Escolar Documentos
Profissional Documentos
Cultura Documentos
3.
4.
5.
6.
Contingency
Though EPC contract is a fixed price contract, it includes a financial currency component, a cost contingency of 4% has been provided
of the project cost, (excluding financing cost, IDC and margin money for working capital). The contingency provision is expected to
cover any increase in project cost, including increase in township cost and establishment cost due to increase in cost of raw materials
like cement, steel, iron, etc.
As set out in the Project Cost Estimate Report of DCPL, the break up of the project cost for Identified Projects other
than Rosa Phase I are set out below:
(Rs. in million)
Item
Rosa Phase II
Land(i)
Butibori
Sasan
Shahapur Coal
Urthing Sobla
Nila
100.0b
6,130.0c
480.0d
100.0f
1,300.0
1150.0
10,900.0
3,020.0
10,950.0
19,000.0
10,600.0
118,050.0
35,200.0
5,900.0
1,900.0
1,050.0
17,900.0
4,400.0
2,600.0
900.0
550.0
2,100.0
2,000.0
300.0
700.0
150.0
220.0
1,000.0
150.0
800.0
450.0
5,650.0
1,900.0
800.0
N.A.
N.A
22,470.0
N.A
N.A
24,600.0
14,050.0
183,420.0
48,000.0
20,800.0
(ii)
(vii)
Contingency
Land
a.
b.
c.
d.
f.
No additional land requirement as the land procured for Rosa Phase I is estimated to be sufficient for Rosa Phase II.
Estimated land requirement 225 acres
Estimated land requirement for the power plant 3,990 acres
Estimated land requirement 1,198 acres (485 hectares)
Estimated land requirement 618 acres
37