ASSIGNMENT

Do the rate analysis of following materials:Cement Pointing 1:4- unit 1 sq.m. - take 100 sq.m.
12mm cement plastering in ceiling 1:4 with coarse sand- unit 1 sq
m. Take- 100 sq m

Solution:
a) Cement pointing 1:4 -unit 1 sq.m.- take 100 sq. m.
Pointing in block work total dry volume of material = 0.64m3 for 100 m2

For 1:4 cement mortar:

Cement : 0.64/(1+4)= 0.128 m3 = 0.128/0.0347 = 3.68 bag say 4


bag cement
Note: cement density = 1440kg/m3, ie one 50kg bag = 0.0347m3

Sand : 4 x 0.128m3 = 0.512 m3

Page 1 of 4

b) 12mm cement plastering in ceiling 1:4 with coarse sand Unit


1 Sq.m. Take Sq. m.

Wet mixed mortar for uniform layer


= 10x10x0.12m
1.2m3
20% increased to ceiling uneven surface = 1.2x1.2
1.44

=
=

Page 2 of 4

Dry volume of mortar , 25% increased


m3

= 1.44x1.25

= 1.80

For 1:4 cement sand mortar:

Cement = 2/(1+4) = 0.40 m3 = 0.40/0.0347= 11.52 bag = 12


bag cement
Note: cement density= 1440kg/m3, ie; one 50kg bag = 0.0347 m3

Sand

= 4x 0.40 m3 = 1.60 m3 sand

Page 3 of 4