Escolar Documentos
Profissional Documentos
Cultura Documentos
1.0
Version
Date of Issue
14 May 2012
Document No.
HPC-NNBOSL-U0-000-RES-000018
TBA
NNB GenCo
2012 Published in the United Kingdom by NNB Generation Company Limited (NNB GenCo), 90 Whitfield Street - London, W1T
4EZ. All rights reserved. No part of this publication may be reproduced or transmitted in any form or by any means, including
photocopying and recording, without the written permission of the copyright holder NNB GenCo, application for which should be
addressed to the publisher. Such written permission must also be obtained before any part of this publication is stored in a retrieval
system of any nature. Requests for copies of this document should be referred to Head of Management Arrangements, NNB
Generation Company Limited (NNB GenCo), 90 Whitfield Street - London, W1T 4EZ. The electronic copy is the current issue and
printing renders this document uncontrolled. Controlled copy-holders will continue to receive updates as usual.
1273527(&7,9(/<0$5.('
^3,UHPRYHG`
Text within this document that is enclosed within curly brackets {} is AREVA
or EDF Commercially Confidential Information (CCI) or Personal Information (PI)
and has been removed.
TABLE OF CONTENTS
0
INTRODUCTION ................................................................................................................. 4
0.1
Purpose............................................................................................................................... 4
0.2
Scope .................................................................................................................................. 4
1.1
Phase I Individual System Tests.................................................................................... 5
1.1.1 Construction Tests ............................................................................................................ 5
1.1.2 Individual System Tests .................................................................................................... 5
1.2
1.2.1
1.2.2
1.2.3
1.2.4
1.2.5
2.1
Phase III Power Escalation Testing ............................................................................... 8
2.1.1 Initial Start-up..................................................................................................................... 9
2.1.2 Operational Testing (Power Raise Tests) ........................................................................ 9
3
3.1
References........................................................................................................................ 10
3.2
Abbreviations ................................................................................................................... 10
FIGURES ........................................................................................................................... 12
LIST OF FIGURES
Figure 1: Plant Commissioning Programme (Overview) ...............................................................12
Figure 2: Plant Commissioning Programme (Principles) ..............................................................13
INTRODUCTION
0.1
Purpose
Commissioning tests serve as a progressive transition between erection, installation and
the start of normal operation of the various plant systems. These tests may take place at
the manufacturers or suppliers works, on specific test facilities or on the power station
site. The choice depends on the type of equipment, level of a systems integration that
can be simulated off-site (e.g. Instrumentation and Control (I&C) systems) and on the
ability to obtain specific conditions on-site (e.g. for qualification of accident transients)
[Ref 1].
The method of defining commissioning tests is chosen with the following objectives:
x
To ensure that plant commissioning does not compromise nuclear and/or industrial
safety,
To ensure that all operational aspects of system functions are tested, including safety
classified functions, taking into account and credit for, manufacturers, and/or off-site)
tests,
The main purpose of commissioning tests is to ensure that plant systems will perform
according to their design intent and satisfactorily meet the required safety function as
stated in the safety case.
The test programme is based on reference documents that define and describe the
systems related functional aspects and specifications. This reference material is
obtained from manufacturers information, plant systems manuals and design
specifications.
0.2
Scope
A phased approach is employed for plant commissioning. It is conducted from the
completion of erection activities to full power commercial operation. It is organised into
two test categories [Ref 2 and 3] and is carried out in three main phases:
x
Plant commissioning tests cover all testing performed on the installed plant and
equipment. Safety-classified Structures, Systems and Components (SSC) are
specifically tested to ensure correct operation as specified in the design requirements.
The following description gives a preliminary overview of the plant commissioning
programme. Only the main test phases are listed, as a detailed commissioning
UNCONTROLLED WHEN PRINTED
1.1
1.2
Pump water into the vessel to prove RIS/RRA [SIS/RHRS] flow orifices are of the
correct size,
Accumulator discharges, functional Safety Injection Low and High Pressure pumps,
Verify RIS/RRA [SIS/RHRS] and CAE flow rates and control functions,
Loss of Offsite Power and transfer to Emergency Diesel Generator supplies (BAS).
Preliminary Chemical and Volume Control System (CVCS [RCV]) mid loop testing,
Performance of primary hydro pressure test to verify leak tightness and integrity of
RCP [RCS] and high pressure pipework sections,
Initial preparations of the RCP [RCS] and related systems for the start of Hot
Functional Testing.
To safely cool down to ambient conditions from MCR and other control locations,
Reliability and endurance running of the station under normal operating conditions.
Pre-Service Inspection (PSI) of the Reactor Pressure Vessel (RPV) before CFT,
Containment Structural Over-pressure Test (SOT) and Integrated Leak Rate Test (ILRT)
are also carried out during this phase.
x
SOT is to demonstrate that the primary containment structure and its closures have
the ability to withstand successfully a test pressure and that the structure behaves in
accordance with design predictions.
Final construction, inspection and testing of those systems not required for HFT, but
are required for fuel load,
Activities may be brought forward or carried out in parallel to mitigate risk to later stages
of testing. Activities will be planned such that they do not impact on the systematic
confidence building approach to commissioning nor breach any consent hold points.
2.1
Standard start-up tests, which are designed to verify the correct operation of the
plant and compliance with the design intent.
Testing that is repeated at different power levels during power ascension testing (e.g.
core physics and control systems tests) to confirm that the design assumptions are
valid and support the safety analysis.
Operating procedures and test surveillances. These are the normal station operating
procedures widely used during the start-up tests. These procedures and
surveillances are validated and used during this time. Fault and accident procedures
are validated during the plant commissioning. The off-normal procedures for faults
and design basis accidents are validated on the replica simulator prior to plant
testing.
Tests which gradually exercise the plant in a progressively searching and onerous
manner.
System tests,
Transient tests.
There is normally a period of continuous full power commercial operation before the final
rating certificate is issued.
2.1.2.1 System Tests
Power raise tests are normally structured to manoeuvre the plant to ever increasing
power levels and plateaus. The plant is then stabilised while a series of tests are carried
out. A number of tests are carried out during each plateau. These tests are designed to
confirm proper operation at lower core power levels before subjecting the plant to more
rigorous testing at higher power levels.
The major power plateaus can be at a nominal reactor power of 30, 48, 75 and 100 per
cent. Typical tests at these power levels are as follows.
x
Radiation surveys,
Raising reactor power step by step is supported on the secondary side by taking steam
via the atmospheric steam generator dump system, then to condenser steam generator
dump system and finally to the turbine leading to the synchronisation of the alternator
and raising electrical power output to 100 per cent full power.
UNCONTROLLED WHEN PRINTED
Physics testing,
Transient testing; remote shut down, turbine trip, turbine load rejection, station black
out/turbine trip, reactor trip and National Grid response testing.
3.1
References 1
3.2
1.
2.
3.
4.
Abbreviations
Term / Abbreviation
Definition
CAE
Containment Spray
CEC
CFT
DBA
DIN
EFCO
FOAK
First of a Kind
GDA
HFT
I&C
ILRT
BC may show a more recent version, version history can be used to locate specific versions.
Definition
ISI
In-Service Inspection
LC
MCR
NNB
SSC
PSI
Pre-Service Inspection
RCP [RCS]
RCP
RIS [SIS]
RIS/RRA [SIS/RHRS]
RPV
SOT
FIGURES
FACTORY
INTEGRATION
TESTING
(FIT)
CONSTRUCTION
ANDERECTION
ONSITECOMMISSIONING
PREOPERATIONALTESTING(NONACTIVECOMMISSIONING)
PHASEISYSTEMTESTS
PHASEIIPRECORELOADINGTESTS
I.1
I.2
I.3
II.1
II.2
II.3
II.4
SETTING
SITE
SITE
COLD
PREPARATION
HOT
PREPARATION
TO
ACCEPTANCE INTEGRATION FUNCTIONAL
FORHOT
FUNCTIONAL
FORFUEL
WORK
TESTING
TESTING
TESTING
FUNCTIONAL
TESTING
LOAD
(STW)
(SAT)
(SIT)
(CFT)
TESTING
(HFT)
STARTUPTESTING(RADIOACTIVECOMMISSIONING)
PHASEIIIPOWERESCALATIONTESTS
III.1
III.2
III.3
III.4
FUEL
PRE
CRITICALITY
POWER
LOAD
CRITICALITY
TESTING
ESCALATION
TESTING
TESTING