Percentage

7
1
0
1
22
227.2
40

5
5
0
1
16
59.76
32

12
6
2
2
38
365.2
72

41.67
83.33
0.00
50.00
42.11
16.36
44.44

15

16

93.75

14

16

12.50

Installation and fabrication of batch bin

27

36

75.00

10

Installation and fabrication of finish silo

23

24

95.83

Installation and fabrication of railings for stair

50.00

21

24

12.50

26

0.00

Full welding & vertical plate fixing of towers

Corn silos

Fabrication of steel structure upside the corn silo


Assembling of catwalk for corn silos
Assembling of conveyor downside of silos
trusses erection

Soya Warehose

cat walk erection


horizontal column erection
Installation of elevator casing
Installation of belt assembly

Main Building

Installation of slide bin for finish silo


Painting of slide bin for finish silo/weigher batch bin

Painting of beams

Painting Works
Painting of columns

Sand Blasting

sand blasting of columns


sand blasting of beams

4
4
9
5
10

Full welding of flat form/braces/columns/beams

Total man
work

Balance

0
14
17

Remarks
continuaion of fabrication
continuation of fabrication
continuation of assemble
continuation of assemble
preparing for the materials
preparing for the materials
preparing for the materials
continuation of installation
stop
continuation of installation and
fabrication
continuation of fabrication
continuation of installation and
fabrication of railings
continuationf of installation of slide
bin
continue painting of primer

stop working, people transfer to steel


structure
stop working, people transfer to steel
structure
continue painting
continue painting

Você também pode gostar