Escolar Documentos
Profissional Documentos
Cultura Documentos
Commissioning Procedure
Compiled by:
Reviewed by:
Approved by:
2014
Catalogue
1. OVERVIEW ...................................................................................................3
2. MAIN EQUIPMENT TECHNIQUE SPECIFICATION...3
3. COMMISSIONING BASIS AND STANDARD .....................7
4. COMMISSIONING PURPOSE ...........................................................8
5. COMMISSIONING CONDITION..................................8
6. COMMISSIONING PROCESS AND METHOD.......8
7. COMMISSIONING INSTRUMENT AND EQUIPMENT
.....................................................................................................................................11
8.
ASSESSMENT STANDARD....................................................................................11
9. ENVIRONMENT, OCCUPATIONAL
HEALTH AND SAFETY CONTROL PROCEDURE...........................................12
10 ORGANIZATION AND DIVISION..............................................12
11. APPENDIX..................................................................................................15
Boiler IDF and System Commissioning Procedure
1.
Overview
ZMTP 2150MW
2510t/h
The project is Zambia ZMTP 2150MW coal fired power plant, located at
Maamba coal mine, Sinazongwe, Southern Province. The boiler is produced by
Dongfang Boiler Company, which is 2*510t/h high temperature, super high pressure
circulating CFB boiler. Here the procedure is for the boiler IDF and system
commissioning.
Each boiler is matched with two sets of centrifugal IDF, controlled by damper
and hydraulic coupling; two sets of centrifugal PAF, controlled by damper and
hydraulic coupling; two sets of centrifugal FDF; controlled by damper and hydraulic
coupling; three sets of HP fluidized blower, controlled by motor butterfly damper and
3
hydraulic coupling, which are all produced by Shanghai Blower Works Company.
2.
2.1
Boiler specification
Zambia MCL 2150MW Coal Fired Power Plant 2 510t/h
150MW
Zambia MCL 2150MW Coal Fired Power Plant is provided with two sets of
510t/h super high pressure, natural circulating CFB steam drum boilers, which is
single furnace, single medium reheating, thermal isolation cyclone separator, tubetype air preheater, balanced draft, end part double flue, suspension structure, halfunsheltered layout, solid state deslagging, complete steel structure, matched with
150MW condense turbine-generator. The boiler adopts CFB combustion and
limestone desulfurization technique that low pollution and high efficiency.
Item
Unit
T/H
BMCR
BECR
510
485.73
MPa
14.32
14.32
Main steam temp.
LP RH inlet pressure
LP RH inlet temp.
HP RH inlet pressure
HP RH inlet temp.
RH flow
Feed
water
temp.
exclusive all HP
#1
Feed
water
temp.
exclusive #1 HP
#2
Feed
water
temp.
exclusive #2 HP
(LHV)
Boiler
guaranteed
efficiency (LHV)
Boiler
desulfurization
efficiency
540
540
MPa
2.85
2.85
334
334
MPa
2.7
2.7
540
540
T/H
420.42
400.4
248
248
171
228.6
207.3
90
92.3
2.2
Fan technique parameter
IDF system mainly comprises following equipment: two IDFs, two IDF
motors, two hydraulic couplings, two sets of auxiliary equipment of hydraulic
5
Mode: centrifugal
1854AZ/1715
Type: 1854AZ/1715
Blade mode: dual-draft mode, wing shaft blade.
2
Rotation direction: two sets turn to right, while two sets turn to left (see from
motor to air fan)
24
Layout mode: symmetry laying, two sets for each boiler, and total four sets for
the project.
1150SVNL
Hydraulic coupling type: 1150SVNL
STMKK50-6L
The fan is mainly composed of shell, admission box, air inlet, transmission
mechanism, blade wheel, bearing, control mechanism, etc. The fan is linked by
junction box and hydraulic coupling, driven by motor, which the type is STMKK506L, produced by Xiangtan Motor Company.
1
Sheet 1: IDF design parameter
Performance
IDF flow
Inlet temp.
pressure
Pa
point
Nm /h
3
TB
T, B point
load
pressure rising
Pa
425020
153.4
-7461
7700
354185
138.4
-5181
5300
BMCR
Design
(BMCR)
2
Sheet 2: IDF regulation
No.
Manufacturer filling
Item
1
Mode
Dual-draft,
supporting, centrifugal
2
88.7
%
Guaranteed
pressure)
point
88.6
efficiency
(full
kg/h
Quality flow (kg/h)
548401
dual
m3/h
764856
8207
148.8
working
1900.9
condition
TB
Selec
8
ted
9
TB
10
kg/h
457040
599004
1082.3
133.8
working
1045.7
condition
11
12
13
BMCR
Calculat
ed
14
15
(BMCR)
Q235A
16
Shell material
mm
10
17
45#
18
Shaft material
/
15MnV
19
10
20
9000
21
35000
22
23
Bearing mode
Rolling bearing
24
25
Manufacturer
Xiangtan motor
YKK710-6
Type
kW
2100
6600
29
Voltage (V)
r/min
980
30
IP55
31
Protection grade
32
Cooling code
Air-air cooling
33
Bearing mode
Sliding bearing
26
27
28
Drive
n motor
Neutral
34
point
current
Dalian Zhongguang
transformer
3
Sheet 3: hydraulic coupling performance parameter
9
Name
Unit
Rated load
Max.
