PROJECT PROFILE
B. Proponents
Herbert Huyo
Anthea Fay Domail
Roche Amor Gador
Mary Cris Gacasan
Rose Catherine Go
C. Implementing Unit
Cebu Normal University Engineering Department
D. Project Site
ACAD building and Library building third floor
E. Project Duration
2 months (March 15, 2010 - May 15, 2010)
F. Project Cost
P 85, 000.00
A. INTRODUCTION
The amount of work students are given these days has made time a
commodity few are able to afford. Therefore, students no longer have the luxury
of spending time going to a distant, and difficult to access library building.
Instead, they turn to other sources, such as the internet, for information and
research materials. The problem with this, however, is that these online sources
are not always reliable sources of information. Aside from this, not all references
can be found online; in contrast, a wide variety of research materials and
references are easily available within the library for use by students if they had
the time to look.
The construction of a sky bridge will be beneficial not only for the students,
but for the university as well, as it provides a chance for the improvement of the
facilities available. With the active use of the library, the need for a wider, larger
range of reading materials and equipment will be necessary for the better
accommodation of its users. This will prompt a need for renovation and change
which, in turn, would lead to the improvement of the university.
B. RATIONALE
In order to improve the students’ access to the school library and its
resources, we propose the construction of a sky bridge. It will be a connection
from the ACAD building towards the library building. This will reduce the time and
energy the students spend in going to the library, and improve their number of
visits. Also, it will put the library’s available resources to use. With its increased
use, we may develop a need for the acquisition of more reference materials to
cater the students’ demand, as well as improve the facility. This will lead to the
further development of the university as a whole.
C. Project Description
A sky bridge connecting the third floor of the ACAD building to the third
floor of the library building is proposed to the constructed. Constructional
materials are to be used specifically cement, iron bars, and many others. This
would benefit all the users of the library, may they be students or faculty
members. Also, this would allow maximum utilization of the library.
D. Objectives
This project aims to provide easier access to the Cebu Normal University
library. Specifically, this aims to:
E. Significance
Through the construction of the sky bridge connecting the ACAD building
to the library building both in third floor, the following would benefit:
Students. Having a sky bridge connecting the ACAD building to the third floor of
the library building would enable the students easier and faster access to the
library. Lesser time is spent and lesser energy is required to reach the library
compared to climbing flights of stairs. Of course, this is only applicable to those
who are at the third floor of the ACAD building who wants to go to the library or
the other way around. It is a lot advantageous rather than to go down then climb
again.
Faculty. This would help them get various information from books in the library for
the discussion rather than stick to what the internet provides. If the library is this
inaccessible, the faculty would be discouraged to go and those resort to online
researches.
University. This would allow room for improvement. Having a functional library
means additional facilities and updated books to cope up with the demand.
F. Project Components
G. Implementing Schedule
SUMMARY OF CONSTRUCTION
Woodworks………………………………………………... P 9,390.00
Hardware…………………………………………………... P 920.00
Painting…………………………………………………….. P 5,868.00
Roofing…………………………………………………….. P 5,596.00
Steelworks…………………………………………………. P 12,000.00
+
______________________________________
P 64,981.40
30% Labor: P 19,494.42
+
______________________________________
Concrete Works:
Subtotal: P 25,300.00
Woodworks:
Subtotal: P 9,390.00
Hardware:
MATERIALS UNIT QTY UNIT AMOUNT
COST
Roof nails kilo 6 P 65.00 P 390.00
½ “O x 6” Machine kilo 10 P 53.00 P 530.00
bolt
Subtotal: P 920.00
Painting:
MATERIALS UNIT QUA UNIT COST AMOUNT
NTIT
Y
Semi gloss Latex gallon 3 P526.00 P 1,578.00
paint (yellow)
Enamel paint gallon 6 P477.00 P 2,862.00
Concrete primer gallon 3 P 234.00 P 702.00
Wood coal tar gallon 3 P242.00 P 726.00
Subtotal: P 5,868.00
Roofing:
Subtotal: P 5,596.00
Steelworks: