Escolar Documentos
Profissional Documentos
Cultura Documentos
yiningh@kth.se
2
jema@kth.se
goran.engdahl@ee.kth.se
*
lars.liljestrand@se.abb.com
I. INTRODUCTION
With fast growing penetration of photovoltaic (PV) as well
as other distributed power generation, the impact of PV on the
grid and vice versa is under discussion. There are a number of
concerns and possible problems as the distributed generations
reach a high penetration. Such problems comprise flicker [1]
[2], harmonics distortion [3], and voltage rise effects [4].
The voltage rise in the LV distribution grid is one of the
most frequent concerns in the leading countries of residential
PV market. Unlike the loads in an LV distribution grid, that
occur at statistical varying times and thus smoothen the peak
load of the system, the PV production occurs almost
simultaneously in all residential PV systems connected in the
same area. The increased reversed power flow might result in
voltage drops along the distribution feeder and a voltage
above the allowed limits at the end of the feeder. This overvoltage depends on solar irradiation, installed PV capacity,
A. Voltage Requirement
In an LV distribution grid, the nominal line-to-line voltage
level is 400 V. The required voltage range at operation is
400V 10% and applies to every household and every part of
the LV distribution grid.
B. Swedish DSOs regulations:
In Sweden, the companies selling electricity to the
consumers also offer the possibility to buy the excess
production if one installs a PV system. If the annual
consumption is larger than the annual production of electricity,
the grid tariff for the PV system is 0 SEK. If the annual
production exceeds the consumption, the tariff increases to
1875 SEK [8] because they are considered producers of
electrical energy rather than consumers.
For example E.ON, who has a large part of the Swedish
electricity market, offers to buy as much as 43.5 kW PV
production from one individual household since the
distributed PV generation is consumed locally and the grid
loss is then decreased. 43.5 kW is set based on the limit
current of a fuse in one Swedish household [9].
The price for purchase of PV production usually includes
two parts: compensation for the reduced losses in the grid and
payment for the electrical energy. An example is that in
Stockholm, E.ON pays 5.6 re (Swedish currency) per kWh
PV production as the compensation of reduced grid loss and
the spot price on Nord Pool minus 4 re as the electricity price
[8].
III. THE GRID AND ITS MODEL
The studied grid is located in an urban area in Vsters,
Sweden, about 100 km west of Stockholm. It consists of a
primary and secondary distribution grid. The primary
distribution grid is a 10 kV MV grid in the background which
is part of the simulation but omitted in this paper. The
secondary distribution grid is the targeted LV distribution grid
in this paper.
A. The Grid
The single-line diagram of the LV distribution grid [10] is
presented in Fig. 1. It shows the network design and grid
configurations of the targeted LV distribution grid. It is
composed of a 1.6 MVA secondary substation, 9 sections of
power cables, 12 buses, and 11 aggregated loads. Each load
resembles an accumulation of a number of flats, supermarket,
school, day-care center of kids and/or offices. The loads are
assumed as balanced three phase loads (residential-,
commercial-, or mixed-type) operating at a power factor of
0.9 lagging. The residential part of the 11 aggregated loads
consists of 450 flats. Each bus connects different sections of
power cables, loads and/or the secondary substation. The 12
3.5
3
2.5
kWh
2
1.5
Fig. 4. Voltage profile of the winter case
1
0.5
0
1
9 11 13 15 17 19 21 23
D. ZEH Case
This case presents the behavior of the grid if the PV
installations are pushed to the extreme. The voltage profile is
shown in Fig. 10 and the active power flow in Fig. 11.
Fig. 10 shows that the bus voltages have a larger range
compared to the summer base case. The bus voltages are
between 0.97-1.094 pu except Bus 1 that is almost unchanged.
The voltage at Bus 11 reaches 1.094 pu, which is very close to
the upper limit of 1.1 pu, but all buses have voltages within
the specified limits.
Fig. 11 shows that the mismatch between PV generation
and load results in the negative active power flow at all buses
except Bus 5 and Bus 6, which are connected to commercial
loads and involve no households. At Bus 1, the peak of total
active power flow of the LV distribution grid reaches minus
0.6 MW. Such an active power flow is larger than 0.5 MW of
the summer base case, but it means the total apparent power is
still far lower than the load capacity of 1.6 MVA.
If the commercial loads at buses 5 and 6 are removed from
the LV grid, the active power flow results in Fig. 12. The total
power flow of the LV grid goes beyond 0.9 MW, the peak
Case
Fig. 10. Voltage profile of the ZEH case
winter case
summer base
case
Peak-peak
case
ZEH case
Maximum
Voltage
[pu]
0.9919
0.9989
1.0159
1.0942
Time
[Hr.]
4am5am
12pm1am
9am10am
10am11am
Minimum
Voltage
[pu]
0.9298
0.9735
0.9735
0.9735
Time
[Hr.]
7pm8pm
8pm9pm
8pm9pm
8pm9pm
Fig. 13. Hourly active power flow at Bus 11 in the four cases
TABLE II
Case
ZEH case
Active Power
Flow [MW]
-0.1217
-0.2336
-0.2735
-0.2892
-0.2915
-0.1428
-0.1912
-0.0800
Time
[Hr.]
8am-9am
9am-10am
10am-11am
11am-12am
12am-1pm
1pm-2pm
2pm-3pm
3pm-4pm
TABLE III
SUMMARY OF TRANSFORMER LOADING
Case
winter case
summer base case
Peak-peak case
ZEH case
Total Loading
at T1
[MWh]
6.2922
3.7424
3.1229
3.1353
Total Loading
at T2
[MWh]
8.7917
5.2948
4.2952
4.5550
VII.
CONCLUSION
This paper performs simulations of a real low and medium
voltage network in the city of Vsters in Sweden. The
simulations show different scenarios of PV penetration and
none of the cases show problems with over-voltages above the
limit of 10% above the system voltage. However, during
summer days with high PV production and low loads in the
system, the currents might reach levels above the capacity of
the installed cables. The power flow in several buses show
values above the highest flows of the winter case.
The system is partially saved by the mix of commercial
loads and domestic loads since the mismatch between the
domestic loads and PV production in the middle of the day is
compensated by the commercial loads. If the commercial
loads would be disconnected or equipped with PV systems,
the voltage levels and power flow through the distribution
transformers would be close to or beyond their limits.
Even with the highest penetration, the loading of the
distribution transformer decreases. This is thanks to the
commercial loads that consume power also during the day and
are considered not to produce any power. Hence the DSO or