Design value
KW
Output power
Slip
KW
Slip loss
KW
Fixed loss
KW
Input power
r/min
Input speed
r/min
Output speed
Rotation
direction
Driving shaft
Driven shaft
Speed
control
range
As
per As
operation
operation
plan
plan
Working
oil
pump mode
per
Name
mode
Unit
Rated load
Max.
Design value
Working
MPa.g
oil
pressure
l/min
MPa.g
Oil cooler
MPa.g
Design
pressure
of
pressure
of
OC
Design temperature of
working oil cooler
OC
Design temperature of
lube oil cooler
Cooling
area
m2
of
Shall be submitted
11
Name
working oil
Unit
Rated load
Max.
Design value
after
signing
agreement.
m2
Shall be submitted
oil
after
signing
agreement.
Cooling water
Water
flow
t/h
of
Shall be submitted
after
MPa.g
agreement.
Cooling
Shall be submitted
pressure
water
drop
of
after
signing
signing
agreement.
t/h
Shall be submitted
cooler
after
MPa.g
agreement.
Cooling
Shall be submitted
water
after
oil cooler
agreement.
signing
signing
Introduction:
1.TB(test block)
TB (test block): allowance shall be reserved for air flow and pressure in TB
working condition.
2.BMCR BMCR
12
3.
4.
Commissioning purpose
4.1
In order to guide and regulate system and equipment commissioning, and put into
operation safely and normally, hereby the procedure is compiled.
4.2
Check electric and I&C protections interlock and signal devices, and confirm the
action reliability.
4.3
Check equipment operation and systems performance, find and remove the possible
problems.
5.
Commissioning condition
1
condition completely for the system as per appendix 1 content and make recording.
6.
IDF system commissioning work can be carried out as per following flow chart:
Technique handover
Condition confirm
completed.
Safety condition are satisfied.
15
Interlock protection
Alarm test
alarm test
6.1
Actuator check
6.1.1
Check and accept motor air valve dampers, record data;
16
6.1.2
Check and accept motor control air valves, record data.
6.2
Thermal signal check
6.2.1
Check and accept analog and switching value signal, record data.
6.2.2
For above signal, on site position shall be considered to analyze the reality of
collected signal, if not, response and suggest to construction unit.
6.2.3
Air fan emergency button test.
The air fan emergency button erection and wire connection shall be complete
and correct, and the emergency button simulation test can make air fan trip.
6.3
Interlock protection and alarm signal check
6.3.1
IDF power switch shall be at test position.
6.3.2
Check following items:
DCS DCS
Start IDF on DCS with correct response;
DCS DCS
Shutdown IDF on DCS with correct response;
6.3.3
17
g)
Air valves and dampers shall be checked and qualified.
h)
I&C erection and verification shall be qualified.
i)
Interlock protection driving test related to IDF shall be qualified, and protection
and alarm setting shall be completed.
18
j)
k)
IDF emergency button driving test shall be completed and qualified.
l)
m)
Insulation resistance of the motor shall be measured and qualified.
6.3.5.2
Protection or interlock that does not affect safety shall be cut off and recorded.
6.3.5.3
IDF startup preparation
a)
Carry out check as per auxiliary code before startup, which shall be qualified.
b) CRT
Confirm that IDF inlet and outlet dampers shall work well, and local opening shall
be identical with CRT display.
c)
Confirm that IDF bearing is filled with qualified lube oil.
6.3.5.4
Switch on IDF power and check
a)
Whether IDF rotation direction meet design requirement or not;
b)
Whether exist abnormal sound or not;
c)
Whether the system exists obvious leakage or other abnormal situation.
6.3.5.5 30
19
DCS
If no abnormal situation, restart IDF after 30 minutes, then gradually control
parameter of IDF control damper and hydraulic coupling, supervise IDF current to
prevent overcurrent operation. Record all operation parameter (local and DCS data
shall be recorded separately).
6.3.5.6
Operation parameter shall be supervised during operation, which shall be in normal
range.
6.3.5.7
Check the system leakage and air channel vibration.
6.3.5.8 8
IDF and its system commissioning shall be kept for 8 hours, then shutdown the IDF
and record the idle hour.
6.3.5.9
After IDF shutdown, cut off IDF power.
6.3.5.10
The air channel shall be freely flowing to prevent vibration caused by air valve
misoperation closing.
6.3.6
System operation during the complete set operation
6.3.6.1 168
The system reliability shall be checked as per no load stage, on-load stage, full load
stage and 168 hours operation.
6.3.6.2
The system dynamic control.
6.3.6.3
20
The equipment supervision shall be enforced during system operation, especially
during furnace negative pressure control to ensure that the system in optimal
operation condition.
6.3.6.4
Fill in commissioning record.
7.
Vibration gauge
Revolution meter
Clip-on ammeter
Phonometer
8.
21
100% 90%
The air fan operation shall be stable and normal; bearing bush temperature and
vibration, cooling water system and motor coil temperature are normal.
Professional commissioning staff and supervisor shall strictly check and control
the important process of commissioning quality, and report to higher level leader
when find out any problems to solve it under coordination to guarantee operation
successfully.
9.
Environment, occupational health and safety control procedure
9.1
When IDF and its system first startup, relevant staff shall be on equipment site to
supervise strictly with reliable communication to control room.
9.2 ,
When IDF test running, startup time and current shall be supervised strictly,
22
On-site safety regulation shall be carried out strictly by all commissioning staff
to guarantee the reliability.
9.6
If abnormal situation happens during the commissioning, instantly adjust it and
report it to headquarter.
9.7
Pay attention on supervising change of bearing vibration and temperature to
prevent heavy accident.
9.8
Safety helmet shall be worn during on-site commissioning, and possible danger
work shall be analyzed by person in charge on site and eliminate hidden danger.
9.9
Relevant systems, such as inlet and outlet flue channel, ESP, desulfurization,
denitration, steel inner shell of flue, etc. shall be closed and checked to ensure
that there are no person in above area.
23
10
10.1
Erection unit
10.1.1
In charge of organization of subsystem commissioning.
10.1.2
In charge of the system isolation and closing.
10.1.3
In charge of maintenance, overhaul and troubleshooting of commissioning
equipment.
10.1.4
Prepare necessary overhaul tools and material.
10.1.5
Coordinate with the commissioning unit to carry out subsystem commissioning.
10.1.6
In charge of temporary mark on relevant system and equipment.
10.1.7
In charge of check and acceptance after subsystem commissioning.
10.2
Construction unit
10.2.1
In charge of equipment startup, shutdown, operation control and accident elimination
during the commissioning.
24
10.2.2
In charge of formal mark for relevant systems and equipment.
10.2.3
Prepare operation regulation, tools and record sheet.
10.2.4
In charge of inspection and normal maintenance for commissioning equipment.
10.3
Commissioning unit
10.3.1
In charge of compiling commissioning procedure and technique handover.
10.3.2
Prepare relevant measuring instrument, apparatus and tools.
10.3.3
Engage in subsystem commissioning.
10.3.4
In charge of test data recording and filing.
10.3.5
Fill in inspection and qualification sheet of commissioning quality.
10.3.6
Engage in check and acceptance after subsystem commissioning.
10.3.7
In charge of compiling commissioning report.
10.4
Supervisory company
10.4.1
In charge of supervisory work during starting and commissioning as per the contract,
25
26
11.
Appendix
1
Appendix 1: Checking list for IDF commissioning condition
Checking content
Requirement
Remark
Date
Result
No.
1-1
27
Checking content
Requirement
Remark
Date
Result
No.
1-2
Complete
Complete
Normal
bearings
1-5
1-6
Complete,
closing
document is accepted.
1-7
Complete,
closing
document is accepted.
2-1
28
Checking content
Requirement
Remark
Date
Result
No.
2-2
Flexible
operation,
correct direction.
2-3
Measuring meter
2-4
Test is qualified.
Electrical
protection,
and
interlock
I&C
and
signal device
2-5
Qualified
control
and
correct direction.
2-6
3-1
Power
Reliable
On-site road
sufficient
illumination
and
emergency illumination.
4-1
On-site
communication
equipment
4-2
Firefighting facilities
Sufficient
29
Checking content
Requirement
Remark
Date
Result
No.
4-3
Maintenance
tools
and
Enough
material
4-5
Operation
tools
and
Readied
recording sheet
4-6
Test
instrument
and
Readied
apparatus
Date:
30
2
Appendix 2: Commissioning record IDF system air valves
KKS
Name
Remote
Time
KKS
operation
Chec
Chec
Sign
Re
No.
Local
king
king
atur
mar
date
result
indic
ation
corre
ct
XXXX
XXXX
Op
Clo
Corre
Corre
en
se
ct
ct
direct
respo
ion
nse
A IDF inlet
damper
XXXX
XXXX
A IDF outlet
damper
XXXX
XXXX
B IDF inlet
damper
XXXX
XXXX
B IDF outlet
damper
XXXX
XXXX
31
XXXX
XXXX
XXXX
XXXX
XXXX
XXXX
3
Appendix 3: IDF system interlock protection test card
No.
Test content
Re
sult
IDF
<5%
IDF frequency converter feedback <5%
<5%
IDF inlet damper opening <5%
;
IDF no stop and protection action signal
Interlock shutdown
32
Re
mark
No.
Test content
Re
sult
1
75
80
XY
4.6mm/s2S
If any IDF front and rear bearing vibration is over
4.6mm/s to X or Y direction, 2s time delay, (IDF
protection interlock into operation)
63
145
IDF motor stator coil temperature is above 145 (3
selected from 6), (IDF protection interlock into operation)
120
IDF operation outlet damper close, 120s time delay.
MFT32
MFT action and furnace negative pressure low low (select
2 from 3
Introduction
II
33
Re
mark
No.
Test content
Re
sult
III
1
34
Re
mark